05a SOW Attch_Specifications.pdf

PDF 436 KB Posted

Attached to
BLDG 531 Paine Field Demolition, 194 CE Camp Murray
Solicitation number
W50S9E24QA003
Issued by

About this file

This document is a Statement of Work (SOW) for the demolition of Building 531 located at Paine Field in Everett, Washington. The key details are:

The SOW requires the contractor to provide all materials, labor, equipment, and transportation to perform the demolition of Building 531, which is approximately 3,765 square feet and contains offices, classrooms, and restrooms. The work includes hazardous material abatement, removal and/or recycling of all demolished materials, and minor site restoration. Asbestos, lead, and PCBs are known or presumed to exist throughout the structure, and all work must be performed in accordance with local, state, and federal regulations.

The SOW provides details on the site location and access, utility disconnections, fire prevention requirements, permits and fees, utility locates, contractor quality control, government inspections, and closeout procedures. It also includes a detailed submittal schedule covering items such as the demolition plan, hazardous materials forms, progress schedule, and waste management plan. The anticipated period of performance is 60 calendar days from the Notice to Proceed.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Demolish B531 STDF172115

PAINE FIELD, EVERETT, WA

Section 01 10 00 Page 1

SECTION 01 10 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Contractor Use of Site and Premises B. Permits, Fees, and Notices C. Utility Locates D. Indemnification of Government E. Number of Items F. Subcontracting G. Discrepancies in Documents H. Abbreviations/Definitions

1.02 CONTRACTOR USE OF SITE AND PREMISES

A. The Contractor will have access to the work area during normal WA ANG working hours. With prior coordination, the Contractor may have access to work a five-day presence. All Western WA ANG facilities will not be accessible during Federal holidays plus one additional day. (e.g. holiday is on a Monday, the Friday prior will be observed as a Federal holiday or holiday is on a Friday, the Monday after will be observed as a Federal holiday). Working hours will be established at the Pre- Construction Conference.

Normal WA ANG Working Hours Tuesday – Friday 0600-1630 Alternative, 5-day presence Monday – Friday 0700-1600

B. The Contractor shall not work outside the established working hours without prior written approval from the Contracting Officer. Requests to work outside the established working hours shall be provided not later than three workdays prior to the date requested. Unauthorized work outside the established working hours shall be at no additional expense to the Government.

C. Utility disconnection and demolition: Utilities to the building have been terminated, with some existing infrastructure in place but not in service. Contractor shall coordinate demolition of existing utility infrastructure with utility purveyor as applicable.

D. Fire Prevention: The Contractor will assure that fire prevention actions are observed by all employees, including subcontractors.

E. Full Time Tenants: There are no full-time tenants at the Washington Air National

Guard Installation at Paine Field.

Section 01 10 00 Page 2

1.03 PERMITS, FEES, AND NOTICES

A. The contractor shall secure and pay for all temporary or permanent permits, certificates, tests, inspection and "hookup" charges, and other legal fees required by government agencies and private utility-furnishing organizations having jurisdiction over the work under the contracts.

B. The buildings are located off public access roads adjacent to Paine Field

(Snohomish County Airport) in unincorporated Snohomish County.

C. Notify Puget Sound Clean Air Authority and obtain any required permit prior to demolition and abatement work.

D. The following organizations provide utilities to the site:

1. Snohomish County PUD – electric

2. Puget Sound Energy – natural gas

3. Snohomish County Airport – sewer

4. Mukilteo Water - water

1.04 UTILITY LOCATES

A. Public utilities: At least 48 hours before any excavation, the contractor shall arrange for a utility locate (Call Before You Dig, 1-800-424-5555). Most of the utilities on Air National Guard facilities are owned by the utility companies up to the meters on the buildings.

B. Private (military) utilities: The Contractor shall also contact the Base Civil Engineer seven calendar days prior to the excavation to arrange for a military utility locate.

Some utilities such as fiber optics and water lines are installed by military units and require separate locates from the public utilities.

1.05 INDEMNIFICATION OF GOVERNMENT

A. The Contractor shall indemnify and save the Government harmless from any loss to any other Contractor caused by any time extension.

1.06 NUMBER OF ITEMS

A. When an item is referred to in a singular number or where the number of items required is listed, the Contractor shall supply all the items necessary to make the installation complete. The number of items, when given, is for assistance only.

1.07 SUBCONTRACTING

A. A listing of all subcontractors to be used on the project must be submitted to and approved by the Contracting Officer prior to commencement of their work. A Standard Form (SF) 1413 must be submitted in accordance with the instruction

Section 01 10 00 Page 3 given at the Pre-Construction Conference. The Subcontractor will not be allowed on site until the SF 1413 is approved by the Contracting Officer.

1.08 DISCREPANCIES IN DOCUMENTS

A. Some of these specifications may include incomplete sentences. Omissions of words or phrases such as "the Contractor shall", "shall be", "as noted on the drawings", "a", "an", "the", and "all" shall be inferred if omitted from sentences in the specifications or on notes in the drawings.

B. The Contractor shall not be relieved of performing such omissions from drawings, specifications, or details of work which are manifestly necessary to carry out the intent of the work.

C. The Contractor shall check all contract documents furnished immediately upon their receipt and shall promptly notify the Contracting Officer of any discrepancies.

Written dimensions marked on drawings shall, in general, be followed in preference to scaling dimensions from drawings. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby. This means the Contractor is responsible for finding all discrepancies between drawings for different disciplines such as electrical and mechanical. These differences must be submitted to the Contracting Officer during the bid process. The Government will not relieve any discipline of work found on another discipline’s drawings but not on their own.

