Final Optimization Plan for U.S. Army Soldier Systems Center.pdf

PDF 5 MB Posted

Attached to
Groundwater Pump and Treatment System Operation Semi-Annual Groundwater Monitoring (FY26)
Solicitation number
W911QY-26-R-GROUNDWATER
Issued by

About this file

This is a Draft Optimization Plan for groundwater remediation at the U.S. Army Natick Soldier Systems Center in Natick, Massachusetts, prepared by Plexus Scientific Corporation under Contract W91ZLK-13-D-0010, Delivery Order 0004, dated November 2017.

The plan addresses optimization of the existing Groundwater Extraction and Treatment System (GWETS) and identifies specific remedial strategies across four treatment areas. For the T-25 Area, optimized pumping rates are specified for five extraction wells totaling 74 gallons per minute (gpm), with all 422 particles in the model captured. The Buildings 22 and 36 Area requires well rehabilitation and two extraction wells (EW-5 and MW-40BR) are recommended for shutdown based on attainment evaluations showing post-remediation steady-state conditions. The Buildings 63, 2, and 45 Area requires installation of two new extraction wells (EW-9 and EW-10), upgrade of the 1,4-dioxane pre-treatment system from Fenton's chemistry to ozone advanced oxidation process, and re-routing of EW-4 flow directly to the GWETS based on non-detect 1,4-dioxane sampling results. The ARIEM Building Area requires implementation of continuous groundwater extraction as an alternative remedy, including installation of new extraction well EW-11 and conversion of existing monitoring wells MW-182B-4 and MW-165B-2 to extraction wells, with a projected cleanup timeframe of 16 years.

The plan includes comprehensive optimization measures including extraction well rehabilitation using Pantonite acid surging, adjusted design pumping rates totaling 85.65 gpm system-wide, and upgrades to GWETS components including replacement of the programmable logic controller, SCADA software upgrade, installation of multi-bag filter housings, and replacement of flowmeters. Implementation is anticipated to begin with Explanation of Significant Differences (ESD) and Long-Term Monitoring Plan updates in calendar year 2018, achieving Remedy in Place status in 2019, with operations and maintenance continuing through the remedial action operation phase.

View the file

Other files

File Type Posted
Q and A - No. 2 - Groundwater Pump and Treatment System Operation Semi-Annual Groundwater Monitoring (05 FEB 2026).pdf PDF
Final Optimization Plan for U.S. Army Soldier Systems Center (Sep 2018).pdf PDF
Groundwater Remedial Optimization Work Plan - U.S. Army SSC.pdf PDF
T-25 Area (OU-1) Ground Water Treatment System Operation and Maintenance Manual Volume 1 of 2.pdf PDF
DRAFT Groundwater Monitoring Event 89 and 2024 GWETS Annual Report.pdf PDF
Q and A - Groundwater Pump and Treatment System Operation Semi-Annual Groundwater Monitoring (22 JAN 2026).pdf PDF
Final Explanation of Significant Differences for T-25 Area Groundwater (Operable Unit 1) US Army SSC.pdf PDF
Final 2017 Third Five Year Review Report U.S. Army Soldier Systems Center, Natick MA (APR 2017).pdf PDF
Groundwater Monitoring Event 81 and 2020 GWETS Annual Report.pdf PDF
Groundwater Monitoring Event 83 and 2021 GWETS Annual Report.pdf PDF
Groundwater Monitoring Event 87 and 2023 GWETS Annual Report.pdf PDF
Groundwater Solicitation - W911QY26RGROUNDWATER (UPDATED 22 JAN).pdf PDF
Attachment 2 - CLIN Structure (UPDATED 22 JAN).xlsx XLSX spreadsheet
T-25 Area (OU-1) Ground Water Treatment System Operation and Maintenance Manual Volume 2 of 2.pdf PDF
Final Uniform Federal Policy Quality Assurance Project Plan (UFP-QAPP) U.S. Army SSC.pdf PDF
Groundwater Monitoring Event 85 and 2022 GWETS Annual Report.pdf PDF
Attachment 1 - Performance Work Statement (PWS) - Final (UPDATED 22 JAN).pdf PDF
QASP - CERCLA Groundwater Pump and Treatment System Operation and Semi-Annual Groundwater Monitoring (16 JAN 2026).pdf PDF
Record of Decision T-25 Area Ground Water (APR 2001).pdf PDF
Federal Facilities Agreement.pdf PDF
Draft Final Ops. and Maint. Manual OU-1 (T-25 Area, Bldgs 22, 36 Area, and Bldgs 63, 2, 45 Area).pdf PDF
Event 79 (Fall 2019) and Groundwater Treatment System 2019 Annual Report for U.S. Army SSC.pdf PDF
Attachment 1 - Performance Work Statement (PWS) - Final 16 JAN.pdf PDF
Groundwater Solicitation - W911QY26RGROUNDWATER.pdf PDF
Attachment 2 - CLIN Structure (16 JAN).xlsx XLSX spreadsheet
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Draft

Optimization Plan

For U.S. Army Soldier Systems Center

Natick, Massachusetts

Prepared for

United States Army Environmental Command

Northeast Environmental Services and Support Division

2450 Connell Road, Bldg. 2264

JBSA Ft Sam Houston, TX 78234-7664

Prepared by:

