Attachment 0013_2026-0211_Questions and Answers.pdf

PDF 661 KB Posted

Attached to
Bldg Repair & Renovation - Garrison Consolidation
Solicitation number
W519TC-26-R-A044
Issued by

About this file

This document is a Solicitation Questions and Responses (Q&A) for the B104 Garrison Consolidation project (PR 2026-0211) dated July 14, 2026, containing 166 numbered questions and corresponding answers addressing contract clarifications.

The project involves renovation work at Building 104 on a military garrison, requiring selective demolition, abatement, and renovation of interior spaces totaling approximately 13,290 square feet. Key scope elements include asbestos and lead-based paint abatement in designated areas; demolition of walls, ceilings, and flooring; concrete repairs and masonry work; new electrical, HVAC, plumbing, and fire alarm system modifications; flooring and finish installations; and furniture relocation and reinstallation. Critical constraints include a 120 working day completion schedule after Notice to Proceed, phased construction requirements to maintain egress and building operations, and restrictions on work in occupied areas during normal business hours in the north and east wings. The West wing will remain unoccupied during construction. Performance and payment bonds are required, with bids held firm for 90 calendar days. A Level One Site Safety and Health Officer with full-time responsibilities must be designated separately from the superintendent. Notable considerations address long-lead items such as BAA-compliant lighting fixtures (14-16 week lead times) and fire alarm system design review periods (6-8 weeks), with contractors directed to submit these items immediately upon Notice to Proceed. Hazardous materials abatement, including specific VCT and mastic removal requirements, will be performed by the contractor as part of the prime contract scope and incorporated into the safety program.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B104 Garrison Consolidation (PR 2026-0211) Solicitation Questions and Responses (1-166) 14 July 2026

Question 1: Asbestos – D1/H-101, please identify existing wall/partitions that are masonry to confirm LBP removal quantities.

Response - Lead Base Paint shall be assumed in stone/brick walls only, note that per prior project from October 1980 Record Drawing 30-04-10 all existing stone walls in the stairwells were sandblasted and sealed.

The stairwells are in the majority the only masonry walls to be painted. See floor plan for stairwells dimensions and supplemental Record Drawing (highlighted areas) for more detail.

Question 2: Asbestos – AD101, confirm if stair treads per KN#4/AD101, KN#4/AD102, and KN#11/AD103 are LBP.

Response - There is no suspected asbestos or LBP on existing stair treads.

Question 3: Asbestos – AD101, confirm if wall paint per KN#6/AD101 is LBP.

Response - Only the Stairwell has painted masonry (stone/ brick) exposed. See response of question 1 Question 4: Asbestos – AD101, confirm height of 380 LF of wall to receive new paint.

Response - Interior walls at ceiling height ±10’-0”, Vestibule ±14’-0”, see record drawings for stairwells.

Question 5: Asbestos – AD101, confirm how many layers of existing VCT sub floor are to be removed and if we also remove mastic as asbestos per

KN#7/AD101.

Response - Just one layer of existing VCT subfloor. Abate the mastic associated that is asbestos contained material detected on the NE vestibule. See the supplemental sheets for Appendix E

Question 6: Asbestos – AI/AD102, confirm if wall paint per KN#5/AD102 is LBP.

Response - LBP is only suspected at the Stone / Brick walls, for ended only in stairwell masonry walls. Approximately ±21’ x ±11’ – See record drawing

Question 7: Asbestos – A1/AD102, confirm height of 153 LF of wall to receive new paint per KN#5/AD102.

Response - See question # 4 Question 8: Asbestos – A1/AD103, confirm if wall paint per KN#4/AD103 is LBP.

Response - See question # 1 Question 9: Asbestos – AD103, confirm height of 1400 LF of wall to receive new paint per KN#4/AD103.

Response - See question # 4 Question 10: Demolition – AD101, confirm if any furniture requires relocation per

KN#5/AD101.

Response - Dispose furniture, if any relocation/reassemble it will be coordinated by the C.O. R. within B104.

Question 11: Demolition – AD101, confirm height of 380 LF of existing walls per

KN#6/AD10.

Response - See question # 4 Question 12: Demolition – A1/AD102, confirm we are to reinstall furniture per

KN#6/AD102.

Response - Furniture to be disassembled just to allow space to perform the new work shall be reassembled back in place as noted in the partial furniture plans. Contractor to decide if they need to remove the furniture to perform the new work.

Question 13: Demolition – A1/AD102, confirm we will be able to store furniture on the same floor and wing per KN#6/AD101.

Response - Yes Question 14: Demolition – A1/AD103, confirm conference room furniture storage to be in the same wing per KN#6/AD103.

Response - Storage location is “to be determinate” within the complex building

B102-B104, note that the freight elevator of the complex is in B102.

Conference Furniture could be stored in the west wing per the Contractor’ schedule, or to work around the furniture to be protected while performing the work. See picture attached.

Question 15: Demolition – Confirm if we are to reinstall conference room furniture.

Response - Yes, see keynote #18 on A-103 Question 16: Demolition – Please provide furniture layout of conference room furniture per KN#6/AD103.

Response - See picture attached.

Question 17: Demolition – Confirm cubicle furniture, cabinets, and chairs for complex 102-104 storage to be in the same wing per KN#12/AD103.

Response - Storage location is “to be determinate” within the complex building

B102-B104, note that the freight elevator of the complex is in B102.

Furniture in room N105 without label is to be dispose, furniture with label to be reassembled in the West wing according to Furniture plans. Room W133 Furniture could be stored in the west wing per the Contractor’ schedule, or to work around the furniture to be protected while performing the work.

