TE-H.17.7.2 Water Contamination Response Plan.pdf

PDF 326 KB Posted

Attached to
Ft Carson BASOPS (Base Operations Services)
Solicitation number
W5168W-24-R-0009
Issued by

About this file

This document appears to be a water contamination response plan for a maintenance contractor at a military base. The plan outlines the steps the contractor and base personnel must take in response to a potential water contamination threat, including notifying the Contracting Officer's Representative (COR), the Facilities Coordination Operations Center (FCOC), and other relevant parties. The plan was developed in response to an actual water contamination event that occurred on June 25, 2013, which was ultimately determined to be non-credible.

The related federal contract opportunity is for a solicitation to provide Base Operations Support Services at the U.S. Army Fort Carson in Colorado. The contract will include various Common Level of Services (CLS), such as grounds maintenance, facility maintenance, heating and cooling services, and wastewater services.

View the file

Other files

File Type Posted
TE-J.1.2.2.2 Traffic Paint Usage Report.xlsx XLSX spreadsheet
AMENDMENT 0001-FT CARSON W5168W-24-R-0009-24MAY2024.pdf PDF
TE-H.2.11B PCMS and Ft Carson Sewer Manhole Graphic.pdf PDF
TE-H.17.7.1 Environmental Battle Book.pdf PDF
TE-H.1.3.3 IMCOM Facility Maint Instruction.pdf PDF
TE-H.1.1.1 Real Property Facilities.pdf PDF
TE-H.2.15.1 Dampness and Mold Visual Assessment Worksheet.pdf PDF
Attachment U-W5168W-24-R-0009-WAGEDETERMINATION-29APR2024-FTCARSON.pdf PDF
Annex J to OPORD 18-011 Facility Maint Horizontal-Attachment H-18APR2024.pdf PDF
Annex G to OPORD 18-011 Pavement Clearance-18APR2024 - Copy.pdf PDF
TE-H.2.13.9.2A Accreditation Efforts.pptx PPTX presentation
TE-H.2.13.1.6- Individual Boiler Sys.xls XLS spreadsheet
TE-H.2.20.1 LPS and GP test locations.pdf PDF
Attachment T-Past Performance Questionnaire-W5168W-24-R-0009-FTCARSON-9APR2024.pdf PDF
TE-H.2.10.5 Backflow Prevention Devices.xlsx XLSX spreadsheet
TE-H.2.13.4A HVAC-COILS.xls XLS spreadsheet
TE-H.2.13.1.5 Boiler Operating Hours.xls XLS spreadsheet
Annex F to OPORD 18-011 Grounds Maint-FtCarson-8MAY2024.pdf PDF
TE-H.2.13.3 Chiller Wtr Chem.xls XLS spreadsheet
TE-H.2.19 Auxilary Generator.xlsx XLSX spreadsheet
TE-H.2.10.8 Wash Rack Facilities.xlsx XLSX spreadsheet
TE-H.2.13.4.1 Evaporative Coolers.xls XLS spreadsheet
TE-H.13 Propane Tank Locations.xlsx XLSX spreadsheet
TE-H.2.18.1 Emergency signs and lights.xlsx XLSX spreadsheet
TE-H.2.25 List of Facilities with Elevators.xlsx XLSX spreadsheet
TE-H.2.23 Playground locations.xlsx XLSX spreadsheet
TE-H.27 Fire Pumps.xlsx XLSX spreadsheet
TE-H.2.27b Vault Doors.xlsx XLSX spreadsheet
TE-H.2.3A AC-Units.xls XLS spreadsheet
W5168W-24-R-0009-Ft Carson Solicitation - 21MAR2024.pdf PDF
TE-J.2.1.4 Tank Trails.pdf PDF
TE-J.2.2.3c Red Devil Water Distribution.pdf PDF
TE-J.2.1.5 Bridge Locations.pdf PDF
TE-J.2.1.7.4 BAAF Paint Diagram.pdf PDF
TE-J.2.1.7 Butts AAF.pdf PDF
TE-J.2.1.8 Fort Carson Rail.pdf PDF
TE-G.2.5.1 FODPP.pptx PPTX presentation
TE-G.1.3 After Action Review.pdf PDF
TE-F.2.2.1B BAAF_Mowing 1 JAN 2020.PDF PDF
TE-F.2.2.11A PCMS Irrigation.pdf PDF
TE-F.2.2.6 Flower Beds.xlsx XLSX spreadsheet
Annex L to OPORD 18-011 Wastewater Services.pdf PDF
TE-K.3.1 Fuel Ordering Process.pptx PPTX presentation
Annex K to OPORD 18-011 Heating and Cooling.pdf PDF
TE-K.4.2.1 Monthly Chiller Log.xls XLS spreadsheet
TE-A.2D 2021 Workload Data (DMO)-30JAN2024.xlsx XLSX spreadsheet
TE-A.2F-1 2023 Workload Data (PM)-30JAN2024.xlsx XLSX spreadsheet
TE-A.7.4.A Government Furnished Property (GFP) (Equipment)-18MAR2024.xlsx XLSX spreadsheet
TE-A.6.0 Consolidated Deliverable Index.xlsx XLSX spreadsheet
TE-A.2.1.10 Subcontract Report.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RESPONDING TO WATER CONTAMINATION THREAT

MAINTENANCE CONTRACTOR FLOW CHART

Jan 2023

Base O & M Contractor’s 24/7 Control Center

Receives Contamination Threat

Base O & M Contractor’s Facilities Branch Manager and COR

Is Threat Possible ? NOYES *

Close Investigation Return to Normal Operations

Document the Incident And Notify the COR

Notify COR

Notify FCOCNotify DES 911 Call Center

Notify DPW Director

Notify Garrison Command

Notify Preventive Medicine and CBRNE

*** Base O & M contractor shall not shut off any water system without directions from the COR or the FCOC ***

FCOC, DES Preventive Medicine, CBRNE and the Base O & M Contractor

Initiate Process to Determine If Threat is Credible ***

** The COR will notify the Base Maintenance Contractor with additional guidance from the FCOC **

* Coordinate investigation and response with the FCOC until threat is determined non-credible or resolved *

This chart was developed as a after action response to an actual water contamination event that occurred on Jun. 25 2013 The water contamination investigation proved that no contamination took place but recommended that a response process be developed

TE-H.17.7.2

As of 1 Jan 2023