Plexus Scientific Corporation

5510 Cherokee Avenue, Suite 350

Alexandria, VA 22312

Contract W91ZLK-13-D-0010

Delivery Order 0004

November 2017

U. S. Army Natick Soldier System Center, Natick, Massachusetts i

TABLE OF CONTENTS

1.0 INTRODUCTION

1.1 PURPOSE

2.0 SITE DESCRIPTION AND CONCEPTUAL SITE MODEL

2.1 GEOLOGY

2.2 HYDROGEOLOGY

2.3 CONTAMINANTS OF CONCERN

2.4 MONITORED NATURAL ATTENUATION (MNA) POTENTIAL

3.0 CURRENT GROUNDWATER REMEDIATION APPROACH

4.0 ARIEM BUILDING AREA ALTERNATIVE REMEDY

4.1 PERIODIC SLUG VOLUME REMOVAL ACTIONS

5.0 OPTIMIZATION OF THE GWETS

5.1 EXTRACTION WELL REHABILITATION

5.2 EXTRACTION WELL ATTAINMENT EVALUATIONS

5.2.1 Extraction Well EW-5

5.2.2 Extraction Well MW-40BR

5.3 PUMPING STRATEGY

5.3.1 T-25 Area

5.3.2 Buildings 22 and 36 Area

5.3.3 Buildings 63, 2, and 45 Area

5.3.4 ARIEM Building Area

5.4 INDIVIDUAL COMPONENTS

6.0 OPTIMIZATION OF THE 1,4-DIOXANE PRE-TREATMENT SYSTEM (PTS)

6.1 SYSTEM CONDITION

6.2 EXTRACTION WELL EW-4 FLOW RE-ROUTING

7.0 IMPLEMENTATION

8.0 REFERENCES

ii

TABLES

Table 1 Groundwater MNA Parameter Analytical Results

Table 2 Soil MNA Parameter Analytical Results

Table 3 Optimized Extraction Well Design Pumping Rates

Table 4 1,4-Dioxane Groundwater Analytical Results

FIGURES

Figure 1 Site Layout, Natick Soldier Systems Center

Figure 2 Interpreted Deep Overburden Piezometric Surface – Event 73

Figure 3 Distribution of PCE in Groundwater

Figure 4 Distribution of TCE in Groundwater

Figure 5 Distribution of 1,4-Dioxane in Groundwater

Figure 6 Distribution of Primary COCs in Groundwater

Figure 7 GWETS Instrumentation Diagram

Figure 8 1,4-Dioxane PTS Instrumentation Diagram

Figure 9 Proposed New Extraction Wells and Pipe Routing

Figure 10 Optimized Particle Traces for T-25 Area

Figure 11 Optimized Particle Traces for Buildings 22 and 36 Area

Figure 12 Optimized Particle Traces for Buildings 63, 2, and 45 Area

Figure 13 Modeled Distribution of TCE with Optimization, Bldgs 63, 2, 45 Area, 10 Years

Figure 14 Modeled Distribution of TCE without Optimization, Bldgs 63, 2, 45 Area, 10 Years

Figure 15 Optimized Particle Traces for ARIEM Building Area

Figure 16 Modeled Distribution of TCE with Optimization, ARIEM Bldg Area, Six Years

APPENDICES

Appendix A Extraction Well EW-5 Attainment Evaluation

Appendix B Extraction Well MW-40BR Attainment Evaluation

Appendix C Calibration Forms

Appendix D Low Flow Groundwater Purging and Sampling Forms

Appendix E Groundwater Sample Analysis Laboratory Reports iii

LIST OF ACRONYMS AND ABBREVIATIONS

µg/L micrograms per liter

AOP Advanced Oxidation Process

ARIEM Army Research Institute of Environmental Medicine bgs below ground surface

COCs Contaminants of Concern

ECC Environmental Chemical Corporation

ESD Explanation of Significant Differences

FPGS Former Proposed Gymnasium Site ft feet or foot gpm gallons per minutes

GW Groundwater

GWETS Groundwater Extraction and Treatment System

LGAC Liquid-Phase Granular Activated Carbon

LTM Long-Term Monitoring

MCL Maximum Contaminant Level

MCP Massachusetts Contingency Plan

MNA Monitored Natural Attenuation

NSSC Natick Soldier Systems Center

O&M Operations and Maintenance

PCE Tetrachloroethene

PLC Programmable Logic Controller

Plexus Plexus Scientific Corporation

PTS Pre-Treatment System

PVC polyvinyl chloride

RAOs Remedial Action Objectives

RA(O) Remedial Action Operation

RAWP Remedial Action Work Plan

RIP Remedy in Place

ROD Record of Decision

SCADA Supervisory Control and Data Acquisition

TCE Trichloroethene

TCZ Target Capture Zone

TOC Total Organic Carbon

UCL Upper Confidence Limit

UFP-QAPP Uniform Federal Policy - Quality Assurance Project Plan

USEPA United States Environmental Protection Agency

UV Ultraviolet

VGAC Vapor-phase Granular Activated Carbon

WSW Water Supply Well

1.0 INTRODUCTION

Plexus Scientific Corporation (Plexus) has been awarded Delivery Order 0004 under contract number W91ZLK-13-D-0010, with the Department of the Army, U.S. Army Mission and

Installation Contracting Command to provide environmental remediation services for groundwater remediation at U. S. Army Natick Soldier Systems Center (NSSC) in Natick, Massachusetts.

This Optimization Plan builds on the optimization investigation results and recommendations as presented in the Technical Memorandum: Evaluation of Data from the 2016-2017 Optimization

Investigation (“Optimization Investigation Tech Memo”; Plexus, 2017a) to recommend specific alternative technologies, remedy upgrades, and additions at the following four groundwater treatment areas:

• T-25 Area, which requires extraction well rehabilitation;

• Buildings 22 and 36 Area, which requires extraction well rehabilitation, and at which two extraction wells can be taken offline;

• Buildings 63, 2, and 45 Area, which requires extraction well rehabilitation, upgrade or replacement of a pre-treatment system (PTS), re-routing of flow through a PTS, the installation of additional extraction wells, and adjustment of design pumping rates; and

• U.S. Army Research Institute of Environmental Medicine (ARIEM) Building Area, which requires implementation of an alternative remedial technology, which will include installing additional extraction wells and setting design pumping rates.

Additionally, the Groundwater Extraction and Treatment System (GWETS), which services each of the above treatment areas, requires upgrades to and replacements of various individual components.

The Optimization Plan field activities (specifically, the collection of 1,4-dioxane samples in the

Buildings 63, 2, and 45 Area) were performed in accordance with the Uniform Federal Policy –

Quality Assurance Project Plan (UFP-QAPP; Plexus, 2017b). Otherwise, this Optimization Plan utilizes analytical results from the optimization investigation (Plexus, 2017a) and the Fall 2016 semi-annual groundwater monitoring event (Event 73; Plexus, 2017c).

1.1 Purpose

As documented in the Optimization Investigation Tech Memo (Plexus, 2017a), the GWETS is starting to provide diminishing returns. The reduction of the GWETS effectiveness is due to multiple factors that are related to the decrease of contaminant concentrations in groundwater, the reliability of the system, and the ability of the GWETS to sustain yields in extraction wells. The

Optimization Investigation Tech Memo (Plexus, 2017a) identified those factors and areas of the current remedy that require an updated strategy to optimize the remedial approach and minimize the time to achieve site closure, along with recommendations towards meeting those optimization goals. This Optimization Plan presents specific technologies and approaches that, once implemented, will meet the recommendations presented in the Optimization Investigation Tech

Memo (Plexus, 2017a).

