W911KB-09-R-0001
PROPOSAL DOCUMENTS
2009-2011 TRANSITIONAL & MAINTENANCE
DREDGING
PORT OF ANCHORAGE
ANCHORAGE, ALASKA
SOLICITATION, OFFER, AND AWARD
SUPPLIES OR SERVICES AND PRICE COSTS
CONSTRUCTION SPECIFICATIONS/STATEMENT OF WORK
INSPECTION AND ACCEPTANCE
SPECIAL CONTRACT REQUIREMENTS
CONTRACT CLAUSES
LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS
INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
APRIL 2009
OPEN TO LARGE AND SMALL BUSINESS
U.S. ARMY ENGINEER DISTRICT, ALASKA
CORPS OF ENGINEERS
P.O. BOX 898
ANCHORAGE, ALASKA 99506-0898
INCREASE PROFIT SUBMIT VE CHANGE
ANCEXP09
PS-1
PROPOSAL SCHEDULE
2009-2011 TRANSITIONAL & MAINTENANCE DREDGING
PORT OF ANCHORAGE, ALASKA
Item No. Description Quantity Unit Unit
Price Amount
BASE ITEMS (2009 - 2010)
0001.
Bid, Performance, and Payment Bond Cost, 2009, complete
1 Job Lump Sum $__________
0002.
Mobilization and Demobilization, 2009, complete
0002AA. First Dredge 1 Job Lump Sum $__________
0002AB. Second Dredge 1 Job Lump Sum $__________
0002AC. Third Dredge (If Needed) 1 Job Lump Sum $__________
0003.
North Extension and Barge Berths, Virgin Materials, Dredging, Disposal, and Acceptance Surveys, 2009-2010, complete
0003AA. First 1,700,000 CY 1,700,000 CY $__________ $__________
0003AB. All Over 1,700,000 CY 200,000 CY $__________ $__________
0004.
Removal and Disposal of Boulders and Other Obstructions with any Dimension Greater Than 8 Feet, complete
EA $__________ $__________
0004AA.
Boulders with any Dimension Greater Than 8 Feet and Less Than 16 Feet
First 25
25 EA $__________ $__________
0004AB.
Boulders with any Dimension Greater Than 8 Feet and Less Than 16 Feet
All Over 25
15 EA $__________ $__________
0004AC. Concrete Pillbox 1 EA $__________ $__________
ANCEXP
PS-2
0005.
Pre-Dredge, Post- Dredge, and Intermediate Hydrographic Surveys, 2009, complete
__________ EA $__________ $__________
OPTIONAL ITEMS (2009)
0006. Optional Partnering Session, 2009, complete 1 Job Lump Sum $__________
Total of Base and Optional Items (0001 thru 0006) for 2009 $__________
OPTIONAL ITEMS (2010)
0007.
Optional Bid, Performance, and Payment Bond Cost, 2010, complete
0008.
Optional Mobilization and Demobilization, 0008AA. First Dredge 1 Job Lump Sum $__________
0008AB. Second Dredge 1 Job Lump Sum $__________
0008AC. Third Dredge (If
0009.
Optional North Extension, Barge Berths, and Existing Port, Maintenance Dredging and Disposal, 0009AA. First 2,000,000 CY 2,000,000 CY $__________ $__________
0009AB. All Over 2,000,000 CY 800,000 CY $__________ $__________
0010.
Optional South Extension, Virgin Materials, Dredging, Disposal, and
0010AA. First 650,000 CY 650,000 CY $__________ $__________
0010AB. All Over 650,000 CY 100,000 CY $__________ $__________
PS-3
0011.
Optional Pre-Dredge, Post-Dredge, and Intermediate Hydrographic Surveys, Total of Optional Items (0007 thru 0011) for 2010 $__________
OPTIONAL ITEMS (2011)
0012.
Optional Bid, Performance, and Payment Bond Cost, 2011, complete
0013.
Optional Mobilization and Demobilization, 0013AA. First Dredge 1 Job Lump Sum $__________
0013AB. Second Dredge 1 Job Lump Sum $__________
0013AC. Third Dredge (If
0014.
If CLIN 0010 is not awarded, Optional South Extension, Virgin Materials, Dredging, Disposal, and
0014AA. First 650,000 CY 650,000 CY $__________ $__________
0014AB. All Over 650,000 CY 100,000 CY $__________ $__________
0015.
Optional North Extension, Barge Berths, South Extension, and Remainder of Existing Port, Maintenance Dredging and Disposal, 0015AA. First 1,000,000 CY 1,000,000 CY $__________ $__________
0015AB. All Over 1,000,000 CY 400,000 CY $__________ $__________
PS-4
0016.
Optional Pre-Dredge, Post-Dredge, and Intermediate Hydrographic Surveys, Total of Optional Items (0013 thru 0017) for 2011
Total of Base plus Optional Items (0001 thru 0017) 2009-2011: $__________
EVALUTIONS OF OFFERS.
1. AWARD: Award will be made in accordance with Section 00120 – EVALUATION FACTORS
FOR AWARD.
2. INCOMPLETE PROPOSALS: Failure to submit an offer on all items in the schedule will result in an incomplete offer and the offer will be rejected. Unit or lump sum prices must be shown for each item within the schedule.
3. EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will govern.
4. SPECIAL BID CONDITION: If a modification to an offer based on unit prices is submitted which provides for a lump sum adjustment to the total offered price, the application of the lump sum adjustment to each unit price in the proposal schedule must be stated. If it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the proposal schedule.
