Attachment II Quality Assurance Surveillance Plan.pdf
PDF 191 KB Posted
- Solicitation number
- W51AA127QA004
- Issued by
-
Department of the Army
About this file
This is a Quality Assurance Surveillance Plan (QASP) for preventative maintenance, diagnostic inspections, and repairs of thirty-nine (39) 400 Hz cycle converters at Tobyhanna Army Depot (TYAD). The contract, identified as W51AA1-26-QA057, is administered by U.S. Army Contracting Command – Aberdeen Proving Ground (ACC-APG), Tobyhanna Division, with the requiring activity being TYAD's Directorate of Public Works/Maintenance Division in Tobyhanna, Pennsylvania.
The QASP establishes systematic surveillance procedures and evaluation methods for monitoring contractor performance across four primary performance objectives: (1) scheduled preventative maintenance execution without unexcused schedule deviations, with 100% inspection methodology and zero defects acceptable quality level; (2) Stage 1 emergency on-site response within a mandatory 48-hour window with zero deviation tolerance and 100% audit of dispatch logs; (3) Stage 1 diagnostics and quote submission within 15 calendar days with quotes valid for 60 days, requiring 100% technical review; and (4) Stage 2 emergency repair execution within five business days of contract modification executed to original equipment manufacturer specifications with 100% successful load testing required. All thirty-nine converters must be maintained in 100% operational condition under load, with Tier III idle/storage units exempt from annual load-bank testing unless recalled to active status. The COR maintains complete surveillance documentation including daily logs, all deliverables, dispatch records, and Contract Discrepancy Reports. Defective service triggers corrective action requirements, with potential remedies including price reductions, third-party re-performance charges, adverse contractor performance ratings, or termination for cause. The plan incorporates rigorous safety (OSHA/EM 385-1-1), security (Form ELTY 648-C access credentials), and environmental compliance (60% construction and demolition waste diversion) surveillance requirements conducted by TYAD functional advisors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment I Performance Work Statement.pdf | ||
| Attachment V 648C Request for Access to TYAD.pdf | ||
| Attachment III Proposed Pricing Worksheet.xlsx | XLSX spreadsheet | |
| RFQ W51AA127QA004 - 400Hz Coverters.pdf | ||
| Attachment IV 400 Hz Converters List.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
PREVENTATIVE MAINTENANCE, DIAGNOSTIC
INSPECTIONS, AND REPAIRS THIRTY-NINE (39) 400 Hz
CYCLE CONVERTERS
TOBYHANNA ARMY DEPOT (TYAD)
Date Prepared: November 18, 2026 Contracting Activity: U.S. Army Contracting C ommand – Aberdeen Proving Ground (ACC-APG), Tobyhanna Division Requiring Activity: Tobyhanna Army Depot (TYAD), Directorate of Public Works / Maintenance Division, Tobyhanna, PA 18466
1. PURPOSE AND AUTHORITY
1.1 Purpose
This Quality Assurance Surveillance Plan (QASP) is developed in accordance with RFO FAR 37.604, RFO FAR 46.401, and DoDI 5000.72. It establishes the systematic procedures and evaluation methods the United States Government will utilize to monitor, inspect, and evaluate the performance of the Contractor under Solicitation/Contract W51AA1-26-Q- A057 for 400 Hz Cycle Converter Preventative Maintenance, Diagnostic Inspections, and Repairs at Tobyhanna Army Depot (TYAD).
This QASP provides a structured surveillance framework to ensure that:
(a) All thirty-nine (39) 400 Hz cycle converters are maintained in a 100% operational condition under load; Tier III idle/storage units are not subject to annual load-bank testing unless recalled to active status, consistent with PWS 5.2.1.3.
(b) Scheduled Tier I, Tier II, and Tier III preventative maintenance services are executed without unexcused schedule deviations;
(c) Stage 1 emergency call-out assessment and diagnostic visits are performed on-site within the mandatory forty-eight (48) hour response window;
(d) Stage 2 approved emergency repairs are initiated within five (5) business days of contract modification and executed to original equipment manufacturer (OEM) specifications;
(e) All physical security, safety (OSHA / EM 385-1-1 / TYAD Safety Reg 385- 1), environmental (TYAD Reg 200-5), and administrative deliverable requirements are fully satisfied.
