_Compiled Solicitation Packet.pdf

PDF 822 KB Posted

Attached to
RECOVERY - 2009 -2011 Transitional and Maintenance Dredging at the Port of Anchorage
Solicitation number
W911KB-09-R-0001
Issued by

About this file

Solicitation Documents

View the file

Other files

File Type Posted
W911KB-09-R-0001 Amendment 0004.pdf PDF
W911KB-09-R-0001-0003.pdf PDF
3D-2009 Anch Bndy Model .pdf PDF
REGISTER.pdf PDF
QUESITONS AND ANSWERS.doc DOC document
W911KB-09-R-0001-0002 ANCH.pdf PDF
Trial Dredging Report Port of Anchorage Harbor Deeping.pdf PDF
Trial Dredging Report Port of Anchorage Harbor Deeping.pdf PDF
W911KB-09-R-0001 A00001.pdf PDF
FONSI.pdf PDF
Port of Anchorage- ANCEXP09.pdf PDF
Geotechnical Findings Report Anchorage Harbor Deepening June 2008.pdf PDF
C-103 sheet 4 of 6 newwork 2010 Model —
POA_Pre-Dredge 16 may 08 EXHIBITS 1-4 Sheet 4 —
POA_Pre-Dredge 16 may 08 EXHIBITS 1-4 Sheet 1 —
C-501 sheet 6 of 6 newwork 2010 Details Model —
C-102 sheet 3 of 6 newwork 2010 Model —
Trial Dredging Report Port of Anchorage Harbor Deeping.pdf PDF
Geotechnical Findings Report Anchorage Harbor Deepening June 2008.pdf PDF
POA_Pre-Dredge 16 may 08 EXHIBITS 1-4 Sheet 3 —
C-101 sheet 2 of 6 newwork 2010 Model —
POA_Pre-Dredge 16 may 08 EXHIBITS 1-4 Sheet 2 —
C-104 sheet 5 of 6 newwork 2010 Model —
FONSI.pdf PDF
SPECS PORT OF ANCHORAGE DREDGING.pdf PDF
G-001 sheet 1 of 6 newwork 2010 Cover Model —
W911KB-09-R-0001 PORT OF ANCHORAGE DREDGING.pdf PDF
Port of Anchorage Drawings.pdf PDF
Port of Anchorage Dredging Specifications.pdf PDF
Answered QAs Anchorage Harbor Dredging Preproposal Conference.doc DOC document
2009-2011 Transitional Dredging Port of Anchorage Questions and Answers.pdf PDF
POA_Pre-Dredge 16 may 08 EXHIBITS 1-4 Sheet 2 —
sheet 4 of 4 newwork 2010 DETAILS Model —
ANCHORAGE dtl-site North1 nad83 sheet 3 of 5 Model —
POA_Pre-Dredge 16 may 08 EXHIBITS 1-4 Sheet 3 —
sheet 2 of 4 newwork 2010 Model —
Agenda W911KB-09-R-0001 Anchorage Harbor Dredging 2009-2011.pdf PDF
ANCHORAGE dtl-site South1 nad83 sheet 2 o f 5 Model —
ANCHORAGE dtl-site DETAILS sheet 5 of 5 rev2 Model —
ANCHORAGE dtl-site South2 nad83 sheet 1 of 5 Model —
sheet 3 of 4 newwork 2010 Model —
POA_Pre-Dredge 16 may 08 EXHIBITS 1-4 Sheet 1 —
POA_Pre-Dredge 16 may 08 EXHIBITS 1-4 Sheet 4 —
ANCHORAGE dtl-site North2 nad83 sheet 4 of 5 Model —
W911KB-09-R-0001 Proposal Documents Anchorage Harbor Dredging 2009-2011.pdf PDF
ANCHORAGE Cover 08-09 Model —
sheet 1 of 4 newwork 2010 Model —
Synopsis ANCH.doc DOC document
W911KB-09-R-0001 Drawings.pdf PDF
Geotechnical Findings Report Anchorage Harbor Deepening June 2008.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911KB-09-R-0001

PROPOSAL DOCUMENTS

2009 TRANSITIONAL DREDGING

PORT OF ANCHORAGE

ANCHORAGE, ALASKA

SOLICITATION, OFFER, AND AWARD

SUPPLIES OR SERVICES AND PRICE COSTS

CONSTRUCTION SPECIFICATIONS/STATEMENT OF WORK

INSPECTION AND ACCEPTANCE

SPECIAL CONTRACT REQUIREMENTS

CONTRACT CLAUSES

LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS

INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

DECEMBER 2008

OPEN TO LARGE AND SMALL BUSINESS

U.S. ARMY ENGINEER DISTRICT, ALASKA

CORPS OF ENGINEERS

P.O. BOX 898

ANCHORAGE, ALASKA 99506-0898

INCREASE PROFIT SUBMIT VE CHANGE

ANCEXP09

PS-1

PROPOSAL SCHEDULE

PORT OF ANCHORAGE, ALASKA

Item No. Description Quantity Unit Unit

Price Amount

BASE AND OPTIONAL ITEMS (2009)

0001.

Bid, Performance, and Payment Bond Cost, 2009, complete

1 Job Lump Sum $__________

0002.

Mobilization and Demobilization, 2009, complete

0002AA. Bucket Dredge 1

AND/OR

Job Lump Sum $__________

0002AB. Cutter Head Dredge 1

AND/OR

Job Lump Sum $__________

0002AC Hopper Dredge 1 Job Lump Sum $__________

0003.

North Extension, Bucket Dredging and Disposal, 2009, 0003AA. Zone 1, First 400,000

CY 400,000 CY $__________ $__________

0003AB. Zone 1, All Over

400,000 CY 200,000 CY $__________ $__________

0003AC. Zone 2, First 400,000

0003AD. Zone 2, All Over

0003AE. Zone 3, First 400,000

0003AF. Zone 3, All Over

0003AG. Optional Zone 4, First 300,000 CY 300,000 CY $__________ $__________

0003AH. Optional Zone 4, All Over 300,000 CY 150,000 CY $__________ $__________

0003AI. Optional Zone 5, ANCEXP

PS-2

0003AJ. Optional Zone 5, All

AND/OR

0004.

