Exhibit F UFGS 32 01 19 joint sealant.pdf
PDF 82 KB Posted
- Attached to
- Repair Apron Joint Sealant Scott AFB IL
- Solicitation number
- W50S7S21R0001
- Issued by
-
Department of the Army National Guard
About this file
This solicitation is for repairing joint sealant at Scott Air Force Base in Illinois. The base bid includes completing work in Zones 1 and 2, which consists of furnishing all labor, equipment, materials and permits to repair apron joint sealant in compliance with UFC 3-260-04, AFI 31-101 and other codes. An option to complete work in Zone 3 is also included. The magnitude of the project is estimated between $250,000 to $500,000 and work must be completed within 150 days of notice to proceed. A pre-proposal conference will be held on July 13, 2021 at 9:00AM at the base to review requirements, with a site visit following. Questions for the conference are due by July 1, 2021 via email.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q and A 4.docx | DOCX document | |
| Q and A 3.docx | DOCX document | |
| Q and A 2.docx | DOCX document | |
| AMDT W50S7S21R0001 - 0001.pdf | ||
| Q and A 1.docx | DOCX document | |
| Site Visit MFR.pdf | ||
| Site Visit Sign In Sheet - Redacted.pdf | ||
| Exhibit G Grid Map.pdf | ||
| Exhibit E Revised SOW.docx | DOCX document | |
| Apron.Sealing.Grid.Map.pdf | ||
| Exhibit A.doc | DOC document | |
| Exhibit E SOW.docx | DOCX document | |
| Exhibit B.doc | DOC document | |
| Exhibit C_Reference_Questionnaire_Package 18Jan18_NEW.docx | DOCX document | |
| Exhibit D Letter of Commitment.docx | DOCX document | |
| W50S7S21R0001 SF1442.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
126th Repair Apron Joint Sealant VDYD212003 100% Submittal
SECTION 32 01 19
FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS
08/08
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C1016 (2014) Standard Test Method for
Determination of Water Absorption of
Sealant Backing (Joint Filler) Material
ASTM D789 (2015) Determination of Relative Viscosity and Moisture Content of Polyamide (PA)
U.S. ARMY CORPS OF ENGINEERS (USACE)
COE CRD-C 525 (1989) Corps of Engineers Test Method for
Evaluation of Hot-Applied Joint Sealants for Bubbling Due to Heating
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FS SS-S-200 (Rev E; Am 1; Notice 1) Sealant, Joint, Two-Component, Jet-Blast-Resistant, Cold-Applied, for Portland Cement Concrete
Pavement
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Manufacturer's Recommendations; G.
Equipment.
SD-04 Samples
Materials; G.
SD-06 Test Reports
Certified Copies of the Test Reports; G.
SECTION 32 01 19 Page 1
1.3 QUALITY ASSURANCE
1.3.1 Test Requirements
Test the joint sealant and backup or separating material for conformance with the referenced applicable material specification. Conformance with the requirements of the laboratory tests specified will not constitute final acceptance of the materials. Final acceptance will be based on the performance of the in-place materials. Submit samples of the materials
(sealant, primer if required, and backup material), in sufficient quantity for testing and approval 30 days prior to the beginning of work. No material will be allowed to be used until it has been approved.
1.3.2 Trial Joint Sealant Installation
Prior to the cleaning and sealing of the joints for the entire project, prepare a test section at least 200 feet long using the specified materials and approved equipment, so as to demonstrate the proposed joint preparation and sealing of all types of joints in the project. Following the completion of the test section and before any other joint is sealed, inspect the test section to determine that the materials and installation meet the requirements specified. If it is determined that the materials or installation do not meet the requirements, remove the materials, and reclean and reseal the joints at no cost to the Government. When the test section meets the requirements, it may be incorporated into the permanent work and paid for at the contract unit price per linear foot for sealing items scheduled. Prepare and seal all other joints in the manner approved for sealing the test section.
1.4 DELIVERY, STORAGE, AND HANDLING
Inspect materials delivered to the job site for defects, unload, and store them with a minimum of handling to avoid damage. Provide storage facilities at the job site for maintaining materials at the temperatures and conditions recommended by the manufacturer.
1.5 ENVIRONMENTAL REQUIREMENTS
The ambient air temperature and the pavement temperature within the joint wall shall be a minimum of 50 degrees F and rising at the time of application of the materials. Do not apply sealant if moisture is observed in the joint.
PART 2 PRODUCTS
2.1 SEALANTS
Materials for sealing cracks in the various paved areas indicated on the drawings shall be as follows:
Area Sealing Material
PCC-PCC Slab Joints
PCC-HMA Joints
FS SS-S-200 Type M or H and COE CRD-C 525
2.2 PRIMERS
When primers are recommended by the manufacturer of the sealant, use them
SECTION 32 01 19 Page 2 in accordance with the recommendation of the manufacturer.
2.3 BACKUP MATERIALS
Provide backup material that is a compressible, nonshrinking, nonstaining, nonabsorbing material, nonreactive with the joint sealant. The material shall have a melting point at least 5 degrees F greater than the pouring temperature of the sealant being used when tested in accordance with
ASTM D789. The material shall have a water absorption of not more than 5 percent of the sample weight when tested in accordance with ASTM C1016.
