This document contains a solicitation for the construction of a gymnasium and storage facility at Air National Guard Base Quonset Point in Rhode Island. The solicitation is set aside for small businesses and has an estimated value between $1 million and $5 million. The solicitation includes specifications and drawings dated between October 2016 and July 2020. The project scope involves demolishing an existing building, improving foundations, and constructing a new pre-engineered metal building to house a gymnasium and additional storage. The work includes sitework, utilities, HVAC, plumbing, power and lighting. Contractors must submit bids breaking out costs for base construction and optional additions by September 30, 2020. The contract is expected to be awarded to the responsible bidder offering the most advantageous price. The pre-bid conference was held on an unspecified date. The Department of the Army National Guard is the contracting agency. The contractor must complete the work within 365 calendar days of receiving notice to proceed.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W50S9420B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
PRE-BID RFI TABLE
| ID |
| Bid Inquiry |
| Received |
| Response |
| Closed |
| 001 |
| Drawing S-004 calls for the required Special Inspections. Can you please confirm that these inspections will be completed by the designer-of-record and will be compensated by the federal government |
| 26-08-20 |
| POND RESPONSE: |
The contractor is responsible for engaging the special inspection agency
GOVT RESPONSE:
The Government concurs with POND response. The offeror shall be responsible for coordination with and payment of Special Inspection Agencies.
28-08-20
| 002 |
| Drawing S-101 calls for portions of the existing slab to be existing to remain and S-301 calls for new foundation walls. Drawing AD-101 note 3 calls for the demolition of the existing Quonset hut but does not address the existing foundation. Can you confirm that the existing foundation is to be removed in its entirety with a new foundation provided and tied into the existing slab scheduled to remain? |
| 26-08-20 |
| POND RESPONSE: |
The existing footings shall be removed. See note 7 on sheet S-101.
GOVT RESPONSE:
The Government concurs with POND response.
28-08-20
| 003 |
| Note 9 on Drawing S-101 calls for bidders to provide shoring at the patio area “as required”. This is a hidden condition and we do not know what conditions will be found in this area specifically regardless of the Geotech provided. Bidders will be guessing and in absence of a standard assumption that all bidders can carry equally then we are forced to guess or make potentially incorrect assumptions independent of one another. |
Therefore, we strongly suggest an allowance be issued for bidders to carry or have the design team specify a specific shoring that all bidders can carry equally and fairly.
| 27-08-20 |
| An allowance of $10,000 will be provided for shoring. |
| 09-09-20 |
| 004 |
| Will the flooring be a gymnasium or 2’x2’ interlocking flooring like a weight room? |
| 31-08-20 |
| Question withdrawn by company |
| 01-09-20 |
| 005 |
| The bid items numbers differ on Pages 4/5 and page 70 Paragraph 2 of the solicitation. Please confirm that the bid form numbers are correct. |
| 04-09-20 |
| Requires a solicitation amendment to correct Page 70 to match the numbering and sequence on pages 4 & 5 of the solicitation. |
| 09-09-20 |
| 006 |
| Bid item CMRA was discussed at the pre-bid. Please clarify proper notation when not submitting a cost for this item. |
| 04-09-20 |
| Place a Unit Price of $0 and Extended Price of $0 and note NSP on the Line Item which represents Not Separately Priced |
| 08-09-20 |
| 007 |
| Drawing S301 Detail C3 states the existing patio foundation is “illustrated for schematic purpose only.” Please provide existing foundation construction. Information required for shoring requirements. |
| 04-09-20 |
| An allowance of $10,000 will be provided for Shoring costs. Patio foundation data is unavailable at this time. |
| 09-09-20 |
| 008 |
| Specification includes a LEED Version 3 check list. Wood Door Specifications only calling for Urea Free. Is FSC doors required for full LEED requirements? |
| 04-09-20 |
| Yes, FSC doors are required. |
| 09-09-20 |
The following have been modified:
STATEMENT OF WORK
Scope of Work Construct Gym and Storage B12
TWLR: 152518
1. CONTRACTOR RESPONSIBILITIES: Work consists of furnishing all labor, equipment, and materials necessary to perform all work listed in this SOW. The Contractor shall submit to the Base Civil Engineer (BCE), for approval, all catalog cuts, drawings, or brochures of any materials to be used on this project. These submittals must be submitted within ten days of the Notice to Proceed. It is the contractor’s responsibility to ensure compliance with requirements briefed at the Pre-Construction meeting (i.e. Environmental, Safety, Fire Department, Security, etc.).