1.09 ABBREVIATIONS/DEFINITIONS

A. The Drawings and Specifications use accepted standard abbreviations. The

Contractor shall accept the Contracting Officer's interpretations of such abbreviations where in doubt. Certain words are used extensively throughout the documents, and are interpreted as follows:

1. "Owner" means "the Government".

2. "Architect/Engineer" means the "Contracting Officer".

3. "Approved" means "Approved by the Contracting Officer".

4. "For Approval" means "For the Contracting Officer's Approval".

5. "Required" means "Required by the Contracting Officer".

6. "Provide" means "Furnish and Install".

***END OF SECTION***

Section 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF PROJECT

A. Summary of Project B. Government Furnished Property C. Work by Government D. Location E. Commencement and Completion of Work

1.02 SUMMARY OF PROJECT

A. The work covered by these specifications includes furnishing all plant, labor, equipment, materials, tools, permits, and other items required to complete this project in accordance with these specifications and contract documents and subject to the terms of the contract.

B. Principal Features: Demolition, in its entirety, of Building 531 and adjoining sidewalk located at Paine Field, Everett, Washington. Work includes hazardous material abatement, removal and/or recycling of all demolished materials, and minor site restoration. The existing building consists of a single story, wood-frame construction with concrete slab-on-grade flooring. Building 531 is approximately 3,765 square feet and contains offices, classroom space, and restrooms. Exterior finishes include vinyl siding over original cement asbestos board and composition shingle roofing. Building demolition shall include slab and all foundations, and removal of power, water, sanitary, and gas utility infrastructure in accordance with applicable regulations and utility requirements. Site restoration shall include placement of clean fill in voids left by demolition activities. All disturbed areas shall be graded and seeded to provide positive drainage and a smooth, mowable surface. All public utility poles are to remain in place. Shrubs and small trees which interfere with or will be damaged during demolition may be removed with approval from the Contracting Officer; otherwise, landscaping on site shall be protected in place.

C. Hazardous Materials: Asbestos, lead, and polychlorinated biphenyls (PCBs) are known and/or presumed to exist throughout the structure. All work shall be performed as specified herein assuming the entirety of the structure contains hazardous materials.

1. The Contractor may conduct a hazardous materials survey for its sole benefit and at no expense to the Government. Materials that are identified in such a survey as non-hazardous may be removed, recycled, and salvaged as specified in Section 02 41 00 DEMOLITION.

2. All work involving identified and/or presumed hazardous materials shall conform to the Puget Sound Clean Air Agency Regulation III Article 4:

Section 01 11 00 Page 2

Asbestos Control Standards. All work involving removal or disturbance of hazardous materials shall conform to all federal, State, and local regulations and abatement specifications.

3. Documents from past hazardous materials investigations are available for reference only and shall not be considered complete or representative of the entire work area.

a. “Hazardous Building Materials Survey, Air National Guard, Buildings

455 and 456, 215th EIS Squadron, Paine Field, Everett, Washington” prepared by Med-Tox Northwest, Post Office Box 1446, Auburn, Washington 98071-1446, dated September 16, 2011.

b. “Asbestos Management Program” prepared by the Air National Guard

Readiness Center Civil Engineering Technical Services Center, dated 1992.

c. “Building 531 Asbestos/Lead Testing” prepared by Eurofins EMLab

P&K, 19515 North Creek Pkwy N, #100, Bothell, WA 98011, dated June 15, 2021.

1.03 GOVERNMENT FURNISHED PROPERTY

None

1.04 WORK BY GOVERNMENT

None

1.05 LOCATION

A. Washington Air National Guard (ANG) Installation, Paine Field, Everett, Washington

B. Directions to Project Site:

Project address as follows: 2701 112th St SW, Everett, WA 98204. Building 531 is situated northwest of the intersection of 112th St SW and Beverly Park Rd. From I- 5 northbound take the 128th Street exit (Exit 186). Turn left on 128th. At the intersection of 128th St. & Hwy 99, 128th St. becomes Airport Road. Continue on Airport Road to 112th St. SW and take a left at 112th St. SW. Turn right on Minuteman Dr, then turn right into location of ANG complex. Contractor to coordinate access through gate prior to construction phase. Building 531 is located in the southeastern portion of this complex.

From I-5 southbound take the Mukilteo/Paine Field exit going west on 526. Take the Airport Road/Paine field exit from 526. Follow Airport Road until you come to 112th St. SW. Take a right on 112th St. SW. Turn right onto Minuteman Dr and continue as stated above.

Section 01 11 00 Page 3

1.06 COMMENCEMENT AND COMPLETION OF WORK

A. Start Demolition Work – within 30 calendar days from Notice to Proceed (NTP).

B. Demolition Work Completed – within 60 calendar days from NTP. Preliminary Closeout Inspection will be conducted 61 calendar days from NTP.

C. Complete Preliminary Closeout Inspection Items – within 30 calendar days from

Demolition Work Completed. Final Inspection will occur 91 calendar days from NTP.

D. Close Out Documents – 120 calendar days from date of NTP. This allows 30 days for the submittal of final payrolls.

Section 01 19 00 Page 1

SECTION 01 19 00

REFERENCE STANDARDS

1.01 REFERENCES

A. For products or workmanship specified by association, trade, or Federal Standards, comply with requirements of the standard, except when more stringent requirements are specified or are required by applicable codes, then comply with the more stringent requirement. Conform to the most current publication at the time of demolition work.