-- End of Proposal Schedule --
2009-2011 TRANSITIONAL AND MAINTENANCE DREDGING ANCHORAGE, AK ANCEXPO9
00 73 00-1
SECTION 00 73 00.00 29 SPECIAL
CONTRACT REQUIREMENTS
INDEX CLAUSE TITLE PAGE
1. (SCR-24) SIGNAL LIGHTS 2
2. (SCR-25) COMMUNICATION SECURITY 2
3. (SCR-40) KEY PERSONNEL, SUBCONTRACTORS AND OUTSIDE ASSOCIATES OR
CONSULTANTS (MAY 2006) 2
4. (SCR-45) SAFETY AND HEALTH REQUIREMENTS MANUAL
EM 385-1-1, U.S. ARMY CORPS OF ENGINEERS 2
5. (SCR-53) GOVERNMENT FURNISHED RFP DRAWINGS, SURVEYS AND
SPECIFICATIONS (JUL 2002) 2
6. (SCR-54) EQUIPMENT OWNERSHIP AND OPERATING EXPENSE
SCHEDULE (See Section 0700, EFAR 52.231-5000) 2
7. (SCR-62) QUALIFICATIONS OF THE CONTRACTOR QUALITY CONTROL
SYSTEMS MANAGER (CQCSM) 3
8. (SCR-72) REQUIREMENTS FOR CONTRACTORS PERFORMANCE EVALUATION 3
9. (SCR-101) DAMAGE TO WORK 3
10. (SCR-113) ENVIRONMENTAL LITIGATION 3
00 73 00-2
SECTION 00 73 00.00 29 SPECIAL
CONTRACT REQUIREMENTS
1. (SCR-24) SIGNAL LIGHTS:
The Contractor shall display signal lights and conduct its operations in accordance with the General Regulations of the Coast Guard and EM 385-1-1 – Safety and Health Requirements Manual governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed; vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules:
International-inland (COMDTINST M16672.2) of 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable.
2. (SCR-25) COMMUNICATION SECURITY:
All communications with DOD organizations are subject to COMSEC review. Contractor personnel shall be aware that telecommunications networks are continually subject to intercept by unfriendly intelligence organizations. The DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from or terminating at DOD organizations. Therefore, civilian Contractor personnel are advised that any time they place a call to or receive a call from Alaska District offices or Resident Engineer offices located on military installations, they are subject to COMSEC procedures. The Contractor will assume the responsibility for ensuring wideand frequent dissemination of the above information to all employees dealing with official DOD information.
3. (SCR-40) KEY PERSONNEL, SUBCONTRACTORS AND OUTSIDE ASSOCIATES OR
CONSULTANTS (May 2006):
During the performance of this contract, no substitutions shall be made for Subcontractors, outside associates, consultants or individuals specifically identified in the Contractor's accepted proposal to perform key functions in the work, unless determined necessary by the Contracting Officer and approved in writing. Proposed substitutes shall have qualifications comparable to those of the persons being replaced.
4. (SCR-45) SAFETY AND HEALTH REQUIREMENTS MANUAL, MA 385-1-1, U.S. ARMY
CORPS OF ENGINEERS:
In accordance with Contract Clause 52.236-13, ACCIDENT PREVENTION, the Contractor shall comply with the latest version of Engineer Manual 385-1-1, including any interim revisions, in effect at the time of the solicitation. EM 385-1-1 and its changes are available at http://www.hq.usace.army.mil/hqhome/. At the HQ homepage, select the tab “About Us”, scroll down to HQ Offices, Then Safety & Occ. Health; at the Safety and Occupational Health Home page, select EM 385-1-1, then most recent dated edition & changes, English Version (controlling with changes), then Changes to EM 385-1-1.
5. (SCR-53) GOVERNMENT-FURNISHED RFP DRAWINGS, SURVEYS AND SPECIFICATIONS
(JUL 02):
This is to clarify that contract clause 252.236-7001, CONTRACT DRAWINGS AND SPECIFICATIONS, refers to any Government-furnished design or design criteria included in the Request for Proposal (RFP).
6. (SCR-54) GOVERNMENT-FURNISHED SPECIFICATIONS AND DRAWINGS FOR
http://www.hq.usace.army.mil/hqhome/
00 73 00-3
CONSTRUCTION (JUL 2003):
This is to clarify that contract clause 252.236-21, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, refers to any specifications and drawings furnished in the Request for Proposal (RFP). The term "specifications" refers to the design criteria or scope of work, in addition to any attached specifications.
7. (SCR-62) QUALIFICATIONS OF THE CONTRACTOR QUALITY CONTROL SYSTEMS MANAGER (CQCSM):
(a) The CQC System Manager (CQCSM) described in Section 01 45 04.00 29 shall be assigned no other duties.
(b) In lieu of the education and experience requirements for the CQC System Manager listed in the CQC Section 01 45 04.00 29, the CQC Systems Manager may qualify provided they have a minimum of 7 years experience in construction quality control and are International Code Council (ICC) certified as a Commercial Building Inspector. For Military Family Housing projects, ICC Residential Building Inspector certification is required in lieu of the Commercial Building Inspector certification.