1. PROJECT DESCRIPTION: The Gym at the 143d Airlift Wing Quonset Point Air National Guard Base will provide Airmen adequate facilities to maintain combat readiness and meet the required USAF physical fitness standards. Work consists of the demolition of the existing Quonset Hut Building, foundation improvements, and construction of a new pre-engineered metal building. This includes asbestos and lead based paint abatement, sitework, utilities, HVAC systems, plumbing, restrooms, power, lighting, and telecommunications. All work for this project shall be in accordance with the provided project specifications and construction drawings. The contractors’ bid shall include the following Contract Line Items (CLIN) on a Bid Break-Out sheet as indicated on the construction drawings and specifications:
0. LINE 01 Base Bid – Building Construction
0. LINE 02 CMRA (see paragraph 12 below)
0. LINE 03 ABI 1– OPT 1: Floor Coverings
0. LINE 04 ABI 2 – OPT 2: Windows
0. LINE 05 ABI 3 – OPT3: TV mounts, CATV conduit, etc.
1. The Bid Break-Out sheet will be provided on https://beta.sam.gov as part of the Solicitation Package.
1. This project is for a complete and useable system.
1. The bidding contractors must carefully review all the information in the solicitation documents, the Pre-Bid Site Visit, and the Design Drawings & Specifications.
1. APPLICABLE CODES AND STANDARDS: Applicable Codes and Standards shall include, but not be limited to, all pertinent requirements of the following organizations most current standards:
2. API – American Petroleum Institute
2. NFPA – National Fire Protection Association
2. UL – Underwriters Laboratory, Inc.
2. ASTM – American Society for Testing and Materials
2. ACI – American Concrete Institute
2. ANSI – American National Standard Institute
2. AIEE – American Institute of Electrical Engineers
2. ASME – American Society of Mechanical Engineers
2. ASCE – American Society of Civil Engineers
2. CRSI – Concrete Reinforcing Steel Institute
2. IPCEA – Insulated Power Cable Engineers Association
2. NBS – National Bureau of Standards
2. IEEE – Institute of Electrical and Electronic Engineers, Inc.
2. NEC – National Electric Code
2. NBFU – National Bureau of Fire Underwriters
2. NEMA – National Electric Manufacturers Association
2. OSHA – Occupational Safety and Health Administration
2. NAPHCC – National Association of Plumbing – Heating – Cooling Contractors
2. National Standard Plumbing Code
2. ARI – Air Conditioning and Refrigeration Institute
2. ASHRAE – American Society of Heating, Refrigeration and Air-Conditioning Engineers
2. AMCA – Air Movement and Control Association
2. NRCA – National Roofing Contractors Association
2. UBC – Uniform Building Code
2. NFC – National Fire Code
2. RISBC-1 – Rhode Island Building Code
2. RIDOT – Rhode Island Department of Transportation
1. TRASH DISPOSAL: It is the Contractor’s responsibility to dispose of all trash and debris incurred during project construction, off base at an authorized disposal site in accordance with local, state and federal requirements.
1. WORK WEEK AND HOURS OF OPERATION: BCE workweek is Monday through Friday, 0700 to 1530. The Contractor must make arrangements in advance to work outside of normal duty hours.
1. RESTRICTED AREAS: There are numerous areas that are restricted and access to these areas must be coordinated through the BCE Office. The Contractor shall coordinate, three days in advance, for arrangements required to work in these areas. Contactors working in restricted areas shall be required to provide the BCE with a list of names and social security numbers for all personnel expected to work in these areas.
1. MEASUREMENT VERIFICATION: It shall be the Contractors responsibility to verify all measurements, sketches, and descriptions of work for the project.
1. PROJECT DURATION: Duration of this project is 365 Calendar days after Contractor's receipt of the Notice to Proceed. The completion time includes inspections and final cleanup of the premises.
1. ENVIROMENTAL IMPACT: Under NO CIRCUMSTANCES shall any waste materials, cleaning fluids, solvents, paints, etc. be poured into the base storm drains, sewer/septic systems, or discharged onto the ground. Contractor shall adhere to all Federal, State and Local Regulations. All materials on the job will be accompanied by a MSDS (Material Safety Data Sheet). All containers shall be marked clearly and legibly as to the contents inside. All containers shall have lids firmly affixed. All collections of waste will be disposed of properly following IAW State and Federal Regulations to include proper manifesting. Provide the Base Engineer with quantities of recyclable materials discarded such as metals, concrete, etc. Contractor shall follow guidance outlined in the latest issue of the Rhode Island Air National Guard Supply/Services Procurement Vendor/Contractor Guide.
1. SAFETY REQUIREMENTS: The Contractor shall abide by all State, Local, and OSHA safety requirements relevant to the items described in this SOW. If the Contractor is found to be in violation of any applicable safety regulations on the job site, the Government representative shall stop all work until the unsafe practice has been ceased and corrected.
1. RESERVED
1. CMRA: The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract at the secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.sam.gov. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2020. Contractors may direct questions to the help desk at http://www.ecmra.mil.
1. FINAL ACCEPTANCE & COMPLETION OF PROJECT
12. When construction is complete, the Contractor must notify the BCE and make arrangements for a Final Inspection.
12. The project WILL NOT be accepted by the Government until:
1. The Government has received and approved all manufactures & installers Warranty paperwork.
1. The Government has received and approved of construction drawing As-Builts.
1. The Government has received and approved all manufactures & installers Operation & Maintenance Manuals
1. Contractor Manpower Reporting (CMRA) is completed IAW line 12 above.
1. The site is returned to original or better condition according to applicable codes and standards.
(End of Summary of Changes) image1.wmf