North Extension, Cutter Head Dredging and Disposal, 2009, 0004AA. Zone 1, First 400,000

0004AB. Zone 1, All Over

0004AC. Zone 2, First 400,000

0004AD. Zone 2, All Over

0004AE. Zone 3, First 400,000

0004AF. Zone 3, All Over

0004AG. Optional Zone 4, 0004AH. Optional Zone 4, All

0004AI. Optional Zone 5, 0004AJ. Optional Zone 5, All

AND/OR

0005.

North Extension, Hopper Dredging and Disposal, 2009, 0005AA. Zone 1, First 400,000

0005AB. Zone 1, All Over

0005AC. Zone 2, First 400,000

PS-3

0005AD. Zone 2, All Over

0005AE. Zone 3, First 400,000

0005AF. Zone 3, All Over

0005AG. Optional Zone 4, 0005AH. Optional Zone 4, All

0005AI. Optional Zone 5, 0005AJ. Optional Zone 5, All

0006.

Optional Barge facility, Bucket Dredging and Disposal, 0006AA. Optional Zone 1, First 150,000 CY 150,000 CY $__________ $__________

0006AB. Optional Zone 1, All Over 150,000 CY 100,000 CY $__________ $__________

0006AC. Optional Zone 2, 0006AD. Optional Zone 2, All

AND/OR

0007.

Optional Barge facility, Cutter Head

0007AA. Optional Zone 1, 0007AB. Optional Zone 1, All

0007AC. Optional Zone 2, PS-4

0007AD. Optional Zone 2, All

AND/OR

0008.

Optional Barge facility, Hopper

0008AA. Optional Zone 1, 0008AB. Optional Zone 1, All

0008AC. Optional Zone 2, 0008AD. Optional Zone 2, All

0009.

Pre-Dredge, Post- Dredge, and Intermediate Hydrographic Surveys, 81 EA $__________ $__________

Total of Base and Optional Items (0001 thru 0009) for 2009: $__________

0010.

Optional Partnering Session, 2009, 1 Job Lump Sum $__________

Total of Base plus Optional Items (0001 thru 0010) 2009: $__________

EVALUTIONS OF OFFERS.

1. AWARD: Award will be made in accordance with Section 00120 – EVALUATION

FACTORS FOR AWARD.

2. INCOMPLETE PROPOSALS: Failure to submit an offer on all items in the schedule will result in an incomplete offer and the offer will be rejected. Unit or lump sum prices must be shown for each item within the schedule.

3. EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will govern.

4. SPECIAL BID CONDITION: If a modification to an offer based on unit prices is submitted which provides for a lump sum adjustment to the total offered price, the application of the lump sum adjustment to each unit price in the proposal schedule must be stated. If it is not stated, the offeror agrees that the lump

PS-5

sum adjustment shall be applied on a pro rata basis to every unit price in the proposal schedule.

-- End of Proposal Schedule --

2009 TRANSITIONAL DREDGING ANCHORAGE, AK ANCEXP09

DRAFT

SECTION 00 73 00.00 29

SPECIAL CONTRACT REQUIREMENTS

INDEX

1. (SCR-8) SUBMITTALS (ER 415-1-10, 15 April 1997):

2. (SCR-10) ANCHORAGE PHYSICAL DATA (APR 1984):

3. (SCR-24) SIGNAL LIGHTS:

4. (SCR-25) COMMUNICATION SECURITY:

5. (SCR-40) KEY PERSONNEL, SUBCONTRACTORS AND OUTSIDE ASSOCIATES OR

CONSULTANTS (May 2006):

6. (SCR-45) SAFETY AND HEALTH REQUIREMENTS MANUAL, EM 385-1-1, U.S. ARMY

CORPS OF ENGINEERS (MAR 06):

7. (SCR-53) GOVERNMENT-FURNISHED RFP DRAWINGS, SURVEYS AND SPECIFICATIONS

(JUL 02):

8. (SCR-54) GOVERNMENT-FURNISHED SPECIFICATIONS AND DRAWINGS FOR

CONSTRUCTION (JUL 2003):

9. (SCR-62) QUALIFICATIONS OF THE CONTRACTOR QUALITY CONTROL SYSTEMS MANAGER

(CQCSM):

10. (SCR-72) REQUIREMENTS FOR CONTRACTORS PERFORMANCE EVALUATION

11. (SCR-101) DAMAGE TO WORK:

12. (SCR-104) CONTINUITY OF WORK:

13. (SCR-113) ENVIRONMENTAL LITIGATION:

ATTACHMENT: CLIMATOLOGICAL SUMMARY

CLIMATOLOGICAL SUMMARY

00 73 00-1

SECTION 00 73 00.00 29

SPECIAL CONTRACT REQUIREMENTS

1. (SCR-8) SUBMITTALS (ER 415-1-10, 15 April 1997):

SEE SECTION 01 33 00: SUBMITTAL PROCEDURES Within 30 days after receipt of Notice to Proceed, the Contractor shall complete and submit to the Contracting Officer, in triplicate, submittal register ENG Form 4288 listing all submittals and dates. In addition to those items listed on ENG Form 4288, the Contractor shall furnish submittals for any deviation from the plans or specifications. The scheduled need dates must be recorded on the document for each item for control purposes. In preparing the document, adequate time (minimum of 30 days) shall be allowed for review and, only when stipulated, approval and possible resubmittal. Scheduling shall be coordinated with the approved progress schedule. The Contractor’s Quality Control representative shall review the listing at least every 30 days and take appropriate action to maintain an effective system. Copies of updated or corrected listing shall be submitted to the Contracting Officer at least every 60 days in the quantity specified. Payment will not be made for any material or equipment which does not comply with contract requirements.

