W50S7T-20-R-0001_Questions and Answers_as of 9 Jul 20.pdf

PDF 96 KB Posted

Attached to
182AW CONSTRUCTION MATOC - Y - CONSTRUCTION OF STRUCTURES AND FACILITIES - SOLICITATION
Solicitation number
W50S7T20R0001
Issued by

View the file

Other files

File Type Posted
W50S7T-20-R-0001 - Amendment 0005.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 15 Jul 20 Final 2.pdf PDF
Attachment 6 - Addenda No 1 dated 14Jul20.pdf PDF
W50S7T-20-R-0001 - Amendment 0004.pdf PDF
Attachment 7 - Drawings E-301 and E-502 dated 10Jul20.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 10 Jul 20 Final.pdf PDF
W50S7T-20-R-0001 - Amendment 0003.pdf PDF
W50S7T-20-R-0001 - Amendment 0002.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 7 Jul 20.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 6 Jul 20.pdf PDF
PPC and Site Visit Sign In Sheets.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 30 Jun 20.pdf PDF
MATOC Preproposal Conference Presentation Slides.pdf PDF
W50S7T-20-R-0001 - Amendment 0001.pdf PDF
Attachment 5 - 182d Airlift Wing Workplace Precautions to Combat the Spread of COVID-19 dated 17Jun20.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 18 Jun 20.pdf PDF
EXHIBIT C - Reference Questionnaire Package.docx DOCX document
Attachment 1 - 01000 Special MATOC Contract Requirements.pdf PDF
W50S7T-20-R-0001 182AW Construction MATOC Solicitation.pdf PDF
EXHIBIT A - Performance Relevency Questionaire.docx DOCX document
FAR-Part6-JA-May20 Locks 3Jun20.pdf PDF
EXHIBIT D - Proposal Form Seed Project - Repair Building 620.docx DOCX document
EXHIBIT B - Subcontractor Info and Consent Form.docx DOCX document
Attachment 2 - MATOC Master Specifications.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number:W50S7T‐R‐0001 Project Title: Multiple Award Task Order Contract (MATOC) Seed Project: Repair Building 620 Project Number: JLQN152006 Current a/o 9 July 20

Questions and Answers

Number Spec Section Question Answer 1 N/A Regarding Subfactor 1 – Experience and Capability, the proposal is limited to

20 single pages. Is it the Government’s expectation that the response to Subfactor 1 will be close to 20 pages or is the requirement merely to highlight that it is not to exceed 20 pages? We are trying to determine how many pages to devote to each subfactor, as Subfactor 3 alone will take up 8 pages, thereby leaving only 2 pages for subfactors 2,4,5. Would the Government please provide a breakdown of how many pages to devote to each Subfactor?

Subfactor 1 - Experience and Capability is limited to a maximum of 20 pages total. It is up to each contractor how many pages they want to devote to each subfactor not to exceed the maximum. Subfactor 3 is not part of Subfactor 1. The maximum number of pages for each subfactor is listed within the solicitation under each subfactor.

2 N/A Regarding Subfactor 3. Specific Personnel, the requirement is to provide resumes of no more than 2 pages for each proposed key personnel or 8 pages total for Subfactor 3. In addition, we are to include a narrative of no more than two pages describing the experienced key personnel’s abilities.

Please confirm whether the narrative is meant to be WITHIN the resume’s 2 page limit, or is it in addition to the 2 page resume for each personnel (thereby making each resume be 4 pages).

Subfactor 3 - Specific Personnel is limited to a maximum of 8 pages total.

The narrative is inclusive of the maximum of 8 pages for Subfactor 3.

3 N/A Due to the recent spike of Covid-19 cases across the nation, will the pre-preposal conference be available by any form of streaming service? No. There is currently no streaming service of the preposal conference planned at this time.

4 N/A I would like to prepare a site visit/ walkthrough with our potential subcontractors on this project. Given the security protocols on the base, can we schedule this walktthrough on a date and time that would work for you?

Also, how much background information from each visitor prior to a pre-bid walkthrough.

A site visit is scheduled to be held directly after the prepreposal conference. There are no additional site visits planned. Please provide the background information requested within the solicitation to benjamin.yeutson@us.af.mil.

5 N/A Will there be a site visit for the seed project? If so, will it take place at the same time as the pre-proposal conference or does it need to be scheduled separately?

