This document summarizes a pre-bid conference for a federal construction contract opportunity. The project involves repairs to Building 1203 at the 187th Fighter Wing in Montgomery, Alabama to support F-35 maintenance activities. Work includes electrical upgrades including a new transformer and power stations, HVAC and mechanical system upgrades, communications infrastructure installation, and security and fire protection system updates. The base bid value is between $1-5 million with an additive option for telecommunications cabling. The response due date is 24 May 2022. Attendees must submit their names using an EAL form 48 hours prior to the scheduled site visit on 26 April 2022. The pre-bid meeting provides an overview of project requirements and responses should comply with the solicitation.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
187th FIGHTER WING
PRE-BID CONFERENCE
SOLICITATION NO.
W50S6N-22-B-0002
FAKZ182352 –F-35: Repair Fuel Cell, Building 1203, at the 187th Fighter Wing
INTRODUCTIONS
Contracting Personnel Mr. Stephen Shanks, Contracting Officer CMSgt William Hall and Mr. Karey Elias, Contracting Specialist’s
Civil Engineering Maj. Adam Sanders, Base Civil Engineer Maj. William Sanford, Deputy Base Civil Engineer
Architects Mr. David Donovan, Seay, Seay & Litchfield Architects Mr. Jake Johnson, Seay, Seay & Litchfield Architects
DISCLAIMER
The following is a brief overview of the IFB requirements
Contractors are cautioned to carefully read the requirements of the solicitation and comply accordingly
Projects W50S6N-22-B-0002
PROJECT TITLE: Repair Fuel Cell, Building 1203
MAGNITUDE OF PROJECT: $1,000,000 - $5,000,000
LOCATION: 187th Fighter Wing, Dannelly Field, Montgomery, Al.
Project will have one Bid Option
Project Overview Repair Building 1203:
Electrical:
Removal and replacement of existing 500kva transformer with new 1000 kva transformer.
New exterior electrical service panel Removal and replacement of existing concrete paving as required to install new conduit and conductors.
Addendum will be issued to require installation of existing 500 kva transformer at building 1203. Existing transformer at building 1206 will be delivered to the Government.
Removal of 400 hz power systems.
Installation of two new F-35 power stations consisting of a 270VDC converter (Contractor Furnished and Installed) and 3 460VAC disconnects for F-35 support equipment.
Communications New telecommunications raceway for ALIS terminals in hangar (BASE BID) Installation and termination of communications cabling to be included as Bid Option #1.
ALIS terminations are standard base LAN connections patched back to existing comm room in Building 1203 (Bid Option)
Mechanical:
New 12000 CFM DX cooling split system with hot gas reheat unit to condition one of the two hangar bays to support F-35 maintenance activities.
Reconfiguration of existing HVAC systems in room 122 to accommodate new mezzanine.
Plumbing:
Modification of existing compressed air systems as required to meet F-35 maintenance requirements.
Existing compressors will remain. New compressors will be added to meet F-35 requirements.
Filtering to meet F-35 requirements for compressed air to be added.
Upgrading compressed air pipe size as needed to meet F-35 requirements.
New breathing air systems.
Fire Protection:
Relocation of existing sprinkler heads as required to address “obstructions” caused by new HVAC equipment and ductwork.
Architectural:
No space reconfiguration.
Extension of existing mezzanine structure to support new HVAC systems.
Re-striping of hangar floor to accommodate proposed aircraft parking shown on A2.1 Installation of new door hardware systems to support security requirements.
New exterior louver for HVAC intake air.
Security:
Facility contains secure areas. These areas ARE NOT SAPF areas nor are they Governed by ICD 705.
STC rated walls ARE NOT required.
New IDS panel is required with motion sensors and door position switches as indicated on the drawings.
Access control is not required. Access control will be provided via cipher locks indicated on in the hardware schedule.
ADVANTOR systems is the Government’s proprietary security systems provider and will provide all intrusion detection and access control systems for secure and SAPF areas.