2.0 SITE DESCRIPTION AND CONCEPTUAL SITE MODEL

NSSC is located approximately 17 miles west-southwest of Boston in the Town of Natick, Massachusetts. NSSC is a research facility that occupies approximately 74 acres on the eastern shore of the South Pond of Lake Cochituate (Figure 1).

NSSC, formerly called the Quartermaster Research and Engineering Command and subsequently the U.S. Army Natick Research and Development Command, has been a permanent U.S. Army installation since October 1954. NSSC’s mission includes research and development activities in food engineering, food service, clothing, equipment, materials engineering, and aero-mechanical engineering.

Previous investigations at NSSC have focused on characterizing physical conditions and contaminant distribution at several locations or sites within NSSC. These sites consist of: the T-

25 Area, the Water Supply Well (WSW) Site, the Former Proposed Gymnasium Site (FPGS); the

Boiler Plant Area; the Buildings 22 and 36 Area; the Buildings 63, 2, and 45 Area; and the ARIEM

Building Area (Figure 1). The primary Contaminants of Concern (COCs) are tetrachloroethene

(PCE), trichloroethene (TCE), and 1,4-dioxane. A summary of previous monitoring events is presented in the Groundwater Monitoring Event 73 and 2016 GWETS Annual Report (Plexus, 2017c).

The Record of Decision (ROD) for the T-25 Area (Arthur D. Little [ADL], 2001) specified the following Remedial Action Objectives (RAOs):

• Prevent contamination in the groundwater, above federal and state drinking water standards, from migrating outside of the T-25 Area toward off-facility receptors;

• Prevent any potential exposure to groundwater beneath the T-25 area and off-facility with contaminant concentrations in excess of federal and state drinking water standards;

• Restore aquifer to drinking water standards within a reasonable time frame; and,

• Monitor potential future migration of groundwater contamination to verify that elevated concentrations decrease over time.

An Explanation of Significant Differences (ESD; Environmental Chemical Corporation, LLC.

[ECC], 2013) was later developed to expand application of the T-25 Area RAOs to additional areas at NSSC, including the Buildings 22 and 36 Area; the Buildings 63, 2 and 45 Area; and the ARIEM

Building Area.

NSSC is located in a Zone 2 aquifer and is located approximately 2,500 feet (ft) southeast of the

Town of Natick’s Springvale Municipal Water Supply Well Field.

2.1 Geology

The geology at the facility consists predominantly of fill and reworked native soils underlain by glaciolacustrine, lacustrine, and glacial till deposits. Surficial soils are comprised of primarily well-

James.B.Connolly Inserted Text Consistent with other citations graded sands. The surficial soils are underlain by poorly graded, very-fine to fine grained sands which are embedded with thin layers of silty sand and sandy silt. A layer of grey clayey silt and silt underlies the sands (MACTEC Engineering and Consulting, Inc., 2008).

Soil boring observations have noted a transition to poorly graded sands and gravels below the grey clayey silt in the southern portion of the Buildings 22 and 36 Area that continues south into the

Building 63, 2, and 45 Area. Along the eastern shoreline, adjacent to Pegan Cove, a subsurface layer of peat has been observed in soil borings and excavations. Logs of borings advanced during the 2017 optimization investigation were consistent with the known descriptions of, and the heterogeneity of, the previously described site soil formations (Plexus, 2017a).

Bedrock is not exposed at NSSC, but does outcrop on the eastern shore of South Pond of Lake

Cochituate near Pegan Brook. Historically, well borings from the three study areas have noted the bedrock is composed of granodiorite/hornblende gabbro, which is consistent with the regional bedrock geology.

2.2 Hydrogeology

NSSC is located within the Lake Cochituate drainage basin, which encompasses approximately

17.7 square miles. The main hydrogeologic feature at NSSC and the surrounding area is the South

Pond of Lake Cochituate. The South Pond of Lake Cochituate occupies 0.9 square miles, flows northward to the Middle Pond, and through to North Pond of Lake Cochituate. The North Pond drains via the Cochituate Brook into the Sudbury River.

Groundwater in the unconsolidated soils at the Installation is divided into two aquifer intervals:

the unconfined water table aquifer, or “A” interval, and the locally semi-confined, deeper overburden aquifer, or “B” interval. The water table ranges in depth from 0 to 28 ft below ground surface (bgs).

Figure 2 illustrates the interpreted groundwater flow conditions for the deep overburden aquifer

(“B” interval) across the NSSC while the GWETS is in operation. Deeper overburden groundwater appears to move from east to west beneath NSSC, discharging to the South Pond of Lake

Cochituate with local variations beneath the eastern bay and the central and southern portion of the installation. The influence of groundwater pumping is apparent in Figure 2 as cone-of-depression distortions of the piezometric contours in the vicinity of extraction wells.

Based on the current data, all impacted groundwater is found entirely within the locally semi-confined, deeper overburden aquifer, or “B” interval, and no contamination is present in the unconfined water table aquifer, or “A” interval. The average hydraulic conductivity rates in the

“B” interval estimated during the 2017 optimization investigation (Plexus, 2017a) ranged from

0.45 to 1.87 ft/day across the installation, which is consistent with previous capture zone model input values and the known descriptions of, and heterogeneity of, the screened soil formations.

2.3 Contaminants of Concern

PCE, TCE, and, 1,4-dioxane are the primary COCs in groundwater at NSSC. Concentrations of

James.B.Connolly

Clarify, Correct me if I'm wrong but no recent boring or anything you all did as part of the optimization investigation reached or characterized bedrock.

COCs are compared to U.S. Environmental Protection Agency (USEPA) Maximum Contaminant

Levels (MCLs) and the Massachusetts Contingency Plan (MCP) Groundwater (GW)-1 criteria.

The applicable screening criteria for the primary COCs are as follows:

• PCE: MCL of 5 micrograms per liter (µg/L)

• TCE: MCL of 5 µg/L

• 1,4-Dioxane: MCP GW-1 of 0.3 µg/L

The current extents of the PCE, TCE, and 1,4-dioxane plumes, based on the results of both Event

73 (Plexus, 2017c) and the Optimization Investigation, are illustrated in Figure 3, Figure 4, and

Figure 5, respectively. Figure 6 presents the areas in which COCs exceed clean-up levels; these are considered the Target Capture Zones (TCZs) in the capture model analysis.

T-25 Area: PCE and TCE are the primary COCs, where the highest concentrations are 7.7 µg/L for PCE (MW-96B-4) and 21 µg/L for TCE (MW-88B-HP2).

Buildings 22 and 36 Area: PCE is the primary COC, where the highest concentration is 22.3 µg/L

(EW-8).

