Repair Water Mains and Roads_Questions_Answers_28 Aug 2020.pdf

PDF 59 KB Posted

Attached to
Repair Water Mains and Roads
Solicitation number
W50S9A-20-B-0001
Issued by

About this file

This document contains questions and answers related to a solicitation for repair of water mains and roads. The solicitation seeks a firm fixed-price contract to repair water mains and roads at three locations on an Air National Guard base, including replacing water service mains and laterals, fire hydrants, and storm drains. A pre-bid conference is scheduled for August 11th and bids are due August 31st. The base bid is for work at two locations, with two options to accomplish the same work at the remaining locations. A brand name requirement applies to detector check valves. The projected value is between $5-10 million. The performance period is 365 days from notice to proceed. The solicitation is set aside for small businesses in NAICS code 237110 for water and sewer line construction with a $39.5 million size standard.

View the file

Other files

File Type Posted
USEB132009_Sabre Street_Revised Drawing C-02_28 Aug 2020.pdf PDF
Solicitation Amendment_W50S9A-20-B-0001-0003 Repair Water Mains and Roads.pdf PDF
USEB132019_Patriot Way_Revised Drawing GC-03_27 Aug 2020.pdf PDF
Repair Water Mains and Roads_Questions_Answers_27 Aug 2020.pdf PDF
USEB132009_Sabre Street_Revised Drawing GC-03_27 Aug 2020.pdf PDF
USEB132001_Mustang Lane_Revised Drawing GC-03_27 Aug 2020.pdf PDF
W50S9A-20-B-0001-0002_Repair Water Mains and Roads.pdf PDF
USEB132001_Mustang_IRP Summary and Locations Rev2_27 Aug 2020.pdf PDF
Solicitation Amendment_W50S9A-20-B-0001-0001_Repair Water Mains and Roads.pdf PDF
Mustang RFI 01_Marked Drawing.pdf PDF
Repair Water Mains and Roads_Questions_Answers_24 Aug 2020.pdf PDF
USEB132001_Mustang_Building Fire Suppression List.pdf PDF
USEB132009_Sabre Street_Geotech Report.pdf PDF
USEB132001_Mustang_Geotechnical Report.pdf PDF
USEB132001_Mustang Lane_BN Justification_KO Signed_Redacted.pdf PDF
USEB132001_Mustang Lane_Specifications_23Jul20.pdf PDF
USEB132019_Patriot Way_Design Narrative.pdf PDF
USEB132019_Patriot Way_Specifications_23Jul20.pdf PDF
W50S9A-20-B-0001 Repair Water Mains and Roads.pdf PDF
USEB132009_Sabre Street_Specifications_23Jul20.pdf PDF
USEB132019_Patriot Way_Geotechnical Report.pdf PDF
USEB132001_Mustang_Design Narrative.pdf PDF
USEB132001_Mustang_Env Summary.pdf PDF
USEB132009_Sabre Street_Design Narrative.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Water Mains and Roads

W50S9A‐20‐B‐0001

Questions and Answers

1. Question: Mustang and Patriot projects indicate removing the underlying materials under the asphalt to get to the sub‐base. Sabre street plans only indicate to remove the existing asphalt 4‐5” in depth according to the Geotech report. The Geotech report refers to the underlying material to be silty sand. Please clarify if the underlying material needs to be removed under the existing HMA on

Sabre Street.

Answer: See updated Sabre Street Drawing C‐02.

2. Question: The SLC dump is requesting the Phase 1 Environmental Site Assessment (ESA) to determine if the soil is chemically clean. Is this something that has been completed?

Answer: The government is way past a phase I ESA on these sites and past the Remedial Action phase on both sites and into Post Construction Completion. Since the sites are not officially closed, the maps provided on the 27 Aug 2020 IRP Summary document were from the latest Groundwater

Long Term Monitoring Reports. These documents may be viewed in their entirety on the public administrative record at https://ar.afcec‐cloud.af.mil/ (Select the ANG radial, highlight Salt Lake City

Int APT, UT, and then click search for the list of records).

The sample results on the maps provided mark the latest concentrations in groundwater. The contractor can use these numbers or conduct their own sampling of the soil to provide an accurate special waste profile for the landfills.

3. Question: Is there a domestic steel/iron requirement on this project? If so, what requirement do we need to meet (AIS, Buy America, Buy American, etc.)?

Answer: See FAR Provision 52.225‐10 and FAR Clause 52.225‐9.

4. Question: The specs (Environmental Concerns) states that water must be containerized and can be returned to the site. If this is the case and we don’t haul it off to dispose of it, it would be a lot more cost effective. There are containers that filter the water before they are discharged onsite. As the specs states, can we containerize the water and return it to the site? This is based on the assumption that we will be in ground water when installing the utilities.

Answer: IRP Summary (Environmental Concerns) has been updated to be clearer. Regulation allows for the contaminated water to be returned to the site, but this project is stricter than regulation and requires off‐site disposal. See updated IRP Summary (note difference between water from contaminated zones and non‐contaminated zones) and Mustang Dwg G‐04 Note 45.