Section 01 33 00 includes an ENG Form 4288 listing technical items the Contractor shall submit to the Contracting Officer, as indicated in the contract requirements.

2. (SCR-10) ANCHORAGE PHYSICAL DATA (APR 1984):

Data and information furnished or referred to below are furnished for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

A. The indications of physical conditions on the drawings and in the specifications are the result of site investigation.

B. Weather Conditions: Weather records for Anchorage are available at the

National Oceanic and Atmospheric Administration Office in Anchorage, Alaska. Each offeror should satisfy himself before submitting his offer as to hazards likely to arise from weather conditions.

C. Transportation Facilities:

1. Water: Anchorage is a port of call for scheduled and unscheduled commercial and military deep and shallow draft vessels in the Alaska trade.

2. Air: Scheduled and charter commercial airline service is available from airports at Anchorage.

3. Land: Anchorage is connected to the primary and secondary state highway system and is accessible from the lower 48 states via the Alaska Highway.

4. Railroad: The Alaska Railroad offers freight service from the 48 contiguous states and Canada via rail barge and trainship through

00 73 00-2

Whittier, and from Seward, to Anchorage and Fairbanks. In addition to the freight service, scheduled passenger service and express service between Anchorage and Fairbanks, and passenger service between Anchorage and Whittier are also available. Fairbanks (including Eielson Air Force Base and Fort Wainwright) is the northern terminus, and Seward and Whittier are the southern terminals of the Alaska Railroad.

D. Weather Data: A Climatological Summary for Anchorage is attached to the end of this section.

3. (SCR-24) SIGNAL LIGHTS:

The Contractor shall display signal lights and conduct its operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed; vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules: International-inland (COMDTINST M16672.2) of 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable.

4. (SCR-25) COMMUNICATION SECURITY:

All communications with DOD organizations are subject to COMSEC review.

Contractor personnel shall be aware that telecommunications networks are continually subject to intercept by unfriendly intelligence organizations.

The DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from or terminating at DOD organizations. Therefore, civilian Contractor personnel are advised that any time they place a call to or receive a call from Alaska District offices or Resident Engineer offices located on military installations, they are subject to COMSEC procedures. The Contractor will assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with official DOD information.

5. (SCR-40) KEY PERSONNEL, SUBCONTRACTORS AND OUTSIDE ASSOCIATES OR

CONSULTANTS (May 2006):

During the performance of this contract, no substitutions shall be made for Subcontractors, outside associates, consultants or individuals specifically identified in the Contractor's accepted proposal to perform key functions in the work, unless determined necessary by the Contracting Officer and approved in writing. Proposed substitutes shall have qualifications comparable to those of the persons being replaced.

6. (SCR-45) SAFETY AND HEALTH REQUIREMENTS MANUAL, EM 385-1-1, U.S. ARMY

CORPS OF ENGINEERS (MAR 06):

In accordance with Contract Clause 52.236-13, ACCIDENT PREVENTION, the Contractor shall comply with the latest version of Engineer Manual 385-1-1, including any interim revisions, in effect at the time of the solicitation. EM

00 73 00-3

385-1-1 and its changes are available at ttp://www.hq.usace.army.mil/hqhome/.

At the HQ homepage, select HQ Offices, scroll to Safety & Occ. Health; at the Safety and Occupational Health Home page, select EM 385-1-1, then most recent dated edition & changes, English Version (controlling with changes), then Changes to EM 385-1-1.

7. (SCR-53) GOVERNMENT-FURNISHED RFP DRAWINGS, SURVEYS AND SPECIFICATIONS

(JUL 02):

This is to clarify that contract clause 252.236-7001, CONTRACT DRAWINGS AND SPECIFICATIONS, refers to any Government-furnished design or design criteria included in the Request for Proposal (RFP).

8. (SCR-54) GOVERNMENT-FURNISHED SPECIFICATIONS AND DRAWINGS FOR

CONSTRUCTION (JUL 2003):

This is to clarify that contract clause 252.236-21, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, refers to any specifications and drawings furnished in the Request for Proposal (RFP). The term "specifications" refers to the design criteria or scope of work, in addition to any attached specifications.

9. (SCR-62) QUALIFICATIONS OF THE CONTRACTOR QUALITY CONTROL SYSTEMS MANAGER

(CQCSM):

(a) The CQC System Manager (CQCSM) described in Section 01 45 04.00 29 shall be assigned no other duties.

(b) In lieu of the education and experience requirements for the CQC System Manager listed in the CQC Section 01 45 04.00 29, the CQC Systems Manager may qualify provided they have a minimum of 7 years experience in construction quality control and are International Code Council (ICC) certified as a Commercial Building Inspector. For Military Family Housing projects, ICC Residential Building Inspector certification is required in eu of the Commercial Building Inspector certification. li

10. (SCR-72) REQUIREMENTS FOR CONTRACTORS PERFORMANCE EVALUATION

The Government will evaluate the contractor’s performance and prepare a performance report using the Construction Contractor Appraisal Support System (CCASS), a web-based system (http://www.cpars.csd.disa.mil/). After an evaluation (interim or final) is generated by the Government, the contractor will have the ability to access, review and comment on the evaluation for a period of 30 days. If the Contractor fails to review, and or comment on the evaluation within the 30-day period, the Contracting Officer will take the appropriate steps to finalize the evaluation without the contractor’s comments. It is the sole responsibility of the Contractor to purchase any necessary software to access the electronic system, including a Public Key Infrastructure (PKI) certificate. Details and information to access the system are listed below. The contractor shall provide the Contacting Officer the primary contact name and email address in order to receive the initial email and to access the system. Additional information and training material is available at http://www.cpars.csd.disa.mil/. This web site will give the contractor an understanding of the system and levels of access, the policies and regulations governing CCASS and the electronic workflow with particular attention to the Contractor comment function. Contractor users are required to obtain a PKI certificate in order to log into CCASS. PKI certificates can

00 73 00-4 be purchased from DoD’s industries partners under External Certificate Authorities (ECAs). A list of ECAs vendors are available at http://www.cpars.csd.disa.mil/pki_info.htm.

