This amendment modifies a solicitation to construct an F-35 flight simulator facility. The amendment revises numerous specification sections and plans, extends the proposal due date from October 1 to October 8, 2020, and consists of changes to specifications, drawings, and solicitation documents. The solicitation seeks a single firm fixed-price contract to demolish an existing 4,646 square foot facility and construct a new 19,000 square foot, four-simulator F-35 training facility for $10-25 million. Work includes demolition, construction, mechanical, electrical, technology, and communications systems installation. The project also includes five options such as security windows and interior wall construction. The solicitation is open to all responsible offerors but provides preferences to small businesses and HubZone firms. Proposals will be evaluated for technical merit, past performance, small business participation, and price. The pre-proposal conference is August 25 and proposals are due September 24, 2020.

View the file

Other files

File Type Posted
Simulator_Questions and Answers_194-222.pdf PDF
Design Amendment 1 attachments.pdf PDF
W50S9F20R0001 Page 6.pdf PDF
A107r.pdf PDF
G001.pdf PDF
Design Amendment 2 attachments.pdf PDF
Attachment 16-B410 from AsbestosMgmtOpPlan_ANG_TSC_AMT_Jun06.pdf PDF
Design Amendment 3 attachments.pdf PDF
08 81 00 Glazing rev.pdf PDF
Attachment 17-HPSB Sustainability Checklist.pdf PDF
C121.pdf PDF
A302.pdf PDF
A106.pdf PDF
Exhibit H - Proposal Schedule rev.docx DOCX document
A501.pdf PDF
W50S9F20R00010006.pdf PDF
09 69 13 Rigid Grid Access Flooring.pdf PDF
M602.pdf PDF
M503.pdf PDF
S302.pdf PDF
T112.pdf PDF
E100.pdf PDF
S103.pdf PDF
M604 rev.pdf PDF
A102 rev.pdf PDF
06 20 00 Finish Carpentry.pdf PDF
M112.pdf PDF
C503.pdf PDF
A304.pdf PDF
M603.pdf PDF
A301.pdf PDF
S101 rev.pdf PDF
E112.pdf PDF
A601.pdf PDF
12-PRE-PROPOSAL SITE VISIT INSTRUCTIONS rev 2.pdf PDF
05 40 00 Cold-Formed Metal Framing.pdf PDF
S102.pdf PDF
23 25 00 Chemical Treatment of Water for Mechanical Systems.pdf PDF
11 31 13 Electric Kitchen Equipment.pdf PDF
E620.pdf PDF
E122.pdf PDF
A103 rev 2.pdf PDF
03 30 00 Cast-In-Place Concrete.pdf PDF
27 51 16 Radio and Public Address Systems.pdf PDF
E121.pdf PDF
07 53 23 Ethylene-Propylene-Diene-Monmer Roofing.pdf PDF
E103.pdf PDF
Simulator_Questions and Answers_47-193.pdf PDF
E113.pdf PDF
T111.pdf PDF
Show 40 more

Latest 50 of 123 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

XGFG189001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to revise numerous specification sections and plans and Attachment 12-PRE-PROPOSAL SITE VISIT INSTRUCTIONS. See the summary of changes for the details.

The proposal due date has changed from 1 October 2020 to 8 October 2020.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 25-Sep-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W50S9F20R0001

X 9B. DATED (SEE ITEM 11)

10-Aug-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

25-Sep-2020

CODE

USPFO WI 115 MISSION SUPPORT CONTRACTING

3110 MITCHELL ST BLDG 500

MADISON WI 53704-2591

W50S9F 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S9F20R0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been modified:

SUMMARY OF CHANGES

Amendment 0005 consists of changes to the specifications, drawings, and solicitation sections listed below. Revised specifications and drawings are also provided with this amendment. Any changes to the plans and specifications are bubbled. For the solicitation, any deletions are strikethrough and any additions are underlined.

Changes to solicitation:

1. Attachment 12-PRE-PROPOSAL SITE VISIT INSTRUCTIONS rev 2

Changes to specifications:

1. Section 03 30 00, Cast-In-Place Concrete, updated paragraph 2.5.1.i.

2. Section 05 40 00, Cold-Formed Metal Framing, updated paragraph 2.1.1.

3. Section 06 20 00, Finish Carpentry, deleted paragraph 3.2.1.1.

4. Section 07 53 23, Ethylene-Propylene-Diene-Monomer Roofing, omitted paragraphs 3.2.3.3 and 3.2.6.

5. Section 09 69 13, Rigid Grid Access Flooring, deleted paragraph 2.2.4.2.b.

6. Section 11 31 13, Electric Kitchen Equipment, deleted in its entirety

7. Section 23 25 00, Chemical Treatment of Water for Mechanical Systems, adding in its entirety

8. Section 27 51 16, Radio and Public Address Systems, updated paragraph 2.1.3.

Changes to plans:

1. Revised A102rev updating wall type

2. Revised A103rev2 updating for wall type clarification and deleting manufacturer

3. Revised A301 to show no walls are built on top of the access floor system

4. Revised A304 changed wall type from E to A

5. Revised A601 updated Room Finish Schedule Remarks #1

6. Revised C503 updated to read L/301

7. Revised E100 correcting keynote 2

8. Revised E103 correcting keynote 19

9. Revised E112 correcting keynote 4 &13

W50S9F20R0001

10. Revised E113 correcting keynote 4 &15

11. Revised E121 correcting keynote 12

12. Revised E122 correcting keynote 2

13. Revised E620 correcting luminaire schedule from A3 to A1

14. Revised M112 to show sound attenuators

15. Revised M503 correcting #20 and adding #37 & #38

16. Revised M602 updating Dry Bed Cooler Schedule note 3

17. Revised M603 updating Makeup Air Handling Unit Schedule note 6 and deleting manufacturer, updating Packaged Rooftop AHU Schedule note 5, updating Air Cool Chiller Schedule note 5 and deleting manufacturer

18. Revised M604rev updating sound attenuator schedule and Motorized Damper Schedule note 1

19. Revised S101rev correcting depressed foundation area

20. Revised S102 correcting depressed foundation area

21. Revised S103 correcting depressed foundation area and removed stepped footing

22. Revised S302 correcting depressed foundation area

23. Revised T111 correcting keynote 1

24. Revised T112 correcting keynote 6

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 01-Oct-2020 03:00 PM to 08-Oct-2020 03:00 PM.