This document contains questions and answers regarding a solicitation to renovate building 41003 at Fort Hood, Texas. Key details include:
-
The scope of work involves demolishing existing structures and infrastructure, installing new HVAC, electrical and plumbing systems, and renovating interior spaces with finishes like LVT flooring. The drawings require revisions to fully define demolition and construction requirements.
-
Questions were asked regarding aspects like vermiculite testing, salvaged materials, scope changes from prior demolition work, floor repairs, roof repairs, utility work, telecommunications and whether a second site visit is required. The responses clarify contract requirements and note revisions to drawings.
-
The period of performance is 365 calendar days. The solicitation was issued by the U.S. Army's Mission and Installation Contracting Command at Fort Hood, Texas for renovations to convert the building into a battalion headquarters.
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFIs
1. Drawing M-101 references mechanical demo. However, all mechanical work on demolition has been complete. Please confirm this drawing will be removed.
See revised Sheet M-101.
2. General Note # 2 on M-102A, states that all units indoors to have secondary drain pans. Please confirm that HP-1 does not require this pan being it’s a wall mounted ductless mini-split?
Confirmed. Note has been revised.
3. General note # 9 on M-102A, states that all take off’s to have dampers. Please confirm the take-offs on the medium pressure supply on main trunk to Vado not get balancing dampers. This is what the VAV is for.
Confirmed. Note states dampers are required at take-offs to Diffusers, Grilles and Registers, NOT VAV boxes.
4. Key Note # 5 on M-102A, states that there needs to be a condensate pump and secondary pan switch, however drawings do not show where the drains will terminate. Please advise.
See Drawing P-101 for routing.
5. Please confirm Note # 1 on VAV schedule stating to connect to existing BMS is incorrect.
See revised Note.
6. Per Detail # 2 on M-801, there is to be a computer and front end at B 41003.This is not common at Fort Hood and standard to have controllers with displays and tied into a router for JCI to connect to front end. Please confirm local front end is required?
Confirmed. Local Front end is not required.
7. Do we need to include a Construction Sign?
Yes, refer the sheet drawing CG500.
8. The drawings say they are at 65%; when will we get the 100% drawings?
Drawing percentage has been removed and revised drawings represent a complete design.
9. Will the government provide the pricing for water, gas, electric and temp?
See notes 4 and 5 on sheet G-003 and Technical Exhibits C, D and E. Temporary electric shall be coordinated with Fort Hood Privatized Utility Partners at the expense of the contractor.
10. G-003 #3 says to protect the utilities. Then it says to demo the utilities. Which is it?
Contractor shall protect all existing utilities to remain. Contractor shall demolish utilities as identified in contract drawings. Reference sheet G-003.
11. On page CG-104 there is a proposed SWPPP. Does the Government want us to implement this or provide our own?
Reference Division 1 Specifications for SWPP requirements – both 01 35 13 Special Project Procedures and 01 57 20.00 10 Environmental Protection
12. The B Deck is in horrible condition- do you want is replaced.
Remove and replace existing deck as noted on sheet AD101.
13. AD-101 Most of the demo appears to be done. Not all. Will the page be revised to reflect what needs to be done?
See Revised Drawings.
14. In two locations the CMU has significant damage and appears that the CMU has vermiculite in the exterior walls. Has the Government had this tested?
Testing has not been performed on vermiculite and DPW is not aware of any hazards. It will be the responsibility of the contractor to take appropriate safety measures when working with suspect material and include in bid price. No cost modifications will be permitted for vermiculite handling.
15. Examples of vermiculite coming out of the CMU and there's some serious structural damage going on with this wall it is leaning badly and it's not addressed in the drawings how to fix it. Please advise. See picture.
Reference RFI response #14.
16. Examples of vermiculite coming out of the exterior CMU. Has this been tested for asbestos?
Reference RFI response #14
17. A-101 #4 says to use salvaged brick for infill. Where is it?
GC shall salvage existing brick per contract drawings where demo occurs at perimeter walls throughout the facility. Additional salvaged brick is stockpiled in the Mechanical room for use on this contract.