Question 18: Demolition – Confirm if we are to reinstall any cubicle furniture, cabinets, and chairs in complex 102-104 per KN#12/AD103.

Response - See question # 17 Question 19: Demolition – Please confirm subfloor construct to be removed per

KN#13/AD103.

Response - Only if VCT sub-flooring is present. See H-102 Question 20: Demolition – Please confirm if there is ceiling demo. If so, please provide reflective ceiling demo plans-assume demo of ex ceilings at new walls and ceiling locations.

Response - See plans AD106, AD108 and AD109. See keynote #1 in A-106, A108 and A109

Question 21: Demolition – A200, please provide landscaping specifications, including required topsoil per KN#5/A-201.

Response - Topsoil must be of uniform quality and free of hard clods, stiff clay, roots, litter and stones larger than 1” and shall receive type 1 permanent grass seed found in section 9010 of Iowa SUDAS specs 2026. If the area of completion falls outside of the seeding window, dates specified in Iowa SUDAS specs 2026 approval of application must be received from the C.O.R. If the project is stopped by winter the contractor shall apply a temporary winter type 5 mixed prior to work ceasing. Once the seeding dates are open again, the type 5 mix shall be tilled, reworked and planted with the correct type 1 seed mixture.

Question 22: Demolition – A200, please confirm wood window removal is to be done by asbestos contractor – per KN#6/A-201 and H-101. Please also confirm if glazing compound is asbestos.

Response - Glazing in original historical windows shall be assumed to be asbestos and led containing material. See page H-102

Question 23: Demolition – MD103, acoustical ceilings will need to be removed and replaced in order to complete the HVAC demolition per MD-103, but the corresponding reflected ceiling plan A-108 does not show any new acoustical ceiling work.

Response - Please see A-108 between columns H and G, and West corridor/ open areas, from column 5 and 9.

Question 24: Concrete – A105, please provide quantity of crack and spall repairs including repair procedure per KN#5/A-105.

Response - Account for the repairs after demolition of cages, walls and the establishment of new Egress path areas. See AD105 and A-105

Question 25: Concrete – Please provide detail for rebuilding moat wall per

KN#11/A-201

Response - Restore the moat wall to the original operation after the removal of the stairs. To match existing, see picture B5/B201

Question 26: Masonry – Please provide masonry specification.

Response - See Keynote # 15, A-201 Question 27: Masonry – A602, please confirm which doors receive head detail C8 and jamb detail B8 per A-602.

Response - SWBE door, See A-201 and A-105 Question 28: Tile – AD101, will moisture mitigation be required for new floor tile per

KN#7/AD101 and KN#2/AD102?

Response - Follow manufacturer recommendations Question 29: Flooring – AD101, confirm if we need to apply moisture mitigation at new carpet per KN#2/AD101.

Response - Follow manufacturer recommendations Question 30: Flooring – Confirm whether moisture testing, alkalinity testing, vapor mitigation, primer, or slab treatment is required before installing sheet vinyl or carpet over existing concrete substances. (Spec 09 65 00 / Spec 09 68 00 / ASTM F710 / Manufacturer Instructions)

Response - Follow manufacturer recommendations Question 31: Signage – Please confirm if signage is part of our scope of work.

Response - No

Question 32: Toilet Accessories – A302, please confirm if toilet accessories (ie manual paper towel dispenser, manual soap dispenser) is per A-302 by owner. If not, please provide specification.

Response - Provided & installed by Contractor.

Question 33: Toilet Accessories – Please confirm that microwave ovens are F&I by owner per D1/A-302.

Response - Microwaves provided by Government.

Question 34: Plumbing – Please confirm if existing building has sprinkler fire protection system. If so, please provide drawings.

Response - Sprinkler work is not part of this contract.

Question 35: Plumbing – M002 – KEYNOTE 66/M-002 is not shown on the drawings.

Response - Keynote 66 is shown on Drawing MD-108 near column lines A and

15.

Question 36: Plumbing – M002 – KEYNOTE 67/M-002 is not shown on the drawings.

Response - Keynote 67 is shown on drawing M-105 and M-107.

Question 37: HVAC – Please provide as builts of basement and first floor showing wall and ceiling types in order to price new penetrations, and in fill at old penetrations.

Response - The walls in question are gypsum on studs on the basement and first floor. The offices in the basement below the east and west restrooms have lay-in ceiling tile.

Question 38: HVAC – MD103, Acoustical ceilings will need to be removed and replaced in order to complete the HVAC demolition per MD-103, but the corresponding reflected ceiling plan A-108 does not show any new acoustical ceiling work.

Response - See AD108 and A-108 Question 39: HVAC - MD105 – Please confirm that there are no finish ceilings in the basement that will need to be removed and reinstalled in order to complete HVAC demotion per MD-105, MD-106, MD-107, MD-108, and new work.

Response - There is existing lay-in ceiling that affects the work associated with Keynote 56 on Sheet MD-106. The offices in the basement below the east and west restrooms have lay-in ceiling tile.

Question 40: Many of the keynotes for the HDMI cables state to connect to a floor box, but there is no floor box shown on the drawings. Can either the floor box be added to the drawings, or can we get a recommended length for the HDMI cords?

Response - Refer to Keynote 58 on Drawing EP-101. Refer to Keynote 66 on Drawing EP-103. Refer to Keynotes 58, 64 and 53 on Drawing EP- 104.

Question 41: What is the HDMI conduit size? Minimum required is 1-1/4”.