1.2 Authority
Government contract quality assurance is performed in accordance with RFO FAR Part 46, RFO DFARS Part 246, AFARS 5137.590, and the terms of the contract. QASP updates may adjust internal surveillance procedures only and may not alter scope, performance standards, AQLs, deliverables, price, or other contract terms without written acceptance by the Contracting Officer.
2. ROLES AND RESPONSIBILITIES
2.1 Contracting Officer (KO)
The Contracting Officer is the sole individual authorized to legally bind the Government, modify contract terms, issue bilateral contract modifications for Stage 2 repairs, deduct funds for non-conforming service, or terminate performance. The KO shall:
(a) Appoint the Contracting Officer’s Representative (COR) in writing IAW DoDI 5000.72;
(b) Review COR surveillance logs, inspection reports, and Contract Discrepancy Reports (CDRs);
2.2 Contracting Officer’s Representative (COR)
The COR is appointed in writing by the KO to perform daily technical surveillance of contractor performance. The COR does not have the authority to alter contract scope, terms, pricing, or period of performance. The COR shall:
(a) Maintain complete surveillance files and inspection logs for every service visit and repair action;
(b) identify/document deficiencies, prepare or recommend CDRs, review QCP/Work Plan changes, and recommend action; KO issues contractual CDRs, accepts QCP changes where required, and determines remedies.
(c) Approve written changes to the Contractor’s Quality Control Plan (QCP) and Work Plan.
(d) Conduct 100% inspection of all maintenance reports, diagnostic quotes, and load-test verifications;
(e) Track emergency call-out dispatch logs to verify compliance with the 48-hour response standard;
(f) Verify contractor compliance with Lockout/Tagout (LOTO), TYAD Form 648-C access requests, security clearances, and safety/environmental submittals;
(g) Review and recommend KO approval for Stage 1 diagnostic quotes prior to Stage 2 repair authorization;
(h) Document contractor performance annually in the Contractor Performance Assessment Reporting System (CPARS).
2.3 TYAD Functional Advisors (Safety & Environmental)
• TYAD Safety Office: Audits contractor compliance with OSHA 29
CFR 1910/1926, EM 385-1-1, Activity Hazard Analyses (AHAs), Confined Space Permits, Crane Lift Plans, Silica Control Plans, and enforces the depot "Red Card" work stoppage program.
• TYAD Environmental Branch (EB): Audits contractor compliance with TYAD Reg 200-5 (ISO 14001 EMS), Safety Data Sheets (SDSs), hazardous waste disposal manifests, and the mandatory 60% construction and demolition (C&D) recycling diversion requirement.
2.4 Contractor Personnel
• Contract Manager & Alternate: Key personnel designated in writing to manage daily operations serve as the single point of contact for the COR and maintain authority to act for the Contractor on all operational matters.
• Quality Control Manager: Responsible for executing the contractor’s internal QCP, conducting pre-delivery inspections, verifying load-test compliance, and ensuring non-reoccurrence of service defects.
3. SURVEILLANCE METHODOLOGY & METHODS
3.1 Primary Surveillance Methods
The Government will utilize three primary methods of surveillance under this QASP:
1. 100% Inspection: Applied to all core technical and emergency deliverables. Every PM report, emergency diagnostic report, emergency repair completion report, and on-site load-test demonstration will be 100% inspected and verified by the COR.
2. Periodic Inspection: Applied to safety compliance, environmental management, badge accountability, key control, and training records.
The COR, Safety Office, and Environmental Branch will conduct periodic unannounced inspections of on-site job sites, LOTO isolation points, and secondary containment areas.
3. 100% Audit of Call-Out Dispatch Logs: Applied to emergency response timelines. The COR will compare the exact timestamp of Government emergency notification against the physical gate arrival log of the contractor’s technician to verify compliance with the 48-hour response standard.