8. (SCR-72) REQUIREMENTS FOR CONTRACTORS PERFORMANCE EVALUATION
The Government will evaluate the contractor's performance and prepare a performance report using the Construction Contractor Appraisal Support System (CCASS), a web-based system (http://www.cpars.csd.disa.mil/). After an evaluation (interim or final) is generated by the Government, the contractor will have the ability to access, review and comment on the evaluation for a period of 30 days. If the Contractor fails to review, and or comment on the evaluation within the 30-day period, the Contracting Officer will take the appropriate steps to finalize the evaluation without the contractor's comments. It is the sole responsibility of the Contractor to purchase any necessary software to access the electronic system, including a Public Key Infrastructure (PKI) certificate. Details and information to access the system are listed below. The contractor shall provide the Contacting Officer the primary contact name and email address in order to receive the initial email and to access the system. Additional information and training material is available at http://www.cpars.csd.disa.mil/. This web site will give the contractor an understanding of the system and levels of access, the policies and regulations governing CCASS and the electronic workflow with particular attention to the Contractor comment function. Contractor users are required to obtain a PKI certificate in order to log into CCASS. PKI certificates can be purchased from DoD's industries partners under External Certificate Authorities (ECAs). A list of ECAs vendors are available at http://www.cpars.csd.disa.mil/pki_info.htm.
9. (SCR-101) DAMAGE TO WORK:
The responsibility for damage to any part of the permanent work shall be as set forth in the clause of the contract entitled "Permits and Responsibilities".
However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged, and this damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or lump sum prices applicable to any part of such work an equitable adjustment pursuant to Clause, "Changes", of the contract, will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except, as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.
http://www.cpars.csd.disa.mil/).
http://www.cpars.csd.disa.mil/ http://www.cpars.csd.disa.mil/pki_info.htm.
00 73 00-4
10. (SCR-113) ENVIRONMENTAL LITIGATION:
A. If the performance of all or part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the "Suspension of Work" clause of this contract. The period of such suspension, delay or interruption shall be considered unreasonable, and an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof.
B. The term "environmental litigation", as used _herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.
--END OF SPECIAL CONTRACT REQUIREMENTS-
00 73 00-5
SECTION 01 19 40.00 29 Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 19 40.00 29
SPECIAL ITEMS (CIVIL WORKS)
PART 1 GENERAL
1.1 SCOPE
1.2 REFERENCES
1.3 ACCIDENT PREVENTION PLAN
1.3.1 Navigation Safety and Coordination Plan
1.4 FIRE SAFETY
1.5 INSPECTION
1.5.1 General Requirements
1.5.2 Contractor Furnished Equipment, Labor, Materials, and
Transportation
1.5.3 Noncompliance
1.6 EXAMINATION AND ACCEPTANCE
1.6.1 Examination
1.6.2 Acceptance
1.7 CAMP FACILITIES
1.8 UTILITIES
1.9 GOVERNMENT FIELD OFFICE
1.10 PARTNERING
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.1 COORDINATION WITH OTHERS
3.1.1 Traffic
3.2 SURVEYS
3.2.1 Equipment
3.2.2 Quantity Computation Drawings
3.2.3 Plan-View Drawings
3.2.3.1 Government-Furnished
3.2.3.2 Contractor Submittals
3.2.3.3 Surveys
3.2.3.4 Daily Report of Hopper Dredge Operations
3.2.3.5 Field Notes
3.2.4 Existing Monuments
3.2.5 Accuracy
3.2.6 Certification
3.3 EQUIPMENT
3.4 MOBILIZATION AND PROGRESS SCHEDULE
3.5 EQUIPMENT SCHEDULE
3.5.1 Number
3.5.2 Type
3.5.3 Capacity
3.6 PLANT AND EQUIPMENT SCHEDULE
3.7 ATTACHMENTS
-- End of Section Table of Contents --
SECTION 01 19 40.00 29 Page 2
SECTION 01 19 40.00 29
SPECIAL ITEMS (CIVIL WORKS)
PART 1 GENERAL
1.1 SCOPE
Items included in this section cover special features and/or requirements which are not otherwise specified or indicated.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-2-1003 (Jan 2002) Engineering and Design - Hydrographic Surveying
EM 1110-1-1005 (Jan 2007) Engineering and Design -
Control and topographic Surveying
EM 385-1-1 (2008) U.S. Army Corps of Engineers Safety and Health Requirements Manual
1.3 ACCIDENT PREVENTION PLAN
The Contractor shall obtain the Contracting Officer's approval of the Accident Prevention Plan required by EM 385-1-1 prior to start of any work at the project site.
1.3.1 Navigation Safety and Coordination Plan
The Contractor shall submit a Navigation Safety and Coordination Plan as part of the Accident Prevention Plan. This plan shall include but not be limited to temporary lights at night and/or marker buoys during construction, "Notice to Mariners" and coordination with local officials, and reference to applicable U.S. Coast Guard regulations for construction vessels as well as SECTION 19, Floating Plant and Marine Activities, of
EM 385-1-1.
1.3.2 Personal Locator Beacons (PLB) and Automated Identification Systems (AIS)
a. Due to local sea and weather conditions, the contractor is required to provide Activity Hazard Analysis (AHA's) pursuant to Section 01 35 29 - SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS, and must include Personal Locator Beacon procedures in the AHA's for the following:
(1) Personnel working on deck without handrails
(2) Personnel outside the handrails without fall protection
(3) Personal cleaning out drag heads and/or cutterheads
b. Personal Locator Beacons (PLB) and Receiver unit.
SECTION 01 19 40.00 29 Page 3
(1) The Contractor is required to furnish a Receiver unit located on the bridge or cab, on or near the ships helm, but within sight of the mate or operator of the dredge, tug or other floating plant operating the Vessel.
(2) As a minimum, the following personnel will be required to wear Personal Locator Beacons.