Buildings 63, 2, and 45 Area: TCE and 1,4-dioxane are the primary COCs, where the highest concentrations are 155 µg/L for TCE (TMW-6; 136 µg/L in duplicate sample) and 3.4 µg/L for

1,4-dioxane (MW-160A-2).

ARIEM Building Area: TCE is the primary COC, where the highest concentration is 28.2 µg/L

(MW125-2).

The Boiler Plant Area, FPGS, and NSSC WSW Site do not have exceedances of primary COCs and are therefore not discussed further in this Optimization Plan.

2.4 Monitored Natural Attenuation (MNA) Potential

A secondary objective of the optimization investigation was to better understand the Monitored

Natural Attenuation (MNA) potential within the impacted areas. Towards that goal, groundwater samples were collected from monitoring wells TMW-3, TMW-6, TMW-7, MW-182B-4, MW-

37B-HP2, MW96B-4, and EW-7 and analyzed for MNA parameters iron, manganese, sulfate, nitrite, nitrate, and chloride; and soil samples were collected from borings TMW-3, TMW-6, TMW-7, and MW-182B-4 and analyzed for total organic carbon (TOC). The analytical results from this sampling event were presented in the Optimization Investigation Tech Memo (Plexus, 2017a); the groundwater and soil results are re-presented in Table 1 and Table 2, respectively, for ease of reference.

Groundwater at NSSC is well oxygenated, providing for an aerobic and oxidizing environment that is not favorable to reductive dechlorination, the preferred natural biodegradation pathway for

PCE and TCE. The elevated concentrations of anions and the high ratio of nitrate to nitrite, given the acidic nature of the groundwater, as well as the absence of PCE degradation daughter products, support this interpretation of the geochemical environment of site groundwater and its role in

James.B.Connolly

Is there new data to support this? Reference table 1? Consistent with ICF data from in-situ optimization study so might need to justify statement applying across the installation.

potential natural biodegradation of PCE and TCE. The soil at NSSC is rich in organic carbon, which both preferably retards contaminant transport via sorption and could serve as a favorable electron donor for biodegradation in a reducing environment. Therefore, it is concluded that, while

MNA may be effective following a driven shift in redox conditions, the current groundwater geochemical environment is not conducive to efficient biodegradation of PCE or TCE. However, when other remedies are found to no longer be efficient, as is expected to be the scenario when concentrations of primary COCs reach asymptotic levels near the clean-up goals (after a period of successful active remediation), MNA is anticipated to be the selected final remedial alternative implemented prior to achieving site closure.

3.0 CURRENT GROUNDWATER REMEDIATION APPROACH

The current groundwater remedial approach at NSSC is extraction and ex situ treatment of impacted groundwater via a GWETS and localized slug volume removal activities at selected impacted wells beyond the treatment system radii of influence.

The GWETS within Building 94 has been in operation since 1997 and currently consists of the following components, as illustrated on Figure 7:

• Twelve (12) groundwater extraction wells;

• Coliform PTS (offline)

• Equalization tank;

• Particulate Filters;

• Air stripper (offline);

• Granulated activated carbon to treat vapor discharge from the stripper (vapor phase granular activated carbon [VGAC]; offline); and,

• Granulated activated carbon for primary treatment of groundwater (Liquid-Phase Granular

Activated Carbon [LGAC]).

Water is extracted from the following 12 extractions wells screened in the “B” interval (Figure 1):

• T-25 Area: MW-90B-4, MW-94B-4, MW-95B-4, MW-96B-4, and MW-39B-HP4

• Buildings 22 and 36 Area: EW-5, EW-6, EW-7 and EW-8

• Buildings 63, 2, and 45 Area: EW-3 and EW-4

• Boiler Plant Area: MW-40BR.

These extraction wells are screened just above the top of a low-hydraulic-conductivity silt layer that prevents deeper migration of the contaminant plumes.

An ex situ wellhead PTS was installed in 2008 to treat 1,4-dioxane in groundwater from extraction wells EW-3 and EW-4 in the Buildings 63, 2, and 45 Area. This 1,4-Dioxane PTS consists of a

Fenton’s Reagent Advanced Oxidation Process (AOP), as illustrated on Figure 8. After treatment for 1,4-dioxane, this groundwater is pumped to the GWETS.

In 2013, another PTS was installed, this one for MW-96B-4, following discovery of suspended solids and coliform in MW-96B-4, apparently caused by a sanitary sewer line leak discovered and repaired in the Spring of 2012. In August 2016, the PTS was taken off-line after multiple quarters with no detections of coliform in the influent samples. Groundwater extracted from MW-96B-4 is currently pumped directly to the GWETS. Quarterly sampling of MW-96B-4 for coliform continues, and the PTS remains in “stand-by” mode, ready to be placed back in service with minimal effort if necessary.

James.B.Connolly Inserted Text I count 14:

MW-39B-HP4

MW-95B-4

MW94B-4

MW-90B-4

MW-96B-4

EW-2 through 8

MW-40BR

Also MW-15B installed as an extraction well but not normally used since MW-95B-4 installed.

Please clarify 14 total wells, 12 active.

Groundwater capture zone assessments have been used to evaluate the effectiveness of the

GWETS in capturing the interpreted plume extents above screening criteria based on extraction well locations and operating pumping rates. The most recent capture zone assessment, based on early 2017 pumping rates, was presented in the Optimization Investigation Tech Memo (Plexus, 2017a). In general, the models have suggested that contaminant plumes in groundwater have been completely captured at the T-25 Area and the Buildings 22 and 36 Area, and were largely captured at the Buildings 63, 2, and 45 Area.

Areas of impacted groundwater outside of the GWETS capture zone, specifically in the ARIEM

Building Area and at MW-114B-2 near the eastern shoreline in the parking lot east of Building 1, have been treated by periodic slug volume removal actions. Historically, the slug removal activities have been successful at monitoring wells MW114B-2 and MW165B-2, but not at MW-181B-2

(which was supplemented by nearby MW-182B-4 as part of the optimization investigation). Low well yields due to hydrogeological constraints minimize the effectiveness of periodic slug volume removal actions near these wells; therefore, it was recommended that remedial alternatives be considered for this area (Plexus, 2017a).

A Long-Term Monitoring (LTM) program (ECC, 2011) is in place to characterize the nature and extent of groundwater contamination at NSSC and the surrounding area, to evaluate trends in contaminant concentrations over time, to characterize the local and regional groundwater flow conditions, to assess the effectiveness of the GWETS, and to collect data for use in designing possible future remedial actions. The most recent annual sampling and analysis event for which data are available was conducted in November 2016—Monitoring Event 73 (Plexus, 2017c).

