TE-12_MCTP_WFX_Generic_Models_Timeline.xlsx
XLSX spreadsheet 29 KB Posted
- Attached to
- MCTP Draft Solicitation Federal contract opportunity
- Solicitation number
- W911S0-16-R-0007
About this file
TE - 12
View the file
Other files for this federal contract opportunity
Show all 50
MCTP Draft Solicitation has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| MCTP WFX Generic Models Timeline | ||||||
| Milestones and Meetings Schedule | ||||||
| Today: | ||||||
| MCT Start Date: | ||||||
| MCT End Date: | ||||||
| Warfighter Start Date: | ||||||
| Warfighter End Date: | ||||||
| Note: All days after Day 0 incorporate all Meeting, Huddles and Rehearsals to include day to day troubleshooting, maintenance issues and Training Audiences/ECG directed changes or requests to support operations. These tasks are in the IOM category of normal network operations for Installation, Operation and Maintnenace of 24-7 Networks and Simulations support. | ||||||
| EVENT | SUSPENSE | DATES | DATES | |||
| Status | OCONUS/CONUS | SEMINAR | CONUS | OCONUS | Seminar | |
| WFX Equipment Shipment to WFX Site | W-19 | -19.0 | ||||
| Advance Party Deploys | W-15/18 | -15.0 | ||||
| TECH Advance Party Deploys(50% Commo FST) | Status | W-16/18 | -16.0 | -18.0 | ||
| Advance Party Procedures | W-15 | |||||
| Tech ADVON ARRIVES | W-15 | |||||
| Equipment Arrives | W-15 | -15.0 | -15.0 | |||
| Unpack/Accountability/Roll Out | W-15 | -15.0 | ||||
| Site Coordinator Meeting | W-15 | -15.0 | ||||
| Tables and Chairs on Hand | W-15 | -15.0 | ||||
| Minimum of four telephones operational | W-15 | -15.0 | ||||
| Send initial report to MCTP HQs | W-15 | -15.0 | ||||
| Advance Party Composition | W-15 | -15.0 | ||||
| Safe Available | W-15 | -15.0 | ||||
| COMSEC/CCI Available | W-15 | -15.0 | ||||
| MCTP OPS DetailReports for Duty | W-15 | -15.0 | ||||
| Conduct Operations Detail In-Brief | W-15 | -15.0 | ||||
| Set Up Table and Chairs | W-15 | -15.0 | ||||
| Off-load of Shipment | W-15 | -15.0 | ||||
| Confirm Life Support Facilities | W-15 | -15.0 | ||||
| Confirm MCTC Climate Control | W-15 | -15.0 | ||||
| Set Up "Working Issues" and "To Do-Checklist" Charts. | W-15 | -15.0 | ||||
| Arrange Daily Site Coordination Meetings | W-15 | -15.0 | ||||
| Establish the WAN | ||||||
| Begin LAN buildout for all Enclaves | ||||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| 10% of Work Completed | Status | |||||
| Advance Party Procedures | W-14 | -14.0 | ||||
| OSPGRPS ADVON ARRIVES 1A | W-14 | -14.0 | ||||
| Equipment arrives, begin setup | W-14 | |||||
| Site Coordinator Meeting | W-14 | |||||
| Establish MCTP Operations/Admin Area | W-14 | |||||
| Installation/Configuration/Test of Workstation/FWD Suites/C2 Adapter | W-14 | |||||
| Confirm Copier Installation | W-14 | |||||
| Establish Distribution Center | W-14 | |||||
| Confirm VOQs for VIPs | W-14 | |||||
| Contact Protocol | W-14 | |||||
| WAN Operational | W-14 | |||||
| Continue LAN buildout for all Enclaves | W-14 | |||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Personal Computer Ready for Installation | W-14 | |||||
| 20% of Work Completed | Status | |||||
| Advance Party Procedures | W-13 | -13.0 | ||||
| Establish MCTP Admin Area & AAR Prep Room | W-13 | |||||
| Installation/Configuration/Test of Workstation/FWD Suites/C2 Adapter | W-13 | |||||
| C4I TiWGs Begin | W-13 | |||||
| Production & Test Federation Golden Checkpoint All Models | W-13 | |||||
| Connect ADMIN Fax Machine | W-13 | |||||
| Establish VIP Offices | W-13 | |||||
| Establish AAR Room/AAR Overflow Areas | W-13 | |||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| 30 % of Work Completed | Status | |||||
