This document contains questions and answers regarding Solicitation Number W56HZV-19-R-0209 from the Department of the Army for Trophy Kits. The Army Contracting Command-Detroit Arsenal proposes to award an indefinite delivery, indefinite quantity contract for five years to procure Trophy Kits and spare parts for the M1A2 SEPv2 and M1A2 SEPv3 Abrams Family of Vehicles. The solicitation includes eight kits for integration on vehicles. Questions were answered clarifying that items referenced in notes would be provided by the government, attachments were replaced, and a missing specification was subsequently provided. The period for questions concluded on August 2, 2021.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TROPHY KIT
Questions for the Government Solicitation Number: W56HZV-19-R-0209
Question # 61
Offeror requires the 3D models for the following drawings:
12591793 12592198 12592199
The 3D models are not available for the listed drawings. Potential offerors have been provided the Portable Document Format (PDF) and specifications for each drawing as part of requesting the Technical Data Package as stated on SAM.gov.
Question #62
• In Kit 1 (57K7358 Rev. B), note 5 on sheet 2 states that P/N 12388558-6 is required for use with this kit. It is our assumption that P/N 12388558-6 will be provided by the government since it is not listed on any BOMs.
• In Kit 2 (57K7392 Rev. -) note 5 on sheet 2 states that when installing this kit P/N 57K7345 is to be used. It is our assumption that P/N 57K7345 will be provided by the government since it is not listed on any BOMs.
• In Kit 3 (57K7393 Rev. -) note 5 on sheet 2 states that when installing this kit P/N 57K7345 is to be used. It is our assumption that P/N 57K7345 will be provided by the government since it is not listed on any BOMs.
• In Kit 4 (57K7364 Rev. -) note 5 on sheet 2 states that P/N 12546244-2 is required for use with this kit. It is our assumption that P/N 12546244-2 will be provided by the government since it is not listed on any BOMs.
• In Kit 5 (57K7370 Rev. -) note 5 on sheet 2 states that when installing this kit P/N 57K7345 is to be used. It is our assumption that P/N 57K7345 will be provided by the government since it is not listed on any BOMs.
• In Kit 6 (57K7371 Rev. A) note 4 on sheet 2 states that when installing this kit P/N 57K7373 is to be used. It is our assumption that P/N 57K7373 will be provided by the government since it is not listed on any BOMs.
• In Kit 8 (57K7371 Rev. A) note 4 on sheet 2 states that Rafael Trophy System FTNG00000A is required for use with this kit, note 5 states the P/N 12591969 may be installed on this kit, note 6 states that P/N 57K7340 is to be used with this kit, note 7 states P/Ns 12592467, 12592468 and a standard Ethernet cable with RJ45 connectors will be required, note 8 states that P/Ns 57K6559 and 57K7348 must be used with this kit. It is our assumption that all these items will be provided by the government since they are not listed on any BOMs.
USG ANSWER: Correct, the items identified will not need to be provided by the offerors.
TROPHY KIT
Questions for the Government Solicitation Number: W56HZV-19-R-0209
• In Kits 2, 3, 5, 6 and 8, there are both -101 (Green) and -201 (Tan) options. Offeror is assuming that the USG will determine at time of ordering which option (color) will be ordered.
USG ANSWER: Correct, the USG will identify at time of order.
• For differences between Attachments 0001 and 0002, and the actual 57K documents, Offeror is assuming that the released 57K documents should be considered the document to propose to.
USG ANSWER: Attachments 0001 and 0002 were deleted in Amendment 0003 and offerors have kit drawings which contain the bill of material.
• Specification SB-SA21057 is missing from the TDP.
USG ANSWER: Specification SB-SA21057 was inadvertently omitted and was provided on 19 OCT 2021 to all cleared offerors that have requested the Technical Data Package.