AA Aluminum Association

AABC Associated Air Balance Council

AASHTO American Association of State Highway and Transportation Officials

ACI American Concrete Institute

ADC Air Diffusion Council

AGC Associated General Contractors of America

AI Asphalt Institute

AIA American Institute of Architects

AITC American Institute of Timber Construction

AISC American Institute of Steel Construction

AISI American Iron and Steel Institute

AMCA Air Movement and Control Association

ANSI American National Standards Institute

APA American Plywood Association

ARI Air-Conditioning and Refrigeration Institute

ASHRAE American Society of Heating, Refrigerating and Air Conditioning Engineers

ASME American Society of Mechanical Engineers

ASPA American Sod Producers Association

Section 01 19 00 Page 2

ASTM American Society for Testing and Materials

AWWA American Water Works Association

AWI Architectural Woodwork Institute

AWPA American Wood-Preservers' Association

AWS American Welding Society

CDA Copper Development Association

CLFMI Chain Link Fence Manufacturers Institute

CRSI Concrete Reinforcing Steel Institute

DOE Department of Ecology

EJCDC Engineers’ Joint Contract Documents Committee

EJMA Expansion Joint Manufacturers Association

FGMA Flat Glass Marketing Association

FM Factory Mutual System

FS Federal Specification

GSA General Services Administration

GA Gypsum Association

IEEE Institute of Electrical and Electronics Engineers

IMIAC International Masonry Industry All-Weather Council

MFMA Maple Flooring Manufacturers Association

MIL Military Specification

ML/SFA Metal Lath/Steel Framing Association

NAAMM National Association of Architectural Metal Manufacturers

NEBB National Environmental Balancing Bureau

NEC National Electrical Code

NEMA National Electrical Manufacturers' Association

NFPA National Fire Protection Association

Section 01 19 00 Page 3

NSWMA National Solid Wastes Management Association

NTMA National Terrazzo and Mosaic Association

PCA Portland Cement Association

PC Prestressed Concrete Institute

PS Product Standard

RIS Redwood Inspection Service

RCSHSB Red Cedar Shingle and Handsplit Shake Bureau

SDI Steel Deck Institute

SDI Steel Door Institute

SIGMA Sealed Insulating Glass Manufacturers Association

SJI Steel Joist Institute

SMACNA Sheet Metal and Air Conditioning Contractors' National Association

SSPC Steel Structures Painting Council

TAS Technical Aid Series

TCA Tile Council of America, Inc.

TMA Thermal Insulation Manufacturer's Association

UL Underwriters' Laboratories, Inc.

UBC Uniform Building Code

UMC Uniform Mechanical Code

UPC Uniform Plumbing Code

WCLIB West Coast Lumber Inspection Bureau

Section 01 21 00 Page 1

SECTION 01 21 00

HAZARDOUS MATERIALS

PART 1 - GENERAL

A. Hazardous Material Usage

B. Hazardous Material Identification

1.02 RELATED SECTIONS

A. All

1.03 HAZARDOUS MATERIAL USAGE

A. The Contractor shall establish a hazardous material (HM) storage and distribution system when hazardous material is to be used. All hazardous material required to support the contract shall be reported to the Hazardous Material Pharmacy (HMP) using the Contractor Hazardous Materials Form (included in this specification section). Additional hazardous materials needed by the Contractor shall be identified to the Contracting Officer for approval by the HMP. See Attachment - Hazardous Materials Form.

B. The Contractor planning to use hazardous material for the work must register with the base HMP prior to start of work in order to support the installation’s compliance with Executive Order 13423, Federal Compliance with Right-to-Know Laws and Pollution Prevention Requirements.

C. The Contractor shall maintain Contractor Hazardous Material Form for hazardous material on the job site for inspection/verification.

D. Contracting Officer will verify that the hazardous material identified to HMP is the only hazardous material in use on the job site.

E. Contractors shall provide the HMP:

1. A list of each material and quantity of material for all proposed hazardous material. Hazardous material shall mean any item that is:

a. A health hazard or physical hazard as defined in 29 CFR, 1910.1200(c).

b. Regulated in its disposal by EPA under 40 CFR.

c. Hazardous as defined by DOT regulations under 49 CFR.

Section 01 21 00 Page 2

d. Hazardous as defined by the Dangerous Goods Regulations of the International Air Transport Association.

2. A material safety data sheet (MSDS) for each item on the list.

F. The Contractor shall establish his/her own HM storage and issue location that complies with federal, State, and local environmental regulations. Materials issued shall be tracked for quantities used. Unused materials shall be inventoried and removed from the ANG installation prior to close out of the contract or expiration date of the HM. Reports of materials delivered, used and removed from the installation shall be submitted to the Contracting Officer monthly and prior to contract close out. See Attachment – Hazardous Materials Form.

G. The Contractor shall comply with all federal, State, and local environmental standards.

H. The contractor shall accompany the Base Environmental Engineer (BEE) and the COR on project close out inspection to ensure all used/unused HM was removed from the installation. This requirement shall not be a punch list item and must be accomplished prior to the Government accepting beneficial occupancy of the facility.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Section 01 21 00 Page 3

ATTACHMENT – HAZARDOUS MATERIALS FORM

Contractor Hazardous Material Identification Form

Date:

Part I

This part is to be completed by Contractor prior to start date and shall be maintained on the job site.

Contractor Company:

Proposed work term: to Contractor Point of Contact:

24-Hour phone/pager number:

HM to be used:

MFG./Product

M.S.D.S.

Attached

Quantity used

Disposal Procedures Used/Unused material removed from ANG installation

Note: This form is good for a one-month period and is to be submitted to the Hazardous Material Pharmacy (HMP). All hazardous material used thereafter will be identified to Contacting Officer for approval by the HMP. See Part II for Contractor close out procedures. HMP phone number is (253) 982-3196.

