A3- SOW Repair Fire Hydrants Basewide SOW_7.11.24 signed.pdf
PDF 170 KB Posted
- Attached to
- Fire Hydrants-Site Lighting-Demo B723 Federal contract opportunity
- Solicitation number
- W50S97-24-B-0005
- Issued by
- Department of the Army National Guard
About this file
This document is a Statement of Work (SOW) for repairing valves and fire hydrants across the Berry Field Air National Guard Base in Nashville, Tennessee. The contractor shall provide all labor, materials, and equipment necessary to test, repair, and replace the fire valves and hydrants basewide. The work must be performed in accordance with the attached plans and specifications, with a performance period of 120 calendar days. The contractor must submit product submittals, a dust/debris control plan, and weekly activity reports to the Contracting Officer's Representative.
The related federal contract opportunity is a solicitation for construction and repair services, including the work described in the SOW, as well as site lighting construction and building demolition at the same base. This is a 100% small business set-aside with a NAICS code of 236220 and an estimated magnitude between $500,000 and $1,000,000. The solicitation includes a pre-bid conference on August 30, 2024 and a bid opening on September 15, 2024.
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
UNITED STATES AIR FORCE
118th Wing Tennessee Air National Guard
Berry Field Air National Guard Base, Nashville, TN
STATEMENT OF WORK
Repair Valves and Fire Hydrants, Basewide
BKTZ212025
11 July 2024
1.0 STATEMENT OF WORK
1.1. The contractor shall provide, unless otherwise noted, all management, tools, equipment, transportation, supervision, and labor necessary to repair the facilities as shown on contract drawings and specifications, Nashville, International Airport (IAP) Repair fire hydrants, base-wide Attachment 1 and 2, hereinafter referred to as "plans". Contractor shall perform all work in accordance with this Statement of Work (SOW) and the plans. Contractor shall coordinate all work with the Contracting Officer and Civil Engineer office and is subject to the work schedule as stated in this document. Upon completion, the facility must be complete and usable for the entire base populace.
1.2. These requirements, together with the technical specifications, standards, and drawings specified in the contract documents, cover the requirements for all work associated with Repair fire hydrants, base-wide, Nashville IAP. The following section is a general description of the work involved:
A. Water Pipe and Hydrant Repairs;
1. Fire valves and hydrants basewide require testing and replacement due to end of useful life
1.3. Work shall be performed as shown on the plans and as described in this document.
1.3.1. Contractor will provide material for and perform all work to repair and replace valves and fire hydrants, base-wide. The contractor must submit dust/debris plan (see attached AF66) that describes measures to prevent the entrance of dust/debris in the areas where work is to be performed. Contractor must provide submittals of materials to the Civil Engineer. (See Submittals Section Below.)
1.3.2. All materials shall meet or exceed all applicable referenced standards, local requirements, and conform to codes and ordinances of authorities having jurisdiction.
1.3.3. Prepare work site and ensure that dimensions are as indicated on shop drawings.
1.3.4. Coordinate with base authorities to obtain all passes required to enter the work site.
1.4. .INSTALLATION:
1.4.1. Installation shall meet or exceed all applicable federal, state and local requirements, referenced standards and conform to codes and ordinances of authorities having jurisdiction.
1.4.2. All equipment and material installations shall be in accordance with manufacturer’s published specifications and guidelines.
1.4.3. Contractor shall furnish all parts, assembly, and connections during construction.
1.5. EXECUTION
1.5.1. The performance period for this project is 120 calendar days.
1.6.2 FIELD QUALITY CONTROL: Contractor shall generate and send activity reports to the COR at james.bell.69@us.af.mil each week with a summary of work completed and 4 new pictures of completed work each week during the period of performance.
2.0 SPECIFICATIONS – B801 repairs: Contractor SHALL comply with attached specifications on the plans and as follows:
2.1. PART 1 – GENERAL
2.1.1. SUBMITTALS: Manufacturer's product literature, data, and warranty information. Contractor will provide submittals for final selection by Base Civil Engineer from manufacturer’s product catalog.
Maj James Bell
DBCE, 118 CES, USAF
| STATEMENT OF WORK |
| Repair Valves and Fire Hydrants, Basewide |
| 1.0 STATEMENT OF WORK |
| 1.3. Work shall be performed as shown on the plans and as described in this document. |
| 1.3.1. Contractor will provide material for and perform all work to repair and replace valves and fire hydrants, base-wide. The contractor must submit dust/debris plan (see attached AF66) that describes measures to prevent the entrance of dust/debris ... |
| 1.3.2. All materials shall meet or exceed all applicable referenced standards, local requirements, and conform to codes and ordinances of authorities having jurisdiction. |
| 1.3.3. Prepare work site and ensure that dimensions are as indicated on shop drawings. |
| 1.3.4. Coordinate with base authorities to obtain all passes required to enter the work site. |
| 1.4. .INSTALLATION: |
| 1.4.1. Installation shall meet or exceed all applicable federal, state and local requirements, referenced standards and conform to codes and ordinances of authorities having jurisdiction. |
| 1.4.2. All equipment and material installations shall be in accordance with manufacturer’s published specifications and guidelines. |
| 1.4.3. Contractor shall furnish all parts, assembly, and connections during construction. |
| 1.5. EXECUTION |
| 1.6.2 FIELD QUALITY CONTROL: Contractor shall generate and send activity reports to the COR at james.bell.69@us.af.mil each week with a summary of work completed and 4 new pictures of completed work each week during the period of performance. |
| 2.0 SPECIFICATIONS – B801 repairs: Contractor SHALL comply with attached specifications on the plans and as follows: |
| 2.1. PART 1 – GENERAL |
| 2.1.1. SUBMITTALS: Manufacturer's product literature, data, and warranty information. Contractor will provide submittals for final selection by Base Civil Engineer from manufacturer’s product catalog. |
| 2024-07-11T13:48:59-0500 | |
| BELL.JAMES.MARK.1149108064 |