PRS
Performance Objective
PWS
Ref
Performance Standard
Acceptable Quality Level
(AQL)
Surveillance Method
Record / Artifact
PRS Scheduled 5.2.1 Perform scheduled PM, execute
Zero 100% PM
#1 Preventative minor repairs unexcused Inspection of Inspection Maintenance
& Minor Repairs
Clean/replace filters test converters IAW manufacturer specs schedule deviations;
100% compliance with Tier PM tasks; NLT 15-day report submittal.
PM reports and equipment physical status.
Reports;
COR
Inspection Log.
PRS Stage 1: 5.2.2.1 Qualified Zero deviation 100% COR #2 Emergency
On-Site Response technician arrives on-site at TYAD for emergency troubleshooting upon COR notification.
from the mandatory 48-hour on-site response window
Inspection of COR dispatch records and gate arrival logs.
Emergency Call-Out Log; TYAD Gate Access Log.
PRS Stage 1: 5.2.2.1 Perform on-site Zero deviation 100% Review Diagnostic #3 Diagnostics &
Quote Submission troubleshooting underload and submit itemized diagnostic report and repair price quote.
from 15-calendar-day submission window for quote valid for 60 days and technical analysis of diagnostic quote package by
COR.
Report & Repair Quote
PRS Stage 2: 5.2.2.3 Initiate repairs Pass/Fail; 100% Bilateral
#4 Emergency Repair Execution & Reporting within 5 business days of contract modification;
execute to OEM specs; load-test;
submit completion report within 15 days
100% prior
KO/COR
written modification authorization before work start; 100% successful load test
Government physical inspection, load-test observation, and report audit
Contract Mod;
Repair Report;
physical load test validation
3.2 Rating & Performance Evaluation Metrics
Performance will be evaluated against the standards and Acceptable Quality Levels (AQLs) specified in Technical Exhibit A (PRS). Performance levels are categorized as:
• Met / Satisfactory: Service output meets or exceeds the PWS standard and AQL threshold.
• Unsatisfactory / Defective: Service output fails to meet the PWS standard or exceeds the allowable AQL threshold.
4. PERFORMANCE REQUIREMENTS SUMMARY (PRS) & SURVEILLANCE MATRIX
The following surveillance matrix directly maps all the four primary performance objectives, performance standards, AQLs, surveillance techniques, and record artifacts.
5. DOCUMENTATION & SURVEILLANCE PROCEDURES
5.1 COR Surveillance Folder
The COR will maintain a master electronic surveillance file containing:
(a) Copy of the contract, all modifications, PWS, and this QASP;
(b) Written COR designation letter from the Contracting Officer;
(c) Accepted Quality Control Plan and Work Plan;
(d) COR Daily/Weekly Surveillance Logs and equipment inspection checklists;
(e) All submitted deliverables
(f) Gate entry logs, call-out dispatch records, and load-test verification sheets;
(g) Copies of all Contract Discrepancy Reports (CDRs) and corrective action communications.
5.2 Inspection & Acceptance Process
1. Scheduled Preventative Maintenance: The COR will inspect unit operation under load during or immediately following PM visits. Within fifteen (15) days of service, the contractor submits the PM Report. The COR verifies that all task steps (a-f) were completed, signs and approves the invoice in WAWF. Emergency Diagnostic Visits (Stage 1): Upon notification of a breakdown, the COR logs the dispatch time.
Upon technician arrival, the COR verifies arrival time against the 48-hour standard.
Within fifteen (15) days, the contractor submits the Diagnostic Report and Quote.
The COR performs technical analysis to verify labor hours and part costs.
2. Emergency Repair Execution (Stage 2): Following KO execution of a bilateral modification funding an FFP repair SLIN under CLIN 0003, the contractor initiates work within 5 business days. Upon completion, the contractor demonstrates unit operation under load using a Contractor-Furnished load bank in the presence of the COR. Upon successful load testing and receipt of the Repair, the COR accepts the repair in WAWF.
6. PROCEDURES FOR UNSATISFACTORY PERFORMANCE & DEFECTIVE SERVICE
6.1 Defective Service Identification
If Government surveillance indicates that services do not conform to contract requirements, the COR will document the deficiency in the surveillance log and notify the Contract Manager verbally within two (2) hours and in writing within twenty-four (24) hours.