Approval Signatures:

KO (Contracting Officer)

BEER (Bio-Environmental Engineering Representative)

EM (Environmental Manager)

SO (Safety Officer)

Contractor Hazardous Material Identification Form (Close Out Procedures)

Part II

Attach this form to Part I

Section 01 21 00 Page 4

The Contractor shall accompany the Contraction Officer and Environmental Manager on the close out inspection to ensure all used/unused hazardous material was removed from the installation.

Close out Signatures: Date:

KO (Contracting Officer)

BEER (Bio-Environmental Engineering Representative)

EM (Environmental Manager)

Contractor

Section 01 22 00 Page 1

SECTION 01 22 00

CONFINED SPACE

A. Notification of Work in a Permit-Required Confined Space.

B. Contractor Compliance with OSHA (Public Law 91-956).

1.02 NOTIFICATION OF WORK IN A PERMIT-REQUIRED CONFINED SPACE

A. The Government shall notify the Contractor that work will be performed in a permit-required confined space and ensure the information is included in the statement of work (SOW) or equivalent contracting tool.

B. Notification requirements are contained in AFI 91-202, The U.S. Air Force Mishap

Prevention Program and AFFARS Clause 5352.223-9001, Health and Safety on Government Installations.

C. The WA Air National Guard Facility Manager will provide details on the contents of the space and any known hazards that make the space permit-required.

1.03 CONTRACTOR COMPLIANCE WITH OSHA (PUBLIC LAW 91-956)

A. It is the Contractor’s sole responsibility for compliance with the OSHA (Public Law 91-956).

B. The Contractor shall coordinate with Paine Field Fire and Emergency Services to approve the use of the rescue team prior to work in the confined space.

C. The Contractor shall provide information regarding hazards encountered or created in the space.

D. The Contractor shall coordinate with the Contracting Officer to agree upon the permit space entry system to be used when both Air Force organizational and contractor personnel will be working in a permit-required confined space. The Contractor program must meet Air Force confined space program requirements, at a minimum, before Air Force personnel may enter a Contractor permit-required confined space.

Section 01 31 00 Page 1

SECTION 01 31 00

ACCESS AND SECURITY REQUIREMENTS

A. Contractor Entry to Air National Guard Installations B. Site Access, Paine Field, Everett, WA C. Site Access, Camp Murray, WA

1.02 CONTRACTOR ENTRY TO AIR NATIONAL GUARD INSTALLATIONS

A. All Contractor personnel requesting access to an Air National Guard installation shall complete a Defense Biometric Identification System (DBIDS) Pre-Enrollment.

The pre-enrollment form and instructions are available at www.mil.wa.gov/camp-murray-gate-access.

B. The Sponsor’s name and contact information can be obtained from the Contracting Officer.

1.03 SITE ACCESS, PAINE FIELD, EVERETT, WA

A. Contractor shall coordinate site access through the Contracting Officer prior to beginning work.

B. Site access will be limited to established working hours per Section 01 10 00 Summary of Work and shall be coordinated with the Contracting Officer at the Pre- Construction Meeting.

C. Contractors will be required to show their security pass obtained through DBIDS

Pre-Enrollment, driver’s license, vehicle registration, and proof of insurance. All Contractor and subcontractor personnel shall comply with terms listed on their security pass.

1.04 SITE ACCESS, CAMP MURRAY, WA

A. Contractors shall coordinate site access through the Contracting Officer prior to beginning work.

B. Site access will be limited to established working hours per Section 01 10 00 Summary of Work and shall be coordinated with the Contracting Officer at the Pre- Construction Meeting.

C. Contractors will be required to show their security pass obtained through DBIDS

Pre-Enrollment, driver’s license, vehicle registration, and proof of insurance.

Vehicle passes and additional information can be obtained at the Camp Murray Security Office, Bldg. 33 on Camp Murray (immediately inside the Commercial

Section 01 31 00 Page 2

Gate). All Contractor and subcontractor personnel shall comply with terms listed on their security pass.

Section 01 33 00 Page 1

SECTION 01 33 00

SUBMITTALS

A. Progress Schedule B. Laboratories and Testing Agencies C. Submittal Schedule

1.02 PROGRESS SCHEDULE

A. The Contractor shall bring a draft progress schedule to the Pre-Construction

Conference. The Contractor shall submit updated progress schedules during each weekly progress meeting, or at a minimum with each pay application.

B. The Schedule will be on an AF form 3064 (or electronic equivalent if approved by the Contracting Officer). In the Work Elements column, list the major components of the project (generally in CSI divisions, or by subcontractor). Identify all milestones as listed in 01 11 00 SUMMARY OF WORK, COMMENCEMENT AND COMPLETION OF WORK. Punchlist and closeout items (O&M Manuals, As-Builts, etc.) must be completed within the contract period.

1.03 LABORATORIES AND TESTING AGENCIES

A. The Contractor may elect to have a Hazardous Materials Survey conducted at no cost to the Government if the Contractor will not presume the whole facility to have asbestos-containing materials. Should this action occur, the following standards must be followed. Submit laboratory and test agency qualification certifications in letter format to the Base Civil Engineer. Include laboratory name, address, and telephone number, and names of full-time registered Engineer and responsible officer.

1.04 SUBMITTALS

A. Provide submittals in electronic PDF format. Compile the submittal file as a single, complete document, to include the Transmittal form provided by the Contracting Officer. Name the electronic submittal file specifically according to its contents and coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. E-mail electronic submittal documents smaller than 10MB to an e-mail address as directed by the Contracting Officer. Provide electronic documents over 10MB through an electronic file sharing system, established and maintained by the Contractor. If licenses are required to access or use the file sharing system, provide the Government with a minimum of two licenses, available for the duration of the contract.