Response - Contractor shall determine the minimum size required for the installation of the HDMI cable.

Question 42: Can the existing IT Room be identified on the drawings?

Response - Refer to Comm Rm E152 and Comm N124 on Drawing AD-101 and

Comm Rm W144 on Drawing AD-103.

Question 43: Is Cat6 or Cat6A cabling required? Both are mentioned in the specs.

Response - Anything new to be installed needs to be Panduit CAT6. Blue CAT6 for phone and White CAT6 for LAN connections.

Question 44: Is there a certain cable manufacturer that we need to use?

Response - See the response to Question 43.

Question 45: How many cables are needed at each location? Keynote 73 states new voice/data port but does not give a count.

Response - All wall mounted outlets require one voice and one data outlet. Drops to furniture require one voice and one data outlet per work station and printer. Refer to the furniture drawings for the number of work stations and printer locations.

Question 46: Please confirm there is no pipe insulation to be abated.

Response - There is no pipe insulation to be abated.

Question 47: Please confirm we are only abating the 3 rooms clearly marked in red on H101, or is it all the ACM listed needing to be abated in both H101 and H102?

Response - Revise drawings and Appendix E / supplemental Question 48: Please confirm that the 3 rooms on H101 is the only asbestos abatement on this project.

Response - Revise drawings and Appendix E / supplemental Question 49: Can the superintendent perform all three roles of Super, QC Manager, and SSHO?

Response - No, the SSHO is a designated employee with full-time SOH responsibilities. See Specs 01 35 26

Question 50: Please confirm requirements for temporary partitions in occupied working spaces, particularly for the first-floor Southeast wing open office area.

Response - Contractor responsible for isolating construction work on Basement North and Southeast wing, partition shall be solid and secure designed to allow users of the Contractor office (NE) and Supply Store, Room E-90 (SE) that will be operating on a regular basis.

Question 51: Please provide a specification section for Masonry and Steel work.

Response - See A-201 Question 52: Please provide a description of the sub-floor makeup for all areas of work.

Response - See H-101, H-102 and A-603 Question 53: Please confirm specifics of the furniture relocation/disassembly/reassembly scope; specifically, who (contractor or owner) is responsible for moving the furniture, where the furniture will be stored if contractor responsibility. If the contractor is responsible for moving the furniture to the original/new locations, and if the contractor will be responsible for assembling/reassembling any furniture.

Response - Contractor is responsible for furniture relocation (disassemble, reassembly), storage (disassemble) within the complex B102-B104, temporary relocation to perform the work and disposal.

Question 54: Please confirm if jobsite storage/trailer will be required, or if we will be provided with an unoccupied space on site/in the building to utilize.

Response - The West wing of B104 is vacant and an office space can be used during construction.

Question 55: Please confirm if basement ceiling paint is lead based, and if any remediation is required. If so, what type of remediation is preferred?

Note, that per the walkthrough, this paint is severely chipping/flaking, and it will likely be disturbed by construction operations.

Response - Assume LBP in basement ceiling, encapsulation is preferred.

Question 56: For lead remediation, please confirm if lead paint should be encapsulated or removed, and if this scope applies in any way to the steel columns throughout the building.

Response - Only stone/brick walls shall be encapsulated where required to be painted, steel columns to be paint only.

Question 57: Fire Alarm/Mass Notification - E-002, Keynote 72 calls out the installation of a new Audio/Visual Combination Notification device.

This existing system utilizes separate speakers and dual strobe devices (Amber/Clear). Are we to match existing devices, or utilize a combination device in these locations?

Response - Keynote 72 only addresses Visual Notification Devices. I believe that you are asking about Keynote 71. Yes, the intent is to match the existing system devices.

Question 58: Fire Alarm/Mass Notification - Spec 283176, Section 1.3.1 calls out the requirement for designing and modifying the existing fire alarm and Mass Notification. Looking at the drawings, it doesn’t appear all of the existing MNS devices are shown on the bid drawings. We show many more devices on the 2104 MNS upgrade drawings. The concern would be whether there have been modifications in the last 12 years, and the missing devices are actually removed. If so, there could be areas where devices in addition to what is shown on the bid drawings may be required. We assume the intent is to only modify what is shown on the bid drawings, and that only devices being modified or added are shown. Please confirm.

Response - Yes, that assumption is correct. We did not show all existing devices on the drawings.

Question 59: Fire Alarm/Mass Notification - In the specification 283176, 1.8.1.3, 1.8.1.4, requires wiring items for the system. We can use the wiring drawings from the 2014 project as a baseline, assuming there haven’t been modifications. 1.1.1.11 requires complete as-built drawings. As with the previous sections, we can assume the 2014 installation is as it was installed. Without using the 2014 drawings, it won’t be feasible to provide these details since much of the system is not being removed, rewired, or replaced. Is our approach acceptable?

Response - Yes, your approach is acceptable.

Question 60: Fire Alarm/Mass Notification - Spec 283176, section3.4.4 (Govt Final tests) and 3.5.1(Minimum Tests) requires loop resistance testing. This is pretty common on completely new system installations. We can perform these tests using the 2014 installation drawings as the guide for where the furthest point is for this test. Is that acceptable?

Response - Yes, that is acceptable.

Question 61: Fire Alarm/Mass Notification – Spec 283176, section 3.5.1.e requires test of battery backup. We are not contracted to maintain the system batteries or annual testing, so we do not have a baseline for this other than the 2014 calculations. We will replace the batteries in the transponders that feed these areas unless directed otherwise. This will allow us to recalculate the estimated battery backup, and verify that it is at the standby requirements of the system as it was installed in 2014. Is our approach acceptable?