6.2 Contractor Reperformance / Correction
For minor discrepancies that can be corrected immediately on-site (e.g., missing PM report detail, uncleaned cabinet debris), the Contractor shall re-perform or correct the service at no additional cost to the Government within forty-eight (48) hours of notification.
6.3 Contract Discrepancy Report (CDR)
For major deficiencies, repeated minor discrepancies, failure to meet the 48-hour emergency response standard, or uncorrected defective service:
1. The COR will draft a formal Contract Discrepancy Report (CDR) detailing the PWS violation, standard missed, and location.
2. The KO will issue the CDR to the Contractor.
3. The Contractor shall respond in writing within five (5) working days of receipt, identifying the root cause, corrective actions taken, and preventive measures implemented to ensure non-recurrence.
4. The KO will evaluate the response to determine if the corrective action is acceptable.
6.4 Deductions and Contract Remedies (RFO FAR 46.407)
If the Contractor fails to correct defective services after written notice, or if re-performance is impossible (e.g., missed 48-hour emergency response window):
(a) The Contracting Officer may reduce the contract price to reflect the reduced value of the services performed IAW RFO FAR 46.407;
(b) The KO may perform the service via Government or third-party resources and charge the full cost of re-performance to the Contractor;
(c) Continued unsatisfactory performance will result in adverse CPARS ratings and potential Termination for Cause / Default.
7. SAFETY, SECURITY & ENVIRONMENTAL SURVEILLANCE
7.1 Safety Surveillance
The COR and TYAD Safety Office will monitor strict compliance with OSHA, EM 385-1-1, and TYAD Safety Reg 385-1.
• LOTO Audit: The COR will conduct 100% inspection of energy isolation protocols prior to any internal cabinet servicing or panel removal.
• Red Card Enforcement: Any depot employee presenting a Red Card causes an immediate work halt. The COR and Safety Office will inspect the site before work is authorized to resume.
• Accident Reporting: All near misses and injuries must be reported to the COR immediately. OSHA 301 reports must be delivered within 5 days.
7.2 Security Surveillance
The COR will continuously audit base access credentials. Form ELTY 648-C must be submitted 10 days prior to visits. All badges and CACs must be accounted for and returned within 3 days of employee exit or contract end.
7.3 Environmental Surveillance
The Environmental Branch will audit hazardous material SDSs 5 days prior to arrival on post. The COR will inspect quarterly C&D landfill weight slips to verify that at least 60% of non-hazardous waste is diverted from landfills.
| QUALITY ASSURANCE SURVEILLANCE PLAN (QASP) |
| TOBYHANNA ARMY DEPOT (TYAD) |
| 1. PURPOSE AND AUTHORITY |
| 1.1 Purpose |
| 1.2 Authority |
| 2. ROLES AND RESPONSIBILITIES |
| 2.1 Contracting Officer (KO) |
| 2.2 Contracting Officer’s Representative (COR) |
| 2.3 TYAD Functional Advisors (Safety & Environmental) |
| 2.4 Contractor Personnel |
| 3. SURVEILLANCE METHODOLOGY & METHODS |
| 3.1 Primary Surveillance Methods |
| 4. PERFORMANCE REQUIREMENTS SUMMARY (PRS) & SURVEILLANCE MATRIX |
| 5. DOCUMENTATION & SURVEILLANCE PROCEDURES |
| 5.1 COR Surveillance Folder |
| 5.2 Inspection & Acceptance Process |
| 6. PROCEDURES FOR UNSATISFACTORY PERFORMANCE & DEFECTIVE SERVICE |
| 6.1 Defective Service Identification |
| 6.2 Contractor Reperformance / Correction |
| 6.3 Contract Discrepancy Report (CDR) |
| 6.4 Deductions and Contract Remedies (RFO FAR 46.407) |
| 7. SAFETY, SECURITY & ENVIRONMENTAL SURVEILLANCE |
| 7.1 Safety Surveillance |
| 7.2 Security Surveillance |
| 7.3 Environmental Surveillance |