(a) All personnel in an area that is not protected by handrails must wear either a PLB or a fall protection system that meets all the requirements of EM 385-1-1. A fall protection system can only be worn where feasible, safe, and practical. Where it is not feasible, safe or practical to provide a fall arrest system, all personnel accessing unguarded decks, shall be equipped with a PLB.
(b) All personnel transiting in small boats including project visitors.
(c) Water quality monitoring crew, including the boat operator.
(d) All personnel actively conducting hydrographic surveys.
(3) Contractor is required to submit their Personal Locator Beacon system for review, prior to work. This can be submitted as part of the Accident Prevention Plan.
(4) The Contractor is required to supply six Personal Locator Beacons to the Government prior to commencement of work. These will be returned to the Contractor after final acceptance. In addition, the Contractor shall provide PLB's to all personnel transiting on their boats including Government visitors.
(5) All Personal Locator Beacons, (including the PLB(s) provided to the Contracting Officer or his representative, that malfunction or break, shall be removed from the project and immediately replaced by the Contractor regardless of the fault or cause. No dredging or disposal will be allowed to occur without the required number of PLB(s) on site. It is recommended that the contractor keep a sufficient number of spare PLB(s) on site to avoid delays in the dredging and disposal, should a PLB malfunction or be damaged. All personnel shall be trained in the use of PLBs. All personnel assigned to the project shall be briefed on the procedure if the system is activated.
(6) Specifications on Personal Locator Beacon (PLB)/ (Emergency Position Indicationg Radiobeacon (EPIRB) and direction/location finder.
(a) Miniature Personal Water Activated 121.5 MHz PLB/ EPIRB (Alerting Unit)
(b) PLB/ EPIRB's must alert a 121.5 MHz Direction finder within two minutes. (Base Unit)
(c) Examples of acceptable units are, Sea Marshall PLB8-LR 'SOS'
SECTION 01 19 40.00 29 Page 4
(alerting unit), Sea Marshall SARfinder 1003(base unit with 'SOS' man overboard alarm and location finder), ACR mini B 300 ILS H2ON EPIRB, ACR Vecta2 Direction Finder, or equivalent.
(7) Single Band Radios for monitoring PLB's. The Contractor shall keep single band radios at the following locations for monitoring the PLB signal. These radios shall be used for no other purpose. In all cases, a monitored radio shall be located within range of all personnel wearing PLBs. The PLB signal will be monitored by the Contractor.
(a) The following sites:
(a) All contractor boats (except the dredge with the base unit)
(b) Contractor's field office(s)
(c) Government office
(d) Government boat
(8) A directional antenna shall be mounted on the Contractor's boat that will be used as a rescue boat.
(9) Automated Identification Systems (AIS). All dredges and assist tugs used on this contract are required to have AIS installed and fully operational prior to the start of work and throughout the life of the contract. The Contractor shall have personnel trained and on-site that meet the U.S. Coast Guard's minimum requirements for the use of AIS.
1.4 FIRE SAFETY
The Contractor shall obtain a permit from the organization having jurisdiction over the job site for any welding or open flame work.
1.5 INSPECTION
1.5.1 General Requirements
The Contractor shall provide, install and maintain any required gauges, ranges, location marks and limit marks in proper order and position.
1.5.2 Contractor Furnished Equipment, Labor, Materials, and Transportation
The Contractor shall immediately furnish, upon the request of the Contracting Officer, the use of such boats, boatmen, laborers, and material forming a part of the ordinary and usual equipment and crew of the dredging plant as required by the Government for inspection of the work and suitable transportation from all points on shore designated by the Contracting Officer to and from the various points of plant. The Contractor shall also furnish 2 VHF handheld radios and/or 2 cellular telephones, as determined by the Contracting Officer, with a local Anchorage number subscribed to a local Anchorage system. The contractor shall also furnish necessary computer equipment and software as specified in SECTIONS 35 20 23 MECHANICAL DREDGE SILENT INSPECTOR and 35 22 24.00 29 HOPPER
DREDGE SILENT INSPECTOR.
1.5.3 Noncompliance
Should the Contractor refuse, neglect, or delay compliance with these
SECTION 01 19 40.00 29 Page 5 requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from any amounts due or to become due the Contractor.
1.6 EXAMINATION AND ACCEPTANCE
1.6.1 Examination
As soon as practicable after completion of each area of dredging, such work shall be thoroughly examined as specified in paragraph SURVEYS herein.
Should any shoals, lumps, or other lack of depth 1 foot or more above Project Depth be disclosed by this examination, the Contractor will be required to remove same.
1.6.2 Acceptance
Acceptance of whole or part of the work and the deductions or corrections of deductions is final, except on evidence of collusion, fraud, or obvious error. The acceptance of a completed section shall not change the time of payment of the retained percentages of the whole or any part of the work.
1.7 CAMP FACILITIES
There are no Government owned camp facilities at the job site for the Contractor's use.
1.8 UTILITIES
The furnishing of water, electricity, and other utilities for work under this contract will be the Contractor's responsibility.
1.9 GOVERNMENT FIELD OFFICE
The Contractor shall provide the Contracting Officer's Representative with access to an office of at least 100 square feet, with a desk, copier;
access to a toilet; and an area to observe the project operations while protected from the weather; to the satisfaction of the Contracting Officer.
All costs shall be borne by the Contractor and included in the contract price.
