CLIN 0004 SOW.pdf

PDF 183 KB Posted

Attached to
Multiple Construction Projects Osan AB - Amendment 0001
Solicitation number
W90VN624R0028
Issued by

About this file

This document is a Statement of Work (SOW) for the SMYU 24-1071 project to replace the flooring and bleachers at the Youth Center Gym, Building 433, at Osan Air Base, South Korea.

The SOW details the scope of work, which includes removing and disposing of the existing bleachers and flooring components, cleaning the concrete slab, and installing new wood strip flooring and bleachers. It also outlines the references and standards, construction schedule information, additional requirements, security requirements, and environmental requirements for the project. Key details include a 120-day period of performance, the need for base passes, restrictions on work hours due to military training events, and specific environmental compliance measures. The project is a Non-Work Plan Task Order under a Multiple Award Task Order Contract issued by the 411th Contracting Support Brigade, Korea.

View the file

Other files

File Type Posted
Section K.docx DOCX document
SMYU 22-1063 SOW_revised_20240820.pdf PDF
C-02.pdf PDF
C-03.pdf PDF
Amendment 0001to RFP W90VN624R0028.pdf PDF
Consolidated Construction Project RFP.pdf PDF
CLIN 0004 Drawings.pdf PDF
CLIN 0002 Drawings.pdf PDF
CLIN 0003 SOW.pdf PDF
CLIN 0002 Submittal Register.pdf PDF
CLIN 0004 Submittal Register.XLS XLS spreadsheet
CLIN 0001 SOW.docx DOCX document
CLIN 0003 SUBMITTAL-REGISTER.pdf PDF
CLIN 0001 Submittal Register.pdf PDF
CLIN 0003 DRAWING.pdf PDF
CLIN 0001 Drawings.pdf PDF
CLIN 0002 SOW.docx DOCX document
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

FOR

SMYU 24-1071, REPLACE FLOORING BOARD AND BLEACHERS AT YOUTH CENTER GYM, B433

OSAN AB, ROK

51ST CIVIL ENGINEER SQUADRON

TABLE OF CONTENTS

SMYU 24-1071

REPLACE FLOORING BOARD AND BLEACHERS AT YOUTH CENTER GYM, B433

Contents

1. GENERAL

2. SCOPE OF WORKS (SOW):

3. REFERENCES AND STANDARDS:

4. CONSTRUCTION SCHEDULE INFORMATION:

5. ADDITIONAL REQUIREMENTS:

6. SECURITY REQUIRMENTS:

7. ENVIRONMENTAL REQUIREMENTS:

8. APPENDIX “A”

Page | 3

STATEMENT OF WORK

1. GENERAL

The work to be performed for completion of this Non-work Plan project shall be as described in general below.

1.1 The contractor shall provide all labor, tools, equipment, supplies, and any other resources necessary to accomplish the scope of work contained herein and as included in the drawings and specifications.

1.2 All work shall be completed IAW specifications and standards referenced in section 3 and drawings associated with this project.

1.3. Contract Type: This project is an individual Non-Work Plan Task Order under the Multiple Award Task Order Contract (MATOC) issued by the 411th CSB, Korea. The definition of Non-Work Plan is a task order in which the Government provides a written statement of work and completed design. The task order proposal submission requirements are as below:

2. SCOPE OF WORKS (SOW):

2.1. ARCHITECTURAL WORKS:

2.1.1. Remove and dispose of existing bleachers. (4.3m X 18.3m)

2.1.2. Remove and dispose of all existing wood flooring components, including wood flooring, plywood, sleepers, rubber pads, and vent rubber base in the gym area (approximately 615m²).

2.1.3. Clean the surface of concrete slab. The existing volleyball post sleeves should remain intact.

2.1.4. Install wood strip flooring, including a polyethylene membrane, rubber pads, sleepers, plywood, wood flooring, and vent rubber base in the gym area (approximately 615m²).