Response - Yes, your approach is acceptable.

Question 62: Fire Alarm/Mass Notification - Are there any known deficiencies you would like us to cover as part of this project? Since we are not under contract to maintain the system, we are not always aware of any existing conditions the Government will need to be resolved. We will typically exclude repairs of pre-existing issues on construction projects. Please advise if there are any existing issues we should get rectified under this project.

Response - There are no known existing system deficiencies that need to be resolved as part of this project.

Question 63: General / Existing Conditions – Confirm note 23 on drawing G-004, building related permits required? By GC?

Response - Contractors shall navigate the Department of The Army regulatory framework, specifically to hot work permits, digging permits, environmental permits if required at any moment during the performance of the contract.

Question 64: General / Existing Conditions – Confirm if the government requires the master schedule to be submitted via specific software (e.g., Primavera P6) or if standard scheduling platforms such as MS Project are acceptable.

Response - Yes, any standard platform will be accepted Question 65: General / Existing Conditions – Clarify if there are specific hours or route restrictions enforced by the base for heavy-vehicle delivery hauling routes.

Response - Heavy-vehicle delivery & hauling are to use Moline Gate from 07:00 am to 05:00 pm

Question 66: General / Existing Conditions – Identify the contractor laydown, storage, dumpster, trailer, and employee parking areas within the installation.

Response - To be determined during pre-construction meeting. See response to question # 54.

Question 67: General / Existing Conditions – Identify whether contractor escorts are required for deliveries, after-hours work, or access to secured areas.

Response - No escort will be provided; see requirements at https://home.army.mil/ria/about/visitor-information

Question 68: General / Existing Conditions – Identify Government notification requirements for all building utility shutdowns (electrical, HVAC, domestic water, communications, fire alarm).

Response - Coordinate the request with C.O.R. 15 days prior any utility shutdown Question 69: General / Existing Conditions - Confirm if the government-furnished office desks and modular panels require re-installation under a later phase or if they are permanently leaving the facility.

Response - See Picture request 4: Pictures # 7 Question 70: General / Existing Conditions – Identify any core building utilities passing through the ±13,290 s.f. footprint that must remain active during the selective strip-out.

Response - All core building utilities to remain active unless required (temporary) in appendix B

Question 71: General / Existing Conditions – Clarify if the State Historic Preservation Office (SHPO) or a local installation preservation officer requires physical mockup inspections and field approvals for the matched mortar, plaster, and replicated trim profiles before full-scale application.

Response - We don’t require mockups, just submittals.

Question 72: General / Existing Conditions – Identify if the concealed structural metal plates used to reinforce the historic stairs require third-party non-destructive testing (NDT) or field welding certification checks upon assembly.

Response - Not applicable, no welding required.

Question 73: General / Existing Conditions – Clarify total stair tread count for NE-B, SE-B, and NW-B stairwell renovations based on Drawing A-603.

Response - See Appendix B and requested pictures Question 74: General / Existing Conditions – Are original historical architectural profile details or milled drawings for Building 104's baseboards, moldings, and balusters available as Government-Furnished Information (GFI) to expedite knife fabrication, or is the contractor entirely dependent on taking physical field mold impressions during Phase 2 mobilization?

Response - Not applicable, not working on historical baseboards, molding or balusters.

Question 75: General / Existing Conditions – Provide a consolidated list of all Government-Furnished Equipment (GFE), Government-Furnished Contractor-Installed (GFCI), and Owner-Furnished Contractor- Installed (OFCI) items for the entire project.

Response - 4 TV’s and a Depository Safe to be Contractor Furnished and Installed as required on Appendix B

Question 76: Abatement / Demolition – Is there any pipe insulation that needs to be abated?

Response - See Appendix B, Appendix E and supplemental information Question 77: Abatement / Demolition – Three identified rooms in diagram H101 and ALL the floor tile in H102 diagram need to be abated? Or is H102 just spot abatement for penetrations?

Response - See Appendix B, Appendix E and supplemental information Question 78: Abatement / Demolition – All abatement and demolition is to be completed by the awarded subcontractor(s) and not any individual trades other than possible minor scope that may follow the completion of the abatement & demolition scope?

Response - It is the prime’s contractor responsibility for the asbestos and demolition scope and it shall be included in the safety program.

Question 79: Abatement / Demolition – Verify the scope of floor tile abatement in H102; specifically ask if it is total room abatement or limited to mechanical penetrations.

Response - See Appendix B, Appendix E and supplemental information Question 80: Abatement / Demolition - Identify all utilities that must remain operational throughout demolition.

Response - All core building utilities to remain active unless required (temporary) in appendix B Question 81: Concrete – Confirm the baseline Floor Flatness (𝐹𝐹𝐹𝐹) and Floor

Levelness (𝐹𝐹𝐿𝐿) numbers required for the concrete slab preparation prior to the installation of the commercial LVT.

Response - Follow the manufacturer recommendations Question 82: Concrete - Specify the minimum structural doweling depth and spacing configuration required to tie the new trench concrete infill blocks back into the existing historic concrete slab assembly.

Response - Please specify the location in order to respond. It would appear that this question applies to another project that is currently out for bid..

Question 83: Masonry – Are there any specific structural shoring requirements provided by the structural engineer of record prior to cutting major ductwork openings through the historic masonry walls?

Response - Please specify the location in order to respond. According to the plans, there are no openings of this type.