Use backup material that is 25 plus or minus 5 percent larger in diameter than the nominal width of the crack.
2.4 BOND BREAKING TAPES
Provide a bond breaking tape or separating material that is a flexible, nonshrinkable, nonabsorbing, nonstaining, and nonreacting adhesive-backed tape. The material shall have a melting point at least 5 degrees F greater than the pouring temperature of the sealant being used when tested in accordance with ASTM D789. The bond breaker tape shall be approximately
1/8 inch wider than the nominal width of the joint and shall not bond to the joint sealant.
PART 3 EXECUTION
3.1 EXECUTING EQUIPMENT
Machines, tools, and equipment used in the performance of the work required by this section shall be approved before the work is started maintained in satisfactory condition at all times. Submit a list of proposed equipment to be used in performance of construction work including descriptive data, 30 days prior to use on the project.
3.1.1 Joint Cleaning Equipment
3.1.1.1 Tractor-Mounted Routing Tool
Provide a routing tool, used for removing old sealant from the joints, of such shape and dimensions and so mounted on the tractor that it will not damage the sides of the joints. The tool shall be designed so that it can be adjusted to remove the old material to varying depths as required. The use of V-shaped tools or rotary impact routing devices will not be permitted. Hand-operated spindle routing devices may be used to clean and enlarge random cracks.
3.1.1.2 Concrete Saw
Provide a self-propelled power saw, with water-cooled diamond or abrasive saw blades, for cutting joints to the depths and widths specified or for refacing joints or cleaning sawed joints where sandblasting does not provide a clean joint.
3.1.1.3 Waterblasting Equipment
Include with the waterblasting equipment a trailer-mounted water tank, pumps, high-pressure hose, wand with safety release cutoff control, nozzle, and auxiliary water resupply equipment. Provide water tank and auxiliary resupply equipment of sufficient capacity to permit continuous operations.
The nozzle shall have an adjustable guide that will hold the nozzle aligned
SECTION 32 01 19 Page 3 with the joint approximately 1 inch above the pavement surface. Adjust the height, angle of inclination and the size of the nozzle as necessary to obtain satisfactory results. A pressure gauge mounted at the pump shall show at all times the pressure in psi at which the equipment is operating.
3.1.1.4 Hand Tools
Hand tools may be used, when approved, for removing defective sealant from a crack and repairing or cleaning the crack faces.
3.1.2 Sealing Equipment
3.1.2.1 Two-Component, Cold-Applied, Machine Mix Sealing Equipment
Provide equipment used for proportioning, mixing, and installing FS SS-S-200
Type M joint sealants designed to deliver two semifluid components through hoses to a portable mixer at a preset ratio of 1 to 1 by volume using pumps with an accuracy of plus or minus 5 percent for the quantity of each component. The reservoir for each component shall be equipped with mechanical agitation devices that will maintain the components in a uniform condition without entrapping air. Incorporate provisions to permit thermostatically controlled indirect heating of the components, when required. However, immediately prior to proportioning and mixing, the temperature of either component shall not exceed 90 degrees F. Provide screens near the top of each reservoir to remove any foreign particles or partially polymerized material that could clog fluid lines or otherwise cause misproportioning or improper mixing of the two components. Provide equipment capable of thoroughly mixing the two components through a range of application rates of 10 to 60 gallons per hour and through a range of application pressures from 50 to 1500 psi as required by material, climatic, or operating conditions. Design the mixer for the easy removal of the supply lines for cleaning and proportioning of the components. The mixing head shall accommodate nozzles of different types and sizes as may be required by various operations. The dimensions of the nozzle shall be such that the nozzle tip will extend into the joint to allow sealing from the bottom of the joint to the top. Maintain the initially approved equipment in good working condition, serviced in accordance with the supplier's instructions, and unaltered in any way without obtaining prior approval.
3.1.2.2 Two-Component, Cold-Applied, Hand-Mix Sealing Equipment
Mixing equipment for FS SS-S-200 Type H sealants shall consist of a slow-speed electric drill or air-driven mixer with a stirrer in accordance with the manufacturer's recommendations. Submit printed copies of manufacturer's recommendations, 30 days prior to use on the project, where installation procedures, or any part thereof, are required to be in accordance with those recommendations. Installation of the material will not be allowed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material.
3.2 SAFETY
Do not place joint sealant within 25 feet of any liquid oxygen (LOX) equipment, LOX storage, or LOX piping. Thoroughly clean joints in this area and leave them unsealed.
SECTION 32 01 19 Page 4
3.3 PREPARATION OF JOINTS
Immediately before the installation of the sealant, thoroughly clean the joints to remove all laitance, curing compound, filler, protrusions of hardened concrete, and old sealant from the sides and upper edges of the joint space to be sealed.
