W911QY25R0003 Questions and Responses Master 06262025.pdf
PDF 77 KB Posted
- Attached to
- Natick Soldier Systems Center Multiple Award Task Order Contract (MATOC) for Construction
- Solicitation number
- W911QY25R0003
About this file
This document contains questions and responses related to the Natick Soldier Systems Center Multiple Award Task Order Contract (MATOC) solicitation W911QY25R0003. The Q&A addresses technical and procedural details for potential bidders, including telecommunications requirements, licensing clarifications, and bid bond specifications. Key clarifications include confirmation of a 20% bid bond requirement, acceptance of master's licenses for electrician and plumber qualifications, and specifications for ductbank and fiber optic cable installations between various buildings at the Natick facility. The responses provide guidance on documentation, design requirements, and specific technical aspects of the proposed construction project, helping potential contractors understand the exact requirements for bidding on this small business set-aside contract.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 Sheet TN-01. Telecommunications Additional requirements. Please clarify scope #1 "From building #45 Basement IT Cabinet to 2nd Floor Basement IT Cabinet". Should this be 2nd Flr. IT Room in Building 3?
Yes, 2nd floor of building #3.
2 Per Questions and answers published in Addendum 7 bid bond is required. What is the percentage of the bid bond? This is traditionally with military 20% and has a specific form. Please consider an extension of bid date as this takes time to process through bonding companies. Please Advise
Bid Bond form has been included as an attachment. The requirement is 20%. Please see RFP amendment 0005 for details. Section 00 21 16
3 Clarification on question 29 & 30 answer. Please advise if a company's master license is acceptable and will meet the Electrician, Plumber & Gas Fitter MA State Licenses requirements.
Yes, masters is acceptable.
4 Per answer to question 25 a letter of consent will need to be provided if utilizing the subcontractors' licenses. The letter of consent form was not provided as part of the bid documents. Please provide.
This shall be provided by the contractor. There is no form, and contractor format is premissible.
5 Per answer to question 243 a bid bond is required for the seed project. please advise which section this should be in.
Please include the Bonding inforation in Volume III-Cost Proposal. Please see RFP amendment 0005 for details.
Section 00 21 16
6 During the site visit, there was no mention of an existing ductbank conduit between Buildings 45 and 2. However, Drawing TN-101 in Addendum #1 indicates that such a connection exists. Please confirm that the only new ductbank required is the segment between Buildings 2 and 65.
Yes, new ductbank between bldg 2 and 65.
7 Does the government intend for the contractor to construct the ductbank between Buildings 45 and 2 based on the information provided on TN-101 (Addendum #1), or if some design work is required prior to construction to define more precise earthwork, concrete, and electrical requirements/details? In other words, should this be considered part of the delegated design required for the task order, along with the fire suppression modifications?
No, design is not required. Ductbank to be minimum 24" below grade in rigid conduit.
8 Please confirm that there is adequate space in the conduits in the tunnel between Building 45 and 3;
and the ductbank between Buildings 45 and 2 (if this indeed is existing).
Existing conduits are able to be utilized to run new fiber optic cable through.
9 What are the cabling requirements between Buildings 45 and 3 (size, pairs)? TN-101 (Addendum #1) does not provide.
(12) Pair single mode fiber cable.
Can you please send me Amendment 1?
RFP Amendment 0001 has been uploaded as an attachement.