TE-H.17.7.2 Water Contamination Response Plan.pdf
PDF 326 KB Posted
- Attached to
- Ft Carson BASOPS (Base Operations Services)
- Solicitation number
- W5168W-24-R-0009
- Issued by
-
Department of the Army
About this file
This document appears to be a water contamination response plan for a maintenance contractor at a military base. The plan outlines the steps the contractor and base personnel must take in response to a potential water contamination threat, including notifying the Contracting Officer's Representative (COR), the Facilities Coordination Operations Center (FCOC), and other relevant parties. The plan was developed in response to an actual water contamination event that occurred on June 25, 2013, which was ultimately determined to be non-credible.
The related federal contract opportunity is for a solicitation to provide Base Operations Support Services at the U.S. Army Fort Carson in Colorado. The contract will include various Common Level of Services (CLS), such as grounds maintenance, facility maintenance, heating and cooling services, and wastewater services.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RESPONDING TO WATER CONTAMINATION THREAT
MAINTENANCE CONTRACTOR FLOW CHART
Jan 2023
Base O & M Contractor’s 24/7 Control Center
Receives Contamination Threat
Base O & M Contractor’s Facilities Branch Manager and COR
Is Threat Possible ? NOYES *
Close Investigation Return to Normal Operations
Document the Incident And Notify the COR
Notify COR
Notify FCOCNotify DES 911 Call Center
Notify DPW Director
Notify Garrison Command
Notify Preventive Medicine and CBRNE
*** Base O & M contractor shall not shut off any water system without directions from the COR or the FCOC ***
FCOC, DES Preventive Medicine, CBRNE and the Base O & M Contractor
Initiate Process to Determine If Threat is Credible ***
** The COR will notify the Base Maintenance Contractor with additional guidance from the FCOC **
* Coordinate investigation and response with the FCOC until threat is determined non-credible or resolved *
This chart was developed as a after action response to an actual water contamination event that occurred on Jun. 25 2013 The water contamination investigation proved that no contamination took place but recommended that a response process be developed
TE-H.17.7.2
As of 1 Jan 2023