| Advance Party Procedures | W-12 | -12.0 | ||||
| Site Coordinator Meeting | W-12 | |||||
| Establish MCTP Operations/Admin Area | W-12 | |||||
| Installation/Configuration/Test of Workstation/FWD Suites/C2 Adapter | W-12 | |||||
| Limited DSN/NIPR Services Established | W-12 | -12.0 | ||||
| OPSGRPS ADVON 1B ARRIVES | W-12 | -12.0 | ||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| 40% of Work Completed | Status | |||||
| Advance Party Procedures | W-11 | -11.0 | ||||
| Establish White Cell Meeting Area | W-11 | |||||
| Installation/Configuration/Test of Workstation/FWD Suites/C2 Adapter | W-11 | |||||
| Install Maps/Boards | W-11 | |||||
| Verify Telephones | W-11 | |||||
| Establish LNO Area | W-11 | |||||
| Continue LAN buildout for all Enclaves | W-11 | |||||
| Establish Break Area | W-11 | |||||
| SIM Specialists & FST Arrive(100%) | W-11 | -11.0 | ||||
| Confirmation of Supply Stockages | W-11 | |||||
| Establish OC Hooch | W-11 | |||||
| Coordinate ENDEX Plaque | W-11 | |||||
| Verify Work Cell Supplies are on Hand | W-11 | |||||
| Verify Badge System | W-11 | |||||
| Install Secure Fax Machines | W-11 | |||||
| OCPOC/NCO Arrive | W-11 | |||||
| LAN buildout for all Enclaves Complete | W-11 | |||||
| Site Coordinator Meeting | W-11 | |||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| 50% of Work Completed | Status | |||||
| Advance Party Procedures | W-10 | -10.0 | ||||
| Installation/Configuration/Test of Workstation/FWD Suites/C2 Adapter | W-10 | |||||
| Production & Test Federation restored to Golden Checkpoint | W-10 | |||||
| Site Coordinator Meeting | W-10 | |||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| 60% of Work Completed | Status | |||||
| Advance Party Procedures | W-9 | -9.0 | ||||
| Installation/Configuration/Test of Workstation/FWD Suites/C2 Adapter | ||||||
| OPSGRP ADVON 2 ARRIVES | W-9 | -9.0 | ||||
| CIC DST ARRIVAL | W-9 | -9.0 | ||||
| Site Coordinator Meeting | ||||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| 70% of Work Completed | Status | |||||
| Advance Party Procedures | ||||||
| VoIP Established | W-8 | -8.0 | ||||
| Electronic Telephone Book Completed | W-8 | -8.0 | ||||
| Test Federation available for Senior Control | W-8 | |||||
| Validate that contact information has been shared between: WIM & CSP operators | W-8 | |||||
| BE Server / AWSIM to ADSI | W-8 | |||||
| C2 Adapter to GCCS-A / AJAX | W-8 | |||||
| C2 Adapter to AFATDS | W-8 | |||||
| Main Gateway (FT Lee) to DFG | W-8 | |||||
| MTI Sim to TGS | W-8 | |||||
| Obtain Orders/Make Copies | ||||||
| Site Coordinator Meeting | ||||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| 80% of Work Completed | Status | |||||
| Advance Party Procedures | W-7 | -7.0 | ||||
| Inform TA to clear all COPs 2 hours prior | W-7 | |||||
| Begin inject point stimulation to Training Audience @0900 | W-7 | -7.0 | ||||
| MCTC Secure for Open Storage of COMSEC/CCI | W-7 | -7.0 | ||||
| Exercise Control Group Services Available | W-7 | -7.0 | ||||
| Email/Portal/MSEL Services Available | W-7 | -7.0 | ||||
| Site Coordinator Meeting | W-7 | |||||
| Functional Testing Begins | W-7 | -7.0 | ||||
| MUSE and MTI Sim available | W-7 | -7.0 | ||||
| Provide TA with MUSE Media page link | W-7 | |||||
| Map to TOC Sites with Grid Coordiantes & Routes | W-7 | |||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| 90% of Work Completed | Status | |||||
| Advance Party Procedures | W-6 | -6.0 | ||||
| Cellular Phones Ready for Issue | ||||||
| Parking Signs Installed | ||||||
| COG, BOS Chief, EXCON, and Contractor Main Body Arrive | W-6 | -6.0 | ||||
| Install Work Cell Supplies | W-6 | -6.0 | ||||