Results from the optimization investigation groundwater sampling effort supplemented the

Monitoring Event 73 data (Plexus, 2017a). In general, concentrations of primary COCs are declining and the lateral extents of the COC plumes are decreasing.

The GWETS is monitored weekly and sampled monthly (with an expanded analyte list on a quarterly basis) to continuously evaluate the system’s efficiency and effectiveness, to continuously implement micro-optimizations, to assure compliance with discharge limits, and again to collect data for use in designing possible future remedial actions. The treatment of groundwater at the

GWETS from the Buildings 22 and 36 Area and the Buildings 63, 2, and 45 Area has been successful and continues to remove the bulk of contaminant mass from groundwater. However, as noted in the Introduction above, the GWETS is starting to provide diminishing returns, especially in the Buildings 63, 2, and 45 Area.

4.0 ARIEM BUILDING AREA ALTERNATIVE REMEDY

Following review of the results of the optimization investigation, it was concluded that low well yields due to hydrogeological constraints minimize the effectiveness of periodic slug volume removal actions in the ARIEM Building Area; therefore, it was recommended that remedial alternatives be considered for this area (Plexus, 2017a). Regular slug volume removal activities will be continued until a remedial alternative is implemented.

Due to regulatory requirements, the selected remedial alternative is required to capture both impacted groundwater and any materials potentially injected for in situ treatment of contaminants.

Given that, the preliminary evaluation of alternative remedial technologies to be potentially implemented in the ARIEM Building Area found that extraction of groundwater must be either the selected remedial alternative or a component thereof. Evaluated alternative remedial technologies included in situ chemical oxidation (ISCO), in situ chemical reduction (ISCR), and enhanced reductive bioremediation. Given the relatively low contaminant concentrations, unfavorable existing groundwater geochemical environment, and low “B” interval aquifer permeability, the evaluated in situ remedial alternatives were found to not be efficient options. Ultimately, due to the requirement to achieve capture, following review of the particle trace model for this area under the optimal extraction scenario, as presented and discussed in Section 5.3.4, and given the presence of the existing GWETS infrastructure, it was found that constant groundwater extraction alone will be most efficient to achieve site cleanup goals in a reasonable timeframe. Therefore, constant groundwater extraction and treatment is the recommended remedy for the ARIEM Building Area.

Specifically, it is recommended that a new extraction well be installed near MW125B-2 (identified as EW-11) and existing monitoring wells MW-182B-4 and MW165B-2 be converted to extraction wells. Refer to Figure 9 for the locations of proposed new and converted extraction wells, as well as the proposed routing of piping from these extraction wells to the GWETS. The existing GWETS infrastructure has an influent flow capacity of 160 gallons per minute (gpm), well above its current and anticipated future rate (approximately 86 gpm), and able to accept the anticipated 3 gpm of extracted groundwater from the ARIEM Building Area.

As discussed in Section 2.4, and as is the scenario at the T-25 Area, Buildings 22 and 36 Area, and

Buildings 63, 2, and 45 Area, following a period of successful active remediation, it is anticipated that the recommended groundwater extraction and treatment remedy at the ARIEM Building Area will reach asymptotic conditions as concentrations of TCE near the MCL, at which time a shift to

MNA, as a final remedy, is expected to be recommended. Prior to this change in remedy, it is anticipated that a detailed MNA evaluation will be conducted to determine which, if any, supplemental nutrient, culture, or geochemical adjusting augmentations would increase MNA effectiveness to achieve site closure more efficiently.

Specific details of the selected alternative remedy are presented in Section 5.3.4 below.

4.1 Periodic Slug Volume Removal Actions

Regular slug volume removal activities will be continued until MW-182B-4, MW165B-2, and

EW-11 are operating as GWETS extraction wells.

Periodic extraction of contaminated groundwater from the newly installed extraction well MW-

182B-4 and existing well MW165B-2 (Figure 1), both in the ARIEM Building Area and outside the capture zones for the GWETS, will occur on a quarterly basis. If groundwater results indicate a rebound of contamination at MW-114B-2, then this well will be added to the periodic slug volume removal scope of work.

The periodic slug volumes will be removed by “pulse pumping” via vacuum extraction. The vacuum-enhanced extraction will maximize groundwater recovery. By increasing the pressure gradient at the extraction well, groundwater flow rates, radius of influence, and overall effectiveness of the remedy will be maximized. Extracted groundwater will be transported to

Building 94 where the water will be processed in the GWETS.

Subsequent removals will target the same volumes and frequency that have been previously established (ECC, 2015). Target slug volumes of contaminated groundwater to be removed from

MW-182B-4 and MW165B-2 combined will be approximately 960 gallons every quarterly event

(480 gallons from each well). It is planned to extract groundwater from these two wells at an approximate rate of four gallons per minute, simultaneously from both wells, for four hours.

However, historically, MW-181B-2 and MW-182B-4 have provided low yields, so actual extracted volumes may be closer to 500 gallons total over those four hours.

Performance monitoring of the remedy will consist of sampling groundwater at MW182B-4 and

MW165B-2 prior to and one week after each slug removal event. Groundwater samples will be collected in accordance with USEPA Region I Low Stress (low-flow) Purging and Sampling

Procedure (USEPA, 2010) and analyzed for PCE and TCE by Method 8260B.

5.0 OPTIMIZATION OF THE GWETS

Following review of the results and conclusions of the optimization investigation, in which the factors affecting GWETS effectiveness and areas of the current remedy that require and updated strategy were identified, the Optimization Investigation Tech Memo (Plexus, 2017a) presented recommendations toward optimizing the remedial approach and minimizing the time to achieve site closure. The following subsections detail the approaches to implement those recommendations.

The Operations and Maintenance (O&M) Manual, including all drawings (layout, piping and instrumentation, and electrical) will be updated to capture the system upgrades, equipment changes, and recent changes in site conditions.

5.1 Extraction Well Rehabilitation

Precipitation of metals, primarily iron, has fouled extraction well screens and sand packs, reducing sustainable extraction rates. In order to re-establish and maintain complete capture at Buildings 22 and 36 Area, to increase efficiency at the T-25 Area, and to increase capture at the Buildings 63, 2, and 45 Area, the Optimization Investigation Tech Memo (Plexus, 2017a) found that existing extraction wells MW-90B-4, MW-96B-4, EW-3, EW-4, EW-6, EW-7, and EW-8 specifically need be rehabilitated to attain improved pumping rates. However, it is recommended that all extraction wells be rehabilitated regularly, at least once every two years. Therefore, all currently operating extraction wells will initially be rehabilitated to restore all recovery capacities to a baseline that can be used for future evaluations of well-specific rehabilitation schedules.