B. A summary listing of items to be submitted to the Contracting Officer by the Contractor is included for convenience only. Such listing is not necessarily complete. The Contractor shall examine all portions of the Contract Documents for

Section 01 33 00 Page 2 complete submittal requirements. The estimated dates of submittals are projected dates only and may require modification based on actual project conditions and progress of work. The Contractor is responsible for ensuring all Contract requirements are met by the final schedule completion date.

Section 01 33 00 Page 3

CONTRACT NO. PROJECT NO.

Item No. Specification Item Description

Sub-mittal No.

Estimated Date of

Submittal

Date to A-E

Date to

BCE

Date to Contracting

Officer

Date to Contractor APPR DIS-

APPR

1 01 21 00 / 1.03

Hazardous Materials Form

2 01 33 00 / 1.02

Progress Schedule

3 01 33 00 / 1.03

Laboratory and Testing Agency Qualifications

4 01 40 00 / 1.04

Progress Reports

5 01 55 00 / 1.04

Waste Management Plan

6 01 70 00 / 1.02.A.

Inspection Request

7 02 41 00 / 1.02

Demolition Plan

8 02 41 00 / 1.05.C.

Demolition Receipts

9 02 41 00 / 1.06

Notification

10 02 82 14.00 10 / 1.01

Weight Bills and Delivery Tickets

11 02 82 14.00 / 1.06

Written Qualifications and Organization Report

12 02 82 14.00 / 1.07

Accident Prevention Plan (APP)

13 02 82 14.00 / 1.07

Asbestos Hazard Abatement Plan (AHAP)

14 02 82 14.00 / 1.07

Activity Hazard Analyses (AHAs)

Section 01 33 00 Page 4

15 02 82 14.00 / 1.09

Medical Surveillance

16 02 82 14.00 / 1.11

Training Program

17 02 82 14.00 / 2.01-2.05

Asbestos Hazard Control Products and Equipment

18 02 83 13.00 20 / 1.04

Lead Preconstruction Submittals

19 02 83 13.00 20 / 1.04

Lead Test Reports

20 02 83 13.00 20 / 1.04

Lead Certificates

21 02 83 13.00 20 / 1.04

Lead Closeout Submittals

22 02 84 16 / 1.05

PCB and Lamp Removal Work Plan

23 02 84 16 / 1.05

PCB and Lamp Disposal Plan

24 02 84 16 / 1.05

PCB and Lamp Closeout Submittals

25 31 00 00 /

Borrow Plan

26 31 00 00 /

Material Testing Report

Section 01 40 00 Page 1

SECTION 01 40 00

QUALITY CONTROL

A. Progress Meetings

B. Requests for Information (RFI/PRFI)

C. Progress Reports

D. Contractor Quality Assurance and Workmanship

E. Government Inspections

F. Testing Agency Labels

G. Inspection and Testing Laboratory Services

H. Laboratory Reports

1.02 PROGRESS MEETINGS

A. The Contracting Officer will host a weekly progress meeting that includes the Contractor, the Contracting Officer, and the Contracting Officer’s Representative. The meeting will normally be held via teleconference or in the Contracting Officer’s conference room at Camp Murray, WA.

Subcontractors who are performing significant project tasks are recommended to attend.

B. The agenda will cover work accomplished during the previous week, work expected to be accomplished during the next two weeks, submittals, Requests for Information (RFIs), utility coordination, safety, and other issues.

C. The Contractor shall provide an updated Progress Schedule at each weekly progress meeting. The Progress Schedule shall meet the requirements of

01 33 00 SUBMITTALS, 1.02 PROGRESS SCHEDULE.

1.03 REQUESTS FOR INFORMATION (RFI/PRFI)

A. Should a question arise requiring a response from the Government, the

Contractor shall initiate a Request for Information (RFI) or a Proposal Request for Information (PRFI) using the form provided at the Pre- Construction Conference. The Contractor will state the problem and list a recommended solution (for example, “The plans specify 10 feet between fence posts, but on this leg of the fence there is a span of 21 feet. I

Section 01 40 00 Page 2 recommend extending the distance between posts to 10.5 feet, eliminating the 1-foot fence section. How should I proceed?”).

B. The Contractor will email the form to the Contracting Officer who will then email it to the Contracting Officer’s Representative. The COR will make a recommendation, and also indicate if this should be a cost or no cost change, and if a time extension is required. If there is a time extension or cost change required, the COR will attach a Statement of Work and Request For Proposal and return it to the Contracting Officer, who will email it back to the Contractor with an RFP if applicable.

C. The Contractor will then act on the response. Should the Contractor disagree with the COR’s response, the Contractor will bring this to the attention of the Contracting Officer.

1.04 PROGRESS REPORTS

A. The Contractor shall submit progress reports on AF Form 3065 (or electronic equivalent approved by the Contracting Officer). Submit on a 14-calendar day cycle from the date of the Notice to Proceed, based on the Progress Schedule. Progress Reports are not required to be submitted with an AF Form 3000.

1.05 CONTRACTOR QUALITY ASSURANCE AND WORKMANSHIP

A. The Contractor will monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality. Comply with specified standards as a minimum quality for the work except when more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

Where a quality standard is not specified, the Contractor shall provide a level of workmanship that meets a recognized industry standard. The Contracting Officer shall resolve conflicts in interpretations of quality of workmanship.

B. Comply fully with manufacturers' instructions, including each step in sequence. Should manufacturer's instructions conflict with Contract Documents, request clarification from the Contracting Officer before proceeding.

C. Perform work by persons qualified in the specified trade or specialty to ensure quality workmanship.

D. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion or disfigurement.

E. Furnish and maintain a printed copy of contract specifications onsite, accessible by all Contractor and Subcontractor personnel.

Section 01 40 00 Page 3

1.06 GOVERNMENT INSPECTIONS

A. Provide equipment to permit the Contracting Officer or his appointed representative to inspect the work in safety, such as ladders, scaffolding and gangways.

