A6- SOW BKTZ239011 Demolition and pavement B723.pdf

PDF 207 KB Posted

Attached to
Fire Hydrants-Site Lighting-Demo B723 Federal contract opportunity
Solicitation number
W50S97-24-B-0005
Issued by
Department of the Army National Guard

About this file

This document is a Statement of Work (SOW) for the demolition of an existing building and paving of the project site at the 118th Wing in Nashville, Tennessee under contract BKTZ239011.

The key details are:

  • The scope of work includes demolishing 10,829 square feet of an existing building and paving 15,615 square feet of the project site with 6 inches of aggregate base, 3 inches of asphalt base, and 1.5 inches of surface course. It also includes installing 105 linear feet of chain link fence.
  • The performance period is 90 calendar days.
  • The contractor will be responsible for obtaining necessary permits, performing testing and inspections, coordinating access to the site, and providing weekly activity reports to the Contracting Officer's Representative.
  • The contractor must comply with all base, local, state, and federal laws and regulations, including environmental and occupational safety requirements.

View the file

Other files for this federal contract opportunity

Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

118th Wing SECTION 01000 Nashville, Tennessee Statement of Work

BKTZ 239011

5/16/2024

STATEMENT OF WORK

DEMOLITION & PAVEMENT, B723

BERRY FIELD, NASHVILLE, TENNESSEE

1) GENERAL

a) The work covered by this Statement of Work (SOW) consists of furnishing all labor, equipment, and materials to demolish the existing building and furnish supplies, labor, and equipment to pave existing site with asphalt for project BKTZ239011 DEMOLITION and PAVEMENT, B723 in accordance with this written statement of work, construction plans, specifications, and manufacturer specifications, hereon referred to as “plans”. The work location is the 118th Wing, Nashville, Tennessee. Contractor will be fully responsible for compliance with all base, local, state, and federal laws and regulations that apply to include environmental and occupational safety.

2) PERFORMANCE PERIOD

a) The performance period for this project is 90 calendar days.

3) SCOPE OF WORK

a) Contractor will perform all work as described herein and as shown on drawings for project BKTZ239011, demolition and pavement, B723. Work includes but is not limited to the following items.

1. CLIN 0001 – Base Bid: Demolish and remove 10,829 square feet of existing building materials and equipment for building 723.

a. Furnish labor and equipment to demolish, remove, and dispose of all building materials, equipment, piping, fencing, HVAC, and foundation within building 723 envelope and on project site.

2. CLIN 002 – Base Bid: Pave project site

a. Furnish and install 15,615 square feet of asphalt pavement on B723 project site.

b. Asphalt pavement will be a minimum of 6 inches of aggregate base course

(TDOT Grading D), 3 inches deep asphalt base course (TDOT Grading “A”) , and 1 1/2 inches deep surface course (TDOT Grading “E”). All job mix formulas will be approved by the COR.

c. Stripe paved area for parking as shown on project drawings with 4 inch solid white painted lines in accordance with TDOT Standard Specification 910.02.

Suitable product includes Sherwin Williams SETFAST Acrylic Waterborne Traffic Marking Paint TM226.

d. Furnish and install 105 linear feet of chain link fence on south side of B723.

BKTZ 239011

5/16/2024

b) Contract Requirements

1. The contractor will adhere to all contract requirements in the solicitation and subsequent contract or delivery order.

2. In addition to those items in the solicitation/contract, the contractor will also be responsible to:

a. Obtain all dig permits, crane permits, or any other permits prior to starting construction.

b. Verify all field and plan measurements and notify the contracting officer’s representative (COR) of any discrepancies.

c. Prepare project site for construction by placing adequate signage and other devices indicating construction zone for vehicular traffic and pedestrians.

d. Submit all project submittals to the COR for approval prior to the manufacture or placement of any construction materials. Mandatory product approvals include all pavement materials including aggregate base gradation, asphalt base course, surface course, prime coat, tack coat, mix design, and pavement markings.

e. Perform all material testing as required by specifications and building code.

f. Perform site finishing and cleanup to include submit dust/debris plan and cleaning plan that describes measures to prevent the entrance of dust/debris in the areas where work is to be performed.

g. Remove all work related debris and dispose of it off the base property upon completion of project.

h. Coordinate with government personnel to gain access to project site

i. Furnish and install shut off valves into existing utilities

j. Contractor shall generate and send activity reports to the COR at james.bell.69@us.af.mil each week with a summary of work completed and 4 new pictures of completed work each week during the period of performance.

3. Contractor Manpower Reporting

a. The contractor will report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for Air Force collection site. The contractor is required to completely fill in all required data fields using the following web address:

https://afcmra.hqda.pentagon.mil/

b. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data must be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk at http://www.ecmra.mil/.

c. Unit Identification Code (UIC) for the Requiring Activity: L41CFTRM

d. Issuing Office DoDAAC: W50S97 https://afcmra.hqda.pentagon.mil/ http://www.ecmra.mil/

BKTZ 239011

5/16/2024

4) REFERENCES

In general, all technical specifications are provided within the Construction Documents. In the event any project element is not covered in the specifications provided, the contractor will refer to the Specification Hierarchy for direction related to the element.

5) SPECIFICATION HIERARCHY

a) The specification hierarchy is the collection of technical specifications to be used for all projects. The contractor should refer to the specifications provided in the Construction Documents first before moving to the next technical specification listed in the specification hierarchy. The hierarchy is listed in the order of precedence (i.e. “1” supersedes “2”). The hierarchy is as follows:

1. Specifications provided with Construction Documents

a. Technical Specifications

b. Construction Drawings

2. For MATOC contracts, the 118th Base Design Standards

6) SECURITY REQUIREMENTS

Access and General Protection/Security Policy and Procedures. Contractor to complete Antiterrorism Level 1 Training and provide documentation of completion upon request. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor will comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

'End of Statement of Work’