1.10 PARTNERING
a. The Government intends to encourage the foundation of a cohesive partnership with the Contractor and its subcontractors. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance, intended to achieve completion within budget, on schedule, and in accordance with plans and specifications.
b. This partnership will be bilateral in makeup, and participation will be totally voluntary. Typical partnering costs include travel and per diem for attendees to the partnering site, meeting room rental, and facilitator costs. Implementation of this initiative will be a topic of discussion at the Pre-construction Conference. Any costs associated with implementing this partnership will be agreed to by both parties and will be shared equally subject to the cost limitations of Section 01 22 00.00 10
- MEASUREMENT, PAYMENT, paragraph 1.3.5. To implement this partnership initiative, it is anticipated that within 30 days after Notice to Proceed the Contractor's on-site Project Manager and the Government's on-site representative will attend a partnership development seminar followed by a team-building workshop to be attended by the Contractor's key on-site staff
SECTION 01 19 40.00 29 Page 6 and Government personnel. Follow-up workshops will be held periodically throughout the duration of the contract, as agreed to by both parties.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.1 COORDINATION WITH OTHERS
3.1.1 Traffic
Dredging may be interrupted by vessels maneuvering or moored anywhere within the dredging limits. The Contractor shall keep advised of vessel arrivals and departures and conduct operations so that interference with vessels will not occur. The Contractor's operations shall allow access to and from the Port at all times. All dredging activities, with special emphasis placed upon those dredging activities near the face of the Port and P.O.L. terminal docks, shall be coordinated with the Port of Anchorage Operations Manager at (907) 343-6200. The Contractor shall also coordinate with the Port of Anchorage Operations Manager in the unlikely event that it becomes necessary to have vessels moved out of the way of dredging operations. Pursuant to Contract Clause OTHER CONTRACTS (FAR 52.236-008) of this contract, the Contractor may be required to work in close proximity with other contractors and share the same disposal site. In the event that multiple contractors are required to work within the project limits, work areas for each contractor will be coordinated with the Contracting Officer's Representative and the Port of Anchorage Operations Manager at the required weekly coordination meetings.
3.2 SURVEYS
Surveys shall be performed through the use of an independent certified hydrographic surveyor for the Base requirement and option years 2010 and 2011 (if awarded). The independent certified hydrographic surveyor shall perform pre-dredge, intermediate, acceptance, and post-dredge surveys.
Actual area(s) dredged between successive surveys shall be shown on each successive survey for each type of dredging equipment. Surveys are to be performed on days when ship traffic at the dock face is minimal in order to provide maximum coverage of the project area. Coordination with the Port Operations Manager, the Contractor Officer's Representative, and any other hydrographic survey vessels operating within the Survey Limits is required. All surveys shall be multi-beam and shall be recorded and legibly plotted across the entire survey limits as shown on the contract drawings.
Care shall be taken to show the highest soundings, that is, those with the least depth, on the final drawings.
A pre-dredge survey of the entire survey limits shown on the contract drawings, shall be performed prior to the start of dredging. The Contractor shall notify the Contracting Officer in writing of its intent to perform a pre-dredge survey at least 10 days in advance.
Intermediate surveys shall generally be performed every Wednesday of each week following the pre-dredge survey and going through October 31 of the base year and option years (if awarded). During any hopper dredging operations, intermediate surveys shall also be performed on Mondays and Fridays for payment purposes. Intermediate may be re-scheduled, as needed, from the specified weekly sequence to accurately reflect final dredging conditions.
Acceptance surveys shall be performed as needed by the Contractor following the pre-dredge survey each year and going through October 31 of the base year
SECTION 01 19 40.00 29 Page 7 and option years (if awarded). Acceptance surveys apply only to transitional dredging of virgin materials.
The Post-dredge survey for each year awarded shall be performed within 1 day following completion of final dredging to verify final dredging results for the dredging season. The Contractor shall notify the Contracting Officer in writing of its intent to perform any post-dredge survey at least 3 days in advance. If the results of any post-dredge survey indicate that the specified project depth has not been achieved for any part of the project, dredging shall resume until the condition has been corrected and the post-dredge survey shall be repeated at no additional cost to the Government. This process shall continue until the specified project depth has been achieved.
3.2.1 Equipment and Survey Plan
The Contractor shall provide a survey plan to the Contracting Officer with information on electronic horizontal positioning, recording/depth-finding, and tidal equipment to be used in the work, demonstrating that it will provide surveys meeting all requirements of EM 1110-1-1005 for topographic Surveying and EM 1110-2-1003 for hydrographic surveying. The information provided shall include, as a minimum, the name, model and year of manufacture of the equipment, the electronic frequencies of the horizontal positioning and depth finding equipment, and the manufacturer's stated positioning accuracy and capability. In addition, the Contractor shall provide proof that the vessel to be used is safe and suitable for operation in the waters in which the work is to be performed, and that experienced staff will be used for operation of the vessel as well as the positioning and recording/depth finding equipment.
3.2.2 Quantity Computation Drawings
Quantity computations shall be performed for all surveys. Quantity computations for the pre-dredge survey shall show quantities available to project depth, required over-depth, and maximum pay-line for each area, as well as the total to each depth for all areas, calculated using the composite method and given in cubic yards. For all successive hydrographic surveys, including progress, intermediate and post-dredge, quantity computations shall show the survey-to-survey overall quantity Cut and Fill between surveys, as well as the quantities available to project depth, required over-depth, and maximum pay-line for each area, and the total to each depth for all areas. Calculations shall be performed using the composite method and given in cubic yards.