18. EP-101 L. Telecommunications cabling shall be installed by clients/vendor. Who is this? Do we figure a price in our bid for this? Or will the GOVT provide?
Telecommunications cabling shall be installed by contractor and shall be included in bid requirements. Reference revised telecommunication drawings.
19. A-201 Note 1 the brick is to match the existing. It is highly unlikely that we will be able to match. This bldg. is very old. Can the Government provide an alternate brick?
No, contractor shall utilize existing salvaged brick. Reference RFI response #17.
20. Basic hollow core door jambs have a 12-14 weeks lead time. JUST FYI.
This does not appear to be an issue as the contract POP exceeds the indicated lead time. Contractor shall furnish all submittals to the government as specified and shall order material in a timely manner.
21. What 3rd party testing will be required?
Refer to Project Specifications for 3rd party testing requirements.
22. Will we received engineered drawings?
Contract drawings are engineered.
23. What will the Government require the contractor to engineer?
Refer to contract drawings.
24. S-001 Shop drawings review #2- what is the Government referring to when they mention the contractor review stamp? IS the government wanting all shop drawings engineered?
Contractor shall thoroughly review all shop drawings before submitting to the government for review and approval. All shop drawings submitted to the government shall bear a review stamp from the prime contractor indicating their acceptance of the drawings and who they were reviewed by.
25. TP-101 Since this demo has already been done we have no way to confirm if anything was damaged or not. Was the fiber pulled back to the manholes?
Yes, refer to TD-101.
26. Will the Government provide the security network switch for communications?
No, contractor shall furnish network switch. Reference revised telecommunication drawings.
27. On design analysis says it should take 180 calendar days to complete. The solicitation says 365. Please confirm the POP.
POP for this project is 365 calendar days
28. Was the grease trap removed during the demo?
Yes
29. Will any LEED requirements need to be met for this project?
Contractor shall perform all work identified in the contract drawings. Requirements are outlined in contract drawings.
30. Will full building commission be required?
Refer to Project Specifications for building commissioning requirements.
31. Since the solicitation was found online on a public website, and there is attributional / proprietary information, controlled technical information, nor any credentials with “CUI” labeled on any W91151-22-B-0010 documents, will the DoD Chief Information Officer approve a variance of Far Clause 252.204-7019/7020; prior to bid being due? A: MICC
a. If no variance is approved, when will the GC be required to have a NIST-800-171 assessment uploaded into SPRS?
If the Clause is not applicable, please disregard. If performance of the contract does not involve covered defense information or operationally critical support, then the clause does not apply and compliance is not required. If the contract does involve covered defense information, but the information is not processed, stored or transmitted on the contractor’s unclassified information system, the requirements related to covered defense information do not apply and compliance is not required.
b. If no variance is approved, will the Subs have to have a NIST-800-171 assessment uploaded into SPRS? A: MICC Just to make note- this could increase the cost substantially by thousands and thousands of dollars per subcontractor’s no variance is approved, when will Subs be required to have a NIST-800-171 assessment uploaded into SPRS.
If the Clause is not applicable, please disregard. If performance of the contract does not involve covered defense information or operationally critical support, then the clause does not apply and compliance is not required. If the contract does involve covered defense information, but the information is not processed, stored or transmitted on the contractor’s unclassified information system, the requirements related to covered defense information do not apply and compliance is not required.
32. During the site visit, the government acknowledged that the drawings currently available to the contractors were not the final drawings to bid from and that updated drawings would be posted in an Amendment. As the contractors did not have the complete information available at the site visit to assess the current scope of work we request a 2nd site visit to assess the space. Please advise.
DPW believes a second site visit is not necessary for this project. The government will not be organizing a follow on site visit for this solicitation.