Pantonite acid will be introduced to each extraction well and the water will be actively surged, catalyzing reactions with the metal oxides fouling the well. The surge water, containing the acid, will then be extracted from the well by the GWETS, and the condition of the recovered surge water will be observed and documented prior to GWETS treatment. Excessively turbid and discolored water is indicative of a highly fouled well. For extraction wells at which these conditions are observed, the acidization process will be repeated until recovered water is indicative of a well screen and sand pack free of significant fouling. It is anticipated that the initial acidization effort will take one day per extraction well.

Additional acidization events will be planned based on the observed initial condition of each well.

It is expected that extraction wells most afflicted by fouling will be rehabilitated twice per year, and the other extraction wells will be rehabilitated on an annual or biennial basis. The rehabilitation schedule will be reevaluated annually.

Other rehabilitation technologies, such as rehabilitation using carbon dioxide, were evaluated.

Pantonite acid was selected based on cost and product availability. Although carbon dioxide rehabilitation has been shown effective in several situations, it is less commonly utilized due to the above reasons—availability and cost efficiency (usually evaluated on a cost per foot of screen basis).

5.2 Extraction Well Attainment Evaluations

Based on modeling simulations presented in the Optimization Investigation Tech Memo (Plexus, 2017a), it was recommended that extraction wells EW-5 and MW-40BR be evaluated for shutdown in accordance with the USEPA’s Groundwater Completion Strategy (USEPA, 2014a), as they no longer contribute to capture of TCZs and have not had exceedances of COCs in the past five years. The following sections present the conclusions from this evaluation that groundwater at these two extraction wells has met and will continue to meet COC cleanup levels and therefore that groundwater remedial action is complete at these individual locations.

5.2.1 Extraction Well EW-5

Extraction well EW-5 was installed and connected to the GWETS in August 2007 to capture PCE in groundwater. PCE has not exceeded the MCL (5 μg/L) at EW-5 since November 2010.

Appendix A presents the outputs of the attainment evaluation for PCE in EW-5 using the

USEPA’s Groundwater Statistics Tool (USEPA, 2014b), including data inputs, outlier testing, normality testing, upper confidence limit (UCL) calculations, and trend testing. The results of 26.5 and 15.9 μg/L from December 11, 2008, and August 27, 2009, respectively, were both considered statistical outliers but were not removed from the dataset prior to normality testing because there is not a valid and defensible reason to expect the outliers are not representative of actual environmental variability. The data did not appear normal, so nonparameteric techniques were used to calculate UCLs. However, the residuals of the linear regression fit did appear normal, so linear regression was used to evaluate slopes and calculate upper confidence bands. The calculated

95% upper confidence band at the final sampling event is below the PCE MCL, indicating that the cleanup level has been met. Trend analysis shows a statistically significant negative slope and concludes that future PCE concentrations will remain below the MCL.

The attainment evaluation for PCE in EW-5 found that PCE concentrations have reached post-remediation, steady-state conditions and will remain below the MCL in the future. Therefore, it is recommended that extraction well EW-5 be taken offline. However, the well should continue to be monitored to demonstrate completion of the attainment following cessation of groundwater extraction from the location and to confirm that there is no indication that rebound may be occurring.

5.2.2 Extraction Well MW-40BR

Extraction Well MW-40BR was installed and connected to the GWETS in August 2010 to address dieldrin persisting in groundwater. Dieldrin has not exceeded the MCP GW-1 (0.1 μg/L) at MW-

40BR since May 2011.

Appendix B presents the outputs of the attainment evaluation for dieldrin in MW-40BR using the

USEPA’s Groundwater Statistics Tool (USEPA, 2014b), including data inputs, outlier testing, normality testing, UCL calculations, and trend testing. The result of 0.19 μg/L from November 23, 2010, is considered a statistical outlier but was not removed from the dataset prior to normality testing because there is not a valid and defensible reason to expect the outlier is not representative of actual environmental variability. The data did not appear normal, so nonparameteric techniques were used to evaluate slopes and calculate UCLs. The calculated 95% UCL on the mean and the calculated 95% upper confidence band at the final sampling event are below the dieldrin MCP

GW-1 level, indicating that the cleanup level has been met. Trend analysis shows a statistically significant negative slope and concludes that future dieldrin concentrations will remain below the

MCP GW-1 cleanup level.

The attainment evaluation for dieldrin in MW-40BR found that dieldrin concentrations have reached post-remediation, steady-state conditions and will remain below the MCP GW-1 in the future. Therefore, it is recommended that extraction well MW-40BR be taken offline. However, the well should continue to be monitored to demonstrate completion of the attainment following cessation of groundwater extraction from the location and to confirm that there is no indication that rebound may be occurring.

5.3 Pumping Strategy

Particle trace and fate and transport modeling simulations were run to optimize the pumping strategy at each area, including adjusting design pumping rates of existing extraction wells and adding extraction wells to the system where optimal. During simulation runs, the maximum allowable extraction flow rate for each well was set based on historic (i.e., sustainable through rehabilitation) flow rates, to ensure that adjusted design pumping rates are attainable. Table 3 presents optimized design pumping rates by extraction well; total optimized flow rate for the

GWETS will be 85.65 gpm, well below the system’s 160 gpm design capacity influent flow rate.

5.3.1 T-25 Area

Modeling efforts have shown that, after implementation of well rehabilitation activities as discussed in Section 5.1, the following pumping rates for existing extraction wells at the T-25 Area are sustainable and will be sufficient to maintain efficient capture of the TCZ, including impact near monitoring well MW-208B-HP2, while permitting a reasonable cleanup timeframe:

• MW-39B-HP4 15 gpm

• MW-90B-4 20 gpm

• MW-94B-4 10 gpm

• MW-95B-4 24 gpm

• MW-96B-4 5 gpm

Under this approach, the total extraction rate from the T-25 Area will be 74 gpm. Figure 10 presents the contaminant particle traces under this pumping scenario; all of the 422 particles seeded are captured.