In addition, each successive survey after the pre-dredge, shall show computations for material removed within the area dredged between successive surveys. Quantity removed to the maximum pay-line for each dredge equipment type shall be shown separately, and likewise any over-dredging within the dredge area for that survey interval shall be computed and recorded. A running count of quantity removed to max pay-line and over-dredged shall be maintained and reported. Calculations shall be performed using the composite method and given in cubic yards.
Preliminary quantities shall be furnished to the Contracting Officer within 2 days after completion of any survey. Final quantities shall be furnished to the Contracting Officer within 10 days after completion of any survey.
3.2.3 Plan-View Drawings
SECTION 01 19 40.00 29 Page 8
3.2.3.1 Government-Furnished
The Contracting Officer will provide the Contractor with a CD-ROM disk(s) containing data in AutoCAD .DWG format meeting all AEC CAD standards, version 3.0, and capable of producing a basic survey contract drawing, complete with area map, borders, title block, and miscellaneous information. The Government will also provide the design control surfaces and the project tidal-geode model (KTD file from Hypac) that shall be used for the duration of this project.
3.2.3.2 Contractor Submittals
3.2.3.3 Surveys
The Contractor shall provide CD(s) of all raw survey data to the Contracting Officer's Representative in the field immediately following any survey. Within 2 days of completing the field data collection for each survey, the Contractor’s independent hydrographic surveyor shall reduce the survey depth soundings to the nearest one-tenth (0.1) foot and transmit AutoCAD (PNEZD comma-delimited ASCII file) point files, Civil 3D AutoCAD DWG data and all supporting files, and quantity computations to the Contracting Officer by email for review. All point file data shall be sorted, edited, tide corrected, and provided in a COGO format ready for used in AutoDESK software and shall not exceed 1.5 megabytes in size. The DWG plots shall include all pertinent title block information and dredged areas as required under SURVEYS above and shall meet all AEC CAD standards, version 3.0. Any information found in error on the Government-furnished drawings provided in paragraph Government-Furnished above, such as vicinity maps, notes, shorelines, floats, docks, navigational aids, control coordinates, etc., shall be replaced with accurate data as it becomes known. Each DWG drawing shall contain all pertinent data respective to it’s survey and be legibly and accurately plotted at the above specified spacing.
Within 10 days after completion of any survey, final survey drawings shall be stamped, signed, and dated by the independent hydrographic surveyor. All AutoCAD files shall be submitted on CD(s) in editable and searchable LAN DESKTOP or CIVIL 3D format for final Government review and signatures. All Surfaces or TINS shall be submitted in XML format. The CD(s) shall also include final volume computations, final Civil 3D data, all supporting files, and all raw survey data.
3.2.3.4 Daily Report of Hopper Dredge Operations
The Contractor shall provide a completed ENG Form 27A - Daily Report of Operations - Hopper Dredges, to the Contracting Officer for each day of hopper dredging. A blank ENG Form 27A is attached at the end of this section.
3.2.3.5 Field Notes
Upon completing any survey, quantity calculations, or plan-view drawings, the Contractor shall furnish the originals of all field notes, notebooks, fathometer data, sorted and corrected electronic point files, and any other records relating to the survey or to the layout of the work to the Contracting Officer. The Contractor shall retain copies of all such materials furnished to the Contracting Officer.
3.2.4 Existing Monuments
SECTION 01 19 40.00 29 Page 9
As part of the pre-dredge survey, the position, elevation, and condition of existing control points mentioned or shown on the drawings shall be verified. The Contracting Officer or his representative shall be notified of any deviations in position or elevation prior to making any corrections to the data. The Contracting Officer or his representative shall also be provided any subsequent corrected survey data of any of the control monuments, which shall be in writing and professionally stamped by a Professional Land Surveyor (PLS) (valid in the State of Alaska).
If, during the performance of the work, the Contractor removes or destroys previously set brass or aluminum survey caps, the survey caps, shall be reinstated by the Contractor at his expense.
3.2.5 Accuracy
All surveys shall conform to requirements specified in the most current USACE Engineering Manual EM 1110-1-1005 (Engineering and Design - Control and Topographic Surveying) and EM 1110-2-1003 (Engineering and Design - Hydrographic Surveying)Specifically, the following accuracies must be obtained:
a. Horizontal Control Point Closure Standard shall be Second Order Class II.
b. Distance closure error, after azimuth adjustment, shall not exceed 1 part in 20,000 parts.
c. Traverse adjustment shall be by the Least Squares method.
d. Levels shall meet NOAA standards for Tidal Bench Mark Ties and USACE Third Order for primary control monuments.
e. Vertical control shall be referenced to Mean Lower Low Water
(MLLW = 0.0 feet) based on the 1983-2001 tidal epoch, holding current published NOAA/CO-OP values.
f. Horizontal control shall be Second Order Class II referenced to Alaska State Plane based on NAD83 in feet holding current NSRS/NGS published values.
3.2.6 Certification
The independent hydrographic surveyor shall be a Professional Land Surveyor (PLS) valid in the State of Alaska, and have current hydrographic certification from the American Congress for Surveying and Mapping (ACSM).
The surveyor shall document at least 3 years of experience in hydrographic surveying of navigable channels.
3.3 EQUIPMENT
The Contractor agrees to keep equipment on the job sufficient to meet the requirements of the work. The equipment shall be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in the specifications and shall be subject to inspection by the Contracting Officer or his representative at all times. The equipment used shall be of a design and have characteristics similar to equipment which has been used successfully for a minimum of 3 years under similar conditions. It shall be the responsibility of the Contractor to prove the equipment has sufficient capacity to accomplish the work in a timely manner without damage to existing port facilities, or obstructing navigation. Prior to the start of any dredging, certifications showing the most recent load and performance test results, recent certification of inspection, and inspector's name, qualifications, and address shall be provided to the Contracting Officer for all cranes/derricks.
