MATOC Preproposal Conference Presentation Slides.pdf

PDF 755 KB Posted

Attached to
182AW CONSTRUCTION MATOC - Y - CONSTRUCTION OF STRUCTURES AND FACILITIES - SOLICITATION
Solicitation number
W50S7T20R0001
Issued by

View the file

Other files

File Type Posted
W50S7T-20-R-0001 - Amendment 0005.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 15 Jul 20 Final 2.pdf PDF
Attachment 6 - Addenda No 1 dated 14Jul20.pdf PDF
W50S7T-20-R-0001 - Amendment 0004.pdf PDF
Attachment 7 - Drawings E-301 and E-502 dated 10Jul20.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 10 Jul 20 Final.pdf PDF
W50S7T-20-R-0001 - Amendment 0003.pdf PDF
W50S7T-20-R-0001 - Amendment 0002.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 9 Jul 20.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 7 Jul 20.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 6 Jul 20.pdf PDF
PPC and Site Visit Sign In Sheets.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 30 Jun 20.pdf PDF
W50S7T-20-R-0001 - Amendment 0001.pdf PDF
Attachment 5 - 182d Airlift Wing Workplace Precautions to Combat the Spread of COVID-19 dated 17Jun20.pdf PDF
W50S7T-20-R-0001_Questions and Answers_as of 18 Jun 20.pdf PDF
EXHIBIT C - Reference Questionnaire Package.docx DOCX document
Attachment 1 - 01000 Special MATOC Contract Requirements.pdf PDF
W50S7T-20-R-0001 182AW Construction MATOC Solicitation.pdf PDF
EXHIBIT A - Performance Relevency Questionaire.docx DOCX document
FAR-Part6-JA-May20 Locks 3Jun20.pdf PDF
EXHIBIT D - Proposal Form Seed Project - Repair Building 620.docx DOCX document
EXHIBIT B - Subcontractor Info and Consent Form.docx DOCX document
Attachment 2 - MATOC Master Specifications.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Unclassified- MATOC Training FY 12

PRE-PROPOSAL CONFERENCE

30 June 2020

Competitive Multiple Award

Indefinite Delivery, Indefinite Quantity(IDIQ)

Contract

5 YEARS

BASE YEARS

“SCOPE”

Covers a broad range of maintenance, repair, & construction services

FEDERAL CONTRACTING OFFICERS

AT

182ND AIRLIFT WING

IN ILLINOIS MAY AWARD TASK ORDERS

DoD FEDERAL CONTRACTING OFFICERS IN STATE OF

ILLINOIS WITH PRIOR APPROVAL FROM PCO

182AW – PEORIA, IL

182AW DROPZONE – IPAVA, IL

$15,000,000.00 per contractor over the life of the entire MATOC contract

$3,000,000.00 Per Task Order for the General Task Order Contract

$2,000 MINIMUM ORDER which will be issued at time of basic contract award

A Minimum Of 3 and Maximum of 7 Small Business Awards Anticipated

• Task orders may be set-aside for socio-economic groups such as HUBZone, Service Disabled Veteran Owned Business, Woman Owned Small Business, etc. provided two or more contractors in the socio-economic group are awarded a MATOC Basic

NOTE:

8(A) Contractors must have approved business plans on file and services by Chicago District Office SBA

THE FOLLOWING IS A BRIEF OVERVIEW OF

THE PROPOSAL REQUIREMENTS

OFFERORS ARE CAUTIONED TO

CAREFULLY READ THE REQUIREMENTS

OF THE SOLICITATION AND COMPLY

ACCORDINGLY

Section 00110 of the RFP details required information and format

• 3 Volumes In 2 Binders are required

• BINDER 1

VOLUME 1 PRICE/COST, PRO FORMA DOCUMENTS

• BINDER 2

VOLUME 2 PAST PERFORMANCE REQUIREMENTS

VOLUME 3 TECHNICAL REQUIREMENTS

Cover Letter SF 1442 – Signed SF 1442 – Amendments Signed AREAS of CONSIDERATION- Section 00010

EXHIBIT E

• Price for Seed Project REPS & CERTIFICATIONS – Section 00600

Volume 2 - Past Performance Proposal

• Complete Exhibit A -Performance Relevancy

Questionnaire Part 1/ One Part 2

Have Subcontractors Complete- Exhibit B

• Subcontractor Consent and Information Form

List of Clients (name and number) you sent Exhibit C questionnaires to and/or final CPARSS forms for the Exhibit A Part 1 projects

(Exhibit C Package) Send Questionnaires to References Introduction Letter, Exhibit C and Questionnaire

• References must return NLT the Closing Date to KO

Not to You

• Email and Fax addresses available

• Do not include copies of what was sent in the proposal !