33. During the site visit, the government acknowledged that the drawings currently available to the contractors were not the final drawings to bid from and that updated drawings would be posted in an Amendment. As the contractors did not have the complete information available prior to the Q&A suspense date we are requesting an additional Q&A period be provided after the final drawings have been posted. This was discussed during the site visit with the government team who concurred that this made sense. Please provide a new due date for submission of additional Q&A once updated drawings have been provided.
Revisions to drawings provided clarity to contract requirements and do not warrant an RFI extension.
34. It appears that the majority of Civil Demolition on CD101 has already been completed by another contract, however there were concrete steps where a roof overhang used to exist that were still in place where we entered the building during the site visit. Will these steps require demolition as part of this contract?
Yes, reference revise sheet drawing AD101
35. It appears that the majority of Civil Demolition on CD101 has already been completed by another contract, however there was a concrete entry into the old mechanical room that was still in place where we entered the building during the site visit. Will this concrete entry require demolition as part of this contract?
Yes, reference revised sheet AD101
36. During the site visit we observed that the existing concrete floor is severely damaged it appears from the demolition that took place in the space. A-601 shows that the majority of the building is to receive Luxury Vinyl Tile (LVT-2). In order to install LVT a floor needs to be level with little to no issues with floor flatness. In order to ensure the floors are ready to receive LVT it appears that the entire building will likely need a topping slab installed to level the surface. This does not appear to be indicated in the drawings as a requirement and would not be apparent to those that did not attend the site visit. Will the government include installing a new topping layer across the entire interior slab so that new flooring can be installed?
Refer to revised sheet AD101 for finish floor and topping requirements.
37. Sheet CP503 includes TXDOT retaining wall details. Where do these apply on the project?
Refer to revised drawings.
38. During the site visit it appeared that all plumbing, HVAC, and electrical piping in the building had already been demolished so we assume this will be removed from the scope when the amended drawings are provided. Has all of this piping also been demolished from the crawl space?
Crawl space plumbing has not been demolished. Refer to revised contract drawings for demolition requirements.
39. During the site visit we observed several corners where interior CMU walls were heavily damaged from demolition. The current scope documents do not address CMU wall repairs which are sporadic throughout the building. Will this be addressed in the new drawings? If not, please advise on repair procedure and number of locations.
Refer to architectural drawings A-303 & A-604 for all wall requirements. If drawings do not indicate to repair walls then wall is not to be repaired.
40. A-301 Detail 3 references the A-301/4 Eave Detail. This detail indicates existing metal decking to remain. During the site visit we observed that the metal deck had significant damage and looked to need to be replaced in its entirety. Please confirm if the metal deck is to be replaced entirely.
Refer to RFI response #12.
41. On S-1011 there are a multitude of foundation repairs required. Are these repairs all in the crawl space or within the building?
Refer to drawings for repair locations.
42. There appears to be a significant amount of work within the crawl space. What is the depth of the crawl space so we can determine clearances to work.
Refer to as-built drawings for existing conditions within the crawl space.
43. Will any work be required to be completed by American Water on this project?
Yes. Refer to Revised drawings and technical exhibit D.
44. Will any work be required to be completed by Dominion on this project?
Yes. Refer to Revised drawings and technical exhibit C & E.
45. The solicitation indicates that the Superintendent and Quality Control Manager are key personnel. Can one of these individuals also serve as the Site Safety and Health officer?
Yes - Superintendent, reference Division 1 Specification Sections 01 35 29 & 01 45 01.00 20.
46. What is the current roof system assembly present on the roof. We need to know exactly how much roof we are tearing out to give an accurate estimate.
Refer to revised drawings and As-built drawings.
47. What will the extent of roof deck replacement be?
Refer to RFI Response #12
48. Drawing A-301/4 calls for ½” plywood under the SSMR, Spec section 07 22 00.3.2.2.1 calls for ½” wood fiber or gypsum roof board or ¾” expanded perlite. Do we estimate according to the spec or the drawing?
Refer to revised contract drawings.