Supervision & Job-Site Trailer:
Contractor shall provide on-site supervision as required to successfully complete the work.
On-site office space for Contractor personnel and project meetings is not required by project scope.
Phasing & Occupancy:
All adjacent facilities will remain occupied. Contractor also must maintain access to flight line.
Access to one maintenance bay shall be maintained at all times.
Do not start work in maintenance bays until all required materials have been procured and are on-site or at an off-site storage location.
21 calendar duration for work in the Corrosion Control Bay 14 calendar duration for work in the Fuel Cell Bay.
Provide the Government 21 days notice prior to commencing work in either maintenance bay.
Sustainability:
Project has been designed to be “LEED Meritable” in accordance with ANGETL 15-01-01 The project is not registered with LEED or the USGBC for any third party registration.
Contractor to submit documentation for products, where noted in the specifications, to required specific sustainable characteristic (energy star rating, recycled content, etc…).
A product not meeting listed sustainable requirements will be grounds for disapproval of the submittal/product.
Limited Source Requirements:
The following products/manufacturers must be provided by name with no exception:
Johnson Controls ADVANTOR Systems Contractor shall contact ADVANTOR during the bid process and get updated pricing information Monaco Transceivers QuadFoam 2.0 for spray foam systems.
Delastic Preformed Pavement Seals BEST Access Cores/Keying System Refer to the Government's solicitation package for requirements/justification regarding limited source requirements.
Project Management Software:
Contractor will be required to utilize Architect's newforma system for all project communication All submittals and RFI will be submitted electronically Web-based interface will be provided at no cost to the Contractor iPad applications will also be made available to contractor at no cost.
Regular progress meetings.
Frequency will be based upon progress schedule and work quality.
A minimum of bi-weekly meetings should be anticipated.
Third party project manager, if utilized, will be required to be on site a minimum of once a month - refer to administrative requirements specification.
Additive Bid Options Telecommunications Cabling Base bid shall include all raceway.
Bid option includes CAT 6 cabling, patch panel, terminations, etc…
PROPOSAL DUE DATE
DATE: 14:00 on 24 May 2022
Documents must be received prior to or on this date Questions (Written Only) Deadline: 14:00 on 13 May
LOCATION: 187th Fighter Wing C/O Base Contracting 5187 Selma Highway Montgomery, AL 36108-4824
Hand carried bids, deliver to Building 1502 Classroom
All documents should have proper signatures
SUBMISSION REQUIREMENTS
Bid Guarantee’s are required
Performance Bond and Payment Bond: On Awarded IFB
Liquidated Damages: $1,002.74
Performance Period: 180 days after NTP
Davis Bacon Wage Rates applicable: AL 20220093, dated 03/18/2022
Questions Send to:
william.k.hall14.mil@army.mil karey.l.elias.civ@army.mil stephen.shanks.1@us.af.mil
All RFI’s/questions must be submitted to the contracting office. DO not contact the A/E or CE directly.
ANSWERS TO QUESTIONS
All questions, on a non-attribution basis, and the answers will be posted to the website https://sam.gov/content/opportunities
All Addendums will be issued by an Amendment and posted to https://sam.gov/content/opportunities
Check website regularly and don’t forget to REFRESH the web page.
Award
Award will be a Firm Fixed Price
Funds are not presently available. Currently the Government anticipates funds will become available prior to, but not later than, midnight 30 September 2021
SITE VISIT SECURITY AND SAFETY BRIEFING
You can have your cell phones, but no driving and talking on your cell phone
All photos must be approved by the Government.
All contractors must be accompanied by an escort during the site visit.
ONCE AGAIN PROPOSALS ARE DUE
NO LATER THAN
Tuesday 24 May 2022 2:00 p.m. Central Time
Thank You
We appreciate your interest in this project Office Open Tuesday - Friday 0700- 17:30
Questions image2.png image3.png image4.png image1.png
File details come from the government source that posted it. Updated .