5.3.2 Buildings 22 and 36 Area

Modeling efforts have shown that, after implementation of well rehabilitation activities, as discussed in Section 5.1, and after taking extraction wells EW-5 and MW-40BR offline, as discussed in Section 5.2 above, the following pumping rates for existing extraction wells at the

Buildings 22 and 36 Area are sustainable and will be sufficient to maintain efficient capture of the

TCZ while permitting a reasonable cleanup timeframe:

• EW-6 1 gpm

• EW-7 1.75 gpm

• EW-8 1.9 gpm

Under this approach, the total extraction rate from the Buildings 22 and 36 Area will be 4.65 gpm.

Figure 11 presents the contaminant particle traces under this pumping scenario; of the 107 particles seeded, only one escapes capture.

5.3.3 Buildings 63, 2, and 45 Area

The particle trace modeling presented for the Buildings 63, 2, and 45 Area in the Optimization

Investigation Tech Memo (Plexus, 2017a) found that, due to declining pumping capacities and the bulk of the remaining contaminant mass being downgradient of existing extraction wells, most particles seeded were not captured and therefore that additional extraction wells are required to re-attain capture of the TCZ. Figure 9 presents the locations of two proposed new extraction wells

(identified as EW-9 and EW-10), as well as the proposed routing of piping from these extraction wells to the GWETS.

Based on the results of the optimization investigation (Plexus, 2017a), groundwater extracted from both new extraction wells EW-9 and EW-10 is not expected to, but may, have concentrations of

1,4-dioxane above the MCP GW-1. Therefore, all new piping for the Buildings 63, 2, and 45 Area will be routed through the 1,4-Dioxane PTS shed, so that groundwater extracted from the new wells can be pre-treated for 1,4-dioxane as needed prior to treatment by the GWETS.

Both proposed new extraction wells EW-9 and EW-10 will be constructed of four-inch-diameter, schedule 40 polyvinyl chloride (PVC) casing and screened within the “B” aquifer interval.

Extraction well EW-9 will be installed to approximately 30 ft bgs, with a 15-foot screened interval;

EW-10 will be installed to approximately 29 ft bgs, with a 20-foot screened interval.

Modeling efforts have shown that, using the two online, existing extraction wells (EW-3 and EW-

4) and these two new extraction wells, the network will be sufficient to maintain efficient capture of the TCZ while permitting a reasonable cleanup timeframe. Optimization simulations of the pumping strategy indicated that the design pumping rates for wells should be as follows, by extraction well:

• EW-3 1 gpm

• EW-4 1 gpm

• EW-9 1 gpm

• EW-10 1 gpm

Under this approach, the total extraction rate from the Buildings 63, 2, and 45 Area will be 4 gpm.

Figure 12 presents the contaminant particle traces under this pumping scenario; of the 96 particles seeded, only three escape capture. The expected cleanup timeframe under this optimized extraction design, based on fate and transport modeling, is approximately 20 years from now (circa 2037).

However, given the results of the fate and transport modeling, it is expected that, following an initial period effective and efficient treatment, the extraction remedy will reach asymptotic conditions in 10 years, after which it is anticipated that MNA is will be implemented until cleanup levels are achieved, as discussed in Section 2.4. Figure 13 and Figure 14 present the anticipated aerial extent of the TCE plume at the Buildings 63, 2, and 45 Area after 10 years, based on fate and transport modeling, with and without the optimization measures proposed in this Optimization

Plan, respectively, for comparison. For point of reference, without implementing the optimization measure, the fate and transport model forecasts that concentrations of TCE will continue to exceed the MCL at the Buildings 63, 2, and 45 Area for greater than 50 years.

5.3.4 ARIEM Building Area

As discussed in Section 4.0, the recommended alternative remedy for the ARIEM Building Area is continuous groundwater extraction utilizing a new extraction well near MW125B-2 (identified as EW-11) and existing wells MW-182B-4 and MW165B-2, each tied into the existing GWETS.

Figure 9 presents the locations of proposed new and converted extraction wells, as well as the proposed routing of piping from these extraction wells to the GWETS.

Extraction well EW-11 will be constructed of four-inch-diameter, schedule 40 PVC casing, installed to approximately 40 ft bgs, in the “B” aquifer interval, with a 15-foot screen.

Modeling efforts have shown that, using these three extraction wells, the network will be sufficient to maintain efficient capture of the TCZ while permitting a reasonable cleanup timeframe.

Optimization simulations of the pumping strategy indicated that the design pumping rates for wells should be as follows, by extraction well:

• MW-182B-4 1 gpm

• MW165B-2 1 gpm

• EW-11 1 gpm

Under this approach, the total extraction rate from the ARIEM Building Area will be 3 gpm.

Figure 15 presents the contaminant particle traces under this pumping scenario; all particles seeded are captured. The expected cleanup timeframe under this optimized extraction design, based on fate and transport modeling, is approximately 16 years from now (circa 2033).

However, given the results of the fate and transport modeling, it is expected that, following an initial period effective and efficient treatment, the extraction remedy will reach asymptotic conditions in six years, after which it is anticipated that MNA will be implemented until cleanup levels are achieved, as discussed in Section 2.4. Figure 16 presents the anticipated aerial extent of the TCE plume at the ARIEM Building Area after six years, based on fate and transport modeling, given implementation of the optimization measures proposed in this Optimization Plan.

5.4 Individual Components

James.B.Connolly Inserted Text Going to suggest you route the pipes another way. There are two buildings proposed in the area, one south of the ARIEM building which will be taking up about 2/3 of the available space (construction 2018)and another where Bldg 30 is now with a larger footprint (similar to grassy area around Bldg 30. Proposed layout between 30 and 2 will not work. Suggest routing pipes under grass between sidewalk and street along west side of Rich Ave. Continue south until past proposed building footprint, then across parking lot or slope outh of lot to vicinity EW-4. EW-11 location might also need to be moved. Utilities for ARIEM addition proposed in that area. Possible routing south along Greeley Ave would require ConsCom filing, which I prefer to avoid.

James.B.Connolly Sticky Note Is there any option that would reduce or eliminate the >5ug/L area northeast of Bldg 42 in the ~6 year timeframe?

(e.g., more wells, horizontal well/recovery trench) to get more flow and more removal) Shutting system off with exceedance beneath an occupied structure will likely be a hard sell.