Question 84: Masonry – Confirm if the mortar mix for obsolete penetration infills must match historic lime configurations or if modern Type N mortar is acceptable in hidden wall spaces.

Response - See general note # 7 in A-105 Question 85: Misc. Metals – Provide details for the welding connection limitations on the historic stair structural iron elements to avoid heat damage to historic substrates.

Response - Welding is not required Question 86: Misc. Metals – Clarify the engineered weight capacity requirements for the heavy monitor steel backing to confirm gauge thickness.

Response - See A-103 Keynote #11 to obtain the Basis of Design specs Question 87: Misc. Metals – Clarify whether field welding within historic areas requires special inspection or historic preservation oversight.

Response - Welding is not required Question 88: Carpentry – Identify all existing casework intended to remain so replacement quantities can be accurately established.

Response - There is no existing casework replacement as part of the contract.

Question 89: Thermal & Moisture Protection – Specify the baseline Sound

Transmission Class (STC) performance value required for the secure conference room wall assemblies.

Response - See A1/ A-301 Wall Types Question 90: Thermal & Moisture Protection – Identify if any existing penetrations left by the demolition contractor outside our immediate boundary require firestopping upgrades.

Response - Contractor to perform work within the contract boundaries otherwise required by Appendix B

Question 91: Openings – Confirm the fail-safe vs. fail-secure operational status required for the Division 28 electric strikes on secure office doors.

Response - According to Section 08 71 00, paragraph 2.3.7.1; “Provide electric door strikes that release automatically during power failure.”

Question 92: Openings – Provide the exact historic profile criteria required by the base command for the two exterior storefront windows.

Response - Storefront to match existing adjacent buildings, See A-303

Question 93: Openings – Identify which existing doors and frames are intended to remain versus be replaced.

Response - See appendix B Question 94: Openings – Confirm whether existing door hardware cores are to remain on the existing base master key system.

Response - Door hardware cores from demo doors and new doors to be provided to the C.O.R.

Question 95: Openings – Verify the existing Door Schedule.

Response - Refer to the Appendix B, A-601 and A-602 Question 96: Flooring / Finishes – Confirm the approved manufacturer color catalog for the high-pressure plastic laminates to initiate the submittal process.

Response - Refer to the Appendix B, A-604 Question 97: Flooring / Finishes – Clarify if clear access to the elevator or stairways is available for routing the single-piece solid-surface countertop runs.

Response - Refer to the Appendix B for basement access, the only freight elevator in the complex B102-B104 is in B102

Question 98: Flooring / Finishes – Identify if the installation requires independent pop-up compression struts or localized lateral seismic bracing wires for the ceiling grid system to comply with local base codes.

Response - Existing ceiling system in building B104 was replaced in the beginning of 2025

Question 99: Flooring / Finishes – Clarify the detail required for perimeter wall molding connections where the ceiling grid runs flush against uneven, historic interior plaster wall surfaces.

Response - See appendix B, A-303 Question 100:

Flooring / Finishes - NE-B STAIRS, RFS (A-603) INDICATES "RT-1

OVER REPAIRED STONE STEPS ONLY." - PLEASE ADVISE THE

NUMBER OF STAIR TREADS REQUIRED?

Response - See Appendix B, and supplemental information/pictures Question 101:

Flooring / Finishes - E-10, W-10 CORRIDOR, RFS (A-603)

INDICATES EXISTING (IF REQ.)** - PLEASE ADVISE IF ANY

FLOORING OR WALL BASE IS REQUIRED FOR THIS CORRIDOR?

Response - See Appendix B, AD105, A-105 and supplemental information/pictures

Question 102:

Flooring / Finishes - SE-B STAIRS, RFS (A-603) INDICATES "RT-1

OVER REPAIRED STONE STEPS ONLY." - PLEASE ADVISE THE

NUMBER OF STAIR TREADS REQUIRED?

Response - See Appendix B, AD105, A-105 and supplemental information/pictures

Question 103:

Flooring / Finishes - NW-B STAIRS, RFS (A-603) INDICATES "RT-1

OVER REPAIRED STONE STEPS ONLY." - PLEASE ADVISE THE

NUMBER OF STAIR TREADS REQUIRED?

Response - See Appendix B, AD105, A-105 and supplemental information/pictures Question 104:

Flooring / Finishes - NW-B STAIRS, RFS (A-603) INDICATES "RT-1

OVER REPAIRED STONE STEPS ONLY." - PLEASE ADVISE THE

NUMBER OF STAIR TREADS REQUIRED?

Response - See Appendix B, AD105, A-105 and supplemental information/pictures

Question 105:

Flooring / Finishes - N100A CORRIDOR, QUOTE IS BASED ON

440SF + 5% WASTE.

Response - It is a partial carpet replacement on N100A corridor, see Appendix B Question 106:

Flooring / Finishes - Identify attic stock requirements for Carpet, LVT, Ceiling tile, and Paint.

Response - See Appendix A Question 107:

Specialties / Furnishings - Confirm the total dry weight of the through-wall depository safe to verify that standard floor rigging routes and basement shoring are sufficient.

Response - See appendix B keynote #21 in A-103 to obtain the manufacturer specs

Question 108:

Specialties / Furnishings - Provide the exact mounting height constraint for the semi-recessed fire extinguisher cabinets to comply with ADA maximum forward reach limits.

Response - See Appendix B, A-301 Question 109:

Specialties / Furnishings - Clarify responsibility for relocation and reinstallation of existing furniture systems.

Response - See appendix B and requested pictures Question 110: Plumbing - Identify available domestic water shutdown windows.

