This document is a pricing proposal from Dominion Privatization Holdings, Inc. in response to Request for Proposal (RFP) 510 for the B37011 BN HQ Renovation project at Fort Cavazos, Texas. The proposal provides a firm-fixed price of $81,254.98 to furnish material, equipment, and labor for the scope of work, which includes installing fuses, upgrading transformers, upgrading underground wire and poles, and installing a watt node. The proposal notes that work will be conducted in coordination with a third-party contractor and that an adjustment to the Operations and Maintenance fixed monthly service charge of $243.67 will be provided upon project completion. Additional Facilities Charges are also outlined, split between Renewal and Replacement and Operations and Maintenance. The document lists the changes in inventory components required for the project. The related federal contract opportunity is for the Renovation of Building 37011 at Fort Cavazos, to be awarded as a firm-fixed price contract by the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Dominion Privatization Holdings, Inc 49011 Santa Fe Ave, Fort Cavazos, TX 76544
∗ The above pricing is valid for 90 days from the date of this quote.
∗ All services will be provided during Dominion's normal work hours.
∗ Contract authorization and installation of equipment for service cable termination at the customer facility are required prior to releasing and scheduling this project for construction.
RFP 510 – B37011 BN HQ Renovation
February 26, 2024
NOTIFICATION OF PROJECT COST
Contract No. SP-0600-16-C-8312 Fort Cavazos, Texas – Electric
RFP 510 – B37011 BN HQ Renovation
Fort Cavazos DPW:
In response to RFP 510, Dominion Privatization Holdings, Inc (DOM) has determined the Firm- Fixed Price proposal for the project requirements to be: $81,254.98.
This proposal is for DOM to provide material, equipment, and labor for the Scope of Work as described: Install fuses at the tap, upgrade existing transformers, upgrade underground secondary wire, upgrade pole, and install watt node.
Work for this proposal will be conducted in coordination with the third party contracted for this project. Third party payment to DOM has been authorized by the UP contract COR.
Authorization for an adjustment to the Operations and Maintenance fixed monthly service charge to be modified into Contract SP0600-16-C-8312, in the amount of $243.67 will be provided upon notification of project completion. Additional Facilities Charge is split between R&R and O&M as follows:
Distribution Facilities Charge R&R = $158.14/Month Distribution Facilities Charge O&M = $85.53/Month
Questions regarding this proposal should be addressed to the Dominion Energy Team at FortCavazosConstruction@dominionenergy.com. Contractual questions should be addressed to the Utilities Privatization COR, Dominic Miles at dominic.q.miles.civ@army.mil.
mailto:FortCavazosConstruction@dominionenergy.com mailto:dominic.q.miles.civ@army.mil
Dominion Privatization Holdings, Inc 49011 Santa Fe Ave, Fort Cavazos, TX 76544
∗ The above pricing is valid for 90 days from the date of this quote.
∗ All services will be provided during Dominion's normal work hours.
∗ Contract authorization and installation of equipment for service cable termination at the customer facility are required prior to releasing and scheduling this project for construction.
RFP 510 – B37011 BN HQ Renovation
Change in Inventory:
Component Size Quantity Unit Install Year
Overhead Transformer 50KVA 3 Each
Underground Service Wire 4/0AL 40 Feet
Crossarm 10’ 3 Each
Pole 1 Each
Watt Node 1 Each
Overhead Fuses 3 Each
Overhead Transformer 25KVA 3 Each
Pole 1 Each
Underground Wire 40 Each
Crossarm 5 Each