11. (SCR-101) DAMAGE TO WORK:

The responsibility for damage to any part of the permanent work shall be as set forth in the clause of the contract entitled “Permits and Responsibilities”. However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or lump sum prices applicable to any part of such work an equitable adjustment pursuant to Clause, “Changes”, of the contract, will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except, as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor’s expense, regardless of the cause of such damage.

12. (SCR-104) CONTINUITY OF WORK:

No payment will be made for work done in any area designated by the Contracting Officer until the full depth required under the contract is secured in the whole or such area, unless prevented by ledge rock, nor will payment be made for excavation in any area not adjacent to and in prolongation of areas where full depth has been secured except by decision of the Contracting Officer. Should any such nonadjacent area be excavated to full depth during the operations carried on under the contract, payment for all work therein may be deferred until the required depth has been made in the area intervening. The Contractor may be required to suspend dredging at any time when for any reason the gages or ranges cannot be seen or properly followed.

13. (SCR-113) ENVIRONMENTAL LITIGATION:

A. If the performance of all or part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or subcontractor at any tier not required by the terms of this contract.

If it is determined that the order is not due in any part to acts or omissions of the Contractor or a subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the “Suspension of Work” clause of this contract. The period of such suspension, delay or interruption shall be considered unreasonable, and an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof.

00 73 00-5

B. The term “environmental litigation”, as used herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.

ATTACHMENT: CLIMATOLOGICAL SUMMARY

00 73 00-6

CLIMATOLOGICAL SUMMARY

ANCHORAGE, ALASKA

Mean Annual 35° F

Highest Recorded 86° F Jun 1953

Lowest Recorded ‐38° F Feb 1947

Maximum Freezing Index 3278° Days 1955-1956

T e m p e r a t u r e

F

Maximum Thaw Index 3836° Days 1957

Mean Annual 14.74”

Mean Annual Snowfall (inches) 70.6”

Maximum Monthly 5.43” Sep 1961

Maximum Monthly Mean 2.50” September

Maximum Rainfall (24-hr Period) 2.06” Jul 1956

Maximum Snowfall (24-hr Period) 17.7” Dec 1955P r e c i p i t a t i o n i n c h e s

Maximum Monthly Snowfall 48.5” Feb 1955

Mean Hourly Speed 6.7 mph

Prevailing Direction N

Maximum Velocity 109 mph W i d

Direction Maximum Velocity NNE Feb 2004

Clear 64

Partly Cloudy 65

S u n r i

S u n s t

Cloudy 236

Precipitation 0.01 inch or more 115

Snow, Sleet, or Hail 1.0 inch or more 22

Heavy Fog 26

Thunderstorms 1

Greater than or Equal to 70° F 15

M a x

T m p

Less than or Equal to 32° F 113

Less than or Equal to 32° F 100

M E A N S

A N D

E X T R E M E S

F O R

P E R I O D

O F

R E C O R D

A n u a l

M e a n

N u m b e r o f

D a y

M i

T m p

Less than or Equal to 0° F 37

--END OF SPECIAL CONTRACT REQUIREMENTS--

00 73 00-7

2009 TRANSITIONAL DREDGING ANCEXP09

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 19 40.00 29 SPECIAL ITEMS (CIVIL WORKS)

01 22 00.00 10 MEASUREMENT AND PAYMENT

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR

CONTAMINATED SITES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 01.10 USACE QUALITY CONTROL SYSTEM (QCS)

01 45 04.00 29 CONTRACTOR QUALITY CONTROL

01 57 20.00 10 ENVIRONMENTAL PROTECTION

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 24.00 29 MAINTENANCE DREDGING

35 22 24.00 29 HOPPER DREDGE SILENT INSPECTOR

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 19 40.00 29

SPECIAL ITEMS (CIVIL WORKS)

PART 1 GENERAL

1.1 SCOPE

1.2 REFERENCES

1.3 ACCIDENT PREVENTION PLAN

1.3.1 Navigation Safety and Coordination Plan

1.4 FIRE SAFETY

1.5 INSPECTION

1.5.1 General Requirements

1.5.2 Contractor Furnished Equipment, Labor, Materials, and

Transportation

1.5.3 Noncompliance

1.6 EXAMINATION AND ACCEPTANCE

1.6.1 Examination

1.6.2 Acceptance

1.7 CAMP FACILITIES

1.8 UTILITIES

1.9 GOVERNMENT FIELD OFFICE

1.10 PARTNERING

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 COORDINATION WITH OTHERS

3.1.1 Traffic

3.2 SURVEYS

3.2.1 Equipment

3.2.2 Quantity Computation Drawings

3.2.3 Plan-View Drawings

3.2.3.1 Government-Furnished

3.2.3.2 Contractor Submittals

3.2.3.3 Surveys

3.2.3.4 Daily Report of Hopper Dredge Operations

3.2.3.5 Field Notes

3.2.4 Existing Monuments

3.2.5 Accuracy

3.2.6 Certification

3.3 EQUIPMENT

3.4 MOBILIZATION AND PROGRESS SCHEDULE

3.5 EQUIPMENT SCHEDULE

3.5.1 Number

3.5.2 Type

3.5.3 Capacity

3.6 PLANT AND EQUIPMENT SCHEDULE

3.7 ATTACHMENTS

SECTION 01 19 40.00 29 Page 1

-- End of Section Table of Contents --

SECTION 01 19 40.00 29 Page 2

SECTION 01 19 40.00 29

SPECIAL ITEMS (CIVIL WORKS)

PART 1 GENERAL

1.1 SCOPE

Items included in this section cover special features and/or requirements which are not otherwise specified or indicated.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 1110-2-1003 (Jan 2002) Engineering and Design - Hydrographic Surveying

EM 385-1-1 (1996) U.S. Army Corps of Engineers Safety and Health Requirements Manual

1.3 ACCIDENT PREVENTION PLAN

The Contractor shall obtain the Contracting Officer's approval of the Accident Prevention Plan required by EM 385-1-1 prior to start of any work at the project site.