Response - The available shutdown windows are dependent upon the time required for the work activities. Refer to the requirements in Section 01 35 26, paragraph 3.2.

Question 111: Plumbing - Please confirm plumbing system balancing, flushing, and testing requirements.

Response - There are no balancing requirements. Pressure testing shall be at normal system pressure. Flushing shall be in accordance with Section 22 00 00, paragraph 3.4.2.1.

Question 112: HVAC – Identify if the existing perimeter hydronic baseboard metal enclosures can be cut and re-fit, or if all-new custom-length convective enclosures are required for the new partitions.

Response - The existing fintube cover can be trimmed to the required length.

Provide new wall extension pieces as noted in Detail M1 on Drawing M-501.

Question 113: HVAC – Confirm that the existing air-handling equipment is adequate for the modified duct distribution, and no central equipment replacement is anticipated.

Response - Modifications to the central HVAC equipment are not part of this contract.

Question 114: HVAC – Provide the latest Testing, Adjusting, and Balancing (TAB) report for the existing HVAC system, if available.

Response - We presently do not have a TAB report for the HVAC system.

Question 115: HVAC – Confirm the existing HVAC capacity.

Response - Modifications to the central HVAC equipment are not part of this contract.

Question 116: Base Network Compatibility and Gateway Requirements -

• Context: The specifications demand seamless integration of the newly modified wings into the active, overarching base-wide Energy Management and Control System (EMCS) network interface.

• Clarification Request: Please confirm if the existing base-wide system utilizes an open-protocol framework (e.g., BACnet/IP or LonWorks) or if a proprietary hardware gateway license or specific software driver must be procured to safely push data across the Rock Island Arsenal public works server trunk.

Response - Section 23 09 23.02 requires an extension / revision to the existing DDC System. The existing system is Delta.

Question 117: Risk Management Framework (RMF) and Cybersecurity Clearances -

• Context: Division 25 components will communicate across building-level and base-level network backbones to deliver telemetry and schedule adjustments to the Garrison departments.

• Clarification Request: Are the Division 25 network controllers required to undergo formal Risk Management Framework (RMF) validation, or must they pass specialized automated Assured Compliance Assessment Solution (ACAS) vulnerability scans before the Government will authorize a live physical network connection to the active base IT infrastructure?

Response - Section 23 09 23.02 requires an extension / revision to the existing DDC System. The existing system is Delta. Therefore, the controllers available from Delta comply with the Division 25 requirements.

Question 118: Software Graphics and Programming Stand arounds -

• Context: The contractor is tasked with building localized system graphics, trend logs, and alarm notification menus for the first floor and partial basement layouts.

• Clarification Request: Does the Rock Island Arsenal Public Works department maintain a standardized historical graphics library, color-coding hierarchy, and naming convention template that the contractor must replicate, or is the contractor responsible for proposing a new standalone custom interface format for approval?

Response - Section 23 09 23.02 requires an extension / revision to the existing DDC System. The existing system is Delta. The graphics have been standardized.

Question 119: Electrical - Many of the keynotes for the HDMI cables state to connect to a floor box but there is no floor box shown on the drawings. Can either the floor box be added to the drawings or can we get a recommended length for the HDMI cords?

Response - Refer to Keynote 58 on Drawing EP-101. Refer to Keynote 66 on Drawing EP-103. Refer to Keynotes 58, 64 and 53 on Drawing EP- 104.

120:

Electrical - Identify whether spare conduits, sleeves, and cable trays shown on the drawings have been field verified.

Response - There are no spare conduits, sleeves and cable trays shown on the drawings. There is nothing to field verify.

Question 121:

Electrical – What is the HDMI conduit size? Minimum required is 1- 1/4”.

Response - The contractor shall determine the minimum conduit size required.

Question 122:

Electrical - Can the existing IT Room be identified on the drawings?

Response - Refer to Comm Rm E152 and Comm N124 on Drawing AD-101 and Comm Rm W144 on Drawing AD-103.

Question 123:

Electrical - Is Cat6 or Cat6A cabling required? Both are mentioned in the specs.

Response - Anything new to be installed needs to be Panduit CAT6. Blue CAT6 for phone and White CAT6 for LAN connections.

Question 124:

Electrical - Is there a certain cable manufacturer that we need to use?

Response - Refer to the response in question 123.

Question 125:

Electrical - How many cables are needed at each location? Keynote 73 states new voice/data port but does not give a count.

Response - All wall mounted outlets require one voice and one data outlet. Drops to furniture require one voice and one data outlet per work station and printer. Refer to the furniture drawings for the number of work stations and printer locations.

Question 126:

Electrical - Confirm if the basement structural perimeter wall allows for flush recessing of the 400A panel board, or if surface mounting on structural steel channels is required.

Response - There is no new electrical panel shown on the drawings. This question is not valid.

Question 127:

Electrical - Clarify if the emergency egress fixtures require an independent dedicated circuit tied back to a central facility backup generator system, or if standalone internal battery packs are acceptable.

Response - Refer to the Light Fixture Schedule on Drawing E-601.

Question 128:

Electrical – Identify the existing manufacturers and software platforms for Fire Alarm, Access Control, Intrusion Detection, and CCTV.

Response - Fire Alarm is Simplex and Access Control is Per Mar. There is no

Intrusion Detection or CCTV system noted on the drawings.

129:

Telecommunications Scope of Work - Please define the complete communications scope to be included in the base bid.

• The Statement of Work identifies revisions and extensions to the building's data/communications systems. The contract documents indicate communications outlets and associated infrastructure; however, the required extent of the telecommunications installation is not clearly defined.