2.1.5. Reinforce the area with bleachers by laying double sleepers to prevent sagging.

2.1.6. Sand wood floor surfaces with a machine using coarse, medium, and fine grades of sandpaper.

2.1.7. Apply a seal coat and finish coat after sanding.

2.1.8. Lay out game lines as existed condition.

2.1.9. Install new bleachers. (4.3m X 18.3m, approximately 128 seats)

2.1.10. Perform final cleaning and inspection to ensure the floor meets all requirements.

Page | 4

3. REFERENCES AND STANDARDS:

3.1. This project shall comply with the “Standard Technical Specifications and Standard Detail Drawings for OMA Projects, Korea” dated 30 November 2015 issued by the Department of the Army, Installation Management Agency, Korea Region Office. The most current specifications (O&MA Specification 2014, Revision-1) and standard drawings are available at the Engineering Flight, 51st Civil Engineer Squadron, Osan AB, Unit 2129, APO AP 96278-2129 and also are located on the Web Page http://www.usfk.mil/Resources/ContractingwithUSFK.aspx.

3.2. Unified Facility Criteria (UFC): http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4

3.3 Air Force Criteria as published on the Whole Building Design Guide:

http://www.wbdg.org/ccb/browse_org.php?o=33

3.4 The project shall comply with “Osan AB Architectural Compatibility Plan dated 01 January 2022”.

4. CONSTRUCTION SCHEDULE INFORMATION:

KEY INFORMATION FOR CONSTRUCTION SCHEDULE

Project Site BLDG Location or Area Base Area: B433

Contract Type MATOC, Non-Work Plan 411TH CSB

Performance of Period (PoP) 120 Days (After NTP issued)

30 Days for Submittal review/approval, NTP + 90 Days for material procurement + 30 Days for mobilization/construction

Temporary Airfield Construction Waiver Required (TACW)

No If yes, TACW requires minimum 60 days to be approved

Risk Assessment (RA) Required No If yes, RA requires minimum 60 days to be approved

Phasing Work Required No If yes, Will be determined at pre-con meeting

Military Training Event Anticipated

Yes Minimum 14 days of Military Training Event anticipated during PoP

Restricted Area Escort Required No

4.1. Working Hours: All work shall be accomplished in such a manner that minimum inconvenience shall be caused to the Government. All work shall be accomplished during normal duty hours from 0730 to 1630 hours, excluding weekends and Federal holidays. See MATOC section H-3 for holiday list. The contractor will only be allowed access to the work area during normal base working hours and when building staff and employees are present. Any requests to work outside of normal working hours must be submitted in writing to the Contracting Officer Representative (COR) at least seven (7) days in advance and approved. The Government reserves the right to change hours of operation due to military training events such as exercises and wing down days. Contractor will be notified 72 hours in advance of any required changes in work schedule.

4.2. Military Training Events are anticipated to occur during the construction period as indicated in Table above.

During Training Event, contractor will not be allowed to access the project site. Contractor shall consider these http://www.usfk.mil/Resources/ContractingwithUSFK.aspx http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4 http://www.wbdg.org/ccb/browse_org.php?o=33

Page | 5 conditions in their proposal. Contractors will be given 72 hours’ notice of work stoppage without incurring penalty to the Government.

4.3. Phasing Plan: Phasing plan shall be required for all road work projects or anything interfering with operations/large base functions (Airfield, BX, Gym, etc). Specific phasing shall not be pre-determined but contractor shall submit a plan for approval by construction OIC/NCOIC. If required, three phases shall be planned as a minimum. This minimum can be waived by the construction OIC/NCOIC.

4.4 Time on target of the site release date and phasing work plan will be discussed with user and COR at the pre-con meeting after award.

4.5. Due to the mission requirements on the installation, there may be occasional restrictions on normal working hours and site access. Please be aware that site access windows are subject to change without prior notice. Contractors are advised to take this work environment into account when preparing their bids.

4.6. The following shall be submitted via email to the COR within 30 days of project acceptance:

4.6.1. Dates of material/product testing

4.6.2. Requests to operate equipment taller than 20 feet (6 meters) with timeline of use and exact height required

4.6.3. Any period of time contractor will not be conducting work (wet season, pavement curing time, etc.)

4.6.4. Any expected utility outages, road closures, or other impacts on base users that could affect their work

4.6.5. Requests for Information

4.7. Any correspondence sent from COR to Contractor via email shall be replied to within one work week.

4.8. Contractor is not to incur any cost until NTP has been issued. NTP will be issued after TACW, RA, base access and all submittals have been approved.

