This solicitation package provides details for a firm fixed-price construction contract to repair water mains and roads at the 151st Air Refueling Wing, Utah Air National Guard base. The scope of work includes replacing water service mains and laterals, installing new fire hydrants, storm drains, and road construction. The base bid requirement is for work on Mustang Lane and North Loop, with two optional locations for Patriot Way and Sabre Street. The projected value is between $5-10 million. The pre-bid conference is August 11th and bids are due August 31st. The period of performance is 365 days from notice to proceed. This acquisition is set aside for small business with a NAICS code of 237110 and size standard of $39.5 million. Interested parties should monitor the betaSAM website for solicitation documents and amendments.

View the file

Other files

File Type Posted
Repair Water Mains and Roads_Questions_Answers_28 Aug 2020.pdf PDF
USEB132009_Sabre Street_Revised Drawing C-02_28 Aug 2020.pdf PDF
Solicitation Amendment_W50S9A-20-B-0001-0003 Repair Water Mains and Roads.pdf PDF
USEB132019_Patriot Way_Revised Drawing GC-03_27 Aug 2020.pdf PDF
Repair Water Mains and Roads_Questions_Answers_27 Aug 2020.pdf PDF
USEB132009_Sabre Street_Revised Drawing GC-03_27 Aug 2020.pdf PDF
USEB132001_Mustang Lane_Revised Drawing GC-03_27 Aug 2020.pdf PDF
W50S9A-20-B-0001-0002_Repair Water Mains and Roads.pdf PDF
USEB132001_Mustang_IRP Summary and Locations Rev2_27 Aug 2020.pdf PDF
Solicitation Amendment_W50S9A-20-B-0001-0001_Repair Water Mains and Roads.pdf PDF
Mustang RFI 01_Marked Drawing.pdf PDF
Repair Water Mains and Roads_Questions_Answers_24 Aug 2020.pdf PDF
USEB132001_Mustang_Building Fire Suppression List.pdf PDF
USEB132009_Sabre Street_Geotech Report.pdf PDF
USEB132001_Mustang_Geotechnical Report.pdf PDF
USEB132001_Mustang Lane_BN Justification_KO Signed_Redacted.pdf PDF
USEB132001_Mustang Lane_Specifications_23Jul20.pdf PDF
USEB132019_Patriot Way_Design Narrative.pdf PDF
USEB132019_Patriot Way_Specifications_23Jul20.pdf PDF
W50S9A-20-B-0001 Repair Water Mains and Roads.pdf PDF
USEB132009_Sabre Street_Specifications_23Jul20.pdf PDF
USEB132019_Patriot Way_Geotechnical Report.pdf PDF
USEB132001_Mustang_Design Narrative.pdf PDF
USEB132009_Sabre Street_Design Narrative.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USEB132001 Repair Water Mains & Roads, Mustang Lane & North Loop 7/17/2019

Environmental Concerns

SOIL

• Soil cannot be used as fill elsewhere. It will either be returned to original site or sampled and disposed at approved landfill

• Soil would be disposed as non‐hazardous waste due to LUST site exemption found in 40 CFR 261.4(b)10 [Option] o For the Wasatch Regional Landfill, a sample must be taken and waste profiled (expect 3 day turnaround for lab and profiling before disposal); landfill can provide rolloff container at cost;

estimate disposal at $40/ton o Landfill Profile: Richard McMullin 801‐253‐1111 RMcMullin@republicservices.com o Lab: American West Analytical Services 801‐263‐8686 TCLP Metals, TCLP Volatile, TCLP

Semivolatile (confirm these with McMullin)

WATER

• Any water removed from the site (from rising ground water) must be containerized; it could either be returned to site by permit or sampled and disposed off site o Permit: Contact DEQ, Hillary Mason 801‐536‐4162 for initial assistance https://deq.utah.gov/legacy/programs/water‐quality/ground‐water/permits/index.htm#cuicp [Option] o Dispose of water with ET Technologies

KNOWN CONTAINMANTION ZONE

• Workers must be notified of contaminated soil and groundwater:

o Ground water only: (Vinyl Chloride) (TCE) (Cis‐1,2‐DCE) (1,1‐DCE) o Soil & GW: (Benzene) (TPH‐G) (TPH‐D)

• See maps of IRP zones

• See map of IRP wells; well integrity must be preserved for seven known wells. Nine wells are expected in the zone. Two wells have not been located (ANGMW16‐B & ANGMW16‐C). If located, properly abandon wells.

https://deq.utah.gov/legacy/programs/water‐quality/utah‐underground‐injection‐ control/resources.htm

PIPE MATERIAL IN CONTAMINATION ZONE

• Drinking Water standards apply; Utah Administrative Code R309‐550‐5(10); SLC public utilities does not use PVC in contaminated soil. Similar sites have used a ductile iron pipe with nitrite gaskets, wrapped in a plastic corrosion blanket and surrounded with flowable fill in the areas with petroleum impacts. Another site used a prestressed concrete for a 36‐inch water main. Other options may exist; contractor to verify https://rules.utah.gov/publicat/code/r309/r309‐550.htm

DESIGN REVIEW

Final designs will be sent for review to the Utah DEQ Division of Water Quality per rules as a Non‐ Transient, Non‐Community Public Water System.

mailto:RMcMullin@republicservices.com https://deq.utah.gov/legacy/programs/water-quality/ground-water/permits/index.htm#cuicp https://deq.utah.gov/legacy/programs/water-quality/utah-underground-injection-control/resources.htm https://deq.utah.gov/legacy/programs/water-quality/utah-underground-injection-control/resources.htm https://rules.utah.gov/publicat/code/r309/r309-550.htm