Yes. A site visit is scheduled to be held directly after the prepreposal conference. There are no additional site visits planned.

6 N/A Will the pre-proposal conference only take place in-person, or can we request an option to have a call-in line to the conference instead?

The prepreposal conference will only take place in‐person. There will not be an option to have a call‐in line to the conference at this time. Preproposal minutes will be uploaded to Beta.SAM.gov.

Project Number: JLQN152006 Current a/o 9 July 20

Questions and Answers

7 N/A There is no mention in the proposal submission requirements for Price, just for Schedule Methodology, but there is a Price form for the Seed Project within the attachments. Please clarify if pricing for the Seed Project is to be included in the Submission, and if so does it go in Volume 1 or Volume 2.

Please reference page 10, 15, and 16 of the solicitation for price proposal submission requirements. The pricing being provided is for the Seed Project and CMRA.

8 N/A Is there a safety protocol for COVID‐19 when accessing the 182nd Airlift Wing?

All personnel will comply with all COVID‐19 related CDC, State and Local Public Health recommendations. Please reference Amendment 001, Attachment 5 ‐ 182d Airlift Wing Workplace Precautions to Combat the Spread of COVID‐19 dated 17Jun20.

9 N/A Can you please verify that the delivery address for "hand carried proposals" is also the same address to be used if our proposals are being mailed?

The hand carried proposals and mailed proposals shall be sent to 2416 S.

Falcon Blvd, Peoria, IL 61607.

10 N/A Are there any other site visits planned for this solicitation? No.

11 N/A

It appears that the Volume naming instructions provided in the conference Powerpoint slides differs from those given in in the Amendment 1 file. Could you clarify which naming system we should follow? Follow the instructions within the solicitation and Amendment 1 file.

12 N/A Is there a cost for background checks? No.

13 N/A

Since this appears to be mostly just ceiling work, with the exception of a few new walls, in the areas with existing walls that have wall mounted occupancy sensors, is there an existing box, so we will just replace the wiring and device, or do we need to fish flex down the wall for the new occupancy sensor? Pending

14 ED-101/ E-201

ED-101 shows multiple ceiling devices being removed and reinstalled.

Occupancy sensors, emergency fixtures, speakers, etc. E-201, nor any other drawing, show these being reinstalled? Pending

Project Number: JLQN152006 Current a/o 9 July 20

Questions and Answers

15 E-502, Note 2 Does the CAT 6 need to be in conduit? Is the building monitoring system located in the same room? It does not appear to be located on any drawings. Pending

16 230713, Page 11

The only duct specified to insulated is the rectangular supply and outdoor air where it is exposed. Does the concealed rectangular/ round supply and outdoor air require external insulation? Pending

17 220719, Page 13

Piping that is exposed is specified to receive a PVC jacket. Does this mean exposed anywhere or exposed to the public only? For example is a PVC jacket required in the mobility room, arms vault, mechanical room or janitor closet? Pending

18 N/A Does the condensate require insulation? If so, what type/ thickness is required? Pending

19 N/A

In the General Conditions there is mention of AT Level 1 training on terrorism which is required training for each worker at the site. We would like to have clarification on the length of time involved with this training. Is there any other training required specific to this site.

The training takes approximately 1 hour. There is no other training required at this time.

20 N/A

The drawings mention that the building may bepartially occupied during construction. Can you elaborate on about how many people will be in the building and can we complete loud demolition items during normal business hours. Pending

21 N/A Who is the current Fire Alarm Company servicing the building? Pending

22 ED-101

General notes talk about the Paging system and Intrusion Detection System.

When reinstalled, do these need to be reprogrammed? If so, who manages these systems for them? Pending

23 E-502 Is there a spec on the new Digital Meter Reader? I didn't see anything in the spec book. Pending

24 N/A Will site photos be allowed, or will the air national guard provide photos?

Site photos were allowed during the site visit. The Air National Guard will not be providing any photos.

