Attachment 0021 - Request for Waiver of First Article Testing V.R.1

View the file

Other files

File Type Posted
W56HZV18R0096_conformed.pdf PDF
Tank_Rack_Module_Solicitation_Questions_and_Answers_amd_0003.docx DOCX document
W56HZV18R0096-0003.pdf PDF
Attachment_0021_Request_for_Waiver_of_First_Article_Testing_Requirements_-_v.R.2...docx DOCX document
Tank_Rack_Module_Solicitation_Questions_and_Answers_amd_0002.docx DOCX document
W56HZV18R0096-0002.pdf PDF
TRM_Pricing_Attachment_0017_rev_02.xlsx XLSX spreadsheet
W56HZV18R0096-0001.pdf PDF
TRM_Pricing_Attachment_0017_rev_01.xlsx XLSX spreadsheet
0016_LORA_Candidates_Sustainment_Level_Reparable_Item_Summary.xlsx XLSX spreadsheet
0001_ATPD_2336E_-_Modular_Fuel_System_(MFS)_GPM_12_AUG_2011.pdf PDF
Attachment_0018_Technical_Performance_Factor_Matrix.docx DOCX document
Attachment_0006_-_Request_for_Use_of_Prohibited_Materials.docx DOCX document
TRM_Pricing_Attachment_0017_.xlsx XLSX spreadsheet
Attachment_0019__IMI_Appendix_A.PDF PDF
0014_TRM_General_Publications_Requirements_for_Page-Based_TMs.doc DOC document
0010_TM_Crosswalk_Form.xls XLS spreadsheet
0011_DE_Style_Guide.pdf PDF
Attachment_0020,_TRM_Fielding_Plan_Estimate.xlsx XLSX spreadsheet
0008_TRM_TABLE_A-II_-_TM_Requirements_Matrix_-10.docx DOCX document
W56HZV18R0096.pdf PDF
Attachment_0022_Request_for_Waiver_of_Integrated_Product_Support_and_IMI.docx DOCX document
0004_Abbreviated_FAT_Plan_R1.docx DOCX document
0003_Full_FAT_plan_R1.docx DOCX document
Attachment_0021_Request_for_Waiver_of_First_Article_Testing_Requirements_.docx DOCX document
0013_Transaction_Format.docx DOCX document
0012_Packaging_Data_Products.docx DOCX document
0007_How_To_Access_AMPS_to_Request_WebFLIS_RoleV3.pdf PDF
0005_CARC_Paint_Drawing_12585018.pdf PDF
0009_TRM_TABLE_A-IV_-_TM_Requirements_Matrix_-23&P.docx DOCX document
0015_TRM-_TPG_2016-01_Source_Data.pdf.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 0021 - Request for Waiver of First Article Testing Requirements

Request for Waiver of First Article Testing Requirements Requirements for First Article Testing are specified in Section C.5 – C.5.3.11.2 of the solicitation. The offeror shall provide proposed prices for CLINs 0001, 0002, and 0003 as part of its Price Factor submission in Attachment 0017 – Pricing Spreadsheet.

PLEASE NOTE: The Government does NOT intend to require all activities under CLIN 0001, 0002, and 0003 during contract performance; only one of the FAT requirements is necessary and will be required depending upon whether offeror’s proposed solution has been previously delivered to/accepted by the Government, and (if so), how recent a previously delivered/accepted proposed system was last produced. Therefore offerors shall provide a completed Waiver of First Article Testing Requirements with its proposal which the Government will consider in the evaluation.

INSTRUCTIONS TO THE OFFEROR: It is expected for each offeror to request one of the three Waiver Request options below as part of its proposal, which will enable the Government to eliminate certain priced CLINs during the evaluation phase of the Price Factor. The offeror shall select one of the Waiver Request options based on the system being proposed, and submit this completed Request as part of its proposal. The offeror can only request waivers specific to one of the three options below. If the subject waiver is approved, all related CDRLs and resulting requirements will be removed upon award. We reserve the right to request additional information to determine whether a Government Full Material Release (FMR) has been obtained.

CLIN
0001
0002
0003
SOW Reference
C.5.3
C.5.2
C.5.1
Waiver Request: Select 1 from below 3 choices – X (on the right 3 columns) indicates test activity requested to be waived by Offeror.
Full FAT
PQT
PVT

☐ Option 1: Offeror proposes a new system that has not been previously delivered to and accepted by the Government.

X
X
☐Option 2: Offeror proposes existing system which has not been produced within the last two years from RFP closing date.
X

X

☐Option 3: Offeror Proposes existing system which has been produced within the last two years from RFP closing date.
X
X

If your company proposes Option 1 waiver, please acknowledge the following:

Our company is producing a new system not previously delivered to, and accepted by the Government, and is therefore seeking a waiver from PQT and PVT.

Signature: _____________________
Name: ________________________
Title: _________________________

If your company proposes waiver Options 2 or 3, please complete items 1 and 2 below.

(1) Identify the location where your proposed system/NSN has been manufactured: _____________________________________________________________

(i) Confirm your proposed system was previously furnished by the same manufacturer within the past two years and accepted by the Government by providing the following information:

(a) Contract Number(s):___________________________ Date of most recent acceptance:_______________________________________ Issuing Government Agency (ies):____________________________

(b) Item previously furnished to and accepted by the Government:

NSN: _____________________________________

Part number: _______________________________

(c) Automotive Tank Purchase Description (ATPD) and Version No. the proposed NSN complies with:

(2) Certify to the following information:

(i) There have been no changes to manufacturing processes, tooling, or locations used to manufacture the items successfully in the past;

(ii) There have been no changes to manufacturing data (e.g., drawing revisions that change materials, dimensions, processes, inspection or testing requirements used to manufacture the items successfully in the past);

(iii) The proposed item will be the same design and manufactured by same method at same facilities as item previously accepted by the Government.

I certify the information provided in Section 2 is true and pertains to NSN _______________, and is the identical system proposed in Section 1.