This document is a Statement of Work (SOW) for a federal contract opportunity to demolish an existing building and pave the site with asphalt at the 118th Wing in Nashville, Tennessee.
The SOW outlines the required scope of work, which includes demolishing 10,829 square feet of an existing building, removing all associated materials and equipment, and furnishing and installing 15,615 square feet of asphalt pavement. The performance period for this project is 90 calendar days. The contractor will be responsible for obtaining all necessary permits, performing material testing, and coordinating with government personnel. The contractor must also provide weekly activity reports to the Contracting Officer's Representative.
The related federal contract opportunity is an Invitation for Bid (IFB) to award a single firm fixed-price contract for the construction and repair of fire hydrants, site lighting, and demolition of Building 723 with parking lot paving and fencing installation at Berry Field Air National Guard Base in Nashville, Tennessee. The contract duration is 180 days after notice to proceed, and the project is set aside 100% for Small Businesses under NAICS code 236220. The bid opening date is September 15, 2024.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
118th Wing SECTION 01000 Nashville, Tennessee Statement of Work
BKTZ 232011
8/21/2024
STATEMENT OF WORK
DEMOLITION & PAVEMENT, B723
BERRY FIELD, NASHVILLE, TENNESSEE
1) GENERAL
a) The work covered by this Statement of Work (SOW) consists of furnishing all labor, equipment, and materials to demolish the existing building and furnish supplies, labor, and equipment to pave existing site with asphalt for project BKTZ232011 DEMOLITION and PAVEMENT, B723 in accordance with this written statement of work, demolition drawings, specifications, and manufacturer specifications, hereon referred to as “plans”. The work location is the 118th Wing, Nashville, Tennessee.
Contractor will be fully responsible for compliance with all base, local, state, and federal laws and regulations that apply to include environmental and occupational safety.
2) PERFORMANCE PERIOD
a) The performance period for this project is 90 calendar days.
3) SCOPE OF WORK
a) Contractor will perform all work as described herein and as shown on drawings for project BKTZ232011, demolition and pavement, B723. Work includes but is not limited to the following items.
1. Base Bid: Demolish and remove 10,829 square feet of existing building materials and equipment for building 723.
a. Furnish labor and equipment to demolish, remove, and dispose of all building materials, equipment, piping, fencing, HVAC, and foundation within building 723 envelope and on project site as shown drawings
b. Demolish B723 HVAC and awning connected to B721 walls. Repair exterior and interior walls of building 721 (B721) after completion of building 723 awning and HVAC demolition
c. Repair B721 gutter and tie repaired gutter existing B721 gutter
d. Test paint for lead due to environmental concerns and report results to COR upon receiving test results
e. Disconnect and cap Gas line
f. Disconnect and cap water line
g. Install exterior electrical panel on bldg. 802 for parking lot lighting
2. Base Bid: Pave project site
a. Furnish and install 15,615 square feet of asphalt pavement on B723 project site.
BKTZ 232011
8/21/2024
b. Asphalt pavement will be a minimum of 6 inches of aggregate base course (TDOT Grading D), 3 inches deep asphalt base course (TDOT Grading “A”) , and 1 1/2 inches deep surface course (TDOT Grading “E”). All job mix formulas will be approved by the COR.
c. Stripe paved area for parking as shown on project drawings with 4 inch solid white painted lines in accordance with TDOT Standard Specification 910.02.
Suitable product includes Sherwin Williams SETFAST Acrylic Waterborne Traffic Marking Paint TM226.
d. Install handicap signs as shown on drawings
e. Furnish and install 105 linear feet of chain link fence on south side of B723.
b) Contract Requirements
1. The contractor will adhere to all contract requirements in the solicitation and subsequent contract or delivery order.
2. In addition to those items in the solicitation/contract, the contractor will also be responsible to:
a. Obtain all dig permits, crane permits, environmental, and any other permits prior to starting construction.
b. Verify all field and plan measurements and notify the contracting officer’s representative (COR) of any discrepancies.
c. Prepare project site for construction by placing adequate signage and other devices indicating construction zone for vehicular traffic and pedestrians.
d. Submit all project submittals to the COR for approval prior to the manufacture or placement of any construction materials. Mandatory product approvals include all pavement materials including aggregate base gradation, asphalt base course, surface course, prime coat, tack coat, mix design, and pavement markings.
e. Perform all material testing as required by specifications and building code.
f. Perform site finishing and cleanup to include submit dust/debris plan and cleaning plan that describes measures to prevent the entrance of dust/debris in the areas where work is to be performed.
g. Remove all work related debris and dispose of it off the base property upon completion of project.
h. Coordinate with government personnel to gain access to project site
i. Furnish and install shut off valves into existing utilities
j. Contractor shall generate and send activity reports to the COR at james.bell.69@us.af.mil each week with a summary of work completed and 4 new pictures of completed work each week during the period of performance.
3. Contractor Manpower Reporting
a. The contractor will report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for Air Force collection site. The contractor is required to completely fill in all
BKTZ 232011
8/21/2024 required data fields using the following web address:
https://afcmra.hqda.pentagon.mil/
b. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data must be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk at http://www.ecmra.mil/.
c. Unit Identification Code (UIC) for the Requiring Activity: L41CFTRM
d. Issuing Office DoDAAC: W50S97
4) REFERENCES
In general, all technical specifications are provided within the Construction Documents. In the event any project element is not covered in the specifications provided, the contractor will refer to the Specification Hierarchy for direction related to the element.
5) SPECIFICATION HIERARCHY
a) The specification hierarchy is the collection of technical specifications to be used for all projects. The contractor should refer to the specifications provided in the Construction Documents first before moving to the next technical specification listed in the specification hierarchy. The hierarchy is listed in the order of precedence (i.e. “1” supersedes “2”). The hierarchy is as follows:
1. Specifications provided with Construction Documents
a. Technical Specifications
b. Construction Drawings
2. For MATOC contracts, the 118th Base Design Standards
6) SECURITY REQUIREMENTS
Access and General Protection/Security Policy and Procedures. Contractor to complete Antiterrorism Level 1 Training and provide documentation of completion upon request. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor will comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
'End of Statement of Work’ https://afcmra.hqda.pentagon.mil/ http://www.ecmra.mil/