Project Number: JLQN152006 Current a/o 9 July 20

Questions and Answers

25 23 21 13.33 3.3 B Where can the drilling log referenced in 23 21 13.33 3.3 B be obtained? Pending

26 N/A To what extent will the building be occupied during construction? Pending

27 A-100

Keynote #10 on A-100 states to assume 6" slab. Detail 2/A-101 shows patching for a 4" slab. Is the contractor to pour a 4" patch regardless of the slab thickness? If existing slab is 4" will any reinforcing be needed to construct the 8" CMU for Men 16 on the slab? Pending

E-301, EWC-1,P-

102, GWH-1

Is there to be a plan issued showing electrical receptacles and other power connections not shown on E-301? There does not appear to be any convenience receptacles in Breakroom 2, Women 13 or Men 16. There also does not appear to be power provided for EWC-1, or for the condensate pumps shown on P-102. Is GWH-1 to reuse the existing power supply? Pending

29 N/A Please provide company that currently services/ handles base BAS system. Pending

30 N/A Is the cove heights required to be 4 inches or 6 inches high and what is the cove radius? Pending

31 N/A If there is a required topcoat on this floor, is it required that it be UV resistant polyurethane? Pending

32 N/A

Is this floor coating system a solid color system or will there be decorative materials imbedded within the coating and cove base that would add to the material cost of the floor? For example vinyl flakes or quartz sand. Pending

33 N/A Is there a required minimum solids content? Pending

34 N/A

If there are multiple coatings and there is also a non-skid finish, to which coating do we add the non-skid additive to? The intermediate coat or the topcoat. Pending

35 N/A

Is there a minimum testing performance standard to which coatings must meet or exceed? For example: Adhesion, Tensile strength, Imnpact, Hardness, and Abrasion. Pending

Project Number: JLQN152006 Current a/o 9 July 20

Questions and Answers

36 N/A is the floor to have (1) 30 mils epoxy coating with no primer or polyurethane topcoat, or is it to have multiple coatings with a total nominal thickness of 30 mils minimum? Pending

37 N/A

I've noticed that the specs call out a slip resistance for a finish and yet later it calls out for a finish that is smooth level surface. Which finishe are we to provide? If it is a slip resistant finish what sieve of non-skid additive is requested? Different sizes cost different prices. Pending

38 N/A

Is the existing slab sufficient to support the new 12'H P1 Masonry walls?

There is currently no detail for a thickened footing or additional structural support. Pending

39 P-102 What is the piping to be used for the condensate off of the HP units on P-102?

JLQN152006 Narrative Page 12 under the Plumbing heading (which is page 16 of the PDF document). PVC.

40 N/A

Can you provide any additional information about the existing roof? Can you provide core sample data? If not, can a follow-up site visit be scheduled with access to the roof? Pending

41 N/A Is the mechanical contractor required to obtain and pay for a Mechanical/ HVAC permit to be issued by the city or county on this project? Pending

42 N/A

If no permit required by the city or county will a permit be required by the DoD, etc.? Under Section 013543 Part 2 it references permits but does not state what permits are required or the fees if required for any such permits.

It is the Contractor's responsibility to determine what permits are required by contacting the city and county for the construction location.

43 N/A Will Builder's Risk Insurance be required by the General Contractor?

Insurance requirements are addressed within the solicitation. See FAR 52.228-5.

44 N/A There is no specification on the MDP make and model. Please clarify. Pending

45 230523 3.3 & 3.4

1. There is no spec for valves 2-1/2” and larger in section 230523 3.3 General Duty Valves . Section 230523 3.4 references Polypropylene full port ball valves for 2-1/2” and larger. If the contractor is selecting the option to use Type L copper for the aboveground geothermal piping are polypropylene full port ball valves still desired or can flanged butterfly valves be used? Please provide a valve spec use in coppoer aboveground 2 1/2" and larger. Pending

Project Number: JLQN152006 Current a/o 9 July 20

Questions and Answers

1. There is no spec for check valves 2-1/2” and larger in section 230523 3.3 General Duty Valves . Section 230523 3.4 references Polypropylene full port ball valves for 2-1/2” and larger but does not reference check valves. If the contractor is selecting the option to use Type L copper for the aboveground geothermal piping what are the desired flanged check valves to be used?

Please provide a check valve spec use in copper aboveground 2-1/2" and and larger. Pending

46 N/A Do you anticipate the due date being extended at this time due to the amount of pending Q&As?

Yes. The proposal due date will be amended on 10 July 2020 to move the proposal due date to 22 July 2020 at 2 P.M. Central Standard Time.

File details come from the government source that posted it. Updated .