1.3.1 Navigation Safety and Coordination Plan

The Contractor shall submit a Navigation Safety and Coordination Plan as part of the Accident Prevention Plan. This plan shall include but not be limited to temporary lights at night and/or marker buoys during construction, "Notice to Mariners" and coordination with local officials, and reference to applicable U.S. Coast Guard regulations for construction vessels as well as SECTION 19, Floating Plant and Marine Activities, of

EM 385-1-1.

1.4 FIRE SAFETY

The Contractor shall obtain a permit from the organization having jurisdiction over the job site for any welding or open flame work.

1.5 INSPECTION

1.5.1 General Requirements

The Contractor shall install and maintain any required gauges, ranges, location marks and limit marks in proper order and position.

SECTION 01 19 40.00 29 Page 3

1.5.2 Contractor Furnished Equipment, Labor, Materials, and Transportation

The Contractor shall furnish, upon the request of the Contracting Officer, the use of such boats, boatmen, laborers, and material forming a part of the ordinary and usual equipment and crew of the dredging plant as required by the Government for inspection of the work and suitable transportation from all points on shore designated by the Contracting Officer to and from the various points of plant. Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from any amounts due or to become due the Contractor. The Contractor shall also furnish 2 VHF handheld radios and/or 2 cellular telephones, as determined by the Contracting Officer, with a local Anchorage number subscribed to a local Anchorage system. The contractor shall also furnish necessary computer equipment and software as specified in SECTION 35 22 24.00 29 HOPPER DREDGE SILENT INSPECTOR.

1.5.3 Noncompliance

Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from any amounts due or to become due the Contractor.

1.6 EXAMINATION AND ACCEPTANCE

1.6.1 Examination

As soon as practicable after completion of each phase of dredging, such work shall be thoroughly examined as specified in paragraph SURVEYS herein.

Should any shoals, lumps, or other lack of depth 1 foot or more above Project Depth be disclosed by this examination, the Contractor will be required to remove same.

1.6.2 Acceptance

Acceptance of whole or part of the work and the deductions or corrections of deductions made thereon will not be reopened after having once been made, except on evidence of collusion, fraud, or obvious error. The acceptance of a completed section shall not change the time of payment of the retained percentages of the whole or any part of the work.

1.7 CAMP FACILITIES

There are no Government owned camp facilities at the job site for the Contractor's use.

1.8 UTILITIES

The furnishing of water, electricity, and other utilities for work under this contract will be the Contractor's responsibility.

1.9 GOVERNMENT FIELD OFFICE

The Contractor shall provide the Contracting Officer's Representative with access to an office, with a desk, copier; access to a toilet; and an area to observe the project operations while protected from the weather; to the satisfaction of the Contracting Officer. All costs shall be borne by the Contractor and included in the contract price.

SECTION 01 19 40.00 29 Page 4

1.10 PARTNERING

a. The Government intends to encourage the foundation of a cohesive partnership with the Contractor and its subcontractors. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance, intended to achieve completion within budget, on schedule, and in accordance with plans and specifications.

b. This partnership will be bilateral in makeup, and participation will be totally voluntary. Typical partnering costs include travel and per diem for attendees to the partnering site, meeting room rental, and facilitator costs. Implementation of this initiative will be a topic of discussion at the Pre-construction Conference. Any costs associated with implementing this partnership will be agreed to by both parties and will be shared equally subject to the cost limitations of Section 01 22 00.00 10 - MEASUREMENT, PAYMENT, AND CONTRACT COST BREAKDOWN, paragraph 1.3.5. To implement this partnership initiative, it is anticipated that within 30 days after Notice to Proceed the Contractor's on-site Project Manager and the Government's on-site representative will attend a partnership development seminar followed by a team-building workshop to be attended by the Contractor's key on-site staff and Government personnel. Follow-up workshops will be held periodically throughout the duration of the contract, as agreed to by both parties.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.1 COORDINATION WITH OTHERS

3.1.1 Traffic

Dredging may be interrupted by vessels maneuvering or moored anywhere within the dredging limits. The Contractor shall keep advised of vessel arrivals and departures and conduct operations so that interference with vessels will not occur. The Contractor's operations shall allow access to and from the Port at all times. All dredging activities, with special emphasis placed upon those dredging activities near the face of the Port and P.O.L. terminal docks, shall be coordinated with the Port of Anchorage Operations Manager at (907) 343-6200. The Contractor shall also coordinate with the Port of Anchorage Operations Manager in the unlikely event that it becomes necessary to have vessels moved out of the way of dredging operations. Pursuant to Contract Clause OTHER CONTRACTS (FAR 52.236-008) of this contract, the Contractor may be required to work in close proximity to another contractor and share the same disposal site. In the event that multiple contractors are required to work within the project limits, work areas for each contractor will be coordinated with the Contracting Officer's Representative and the Port of Anchorage Operations Manager at the required weekly coordination meetings.

3.2 SURVEYS

Surveys shall be performed through the use of an independent certified hydrographic surveyor for the basic requirement and option year 2009 (if awarded). The independent certified hydrographic surveyor shall perform pre-dredge, intermediate, and post-dredge surveys. Actual area(s) dredged between successive surveys shall be shown on each successive survey for

SECTION 01 19 40.00 29 Page 5 each type of dredging equipment, as appropriate. Surveys are to be performed on days when ship traffic at the dock face is minimal in order to provide maximum coverage of the project area. Coordination with the Port Operations Manager, the Contractor Officer's Representative, and any other hydrographic survey vessels operating within the Survey Limits is essential. All surveys shall have soundings taken at 100 foot intervals perpendicular to the project baseline and shall be recorded and legibly plotted across the entire survey limits as shown on the contract drawings;

except that within areas A and C, additional soundings shall be taken parallel to the dock face at 25 foot intervals, sorted to show the highest (shoal biased) soundings, and shall be legibly plotted along the lines of survey. Care shall be taken to show the highest soundings, that is, those with the least depth, on the final drawings. Additional survey soundings shall be recorded and plotted where topographic anomalies or obstacles of 2 feet or greater are encountered.