Response - Refer to the response in Question 130.

Question 130:

Telecommunications Scope of Work - Please clarify the Electrical Contractor's responsibility regarding the following:

• Furnishing and installation of communications cabling.

• Termination of communications cabling.

• Testing and certification of communications cabling.

• Labeling and documentation.

• Patch panels, patch cords, and network electronics.

• Coordination with the Owner's Information Technology personnel.

Please identify which items are to be provided by the Electrical Contractor and which items, if any, will be provided by the Owner or others.

Identify the Government point of demarcation for all communications systems.

Response - The contractor shall furnish and install the communications cabling with labeling. All other activities noted in the question are provided by the Government.

Question 131:

Fire Alarm System Modifications - Please define the complete fire alarm scope of work required for the base bid, including responsibilities for programming, testing, commissioning, certification, and final acceptance.

• The contract documents indicate modifications to the existing fire alarm system as part of the renovation work. However, the required extent of programming, testing, commissioning, and whether the existing system is proprietary is not clearly defined.

Please clarify the following:

1. Identify the existing fire alarm system manufacturer and model.

2. Confirm whether the existing system is proprietary.

3. Confirm whether programming shall be performed by the

Electrical Contractor or the Owner's authorized fire alarm service provider.

4. Confirm responsibility for final acceptance testing, system certification, and AHJ coordination.

5. Confirm whether the Electrical Contractor is responsible for any required software licenses, programming tools, or factory-certified technicians.

6. Confirm whether all fire alarm modifications shall be included in the base bid or coordinated through the existing service provider.

Response - 1. The existing Fire Alarm System is Simplex.

2. The existing Fire Alarm System is proprietary.

3. Programming shall be provided by an authorized system installer and shall be provided as part of this contract.

4. System acceptance testing, certification and coordination with the AHJ is the responsibility of the contractor.

5. The contractor is responsible for the services of factory-certified technicians.

6. All Fire Alarm modifications required shall be included in the base bid of this contract.

Question 132:

Access Control System Scope - Please define the complete access control scope to be included in the base bid, including equipment procurement, installation, programming, testing, and system integration responsibilities.

Please clarify the Electrical Contractor's responsibility for the following:

• Furnishing and installation of card readers.

• Door position switches, request-to-exit devices, electric strikes, and magnetic locks.

• Access control panels, power supplies, and controllers.

• System programming, software licensing, and database configuration.

• Integration with the existing access control system.

• Functional testing, commissioning, and Owner training.

Please identify which items are Contractor Furnished/Installed and which items, if any, will be provided by the Owner or by others.

Response - It is the contractor’s responsibility to provide a complete operational extension to the existing system.

Question 133:

Audio/Visual Equipment Scope - Please define the complete audio/visual scope to be included in the base bid, including procurement, installation, testing, and coordination responsibilities.

The contract documents indicate the installation and/or relocation of audio/visual devices, including televisions, HDMI connections, projector equipment, and associated infrastructure. However, the procurement and installation responsibilities for the AV equipment are not clearly defined.

Please clarify the Electrical Contractor's responsibility for the following:

• Furnishing televisions, monitors, projector equipment, and display devices.

• Furnishing wall mounts, ceiling mounts, and support hardware.

• Furnishing HDMI cabling, extenders, and AV accessories.

• Installation of Owner-furnished AV equipment, if applicable.

• Testing, commissioning, and coordination with the Owner's AV representative.

Please identify which items are Contractor Furnished/Installed and which items, if any, will be provided by the Owner or by others.

Response - See Appendix B : Keynotes #14 in A-101 and #11 in A-103 Question 134:

Existing Panelboard Capacity and Available Circuit Breakers - The contract documents require new branch circuits to be extended from existing electrical panelboards. However, the available spare capacity within the existing equipment cannot be verified from the contract documents. Please confirm the following:

• Existing panelboards serving the new work have sufficient ampacity and load capacity for the proposed circuits.

• Adequate spare breaker spaces are available within the existing panelboards.

• Existing circuit breakers required for the work are available or compatible with the existing equipment.

• Existing panelboards have adequate short-circuit interrupting ratings for the proposed modifications.

• No panelboard replacement or major modifications are anticipated beyond the work specifically identified in the contract documents.

If additional panelboard modifications or replacement are required due to existing field conditions, please clarify how such work will be addressed.

Please confirm that the existing electrical distribution equipment has sufficient capacity to support the proposed work, or provide additional information necessary for bidding.

Response - Existing panelboards have sufficient capacity and spare breakers. No panelboard replacement or major modifications are required.

Question 135:

Electrical Shutdown and Outage Coordination Requirements - The project requires modifications to existing electrical systems within an occupied Government facility. The contract documents do not clearly define the allowable outage windows or operational restrictions associated with electrical shutdowns. Please clarify the following:

• Permitted days and hours for planned electrical outages.

• Maximum allowable outage duration for each shutdown.

• Required advance notification period for scheduled outages.

• Whether after-hours, weekend, or holiday work will be required.

• Whether temporary power will be required to maintain building operations during electrical shutdowns.

• Whether Government personnel must be present during outages or restoration of service.

• Any mission-critical equipment or areas that must remain energized throughout construction.

Please provide the operational constraints and shutdown requirements to be incorporated into the Contractor's base bid.

Response - Refer to Section 01 35 26, paragraph 3.2. It is anticipated that any outages will have minimal effect on areas outside the defined work area.