| MCTC Security Sweep | W-6 | -6.0 | ||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| WFX Unit and MSC OPORDs to MCTP | ||||||
| 100% of Work Completed | Status | |||||
| Key Events W-5 | W-5 | -5.0 | ||||
| 12 Hour Shifts Begin | ||||||
| DAY ONE of Workstation Training Begins | W-5 | -5.0 | ||||
| CIC/ADOBE/CHAT Available | W-5 | -5.0 | ||||
| Set-Up Theater for In-Brief | ||||||
| Unit Issues Badges | ||||||
| Pre-Exercise Schedule | ||||||
| Work Cell OIC In-Brief | ||||||
| Theater In-Brief with Security Check | ||||||
| Receive Tactical Vehicles | ||||||
| Driver/NCO Brief | ||||||
| Drivers Check Out TOC Sites | ||||||
| Briefing Officers Returns | ||||||
| OPS Section establishes two shifts | ||||||
| OPS Detail receives WARSIM Training | ||||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| Status | ||||||
| Key Events W-4 | W-4 | -4.0 | ||||
| DAY TWO of Workcell Training Begins | W-4 | |||||
| Main Body of MCTP and Augmentee OCs Arrive | W-4 | |||||
| Precision Targeting Testing with MUSE | W-4 | |||||
| MUSE Training / Chat | W-4 | |||||
| Confrim Visitor List | W-4 | |||||
| MCTP VIP Books Prepared | W-4 | |||||
| Cell Phones and Pagers to OCs | W-4 | |||||
| WCOPFOR Advance Party Arrives | W-4 | |||||
| Senior Observer Escort Officer Brief | W-4 | |||||
| Coordinate Preparation of Certificates of Achievements for Support Personnel | W-4 | |||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| Status | ||||||
| Key Events W-3 | W-3 | -3.0 | ||||
| DAY THREE of Workcell Training Begins | ||||||
| Telephone Cards Made | W-3 | -3.0 | ||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| White Cell Rehearsal | ||||||
| White Cell | ||||||
| Attend Daily ECG meeting | ||||||
| Commander, MCTP Arrives | ||||||
| Senior Observer Arrives | ||||||
| Status | ||||||
| Key Events W-2 | W-2 | -2.0 | ||||
| Startup from Golden Checkpoint | W-2 | |||||
| Simulation runoff (Gametime =Zulu) | W-2 | |||||
| STARTEX DATALOAD BEGINS (Blue & Red) | W-2 | -2.0 | ||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| White Cell Rehearsal | ||||||
| White Cell | ||||||
| Attend Daily ECG meeting | ||||||
| Status | ||||||
| Key Events W-1 | W-1 | -1.0 | ||||
| STARTEX DATALOAD CONTINUES (Blue & Red) | W-1 | |||||
| After Task Org Checkpoint (Platinum) | W-1 | |||||
| OPFOR Data Load (Stuff Files) | ||||||
| STARTEX Checkpoint after OPFOR Load (Diamond) | ||||||
| Mini-Ex | W-1 | -1.0 | ||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| White Cell Rehearsal | ||||||
| White Cell | ||||||
| Attend Daily ECG meeting | ||||||
| Status | ||||||
| Key Events W Day | ||||||
| Continuation of Mini-Ex | W-0 | 31-Dec-99 | ||||
| Reset Federation to STARTEX Checkpoint | W-0 | |||||
| Unlock Approved Workstations | W-0 | |||||
| Final Adjustments | W-0 | |||||
| Run Time Forward to Zulu | W-0 | |||||
| Take WARMSTART Check Point | W-0 | |||||
| Confirm PAUSEX Procedures w/ OPS | W-0 | |||||
| Begin WARM START / INTEL Build | W-0 | |||||
| STARTEX +/- 6 | W-0 | |||||
| Host the Models and Simulation Techicnal Information Forum(MASTIF) | ||||||
| Attend Primary training audience Technical Integration Meeting | ||||||
| Calculate Simulations Up and Down time and Update slides | ||||||
| Update daily synch slides | ||||||
| Conduct twice daily Simulations Update over Technical Bridge | ||||||
| Attend Daily ECG meeting | ||||||
| Note: All days after Day 0 incorporate all Meeting, Huddles and Rehearsals to include day to day troubleshooting, maintenance issues and Training Audiences/ECG directed changes or requests to support operations. These tasks are in the IOM category of normal network operations for Installation, Operation and Maintnenace of 24-7 Networks and Simulations support. |