3.3.1 Existing Sealant Removal
Cut loose the in-place sealant from both joint faces and to the depth shown on the drawings, using the concrete saw as specified in paragraph
EQUIPMENT. Depth shall be sufficient to accommodate any separating or backup material that is required to maintain the depth of new sealant to be installed. Prior to further cleaning operations, remove all loose old sealant remaining in the joint opening by blowing with compressed air.
Hand tools may be required to remove sealant from random cracks. Chipping, spalling, or otherwise damaging the concrete will not be allowed.
3.3.2 Sawing
3.3.3 Waterblasting
The newly exposed concrete joint faces and the pavement surfaces extending a minimum of 1/2 inch from the joint edges shall be waterblasted clean.
use a multiple-pass technique until the surfaces are free of dust, dirt, curing compound, filler, old sealant residue, or any foreign debris that might prevent the bonding of the sealant to the concrete. After final cleaning and immediately prior to sealing, blow out the joints with compressed air and leave them completely free of debris and water.
3.3.4 Back-Up Material
When the joint opening is of a greater depth than indicated for the sealant depth, plug or seal off the lower portion of the joint opening using a back-up material to prevent the entrance of the sealant below the specified depth. Take care to ensure that the backup material is placed at the specified depth and is not stretched or twisted during installation.
3.3.5 Bond Breaking Tape
Where inserts or filler materials contain bitumen, or the depth of the joint opening does not allow for the use of a backup material, insert a bond breaker separating tape to prevent incompatibility with the filler materials and three-sided adhesion of the sealant. Securely bond the tape to the bottom of the joint opening so it will not float up into the new sealant.
3.3.6 Rate of Progress of Joint Preparation
Limit the stages of joint preparation, which include sandblasting, air pressure cleaning and placing of the back-up material to only that lineal footage that can be sealed during the same day.
3.4 PREPARATION OF SEALANT
3.4.1 Type M Sealants
Inspect the FS SS-S-200 Type M sealant components and containers prior to use. Reject any materials that contain water, hard caking of any separated
SECTION 32 01 19 Page 5 constituents, nonreversible jell, or materials that are otherwise unsatisfactory. Settlement of constituents in a soft mass that can be readily and uniformly remixed in the field with simple tools will not be cause for rejection. Prior to transfer of the components from the shipping containers to the appropriate reservoir of the application equipment, thoroughly mix the materials to ensure homogeneity of the components and incorporation of all constituents at the time of transfer. When necessary for remixing prior to transfer to the application equipment reservoirs, warm the components to a temperature not to exceed 90 degrees F by placing the components in heated storage or by other approved methods but in no case shall the components be heated by direct flame, or in a single walled kettle, or a kettle without an oil bath.
3.4.2 Type H Sealants
Mix the FS SS-S-200 Type H sealant components either in the container furnished by the manufacturer or a cylindrical metal container of volume approximately 50 percent greater than the package volume. Thoroughly mix the base material in accordance with the manufacturer's instructions. The cure component shall then be slowly added during continued mixing until a uniform consistency is obtained.
3.5 INSTALLATION OF SEALANT
3.5.1 Time of Application
Seal joints immediately following final cleaning of the joint walls and following the placement of the separating or backup material. Open joints, that cannot be sealed under the conditions specified, or when rain interrupts sealing operations shall be recleaned and allowed to dry prior to installing the sealant.
3.5.2 Sealing Joints
Immediately preceding, but not more than 50 feet ahead of the joint sealing operations, perform a final cleaning with compressed air. Fill the joints from the bottom up to 1/8 inch plus or minus 1/16 inch below the pavement surface. Remove and discard excess or spilled sealant from the pavement by approved methods. Install the sealant in such a manner as to prevent the formation of voids and entrapped air. In no case shall gravity methods or pouring pots be used to install the sealant material. Traffic shall not be permitted over newly sealed pavement until authorized by the Contracting
Officer. When a primer is recommended by the manufacturer, apply it evenly to the joint faces in accordance with the manufacturer's instructions.
Check the joints frequently to ensure that the newly installed sealant is cured to a tack-free condition within the time specified.
3.6 INSPECTION
3.6.1 Joint Cleaning
Inspect joints during the cleaning process to correct improper equipment and cleaning techniques that damage the concrete pavement in any manner.
Cleaned joints will be approved prior to installation of the separating or back-up material and joint sealant.
3.6.2 Joint Sealant Application Equipment
Inspect the application equipment to ensure conformance to temperature
SECTION 32 01 19 Page 6 requirements, proper proportioning and mixing (if two-component sealant) and proper installation. Evidences of bubbling, improper installation, failure to cure or set will be cause to suspend operations until causes of the deficiencies are determined and corrected.
3.6.3 Joint Sealant
Inspect the joint sealant for proper rate of cure and set, bonding to the joint walls, cohesive separation within the sealant, reversion to liquid, entrapped air and voids. Sealants exhibiting any of these deficiencies at any time prior to the final acceptance of the project shall be removed from the joint, wasted, and replaced as specified herein at no additional cost to the Government.
3.7 CLEAN-UP
Upon completion of the project, remove all unused materials from the site and leave the pavement in a clean condition.
-- End of Section --
SECTION 32 01 19 Page 7
File details come from the government source that posted it. Updated .