A pre-dredge survey of the entire survey limits shown on the contract drawings, shall be performed prior to the start of dredging. The Contractor shall notify the Contracting Officer in writing of its intent to perform a pre-dredge survey at least 10 days in advance.

Intermediate surveys shall generally be performed every Wednesday of each week following the pre-dredge survey and going through October 31 of the base year and option year (if awarded). Intermediate may be re-scheduled, as needed, from the specified weekly sequence to accurately reflect final dredging conditions.

The Post-dredge survey for each year awarded shall be performed within 1 day following completion of final dredging to verify final dredging results for the dredging season. The Contractor shall notify the Contracting Officer in writing of its intent to perform any post-dredge survey at least 3 days in advance. If the results of any post-dredge survey indicate that the specified project depth has not been achieved for any part of the project, dredging shall resume until the condition has been corrected and the post-dredge survey shall be repeated at no additional cost to the Government. This process shall continue until the specified project depth has been achieved.

3.2.1 Equipment

The Contractor shall provide information to the Contracting Officer on electronic, horizontal positioning and recording/depth finding equipment to be used in the work, demonstrating that it will provide surveys meeting all requirements of EM 1110-2-1003 for hydrographic surveying. The information provided shall include, as a minimum, the name, model and year of manufacture of the equipment, the electronic frequencies of the horizontal positioning and depth finding equipment, and the manufacturer's stated positioning accuracy and capability. In addition, the Contractor shall provide proof that the vessel to be used is safe and suitable for operation in the waters in which the work is to be performed, and that experienced staff will be used for operation of the vessel as well as the positioning and recording/depth finding equipment

3.2.2 Quantity Computation Drawings

Quantity computations shall be performed for all surveys. Quantity computations for the pre-dredge survey shall show quantities available to project depth, required over-depth, and maximum pay-line for each area, as well as the total to each depth for all areas, calculated using the average-end-area method and given in cubic yards. For all successive

SECTION 01 19 40.00 29 Page 6 hydrographic surveys, including progress, intermediate and post-dredge, quantity computations shall show the survey-to-survey overall quantity Cut and Fill between surveys, as well as the quantities available to project depth, required over-depth, and maximum pay-line for each area, and the total to each depth for all areas. Calculations shall be performed using the average-end-area method and given in cubic yards.

In addition, each successive survey after the pre-dredge, shall show computations for material removed within the area dredged between successive surveys. Quantity removed to the maximum pay-line for each dredge equipment type shall be shown separately, and likewise any over-dredging within the dredge area for that survey interval shall be computed and recorded. A running count of quantity removed to max pay-line and over-dredged shall be maintained and reported. Calculations shall be performed using the average-end-area method and given in cubic yards.

Preliminary quantities shall be furnished to the Contracting Officer within 2 days after completion of any survey. Final quantities shall be furnished to the Contracting Officer within 10 days after completion of any survey.

3.2.3 Plan-View Drawings

3.2.3.1 Government-Furnished

The Contracting Officer will provide the Contractor with a CD-ROM disk(s) containing data in the AutoCAD .DWG format capable of producing a basic survey contract drawing, complete with area map, borders, title block, and miscellaneous information.

3.2.3.2 Contractor Submittals

3.2.3.3 Surveys

The Contractor shall provide CD(s) of all raw survey data to the Contracting Officer's Representative in the field immediately following any survey. Also following each survey, the Contractor shall reduce the survey depth soundings for all surveys to the nearest one-tenth (0.1) foot and plot them onto plan-view mylars computer-generated by the independent hydrographic surveyor from the CD(s) provided. All pertinent title block information shall be printed within the block. Dredged areas shall be shown as required under SURVEYS above. Proposed title block information shall be submitted to the Contracting Officer in advance for approval. Any information found in error on the Government-furnished drawings provided in paragraph Government-Furnished above, such as vicinity maps, notes, shorelines, floats, docks, navigational aids, control coordinates, etc., shall be eradicated and replaced with accurate data as it becomes known.

Each drawing shall contain all pertinent data ink-plotted by machine legibly and accurately at above spacing. Final survey drawings shall be signed, dated and stamped by the independent hydrographic surveyor, complete and ready for Government review and signatures. Survey drawings shall also be submitted on CD(s)in AutoCAD DWG format as specified above, capable of reproducing the complete plotted survey drawings. Preliminary drawings in DWF format and point files shall be submitted electronically by email within 2 days after completion of any survey. All point file data shall be sorted, edited, tide corrected, and provided in a COGO format ready for used in AutoDESK software. An edited point file shall not exceed

1.5 megabytes in size. Final drawings and CD(s), including point files, shall be submitted within 10 days after completion of any survey.

SECTION 01 19 40.00 29 Page 7

3.2.3.4 Daily Report of Hopper Dredge Operations

The Contractor shall provide a completed ENG Form 27A - Daily Report of Operations - Hopper Dredges, to the Contracting Officer for each day of hopper dredging. A blank ENG Form 27A is attached at the end of this section.

3.2.3.5 Field Notes

Upon completing any survey, quantity calculations, or plan-view drawings, the Contractor shall furnish the originals of all field notes, notebooks, fathometer data, sorted and corrected electronic point files, and any other records relating to the survey or to the layout of the work to the Contracting Officer. The Contractor shall retain copies of all such materials furnished to the Contracting Officer.

3.2.4 Existing Monuments

As part of the pre-dredge survey, the position, elevation, and condition of existing control points mentioned or shown on the drawings shall be verified.

If, during the performance of the work, the Contractor removes or destroys previously set brass or aluminum survey caps, the survey caps, shall be reinstated by the Contractor at his expense.