If you have a CPARS Final Evaluation for the project that may be included in lieu of sending form- place behind applicable Exhibit A

Offerors should carefully read section 00800- and DIVISION 01/00800 General Requirements before preparing proposal

• Important basic contract requirements and conditions are contained in these sections

Volume 3 -TECHNICAL PROPOSAL

• Read the sub factor requirements in Exhibit D LIMIT to

10 double sided pages (20 single pages) exclusive of tabs, indexes, dividers, and attachments listed in this exhibit. Any additional attachments you provide will be included in the page count provided

• Complete Exhibit D Answer questions carefully and thoroughly Include required Attachments Consider evaluating your proposal IAW

Section 00120 before submitting

Represents type of smaller projects that may be awarded under this contract

Measures contractors’ estimating system

Detailed in Section 00120 of the RFP CAREFULLY review sections 00100, 00110

& 00120 and 00800 through Division 01 when preparing proposal

Comply with Section 00100 AND 00110 requirements

Inquire in writing if you have questions Failure to furnish a complete proposal may result in elimination from consideration

Past Performance and Technical when combined are approximately equal to price

Best Value is defined as an award based on the greatest overall benefit in response to the requirement.

Award is based on other factors in addition to price.

The Contractors whose proposals provide the best value to the

Government, price and other non-cost factions considered will be awarded contracts

Every Contractor who is awarded a MATOC contract will be given a FAIR OPPORTUNITY to compete for the award of Task or Projects unless and exemption applies

Urgent or emergency requirements

Services are unique or highly specialized interest of economy and efficiency

Satisfy the minimum guarantee

NOTE: THIS IS NOT A

REQUIREMENTS CONTRACT

KO May limit competition or exclude a contractor for the following reasons:

• Satisfy Agency Small Business Program Goals Projects will be set-aside for 8(a) MATOC Contractors and/or HUB Zone and/or SDVB MATOC Contractors and/or Women Owned Small Business

• Failure to prosecute the work diligently on a current Task Order Award

• Order outside your areas of consideration

• The Master specification, also referred to as the default specification

• Establishes an industrial and/or commercial standards for maintenance and repair of Government Facilities

•If SOW does not address a specification for an element of work, the master/default specification applies

Normal response time is two (2) days for site visit and three (3) days to thirty (30) for proposal depending on complexity

Contractors must be able to respond within 120 Minutes in the event of an emergency to view a site and possibly give a price.

MATOC contractors are required to have insurance while under contract- not just when the task order is issued.

You will have access to base for contract related events

Must be in place if responding to emergencies

Most current Construction Wage rates will apply to each MATOC Request for Proposal

• Link to Web site will be provided;

www.beta.sam.gov. - Note the most current wage determination at time of award of Task Order applies to the Task Order

Performance and Payment bonds are established by each Task Order

• PAYMENT BOND - T.O.>35K

• PERFORMANCE BOND - T.O.>$150K

If a Performance & Payment Bond are required, i.e. projects > $150K will require a bid bond submitted with the proposal

KO establishes site visit & notifies MATOC Contractors by email or Beta.SAM.gov/ Contract Opportunities site.

• Provides MATOC Project synopsis, offering letter and basis for award & when available SOW/Plans/Wage Rates etc.(RFQ/RFP) (Note in some instances this will be provided at the site visit)

• KO & Engineer conducts the site visit with MATOC Contractors

• KO validates proposal due date with Contractors

Contractor submits questions to KO who will provide answers to all

If necessary, engineer makes changes via addendum and forwards to KO who issues Amendment

Contractor submits price or best value proposal by hand carried, email, or fax as applicable

KO does evaluation and makes award upon receipt of funds

KO emails award notice to awardees Notifies all others of award only

• Normal method of distribution will be via email or web posting

• When issued on CD/DVD one set of project plans & specifications will be provided to each MATOC contractor at no cost.

• It is the MATOC contractors responsibility to notify their subcontractors and provide them copies.

• Electronic versions when available will be on the Web

16 July 2020 @ 2PM

CST

DON’T FORGET TO HAVE REFERENCES SENT IN

BY THIS TIME & DATE

Award is contemplated to be made without discussions- Do Not anticipate a chance to make corrections or changes

Your first proposal will probably be your only proposal!!

Read the solicitation requirements carefully!!

Consider using Section 00120 to “rate” yourself before submitting the proposal-is it complete??

All Amendments Will On The Beta SAM Web Site

Check Site Regularly For Changes & Refresh The Page

After Closing No Information Will Be Available Until Award

• Awards Will Be Posted To The Web

• Results should be announced in Approximately 90

Days

Questions Must Be Submitted In Writing Via Email to- benjamin.b.yeutson.mil@mail.mil

Submit Questions NLT COB 9 July 2020 Submit Questions To KO Only Do Not Call

Other Government Personnel Questions Received Late May Be Held And

Addressed After RFP Closing With Those Who Submitted Offerors

Questions And Answers Will Be Posted To The BETA SAM Web Site Only

All Questions, On A Non-Attribution Basis, And The Answers Will Be Posted To The Beta SAM/ Contract Opportunities Web Site

If Necessary Addendums, Issued By An Amendment, Will Also Be Posted

Check Web Site Regularly And Don’t Forget To Refresh Web Page www.sam.gov/ https://beta.sam.gov/search?index=wd https://www.beta.sam.gov