Upgrades to individual components of the existing GWETS will be completed to allow for increased flow from additional extraction wells and to replace obsolete control software, computer, and hardware. These upgrades will include:

• Replacement of the existing Programmable Logic Controller (PLC) with a new one that has readily available parts;

• Upgrade of the existing Wonderware Supervisory Control and Data Acquisition (SCADA) program to the most recent version;

• Replacement of the existing control computer with one that is able to efficiently run the most recent version of the Wonderware SCADA program;

• Installation of two multi-bag filter housings to permit increased flow through the system;

• Installation of a higher-pressure transfer pump to allow for full-capacity use of the bag filters and allow for the increased flow through the system;

• Relocation of the MW-96B-4 electrical pull box out of the roadway to avoid future issues related to snow plowing;

• Add controls to allow for automatic switching between bag filter units, increasing uptime;

and

• Replace all flowmeters, and add one at MW-39B-HP2, so that all extraction wells have dedicated meters for measurement of precise flow rates at each location.

James.B.Connolly

Although I want EW-8 repaired and not to wait on funding this optimization, I'd like to add a note here about traffic rating for future and repaired extraction well vaults per our discussion at EW-8. I have the specs on the 36K forklift axle loading if that is a factor.

James.B.Connolly Inserted Text Note that there is still a damaged electrical pull box on the north side of the road southeast of EW-3 and heading towards EW-2. Needs to be fixed.

James.B.Connolly replacement

6.0 OPTIMIZATION OF THE 1,4-DIOXANE PRE-TREATMENT

SYSTEM (PTS)

Following review of the results and conclusions of the optimization investigation, in which the factors affecting the 1,4-Dioxane PTS effectiveness were identified, the Optimization Investigation

Tech Memo (Plexus, 2017a) presented recommendations toward optimizing the 1,4-dioxane remedial approach. The following subsections present the results of 1,4-dioxane groundwater sampling at select monitoring wells around extraction well EW-4 and detail the approaches to implement the related Optimization Investigation Tech Memo recommendations.

6.1 System Condition

The existing 1,4-Dioxane PTS utilizes Fenton’s chemistry to reduce levels of 1,4-dioxane to below the permitted limits. This technology is dependent on the level of iron in the water, introduction of acid to lower the pH to the ideal reaction pH, and addition of hydrogen peroxide. If the iron levels in groundwater change with the introduction of additional wells, as discussed in Section

5.3.3 above, it may be necessary to introduce iron into the groundwater stream to achieve effective treatment.

Other methods of treating 1,4-dioxane include ozone or ultraviolet (UV) light AOPs. Both technologies also create free hydroxyl radicals that destroy 1,4-dioxane. Based on knowledge of the groundwater at the Buildings 63, 2, and 45 Area, utilizing of the ozone AOP is recommended.

High levels of iron from extraction well EW-3 would tend to foul the UV bulbs, requiring greater energy requirements and maintenance. The ozone process will still require hydrogen peroxide, as the existing PTS does, but will not require pH adjustment. Controlled introduce of ozone allows for a better controlled reaction, providing greater reliability for treatment of 1,4-dioxane to below discharge limits.

Prior to final design of the ozone PTS, a bench scale test will be conducted to determine specific ozone dosing, and therefore hydrogen peroxide dosing, air compressor size, oxygen sieve size, and other O&M requirements.

Installation of the ozone PTS will require demolition and disposal of the existing equipment, installation of the PTS, system piping, electrical connections, and piping of new extraction wells through the remote building. The ozone PTS is anticipated to fit within the existing treatment shed.

6.2 Extraction Well EW-4 Flow Re-routing

The Optimization Investigation Tech Memo (Plexus, 2017a) recommended that an evaluation be made regarding potentially re-routing flow from extraction well EW-4 directly to the GWETS

(without first passing through the 1,4-Dioxane PTS) based on 1,4-dioxane concentrations in the area surrounding EW-4. Groundwater at monitoring wells EW-4, PZ144-2, MW159A-2, and

MW103A*4 (refer to Figure 1 for well locations) was low-flow sampled on October 26, 2017, and submitted for analysis of 1,4-dioxane by Method 8270 SIM by ALS Environmental of

James.B.Connolly Inserted Text Electrical capacity in that area is limited, I believe. Will ozone PTS require different voltage or higher current? If so, more pre-planning and expense running power from Building 45.

James.B.Connolly Sticky Note What will impact of ozone be on iron and/or manganese and where will it be seen? Conversely what will impact of Fe/Mn on ozone equipment?

Middletown, Pennsylvania. Refer to Appendix C for equipment calibration forms, and to

Appendix D for groundwater purging and sampling sheets.

Refer to Table 4 for the analytical results by monitoring well, and to Appendix E for the laboratory analytical report for these groundwater samples. All four groundwater samples (EW-4, PZ144-2, MW159A-2, and MW103A*4) were non-detect for 1,4-dioxane, each with limits of detection of

0.039 μg/L or less. The MCP GW-1 standard for 1,4-dioxane is 0.3 μg/L.

Therefore, it is recommended that flow from extraction well EW-4 be re-routed directly to the

GWETS. This re-routing will minimize the dilution of 1,4-dioxane concentrations in groundwater extracted from extraction well EW-3 prior to 1,4-dioxane pre-treatment. The effect will be reduction of flow through the 1,4-Dioxane PTS, increasing mass-removal efficiencies and minimizing the impact of maintenance issues that may occur at the PTS.

James.B.Connolly

Earlier in text, you indicated that potential new extraction wells in the area *might* need to be routed through dioxane PTS or not. Once you start expanded pumping in that area, might EW-4 not need dioxane pretreatment again? Suggest you design piping so that all the Bldg 63, 2 & 45 wells either routed individually through or bypass PTS as needed.

7.0 IMPLEMENTATION

Following approval of the Optimization Plan recommendations, the U.S. Army will prepare and submit an ESD to incorporate the optimized remedy and facilitate implementation of the alternative remedy at the ARIEM Building Area. Concurrently, an LTM Plan update will be prepared and submitted.

Following acceptance of the ESD, a Remedial Action Work Plan (RAWP) will be prepared and submitted. The RAWP will be implemented and subsequent performance monitoring will show the remedy operating at designed, achieving Remedy in Place (RIP). The O&M Manual will be updated to reflect implementation of the Optimization Plan and RAWP. Completion of the RAWP will be documented in a Remedial Action Completion Report. Following RIP, the program will return to Remedial Action Operation (RA[O])—the phase we’re currently in, pre-optimization— which will include system O&M and LTM.

It is anticipated that the ESD and RAWP will be completed and approved in calendar year 2018, RIP will be achieved in calendar year 2019, and RA(O) will be implemented until additional optimization (specifically, the shift to MNA at any Area) is recommended.

James.B.Connolly

Historically, EPA has been unwilling to appear to go backwards…