3.2.5 Accuracy

All surveys for layout, quantities and final As-Built conditions shall conform to standard third order traverse requirements as specified in Field Manual FM 3-34.331, , Ch. 1. The following accuracies shall be attained:

a. Azimuth closure shall not exceed 5 seconds per angle in traverse.

b. Distance closure error, after azimuth adjustment, shall not exceed 1 part in 5,000 parts.

c. Traverse adjustment shall be by the Compass Rule.

d. Levels shall be to third order standards.

e. Vertical control shall be in feet and refer to Mean Lower Low Water Datum (MLLW = 0.0 feet).

f. Horizontal control shall be as stated on the individual contract drawings.

3.2.6 Certification

The independent hydrographic surveyor shall be a State of Alaska Registered Land Surveyor (RLS) or have current hydrographic certification from the American Congress for Surveying and Mapping (ACSM), valid in the State of Alaska. The surveyor shall document at least 3 years of experience in hydrographic surveying of navigable channels.

3.3 EQUIPMENT

The Contractor agrees to keep equipment on the job sufficient to meet the requirements of the work. The equipment shall be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in the specifications and shall be subject to inspection by the Contracting Officer or his representative at all times. The equipment used shall be of a design and have characteristics similar to equipment which has been used successfully for a minimum of 3 years under similar

SECTION 01 19 40.00 29 Page 8 conditions. Any clamshell bucket shall be at least 14 cubic yard capacity and a minimum weight of 50,000 pounds. It shall be the responsibility of the Contractor to prove the equipment has sufficient capacity to accomplish the work in a timely manner without damage to existing port facilities, or obstructing navigation. Prior to the start of any dredging, certifications showing the most recent load and performance test results, recent certification of inspection, and inspector's name, qualifications, and address shall be provided to the Contracting Officer for all cranes/derricks.

3.4 MOBILIZATION AND PROGRESS SCHEDULE

The Contractor shall furnish a complete mobilization and projected work progress schedule within 10 days of Notice to Proceed. The equipment listed, manpower to be utilized, and proposed work schedule shall be furnished in sufficient detail to permit determination by the Contracting Officer that the contract requirements can readily be met.

3.5 EQUIPMENT SCHEDULE

The PLANT AND EQUIPMENT SCHEDULE attached to this section shall be completed by the Contractor as hereafter described, and submitted within 10 days of receipt of the Notice to Proceed.

3.5.1 Number

For equipment, give identifying number or name.

3.5.2 Type

Under this heading give general description. Sufficient detailed information shall be furnished to properly delineate the proposed equipment and operation.

3.5.3 Capacity

Under this heading, state the estimated capacity of the plant in cubic yards per day when working materials similar to those anticipated in the work, for each location, accounting for the variable distances to disposal sites. No reduction in the stated capacity of the plant employed on the work shall be made except by written permission of the Contracting Officer.

(The measure of the "capacity of the plant" shall be its actual performance on the work which these specifications apply).

3.6 PLANT AND EQUIPMENT SCHEDULE

Minimum Plant To Be Used * Crew Age and No. Type Capacity Requirements Condition Location

*NOTE: In preparing the above tabulation, the Contractor shall insert the following information under the appropriate heading, using a separate line for each major item and additional pages if necessary.

a. Number. For dredges, towboats, and material scows give identifying number or name.

b. Type. Under this heading give description as follows: For clamshell dredges, show bucket capacity in cubic yards, horsepower of hoist engine, SECTION 01 19 40.00 29 Page 9 type of power, number of swings per hour, and maximum draft, beam, and length of dredge. Show pump size and pump and cutter-head horsepower (hp) for pipeline dredges. For hopper dredges, show number of drag arms including diameter(s) and length(s), hopper capacity, pump size(s) and horsepower, maximum draft, length, beam, and type and horsepower of propulsion. Show maximum draft, length, beam, and hopper capacity of material scows. Show maximum draft, length, beam, and horsepower of towboat. Indicate number of crew required for each item of plant.

3.7 ATTACHMENTS

SAMPLE LETTER

SECTION 01 19 40.00 29 Page 10

S A M P L E L E T T E R

Contracting Officer Date__________________ Address (as stated in Notice of Award)

SUBJECT: Warranty Provisions, Contract

GENTLEMEN:

This is to acknowledge our responsibility in connection with the warranty provisions of this contract as set forth in the contract specifications.

The following items, equipment or systems furnished or installed under this contract are hereby warranted against defective design, material and workmanship for a period as indicated:

Warranted Item, Identification Warranty Expires at Equipment or System Serial Number, Etc. 11:59 PM Std. Time

Upon receipt of notice from the Government of failure of any part or parts of the warranted item, equipment, or system during the warranty period, the affected part or parts will be replaced promptly with new parts. Such replacement will include furnishing and installing the new part or parts, making all necessary repairs, restoring the item, equipment, or system to the operating condition specified in this contract and making all such tests as are necessary to ensure that there are no remaining defects. Such tests will be performed in the presence of the Representative of the Using Agency indicated below.

We are responsible to ______________________________________ for the warranty provisions of this contract. Correspondence regarding the failure of any of the preceding items, equipment or systems covered by the warranty provisions of this contract should be addressed to:

___________________________________ Telephone Number:

Very truly yours, Signed: ________________________________________ Title: _________________________________________ Organization: __________________________________

SECTION 01 19 40.00 29 Page 11

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL

1.2 MEASUREMENT

1.2.1 Job, Each, or Day

1.2.2 Cubic Yard (CY)

1.2.3 Barge Count

1.2.4 Hopper Dredge

1.3 PAYMENT

1.3.1 Items 0001, Bid, Performance, and Payment Bond Cost

1.3.2 Mobilization and Demobilization

1.3.3 Dredging and Disposal

1.3.4 Item 0009 Hydrographic Surveys

1.3.5 Item Optional 0010 (if awarded), Partnering Session

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3.1 CONTRACT COST BREAKDOWN

3.2 ATTACHMENT

SECTION 01 22 00.00 10 Page 1

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL

Payment will be made at the contract unit or lump sum price. The price for each item shall constitute full compensation for furnishing all labor, equipment, and materials, and performing all operations necessary to construct and complete the work in accordance with the specifications and drawings. Payment shall be considered as full compensation, notwithstanding that minor features of the work to complete items may not be mentioned.