B. No underground utility or structure shall be backfilled until they are inspected and approved by the Contracting Officer. The Contractor shall give the Contracting Officer two workdays’ notice of the intention to backfill or cover work. Work covered up without approval or required inspection shall, upon request of the Contracting Officer, be uncovered for inspection at the expense of the Contractor.

1.07 TESTING AGENCY LABELS

A. The Contractor shall submit proof that the items which he/she proposes to furnish under this specification conform to the standards of the Underwriter's Laboratories (UL). The UL label shall be accepted as conforming to this requirement.

B. In lieu of the label, the Contractor may submit a written certification from any nationally recognized testing agency, adequately equipped and competent to perform such services, that the item has been tested and conforms to the standards, including methods of test, of the Underwriter's Laboratories.

C. Should specified reference standards conflict with Contract Documents, request clarification from the Contracting Officer.

1.08 INSPECTION AND TESTING LABORATORY SERVICES

A. The Contractor shall employ and pay for services of an independent testing laboratory to perform inspections and testing as outlined in the specifications. The Contractor will perform additional inspections and tests if required by the Contracting Officer.

B. Employment of a testing laboratory shall in no way relieve the Contractor of the obligation to perform work in accordance with the requirements of the Contract Documents.

C. Testing Agencies will:

1. Comply with requirements of the individual specification sections.

2. Be licensed by the State of Washington.

3. Maintain a full time Engineer registered by the State of Washington.

D. Testing Equipment should be calibrated at reasonable intervals with devices of an accuracy traceable to either National Bureau of Standards (NBS) or accepted values of natural physical constants.

Section 01 40 00 Page 4

E. The Contractor will provide incidental labor and facilities to provide access to the work to be tested, to obtain and handle samples at the site or at source of products to be tested, and to facilitate tests and inspections, storage and curing of test samples.

F. Notify the Contracting Officer and laboratory three workdays prior to expected time for operations requiring inspection and testing services.

1.09 LABORATORY REPORTS

A. After each inspection and test, promptly submit (using a Transmittal Letter) two copies of laboratory report(s) to the Contracting Officer’ Representative.

B. Include:

1. Date issued.

2. Project title and number.

3. Name of inspector.

4. Date and time of sampling or inspection.

5. Identification of product and Specifications section.

6. Location in the project.

7. Type of inspection or test.

8. Date of test.

9. Results of tests.

10. Conformance with Contract Documents

C. When requested by the Contracting Officer, provide interpretation of test results.

Section 01 50 00 Page 1

SECTION 01 50 00

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

PART 1 – GENERAL

A. Temporary Utilities: electricity and lighting, ventilation, water, sanitary facilities, and rubbish removal.

B. Temporary Controls: Barriers, enclosures, protection of work.

C. Construction Stormwater Pollution Prevention: Erosion and sediment control

D. Construction Facilities: Cleaning, temporary buildings, and removal of utilities.

1.02 TEMPORARY ELECTRICITY AND LIGHTING

A. Connect to the existing power service. Power consumption shall not disrupt the

Government's need for continuous service. The Government will provide electricity at no cost to the Contractor. The Contractor will provide all equipment and services required for hook up at no expense to the Government.

B. The Contractor shall exercise measures to conserve energy.

C. The Contractor shall provide temporary distribution equipment, overcurrent protection, wiring, outlets, meters, lighting, and other items, as required.

1.03 TEMPORARY VENTILATION

A. The Contractor shall ventilate enclosed areas to assist cure of materials, dissipate humidity, and prevent accumulation of dust, fumes, vapors, or gases.

1.04 TEMPORARY WATER

A. The Government will pay the cost of reasonable amounts of water used when taken from Government sources. The Contracting Officer shall determine what a reasonable amount of water is. The Contractor will take steps to conserve water.

B. The Contractor will provide hoses, manifolds, adapters, backflow prevention devices and other equipment required for water service.

1.05 TEMPORARY SANITARY FACILITIES

A. Provide and maintain in sanitary condition, required facilities and enclosures. Place as directed by the Contracting Officer.

Section 01 50 00 Page 2

1.06 RUBBISH REMOVAL

A. The contractor will collect and dispose of all construction debris. Disposal shall be off site at a legal refuse collection site. Do not use Government rubbish containers.

B. See Section 1.10 Progress Cleaning, for frequency of rubbish removal.

C. See Specification 02 82 14.00 10 Asbestos Hazard Control Activities for hazardous material removal.

1.07 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations.

B. Provide protection for plant life designated to remain. Replace damaged plant life.

C. Protect non Contractor-owned vehicular traffic, stored materials, site and structures from damage.

D. Provide detour signs to route traffic around closed work areas.

E. Notify the Contracting Officer seven calendar days prior to closing a work area. Keep building occupants informed of changes in building access, parking areas, etc.

1.08 CONSTRUCTION STORMWATER POLLUTION PREVENTION

A. Contractor shall contain all stormwater runoff generated onsite during construction/demolition phase.

B. Provide protection from erosion and sediment accumulation by use of fabric fence barriers, inlet protection socks, and construction stormwater best management practices (BMPs) as outlined in the current edition of the Department of Ecology Stormwater Management Manual for Western Washington (SWMMWW)

C. Contractor shall ensure hazardous materials demolished or abated onsite are not introduced into public stormwater infrastructure or other natural streams or drainage systems.

1.09 PROTECTION OF INSTALLED WORK

A. Protect installed work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate work area to minimize damage.

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.

Section 01 50 00 Page 3

E. Prohibit traffic from landscaped areas.

1.10 PROGRESS CLEANING

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.

B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space.

