QA STDF 172115 Demolish Building 531 26 April 2024.pdf

PDF 85 KB Posted

Attached to
BLDG 531 Paine Field Demolition, 194 CE Camp Murray
Solicitation number
W50S9E24QA003
Issued by

About this file

This document is a set of questions and answers (Q&A) related to Solicitation W50S9E24QA003 for the demolition of Building 531 located at Paine Field, Everett, WA. The solicitation requires the contractor to provide all materials, labor, and equipment to perform the demolition work detailed in the Statement of Work (SOW) for project #STDF 172115.

The key details include: the offer due date has been revised to 06 May 2024 at 3:00 PM PDT; the evaluation factors are price, technical, and past performance, with technical and past performance being equal to price; the contractor must submit a technical narrative describing how they will accomplish the SOW work elements and include abatement certificates; the contractor must also submit 2 pages of past performance information from the last 3 years; the contractor must protect the sidewalk and asphalt parking lot, but remove the lift station; and revised solicitation and pricing forms will be provided to reflect the addition of a waste removal alternate.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

26 April 2024

Q&A W50S9E24QA003 STDF 172115 Demolish Building 531

Ques�on: Is the site visit a requirement for the contract?

Answer: No you do not need to atend the site visit to submit a quote. The SOW will be updated to reflect this.

Ques�on: How far back are we to demo the gas? Are we just to demo the meter and cap there or do cap elsewhere?

Answer: Demolish the gas line up to the meter. The Government will coordinate with Puget Sound Energy to disconnect and remove the gas meter before contract work has started.

Ques�on: Are u�li�es currently off at the building? Water, sewer, gas, electrical?

Answer: The Government will coordinate with the u�lity providers to disconnect and remove meters before the start of performance of the contract. Sanitary sewer is already disconnected.

Ques�on: How far back do we demo water and sanita�on?

Answer: Demolish the water line up to the meter. The Government will coordinate with Mukilteo Water and Wastewater District (MWWD) to disconnect and remove the water meter before No�ce to Proceed. Remove all sanitary sewer lines up to and including the li� sta�on. The li� sta�on shall be removed or properly decommissioned (i.e. filled with sand) in accordance with Snohomish County Airport Engineering Department requirements.

Ques�on: The SAM.gov pos�ng states offer due date is April 27, 2024 3:00 PM PDT. However, Block 8 of the SF 1449 states Offer due date is 29 April at 3pm. Please clarify the offer due date.

Answer: The due date has changed in SAM and on the 1449 to 06 May 2024 at 3:00 PM PDT.

Ques�on: SF 1449, FAR Clause 52-212-2 states evalua�on factors are Price, Technical, and Past Performance. Please provide the submission requirements and evalua�on standards for both the Technical and Past Performance factors.

Answer: 52.212-1 states that the contractor will submit 4 documents: Solicita�on filled in to include the amendments, Pricing addendum, 2 pages of past performance, and a technical narra�ve which describes how you will accomplish each work element in the SOW and include abatement cer�ficates. Past performance will be reviewed up to three years from solicita�on date. The 52.212-2 now states that past performance, and technical when combined are equal to price.

Price is evaluated by combining all CLINS, and when totaled is the total evaluated price. Technical is evaluated by reviewing your technical narra�ve against the Gov SOW

Ques�on: For the demo of building 531, do you want us to remove the 100+ feet of sidewalk on the south side of the building?

Answer: The sidewalk immediately adjacent to the asphalt parking lot shall be protected in place. Only remove the por�ons of sidewalk from the Building 531 stoops up to said parking lot sidewalk.

Ques�on: Do you want us to remove the asphalt parking lot?

Answer: No, the asphalt parking lot shall be protected in place.

Ques�on: Do you want us to remove the li� sta�on that is to the northwest corner of the building?

Answer: Yes, the li� sta�on shall be removed or properly decommissioned (i.e. filled with sand) in accordance with Snohomish County Airport Engineering Department requirements.

Ques�on: Will there be revised solicita�on and pricing addendum forms to reflect the addi�on of the waste removal alternate (addendum no. 1)?

Answer: Yes please see the updated 1449, and the Sec�on B Pricing Addendum.

File details come from the government source that posted it. Updated .