SECTION 01 19 40.00 29 Page 10
3.4 MOBILIZATION AND PROGRESS SCHEDULE
The Contractor shall furnish a complete mobilization and projected work progress schedule within 10 days of Notice to Proceed. The equipment listed, manpower to be utilized, and proposed work schedule shall be furnished in sufficient detail to permit determination by the Contracting Officer that the contract requirements can readily be met.
3.5 EQUIPMENT SCHEDULE
The PLANT AND EQUIPMENT SCHEDULE (Sample Letter) attached to this section shall be completed by the Contractor as hereafter described, and submitted within 10 days of receipt of the Notice to Proceed.
3.5.1 Number
For equipment, give identifying number or name.
3.5.2 Type
Under this heading give general description. Sufficient detailed information shall be furnished to properly delineate the proposed equipment and operation.
3.5.3 Capacity
Under this heading, state the estimated capacity of the plant in cubic yards per day when working materials similar to those anticipated in the work, for each location, accounting for the variable distances to disposal sites. No reduction in the stated capacity of the plant employed on the work shall be made except by written permission of the Contracting Officer.
(The measure of the "capacity of the plant" shall be its actual performance on the work which these specifications apply).
3.6 PLANT AND EQUIPMENT SCHEDULE
Minimum Plant To Be Used* Crew Age and No. Type Capacity Requirements Condition Location
*NOTE: In preparing the above tabulation, the Contractor shall insert the following information under the appropriate heading, using a separate line for each major item and additional pages if necessary.
a. Number. For dredges, towboats, and material scows give identifying number or name.
b. Type. Under this heading give description as follows: For clamshell dredges, show bucket capacity in cubic yards, horsepower of hoist engine, type of power, number of swings per hour, and maximum draft, beam, and length of dredge. Show pump size and pump and cutter-head horsepower (hp) for pipeline dredges. For hopper dredges, show number of drag arms including diameter(s) and length(s), hopper capacity, pump size(s) and horsepower, maximum draft, length, beam, and type and horsepower of propulsion. Show maximum draft, length, beam, and hopper capacity of material scows. Show maximum draft, length, beam, and horsepower of towboat. Indicate number of crew required for each item of plant.
3.7 ATTACHMENTS
SAMPLE LETTER
SECTION 01 19 40.00 29 Page 11
Daily Report of Operations – Hopper Dredges (ENG Form 27A)
S A M P L E L E T T E R
Contracting Officer Date________________ Address (as stated in Notice of Award)
SUBJECT: Warranty Provisions, Contract
GENTLEMEN:
This is to acknowledge our responsibility in connection with the warranty provisions of this contract as set forth in the contract specifications.
The following items, equipment or systems furnished or installed under this contract are hereby warranted against defective design, material and workmanship for a period as indicated:
Warranted Item, Identification Warranty Expires at Equipment or System Serial Number, Etc. 11:59 PM Std. Time
Upon receipt of notice from the Government of failure of any part or parts of the warranted item, equipment, or system during the warranty period, the affected part or parts will be replaced promptly with new parts. Such replacement will include furnishing and installing the new part or parts, making all necessary repairs, restoring the item, equipment, or system to the operating condition specified in this contract and making all such tests as are necessary to ensure that there are no remaining defects. Such tests will be performed in the presence of the Representative of the Using Agency indicated below.
We are responsible to _________________________________________ for the warranty provisions of this contract. Correspondence regarding the failure of any of the preceding items, equipment or systems covered by the warranty provisions of this contract should be addressed to:
Telephone Number:
Very truly yours, Signed:
Title:
Organization:
2009-2011 TRANSITIONAL AND MAINTENANCE DREDGING ANCEXP09
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL
1.2 MEASUREMENT
1.2.1 Job or Each
1.2.2 Cubic Yard (CY)
1.2.3 Barge Count
1.2.4 Hopper Dredge
1.3 PAYMENT
1.3.1 Items 0001, 0007 (if awarded), and 0013 (if awarded), Bid, Performance, and Payment Bond Cost
1.3.2 Items 0002AA, 0002AB, 0002AC, 0008AA (if awarded), 0008AB
(if awarded), 0008AC (if awarded), 0014AA (if awarded), 0014AB (if awarded), and 0014AC (if awarded), Mobilization and Demobilization
1.3.3 Items 0003AA, 0003AB, 0009AA (if awarded), 0009AB (if awarded), 0010AA (if awarded), 0010AB (if awarded), 0011AA (if awarded), 0011AB (if awarded), 0015 (if awarded), 0016AA (if awarded), and 0016AB (if awarded), Dredging and Disposal
1.3.4 Items 0004AA (if awarded), 0004AB (if awarded), and 0004AC (if awarded), Removal and Disposal of Boulders and Other Obstructions with any Dimension Greater Than 8 Feet and Less that 16 Feet
1.3.5 Items 0005, 0012 (if awarded), and 0017 (if awarded), Hydrographic Surveys
1.3.6 Item 0006 (if awarded), Partnering Session
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 CONTRACT COST BREAKDOWN
3.2 ATTACHMENT
SECTION 01 22 00.00 10 Page 1
SECTION 01 22 00.00 10
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL
Payment will be made at the contract unit or lump sum price. The price for each item shall constitute full compensation for furnishing all labor, equipment, and materials, and performing all operations necessary to construct and complete the work in accordance with the specifications and drawings. Payment shall be considered as full compensation, notwithstanding that minor features of the work to complete items may not be mentioned.