5. ADDITIONAL REQUIREMENTS:

5.1. Site Orientation will be strongly recommended. The contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the works, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost IAW FAR 52.236-3. This may include restricted access to the site or a higher standard of site cleanliness.

5.2. Submittals: Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES of O&MA Specs:

5.2.1. All submittals shall be submitted to the contracting officer representative with written confirmation of receipt within 30 days after project acceptance. Any rejected submittal will be re-submitted within 10 days. If any submittal is rejected more than once, the contractor shall meet with the contracting officer representative and project engineer to clarify. Any further rejections of the same submittal shall meet with the same action.

5.3. At least one fluent English speaker must be on the site whenever work is being done; Contractor must be able to communicate with project inspectors at any time during approved working hours. Contractor will have the COR’s phone number and shall contact the COR for the following reasons:

Page | 6

5.3.1. Damage caused by Contractor within the installation.

5.3.2. Differing site conditions from Contract documents requiring adjustments.

5.3.3. Any Request for Information (RFI) during project execution.

5.3.4. Changes to project timeline to include weather events, delays in material delivery, or lack of workers shall be relayed to COR within 24 hours.

5.4. Laydown area policy and requirements: Laydown area to be coordinated with construction OIC/NCOIC.

5.5. The contractor shall provide, install, and maintain all necessary signs, lights, flares, barricades, markers, cones and shall take all necessary precautions for the protection and safety of the public and/or military traffic and operations.

5.5.1. The Contractor’s Safety Representative shall be contactable and able to arrive on site within two (2) hours of being requested.

5.6. Site Cleanliness: Contractor shall police their trash and clean up their site to the best extent possible at the end of each working day. In addition, Contractor shall maintain clean and orderly storage areas associated with the project.

5.7. When contractors install new underground infrastructures, they shall notify the government before covering excavated area so that 51st CES GeoBase team can collect as-built geo-referenced data.

5.8. Contractor will coordinate with COR for any construction work on the Airfield or within Restricted Areas for access and/or escort requirements. It is common for users to need partial access to the work site during construction. Contractor shall plan work phasing to facilitate ongoing mission execution upon government request.

5.9. The contractor shall be responsible for verifying the location, size and inverts of all existing utilities and shall protect all such utilities at all times, unless otherwise indicated. Existing utilities whether shown on the drawings or not which have been damaged as a result of the construction work, shall be restored immediately to their original or better condition and shall be paid for by the contractor.

5.10. Whenever connections to existing utilities or where new utilities cross existing utilities are shown, the contractor shall carefully expose the utility by hand excavation to verify their locations and depths prior to excavating trenches for the new utility lines.

5.11. Whenever any change in alignment or grade for the proposed utilities are required due to unforeseen conflict with other utilities, the contractor shall inform the contracting officer immediately for remedial action.

5.12. As-Built Drawings: The Government will at its discretion withhold a portion or all of the final payment until the As-Built drawings have been submitted.

5.13. Warranty: Upon completion the base contract, warranty will apply unless a different timeframe is listed in the RFP.

5.14. Final Cleanup: Upon completion of work, work site shall be cleaned of any spills and debris, all Contractor equipment shall be removed, and any restoration efforts made to leave the site in a clean and orderly condition.

6. SECURITY REQUIRMENTS:

Page | 7

6.1. Contractor’s personnel or any representative of the contractor entering installation/base shall abide by all security regulations imposed by Installation Commander or Base Commander at all times and shall be subject to security checks.

Contractor’s personnel and property shall be subject to search and seizure upon entering the confines of the installation/base, while on, and upon leaving confines of the installation/base.

6.2. The training IWATCH/EAGLE EYES/AT Level I shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 45 calendar days after contract award.

6.3. ALERTS: During military alerts or special operations, the contractor may not be authorized on base or in the work site. When the contractor is prohibited from access to the base or work site for one (1) day or less per month, no adjustment in the contract time shall be made. When the contractor is prohibited access for more than one (1) day per month, adjustments shall be made in accordance with applicable clauses of the General Provisions.

6.4. Physical Security: The Contractor shall be responsible for safeguarding all government property provided for Contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured; lights, and water turned off, adjust heat and air conditioning appropriately, and all doors and windows secured.

6.5. BASE PASSES: The contractor shall be required to obtain base passes to Osan Air Base to perform the requirements of this contract. The contractor shall be responsible to submit a base pass request no later than five (5) calendar days after award of this contract. It should be noted that it can take up to 30 days or more to process base pass paperwork. It shall be the responsibility of the contractor to prepare the necessary base pass paperwork to include USFK Form 82-E, USFK Form 225EK-E, family history register, local register, etc. for each individual requiring access to Osan Air Base. The contractor shall also be authorized to receive vehicle passes for each of the contractor’s vehicles used in the performance of the requirements of this contract. It shall be the responsibility of the contractor to prepare the necessary paperwork to include USFK Form 195EK-E, vehicle registration, vehicle insurance, certificate of safety inspection and a copy of driver’s license for each vehicle requiring access to Osan Air Base. The contractor shall prepare a cover letter listing each individual, skill, escort privileges, vehicle type, vehicle registration number, etc. The contractor shall also provide the COR with two (2) copies of this request letter, with carbons, to include the top copy with original signatures. Escort privileges will be justified and limited to specific needs for contract completion and at the discretion and approval of the sponsor and requesting authorities identified in Block 13 and Section III of the USFK Form 82- E, Application for Installation/Base Access. The contractor shall not be authorized to perform any portion of the contract requirements until such time that the contractor has processed the necessary base pass paperwork for entry onto Osan Air Base. The COR shall not provide or be responsible to provide the contractor with escorts during performance of any part of this contract. All of the above documents shall be turned in to the COR for processing with the 51st Security Forces.

6.6. AT/OPSEC REQUIREMENTS: The contractor and all associated sub-contractors will practice Operations Security.

The contractor shall not talk about work outside of the work area nor discuss the work being performed on social media.

The contractor shall not take pictures/video (to include operation of dashcams or other recording devices in contractor operated vehicles) inside sensitive locations without prior coordination with the organization's OPSEC representative and contracting officer representative. It will be the responsibility of the contractor to safeguard all documents provided.

Documents will be stored away from view when not being used. Documents, media, drawings, and other associated material that are no longer needed must be destroyed via approved methods.

6.7. Key Control: The Contractor shall establish and implement methods of ensuring that all keys issued are not lost or misplaced and are not used by unauthorized persons.

6.7.1. The Contractor shall immediately report to the COR any occurrences of lost or duplicated keys. The Contractor shall re-key or replace keys or reimburse the government for replacement of locks or re-key as a result of Contractor losing keys. In the event a master key is lost or duplicated, all keys and locks for that system shall be replaced or

Page | 8 reimburse the government for replacement of locks or re-key.

7. ENVIRONMENTAL REQUIREMENTS:

7.1. Construction debris and litter from work areas within the construction limits of the project site shall be collected and placed in watertight dumpsters at least weekly regardless of whether the litter was generated by the Contractor, the public, or others. Collected litter and debris shall not be placed in or next to drain inlets, storm water drainage systems or watercourses.

7.2. Solid waste storage areas shall be located at least 15 m (50 ft.) from drainage facilities and watercourses and shall not be located in areas prone to flooding or ponding.

7.3. Place hazardous materials/waste containers in secondary containment. Container to store construction debris has to have water-proof and leak-proof lid.

7.4. The contractor shall submit the HAZMAT information (especially all paints/coating) and AF Form 3952 IAW AFMAN 32-7002, Chemical Hazardous Material Request Authorization along with a copy of Safety Data Sheet to obtain HAZMAT approval from BEE, Safety, and Environmental Office. All paint products should be lead free.

7.5. For welding and brazing: Perform activities indoors. Cover nearby drain inlets and sweep-up metal particulates after each event.

7.6. The Contractor shall comply with USFK Regulation 201-1, Chapter 7, paragraph 7-3.q., specific standards for construction waste. The Contractor shall report the metric tons for construction and demolition (C&D) debris, including cost deposited in a landfill, incinerated, or diverted (recycled), respectively, to Environmental Office thru COR every 30 days for each project site. The Contractor shall use the C&D container (Roll-Off type) with water-proof lid and keep it always covered except when in use.

7.7. Scrap metal, including metal structures, metal roofs, metal roofing part, metal railings, metal beams, copper pipes and tubing, and HVAC equipment (chillers and boilers etc.), shall be collected by the contractor for disposal and sale through the Osan AB Qualified Recycling Program (QRP) in accordance with DOD Instruction 4715.23, which requires the installation’s QRP to receive money through the sale of all installation recyclables. The Contractor shall appropriately segregate and place the scrap metal to the location that QRP manager designates on base. The scrap metal shall be segregated and stored by the contractor for sale through QRP. Reinforcing metal bar in the concrete stuff to be broken on the construction site shall be turned in QRP.

7.8. The contractor shall use lead free coatings and paints. In addition, all surface coating/painting shall be applied by brush or roller. Using spray equipment is prohibited for minimization of air emissions unless otherwise specified or recommended by the paint manufacturer.

7.9. The building contains various of LBP building components. However, removal or replacement is permissible methods of abating lead hazards. Confirmation XRF testing on existing metal roof is not required. If the project includes field activities for repair or repaint such as dry sanding, dry scrapping or abrasive blasting that may disturb existing paint surfaces and release lead paint dust, the presence of LBP for the project areas and methods of abating lead hazards should be confirmed and coordinated with CEIE prior to construction.

7.10. All transformers and electrical equipment shall be properly removed and disposed of IAW USFK Reg 201-1, KEGS.

7.11. The Contractors are prohibited by 10 U.S.C. 2692 from storage, treatment, or disposal of any contractor owned hazardous waste on installation. The Contractors must get approval from HW Program Manager to store Hazardous Waste generated on-site in connection with a contract activity. HW storage will be on a temporary

Page | 9 basis prior to disposal from Osan AB.

7.12. The contractors need either 1) a permit to store hazardous waste while they are working on the installation or 2) they need to remove the hazardous waste from base within 24 hours. In either case, for disposal, the contractor needs to dispose of the waste in accordance with local regulations and provide a stamped manifest or other documentation demonstrating appropriate disposal to Environmental Office.

7.13. The Contractor shall implement Best Management Practices (BMP) specified on Table 4-8 of EGS and paragraph E.7 of the Osan AB Storm Water Pollution Prevention Plan (SWPPP) for outdoor painting/de- painting activities. EGS and Osan SWPPP are available at CE Environmental Office, room #105, building 600, DSN 784-8974.

7.14. A dust controls plan shall be developed/implemented to take appropriate measure to minimize the generation of dust as a result of their works, operations, and activities during and after construction until the site is reclaimed. Standard dust control Best Management Practices (BMPs) for dust generating activities shall be implemented during construction.

Page | 10

8. APPENDIX “A”

LIST OF CONTRACT DRAWINGS

DWG NO. SHT NO. REF NO. DESCRIPTION

24-1071 1 OF 4 A01 FLOOR PLAN & SCOPE OF WORK, B433

24-1071 2 OF 4 A02 WOOD STRIP FLOORING DETAIL

24-1071 3 OF 4 A03 FLOOR PLAN FOR BLEACHERS

24-1071 4 OF 4 A04 BLECHCHERS DETAIL

2. SCOPE OF WORKS (SOW):
3. REFERENCES AND STANDARDS:
4. CONSTRUCTION SCHEDULE INFORMATION:
5. ADDITIONAL REQUIREMENTS:
6. SECURITY REQUIRMENTS:
7. ENVIRONMENTAL REQUIREMENTS:
8. APPENDIX “A”