C. Broom and vacuum clean interior areas prior to start of surface finishing and continue cleaning to eliminate dust.

D. Remove waste materials, debris, and rubbish from site weekly or as required by the Contracting Officer.

E. Remove combustible rubbish and debris from the site daily.

F. Foodstuff and related debris from workmen's lunches and coffee breaks shall be placed in galvanized metal garbage container and removed from the site daily.

Containers shall be sound, watertight and shall provide a barrier to insects, rodents and other animals.

G. See Specification 01 70 00 Contract Closeout.

1.11 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary above grade or buried utilities, equipment, facilities, and materials, prior to final inspection.

B. Clean and repair damage caused by installation or use of temporary work.

C. Restore existing facilities used during construction to original condition.

Section 01 55 00 Page 1

SECTION 01 55 00

CONSTRUCTION WASTE MANAGEMENT

A. Waste Management Goals

B. Waste Management Plan

1.03 WASTE MANAGEMENT GOALS

A. The Government has established that this Project shall generate the least amount of waste possible and that processes that ensure the generation of as little waste as possible due to error, poor planning, breakage, mishandling, contamination, or other factors shall be employed.

B. Of the inevitable waste that is generated, as many of the waste materials as economically feasible shall be recycled, reused, or salvaged. Waste disposal in landfills shall be minimized. For purposes of this section, the following definitions apply:

1. Hazardous Material Abatement/Removal: All hazardous materials identified onsite will be surveyed by an accredited testing agency licensed in the State of Washington. The surveying agency shall determine the type and quantity of the hazardous materials and shall provide the contractor a cost estimate for materials abatement and/or removal in accordance with local, state, and federal regulations. Hazardous Materials Survey to conclude if asbestos present are friable or non-friable. Contractor shall provide a Construction and Demolition Materials Disposition report to the CO prior to project close-out.

2. Recycle: To remove a waste material from the Project site to another site for remanufacture into a new product for reuse by others.

3. Reuse: To reuse a construction waste material in some manner on the Project site.

4. Salvage: To remove a waste material from the Project site to another site for resale or reuse by others.

C. Regarding these goals, the Contractor shall develop, for the Contracting Officer’s review and approval, a Waste Management Plan for this Project. The Final Waste Management Plan must be approved by the Contracting Officer prior to commencement of work.

Section 01 55 00 Page 2

1.04 WASTE MANAGEMENT PLAN

A. Draft Waste Management Plan: Submit to the Contracting Officer within 10 calendar days after receipt of Notice of to Proceed. The Draft Plan shall contain the following:

1. Analysis of the proposed jobsite wastes to be generated, including types and quantities.

2. Analysis of hazardous materials present onsite which will require abatement and/or removal in accordance with local, State, and federal regulations.

3. Landfill options: The name of the landfill(s) where trash will be disposed of, the applicable landfill tipping fee(s), and the projected cost of disposing of all Project waste in the landfill(s).

4. Alternatives to Landfilling: A list of each material proposed to be salvaged, reused, or recycled during the course of the Project, the proposed local market for each material, and the estimated net cost savings or additional costs resulting from separating and recycling (versus landfilling) each material. “Net” means that the following have been subtracted from the cost of separating and recycling:

a. Revenue from the sale of recycled or salvaged materials

b. Landfill tipping fees saved due to diversion of materials from the landfill. The list of these materials is to include, at minimum, the following materials:

(1) Paving materials

(2) Structural and other steel

(3) Gypsum wall board

(4) CMU block

B. Resources for Development of Waste Management Plan: The following sources may be useful in developing the Draft Waste Management Plan:

1. Recycling Haulers and Markets: Local haulers and markets for recyclable materials can be obtained from the Washington Department of Ecology Recycling Assistance office at 1-800-RECYCLE (800-732-9253) or at http://1800recycle.wa.gov. This list is provided for information only and is not necessarily comprehensive; other haulers and markets are acceptable.

2. Recycling Economics Information: Section 01 56 00 contains information that may be useful in estimating the costs or savings of recycling options.

C. Final Waste Management Plan: Once the Contracting Officer has determined which of the recycling options addressed in the draft Waste Management Plan are

Section 01 55 00 Page 3 acceptable, the Contractor shall submit a Final Waste Management Plan to the Contracting Officer within 10 calendar days of the receipt of the approved draft Waste Management Plan. The Final Waste Management Plan shall contain the following:

1. Analysis of the proposed jobsite waste to be generated, including types and quantities.

2. Landfill options: The name of the landfill(s) where trash will be disposed of, the applicable landfill tipping fee(s), and the projected cost of disposing of all Project waste in the landfill(s).

3. Alternatives to Landfilling: A list of the waste materials from the Project that will be separated for reuse, salvage, or recycling.

4. Materials Handling Procedures: A description of the means by which any waste materials identified in item (3) above will be protected from contamination, and a description of the means to be employed in recycling the above materials consistent with requirements for acceptance by designated facilities.

5. Transportation: A description of the means of transportation of the recyclable materials (whether materials will be site-separated and self-hauled to designated centers, or whether mixed materials will be collected by a waste hauler and removed from the site) and destination of materials.

D. Waste Management Plan Implementation

1. Manager: The Contractor shall designate an on-site party (or parties) responsible for instructing workers and overseeing and documenting results of the Waste Management Plan for the Project.

2. Distribution: The Contractor shall distribute copies of the Waste Management

Plan to the Job Site Foreman, each Subcontractor, and the Contracting

3. Instruction: The Contractor shall provide on-site instruction of appropriate separation, handling, and recycling, salvage, reuse, and return methods to be used by all parties at the appropriate stages of the Project.