Deviation in the actual quantity, either above or below the estimated quantity shown, shall not be made a basis for a claim for adjustment in the contract unit price, except as otherwise specified in the CONTRACT CLAUSES under SECTION 00700, FAR 52.211-0018 VARIATIONS IN ESTIMATED QUANTITIES, and EFAR 52.212-5001 VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS.

Work paid for under one item will not be paid for under any other item.

1.2 MEASUREMENT

1.2.1 Job, Each, or Day

Items measured as a "Job", "Each" (EA), or "Day" will be measured for payment as a complete item.

1.2.2 Cubic Yard (CY)

Measurement for clamshell dredging shall be accomplished by calculating the net volume of material removed from within the dredging prism as calculated by "Barge Count" below. Measurement for cutter head and hopper dredging shall be accomplished by calculating the net volume of material removed from within the dredging prism as calculated by "Hopper Dredge" and "Cutter Head" below. Over-dredging shall be calculated by computing by comparing successive hydrographic surveys and calculating the net volume of material removed as specified in Section 01 19 40.00 - SPECIAL ITEMS and by "Hopper Dredge" below. Such hydrographic surveys shall be used to supplement barge counts and hopper dredging as specified below. Partial payments for all dredging shall be adjusted to deduct any quantities removed below the maximum pay line or outside the dredging prism as shown on the contract drawings and as determined from hydrographic surveys.

1.2.3 Barge Count

Prior to commencement of any clamshell dredging, the Contractor shall furnish the dimensions, weight, and volume displacement charts for each of the barges or scows to be used on the project. Displacement charts shall be certified by a registered engineer, marine surveyor, or naval architect.

The volume of material placed in hoppers or scows for transport to the disposal site will be calculated. For converting scow or barge displacement to tonnage, salt- water density will be taken as 64.0 pounds per cubic foot. Tonnage will then be converted to volume by using a sediment density factor. The density factor shall be calculated by the Contractor by

SECTION 01 22 00.00 10 Page 2 weighing a sediment sample taken from a full barge or scow. All sampling, weighing, and calculations related to the density factor shall be performed in the presence of the Contracting Officer's Representative. The sediment density factor shall be recalculated by the Contractor whenever the material changes or upon request of the Contracting Officer's Representative. All calculations are subject to approval by the Contracting Officer's Representative. All barges and dumping vessels shall have staff gauges for measuring vessel displacement, placed and mounted in positions approved by the Contracting Officer. All dumping vessels shall be loaded as evenly as possible to obtain uniform distribution of the dredged material.

An adjustment in volume will be made to compensate for water trapped in a dumping vessel. If any material remains in the dumping vessel upon its return from the disposal site, displacement measurements will be taken prior to reloading, and an adjustment will be made to the next disposal measurement.

1.2.4 Hopper Dredge

Hopper dredging shall be accomplished as follows, with reference to the attachments at the end of this Section:

The Contractor shall provide the following quantity computations of all dredged materials by the average-end-area method on 25 foot spaces.

(1) For each survey interval compute the quantity available to Project Depth, the Required Depth, and Maximum Payline for each designated survey area, including the north and south side slopes.

(2) Find the actual Cut and Fill quantities by doing a survey to survey computation for each survey interval.

(3) Compute the quantity removed by the Hopper Dredge by confining computations to the area covered by the Hopper for each survey interval.

(4) Compute the over dredging for the hopper by comparing the difference of Fill quantity to the Maximum Payline for each survey in their respective intervals. The area for over-dredging is defined by item (3) above.

(5) Shoaling is computed by taking the Maximum Pay Quantity available on the previous survey, subtracting the Maximum Pay Quantity available on the current survey. That quantity is then subtracted from the difference in the raw quantity removed by the Hopper dredge for that interval. This number is the total shoaled amount. The total shoaled amount is multiplied by the ratio of the area covered by the hopper over the area designated for dredging for each interval. The contour for the Maximum Pay depth is used to define the outer limit for both the hopper dredge area and the designated dredge area. A sample computation is attached.

All quantity computations and electronic versions of each survey shall be furnished to the Contracting Officer within four (4) days after the completion of any survey. The preliminary electronic point files (COGO format), used for quantity computations, shall be submitted with the electronic copies of each survey.

SECTION 01 22 00.00 10 Page 3

1.3 PAYMENT

1.3.1 Items 0001, Bid, Performance, and Payment Bond Cost

Payment will be made at the contract lump sum price and shall constitute full compensation for Bid, Performance, and Payment Bond Cost in accordance with SECTION 00700, FAR 52.228-0001 - BID GUARRANTEE, FAR 52.228-0002 - ADDITIONAL BOND SECURITY, and FAR 52.228-0015 - PERFORMANCE AND PAYMENT

BONDS - CONSTRUCTION.

1.3.2 Mobilization and Demobilization

Items 0002AA, 0002AB, and 0002AC, Mobilization and Demobilization

Payment will include transportation of plant, equipment, supplies, and appurtenances to and from the project; assembly of plant; and removal of same after completion of the project. Payment will be made in accordance with SECTION 00700, DFAR 252.236-7004 PAYMENT FOR MOBILIZATION AND

DEMOBILIZATION.

1.3.3 Dredging and Disposal

Items 0003AA thru 0003AF, Optional 0003AG thru 0003AJ (if awarded), 0004AA thru 0004AF, Optional 0004AG thru 0004AJ (if awarded), 0005AA thru 0005AF, Optional 0005AG thru 0005AJ (if awarded), Optional 0006AA thru 0006AD (if awarded), Optional 0007AA thru 0007AD (if awarded), and Optional 0008AA thru 0008AD (if awarded), Dredging and Disposal

Payment will be made at the contract unit price and shall constitute full compensation for performing all dredging and disposal. Payment will be in accordance with above paragraphs GENERAL and MEASUREMENT.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .