ATTACHMENT_0008_-_FIELDING_AND_PROGRAM_SCHEDULES.pdf

PDF 672 KB Posted

Attached to
Systems Engineering Technical Assistance (SETA) and Program Management Office (PMO) Support - Radars
Solicitation number
W56KGY-16-R-0004
Issued by

About this file

Updated Attachment 0008

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AN/TPQ-50 Program Schedule (For Planning Purposes Only)

FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Fiscal Year Quarter

Acquisition Milestones and

Major Events

Major Contracting Events

Deliveries

Legend:

Testing

Logistics

As of 09/16/15

11/26 KP: ATO Approval

12/15 KP:IACORA Approval

J&A

R&D RFP

R&D Cont. Award

51 + 31

3 + 36

CRAM LPWS Spiral 6.4 ENG Test 2

CRAM LPWS Spiral 6.4 ENG Test 3 Q50 C&L

C-RAM C&L

4/1 Begin Organic Depot Capability

FY12/13 FRP

Prod Period FY15/ FY16 FRP

Production Period

Prod Period =LRIP Contract =FRP Contract =RDT&E Contract

FY14 FRP

FY17 FRP

FRP Contract-1

FRP Contract - 2

56 + 25

Request For Proposals No. W56KGY-16-R-0004 Attachment No. 0008

AN/TPQ-53 Program Schedule (For Planning Purposes Only)

FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Fiscal Year Quarter

Acquisition Milestones and

Major Contracting Events

Deliveries

Testing

Logistics

As of 09/15/15

PCA

Delta PCA

MRA

ERB

FRP DR FUE

7/27Retrofit

9/28LRIP Lot 5

2/29 FRP Lot 2

3/1 Retrofit 2

3/31 FRP Lot 3

3/31 FRP Lot 4

3/31 FRP Lot 5

3/31 FRP Lot 6

FY12 LRIP Lot 2 (8) & Directed Buy (13) P3I

9/28

FY13 LRIP Lot 3 (19) FY14 LRIP Lot 4 (13)

LRIP Lot 5 (7)

2/29 3/31

3/31

FRP Lot 2 (24) FRP Lot 3 (23)

FRP Lot 4 (15)

7/27 Retrofit 32 Systems 4/27

3/31 FRP Lot 5 (6)

FRP Lot 6 (2)

OTRR #1

TCB

DT Testing

OTRR #2

OTRR #3

Humidity Test

HAEMP Test

FOT (122 & 240mm) P3I - 6.04sp1 SW Test v6.05 Release

P3I - 6.05 SW Test P3I - 6.05sp1 SW Test

P3I - 7.0 SW Test

CRAM Event LPWS Spiral 6.3

FL Test w/ Aircraft6.03sp1 SW Tstg. v6.03 Release

6.03 SW Ready For Fldg

2.06.04 - SW Ready for Fldg

FL Test Capstone NET

Capstone Event Drill

IOTE #2 NET

IOTE #2

OER

DT6

v6.04 Release

2.06.05 - SW Ready for Fldg DT4 - 6.01 Rel. Test

DT5 - 6.02 Reliability Regression Test

Towing & Recovery DT7 v6.05sp1 Release

SW IV&V Cont.

6.01 IETM Rev & Upd

Oper. Trng. Material Upd w/ LM

6.02 IETM Upd

RPSTL Update (100%)

TMs Completed

Maint. Trng. Material Upd w/ LM RPSTL Update (75%)

6.02 Training Pkg Upd

Materiel Release

Trans to Organic Sust.

Production Period

Production Period

Production Period Prod. Period

Production Period

Production Period

Production Period

AN/TPQ-50 COMMENTS/STATUS

Unit Patch BDE Location OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Unit1 USAREUR 4

Unit2 HOOD 4

Unit3 CARSON 2

Unit4 TN 2

Unit5 BRAGG 2

Unit6 BLISS 4

Unit7 RILEY 4

Unit8 BRAGG 4

Unit9 CARSON 4

Unit10 JBLM 4

Unit11 JBLM 2

Unit12 LA 4

Unit13 WA 4

Unit14 OR 4

Unit15 MA 4

Unit16 NC 4

Unit17 TN 4

Unit18 BRAGG 2

Unit19 BRAGG 2

Unit20 BLISS 4

8 6 0 0 4 8 8 8 8 8 8 8 14 14 14 18 26 34 42 50 58 66 72

FY16 FY16 FY16 FY16 FY17

AN/TPQ-50 Notional Fielding Schedule

AN/TPQ-53 LIN: Z00737

Unit Patch Location Unit Type COMPO MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP

Korea 210TH FAB FAB 1 2

Korea 2ID DIVARTY DIVARTY 1 2

TRADOC USAFAS

TRADOC

1 5

Hood 3/1 CD BCT 1 2

Hood 2/1 CD BCT 1 2

Hood 1ST CD DIVARTY DIVARTY 1 2

Carson 4 ID DIVARTY DIVARTY 1 2

CO 169TH FAB FAB 2 2

Riley 1/1 ID BCT 1 2

Riley 2/1 ID BCT 1 2

Bragg 18TH FAB FAB 1 2

Bragg 82ND DIVARTY DIVARTY 1 2

Germany 173RD ABN BCT 1 2

Germany 2ND CR BCT 1 2

Sill 75TH FAB FAB 1 2

Sill 45TH FAB FAB 2 2

Campbell 1/101 AASLT

BCT

1 2

Campbell 3/101 AASLT

BCT

1 2

JBLM 2/2 ID BCT 1 2

JBLM 17TH FAB FAB 1 2

Stewart 1/3 ID BCT 1 2

Stewart 2/3 ID BCT 1 2

Bliss 1/1 AD BCT 1 2

Bliss 1AD DIVARTY DIVARTY 1 2

UT 65TH FAB FAB 2 2

IN 138TH FAB

FAB

2 2

Bliss 2/1 AD BCT 1 2

Bliss 3/1 AD (ABCT) BCT 1 2

MS 155TH ABCT

BCT

2 2

AR 39TH IBCT

BCT

2 2

NY 27TH IBCT

BCT

2 2

Richardson 4/25 ID (ABN BN TF (K ED

BCT

1 1

Wainwright 1/25 ID

BCT

1 2

FY16

3RD QTR

FY16

4TH QTR

FY17

1ST QTR

FY17

2ND QTR

FY17

3RD QTR

FY17

4TH QTR

AN/TPQ-53 Notional Fielding Schedule*

*fielding of AN/TPQ-53 requires defielding of any existing AN/TPQ-36 or AN/TPQ-37 at same site

Slide Number 1
AN/TPQ-53 Program Schedule�(For Planning Purposes Only)
Slide Number 3
Slide Number 4