4. Separation facilities: The Contractor shall lay out and label a specific area to facilitate separation of materials for potential recycling, salvage, reuse, and return. Recycling and waste bin areas are to be kept neat and clean and clearly marked in order to avoid contamination of materials.

5. Hazardous wastes: Hazardous wastes shall be separated, stored, and disposed of according to local regulations and as specified herein.

6. Application for Progress Payments: The Contractor shall submit with each Application for Progress Payment a Summary of Waste Generated by the Project. The Summary shall be submitted on a form acceptable to the Contracting Officer and shall contain the following information:

Section 01 55 00 Page 4

a. The amount (in tons or cubic yards) of material landfilled from the

Project, the identity of the landfill, the total amount of tipping fees paid at the landfill, and the total disposal cost. Include manifests, weight tickets, receipt, and invoices.

b. For each material recycled, reused, or salvaged from the Project, the amount (in tons or cubic yards), the date removed from the jobsite, the receiving party, the transportation cost, the amount of any money paid or received for the recycled or salvaged material, and the net total cost or savings of salvage or recycling each material. Attach manifests, weight tickets, receipts, and invoices.

Section 01 56 00 Page 1

SECTION 01 56 00

RECYCLING ESTIMATING

A. Estimating the Amount of Recyclable Waste: Generation Rates

B. Estimating the Amount of Recyclable Waste: Conversion Figures

C. Tips on Reducing the Cost of Recycling

D. Estimating the Cost of Waste Management Encompassing Recycling

1.03 ESTIMATING THE AMOUNT OF RECYCLABLE WASTE: GENERATION RATES

A. One method of estimating the generation of different types of waste is to get average figures of waste generation for different construction materials. The following are estimates by material:

1. Corrugated cardboard 7.5% of commercial construction waste is scrap corrugated cardboard.

2. Dimensional lumber and pallets 18% of commercial scrap dimensional lumber and pallets.

3. Metals 4.5% of commercial scrap metal.

4. Gypsum wallboard: 1/2 pound per square foot of commercial becomes scrap.

5. Concrete 15% of commercial scrap concrete.

(Sources: "A New Methodology for Quantifying Construction Waste", Peter Yost and John M. Halstead, in Sustainable Construction: Proceedings of the First International Conference of CIB TG 16 (1994), University of Florida

Section 01 56 00 Page 2

College of Architecture; Construction Materials Recycling Guidebook -- A Guide to Reducing and Recycling Construction and Remodeling Waste, Metropolitan Council of the Twin Cities Area, 1993.)

B. Another method is to look at generation rates from similar projects. Several studies have been conducted on the amount of recyclable waste generated on commercial construction projects:

1. Construction of a 5,000-square foot restaurant generated 12,344 pounds of waste, or 2.46 pounds per square foot. This waste included the following recyclable materials:

a. Wood 7,440 pounds (61% of the waste)

b. Cardboard 1,414 pounds (11% of the waste)

c. Gypsum wallboard 500 pounds (4% of the waste)

(Source: Characterization of Construction Site Waste (1993), Metro Solid Waste Department (Portland OR).)

2. Six commercial renovation projects averaged the following percentages of recyclable materials:

a. Untreated dimensional wood 5% of all project waste

b. Cinderblock 19% of all project waste

c. Concrete without rebar 22% of all project waste

d. Ferrous scrap 5% of all project waste

(Source: "What's in a Building?", Demolition Age, September 1993.)

3. Construction of one commercial low-rise building generated the following percentages of recyclable materials:

a. Wood 8% of all project waste

(Source: Metropolitan Toronto Waste Composition Study, 1991, cited in Construction Waste & Demolition Debris Recycling . . . A Primer (1993) Solid Waste Association of North America (Silver Spring MD.)

1.04 ESTIMATING THE AMOUNT OF RECYCLABLE WASTE: CONVERSION FIGURES

A. Mixed Waste 350 lbs/CY 0.175 tons/CY 5.7 cu yds/ton

B. Wood 300 lbs/CY 0.15 tons/CY 6.7 cu

Section 01 56 00 Page 3

C. Cardboard 100 lbs/CY 0.05 tons/CY 20 cu yds/ton

D. Gypsum wallboard. 500 lbs/CY 0.25 tons/CY 4 cu yds/ton

E. Rubble 1400 lbs/CY 0.7 tons/CY 1.4 cu

(Source: Resource Efficient Building (1994), Metro Solid Waste Department (Portland OR).)

1.05 TIPS ON REDUCING THE COST OF RECYCLING

A. Schedule containers for collecting recyclables only when needed. For example, rent a collection container for cardboard only during the latter part of construction, when the majority of cardboard waste is generated.

B. Be sure to understand the market specifications so that recyclable materials are not rejected. For example, some markets for clean wood waste accept only dimensional lumber; others also accept plywood, particleboard, and oriented strand board.

C. Encourage scrap dealers to be flexible when possible. For example, a scrap metal dealer who initially refused to accept metal bands from around lumber was convinced to accept them when they were repeatedly folded and hit with a hammer, then put into an empty 5-gallon plastic bucket, so as to create a more dense item for transportation. (Creating these more dense bundles of metal bands also had the advantage of cutting down on injuries at the construction site.)

1.06 ESTIMATING THE COST OF WASTE MANAGEMENT ENCOMPASSING RECYCLING

A. The Contractor will submit to the Contracting Officer an estimated cost of construction waste management from the Project with the 75% progress report/pay request. The following steps will help arrive at an estimate of the cost, which involves recycling certain materials.

Section 01 56 00 Page 4

Step One: Estimate Total Project Waste and Amounts of Recyclable Materials.

(Line 1) Estimate the Total Project Waste in cubic yards. (1)____________(cy)

For each material to be recycled, estimate the amount of waste to be recycled.