Question 137:

Hazardous Materials and Existing Electrical Equipment - The project requires demolition and modification of existing electrical systems within an existing Government facility. The contract documents do not clearly identify whether hazardous materials associated with the existing electrical installation have been surveyed or abated. Please clarify the following:

• Has the Owner completed surveys for asbestos-containing materials (ACM), lead-based paint (LBP), PCB-containing electrical equipment, or other hazardous materials that may impact the electrical scope?

• Will any identified hazardous material abatement be performed by others prior to the Electrical Contractor's work?

• If hazardous materials are encountered that are not identified in the contract documents, how will this work be addressed?

• Is the Electrical Contractor responsible for handling, removal, transportation, or disposal of hazardous materials associated with existing electrical equipment?

Please provide any available hazardous material survey reports applicable to the project.

Please clarify the Contractor's responsibility regarding hazardous materials associated with existing electrical systems and identify any Owner-furnished survey information applicable to the project.

Response - Refer to the Architectural Drawings and questions 76 through 80.

Question 138:

Concealed Existing Conditions and Demolition Scope - The contract documents indicate demolition and modification of existing electrical systems within an existing facility. Due to the nature of renovation work, concealed electrical systems and field conditions may differ from those shown on the contract documents. Please clarify the following:

• Whether existing concealed conduit, conductors, junction boxes, and abandoned electrical systems not identified on the drawings are to be removed or may remain in place.

• Whether circuit tracing beyond that reasonably identifiable from the contract documents is included in the base bid.

• How concealed existing conditions that require additional demolition, rerouting, or replacement of electrical systems will be addressed if encountered during construction.

• Whether undocumented electrical systems discovered during demolition shall be considered a change in scope requiring Government direction prior to proceeding.

Please clarify the Contractor's responsibility for concealed existing electrical conditions and demolition work not explicitly identified in the contract documents.

Response - 1. Existing conduits, conductors, junction boxes and abandoned electrical systems may be left in place if not shown on the drawings.

2. Circuit tracing shall be included in the base price in support of the work activities shown on the drawings.

3. Modifications to existing electrical systems not shown on the drawings will be considered a change to site conditions.

Question 139:

Lighting Control System Programming and Commissioning - The contract documents require installation of a new lighting control system utilizing Light components. The documents do not clearly define the responsibilities for programming, startup, commissioning, and Owner training. Please clarify the following:

• Is the Electrical Contractor responsible for complete programming and configuration of the lighting control system?

• Is a factory-authorized representative required for startup and commissioning?

• Is functional performance testing required in the presence of the Owner or Government representative?

• What documentation, system backups, and record drawings are required at project closeout?

• Is Owner training required, and if so, what duration and level of training is expected?

• Are all costs associated with software, licensing, startup, and commissioning to be included in the base bid?

Please define the complete scope for lighting control programming, startup, commissioning, testing, documentation, and Owner training to be included in the Contractor's base bid.

Response - 1. The contractor is responsible for complete programming and configuration of the lighting control system. Refer to Section 26 51 00, paragraph 3.3.1.

2. A factory-authorized representative is required for startup and commissioning. Refer to Section 01 91 00.15.

3. Yes, functional performance testing required in the presence of the COR or other Government representatives. Refer to Section 01 91 00.15.

4. Refer to Section 01 78 23 and Drawing E-602.

5. Owner training is not required.

6. Yes, all costs associated with software, licensing, startup, and commissioning to be included in the base bid?

Question 140:

Temporary Power and Phasing Requirements - The contract documents require renovation within an occupied facility; however, the requirements for temporary power, temporary lighting, and phased construction are not fully defined. Please clarify the following:

• Is the Contractor responsible for providing temporary power to maintain building operations during construction?

• Is temporary lighting required during demolition or renovation activities?

• Are there specific project phasing requirements that will require portions of the electrical system to remain operational while adjacent work is performed?

• Are temporary feeders, panels, generators, or bypass connections anticipated as part of the base bid?

• Are there mission-critical areas requiring uninterrupted electrical service throughout construction?

• Will planned outages be coordinated by the Government, and what notice period is required?

Please define the Contractor's responsibilities for temporary electrical service, temporary lighting, project phasing, and maintaining building operations during construction.

Response - We do not see a need to provide temporary power as the affected areas appear to be restricted to the major remodel areas. Contractor will need to provide temporary lighting in construction areas.

Question 141:

Coordination of Existing Mechanical and Fire Protection Systems - The contract documents indicate new lighting, power, and communications work above existing ceilings. The extent of coordination required with existing mechanical, plumbing, and fire protection systems is not fully defined. Please clarify the following:

• Will existing mechanical, plumbing, fire protection, or other building systems require relocation to accommodate the electrical work?

• Is the Electrical Contractor expected to coordinate and support relocation of existing systems by other trades?

• If existing field conditions prevent installation as shown, how will conflicts between trades be resolved?

• Will modifications to other building systems required solely to accommodate electrical work be performed by others?

Please identify any known congested areas requiring special coordination prior to installation.

Please clarify the coordination responsibilities and identify whether modifications to existing nonelectrical building systems are included in the Electrical Contractor's base bid.

Response - We do not anticipate revisions to existing mechanical or electrical systems to allow for the installation of new work. However, it is the responsibility of the contractor(s) to coordinate the installation of new mechanical and electrical systems.

Question 142:

Owner-Furnished Equipment (OFE) and Government-Furnished Equipment (GFE) - The contract documents reference the installation of new electrical, communications, access control, and audio/visual systems. However, the documents do not clearly identify all Owner- Furnished Equipment (OFE) or Government-Furnished Equipment (GFE) associated with the project.