Deviation in the actual quantity, either above or below the estimated quantity shown, shall not be made a basis for a claim for adjustment in the contract unit price, except as otherwise specified in the CONTRACT CLAUSES under SECTION 00700, FAR 52.211-0018 VARIATIONS IN ESTIMATED QUANTITIES, and EFAR 52.211-5001 VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS.
Work paid for under one item will not be paid for under any other item.
1.2 MEASUREMENT
1.2.1 Job or Each
Items measured as a “Job” or “Each” (EA) will be measured for payment as a complete item.
1.2.2 Cubic Yard (CY)
Measurement for any clamshell dredging shall be accomplished by calculating the net volume of material removed from within the dredging prism as calculated by “Barge Count” below. Measurement for any hopper dredging shall be accomplished by calculating the net volume of material removed from within the dredging prism as calculated by “Hopper Dredge” and “Cutter Head” below. Over-dredging shall be calculated by comparing successive hydrographic surveys and calculating the net volume of material removed as specified in Section 01 19 40.00 - SPECIAL ITEMS, and by “Hopper Dredge” below. Such hydrographic surveys shall also be used to supplement barge counts as specified below. Partial payments for all dredging shall be adjusted to deduct any quantities removed below the maximum pay line or outside the dredging prism as shown on the contract drawings and as determined from hydrographic surveys.
1.2.3 Barge Count
Prior to commencement of any clamshell dredging, the Contractor shall furnish the dimensions, weight, and volume displacement charts for each of the barges or scows to be used on the project. Displacement charts shall be certified by a registered engineer, marine surveyor, or naval architect.
The volume of material placed in hoppers or scows for transport to the disposal site will be calculated. For converting scow or barge displacement to tonnage, salt- water density will be taken as 62.9 pounds per cubic foot based on the average salinity measured over one dredge season. Tonnage will then be converted to volume by using a sediment density factor. The density factor shall be calculated by the Contractor by weighing a sediment sample taken from a full barge or scow. All sampling, weighing, and
SECTION 01 22 00.00 10 Page 2 calculations related to the density factor shall be performed in the presence of the Contracting Officer's Representative. The sediment density factor shall be recalculated by the Contractor whenever the material changes or upon request of the Contracting Officer's Representative. All calculations are subject to approval by the Contracting Officer's Representative. All barges and dumping vessels shall have staff gauges for measuring vessel displacement, placed and mounted in positions approved by the Contracting Officer. All dumping vessels shall be loaded as evenly as possible to obtain uniform distribution of the dredged material. An adjustment in volume will be made to compensate for water trapped in a dumping vessel. If any material remains in the dumping vessel upon its return from the disposal site, displacement measurements will be taken prior to reloading, and an adjustment will be made to the next disposal measurement.
1.2.4 Hopper Dredge
Any Hopper dredging shall be accomplished as follows, with reference to the attachment at the end of this Section:
The Contractor shall provide the following quantity computations of all dredged materials by the average-end-area method on 25 foot spaces.
(1) For each survey interval compute the quantity available to Project Depth, the Required Depth, and Maximum Payline for each designated survey area, including the north and south side slopes.
(2) Find the actual Cut and Fill quantities by doing a survey to survey computation for each survey interval.
(3) Compute the quantity removed by the Hopper Dredge by confining computations to the area covered by the Hopper for each survey interval.
(4) Compute the over dredging for the hopper by comparing the difference of Fill quantity to the Maximum Payline for each survey in their respective intervals. The area for over-dredging is defined by item (3) above.
(5) Shoaling is computed by taking the Maximum Pay Quantity available on the previous survey, subtracting the Maximum Pay Quantity available on the current survey. That quantity is then subtracted from the difference in the raw quantity removed by the Hopper dredge for that interval. This number is the total shoaled amount. The total shoaled amount is multiplied by the ratio of the area covered by the hopper over the area designated for dredging for each interval. The contour for the Maximum Pay depth is used to define the outer limit for both the hopper dredge area and the designated dredge area. A sample computation is attached.
All quantity computations and electronic versions of each survey shall be furnished to the Contracting Officer within four (4) days after the completion of any survey. The preliminary electronic point files (COGO format), used for quantity computations, shall be submitted with the electronic copies of each survey.
1.3 PAYMENT
1.3.1 Items 0001, 0007 (if awarded), and 0013 (if awarded), Bid, Performance, and Payment Bond Cost
SECTION 01 22 00.00 10 Page 3
Payment will be made at the contract lump sum price and shall constitute full compensation for Bid, Performance, and Payment Bond Cost in accordance with SECTION 00700, FAR 52.228-0001 - BID GUARRANTEE, FAR 52.228-0002 - ADDITIONAL BOND SECURITY, and FAR 52.228-0015 - PERFORMANCE AND PAYMENT
BONDS - CONSTRUCTION.
1.3.2 Items 0002AA, 0002AB, 0002AC, 0008AA (if awarded), 0008AB (if awarded), 0008AC (if awarded), 0014AA (if awarded), 0014AB (if awarded), and 0014AC (if awarded), Mobilization and Demobilization
Payment will include transportation of plant, equipment, supplies, and appurtenances to and from the project; assembly of plant; and removal of same after completion of the project.