FAKZ182351 Addendum No. 2 SIGNED.pdf

PDF 6 MB Posted

Attached to
F-35 Repair Fuel Cell, Bldg 1203
Solicitation number
W50S6N-22-B-0002
Issued by

About this file

This is a solicitation for a federal construction contract to repair a fuel cell at Building 1203 for the Alabama Air National Guard. The solicitation number is W50S6N-22-B-0002. A pre-bid conference will be held on April 26th at 10am central time. Bids are due by May 24th and must be submitted to 5187 Selma Highway, Montgomery, AL. Attendees of the pre-bid site visit must submit their names to the specified email addresses 48 hours in advance. The scope of work includes modifications to architectural, structural, mechanical, electrical, and plumbing systems to support an F-35 aircraft. The contracting agency is the Department of the Army Alabama Army National Guard.

View the file

Other files

File Type Posted
OF 1419A Pg 2 or 3.pdf PDF
OF 1419A Pg 3 or 3.pdf PDF
bid opening sign in sheet.pdf PDF
OF 1419 Pg 1 or 3.2.pdf PDF
RFI Responses 003.pdf PDF
Amendment 0005 SF-30.pdf PDF
W50S6N-22-B-0002 0005.pdf PDF
FAKZ182351 RFI Responses 002 SIGNED.pdf PDF
W50S6N-22-B-0002 0004.pdf PDF
FAKZ182351 RFI Responses 001 SIGNED.pdf PDF
J-A Brand Names.pdf PDF
Amendment 0004 SF-30.pdf PDF
B1203 Sign In Sheet.pdf PDF
W50S6N-22-B-0002 0003 SF-1442.pdf PDF
Amendment 3- SF-30.pdf PDF
Amendment 1.pdf PDF
SF-30 Amendment.pdf PDF
FAKZ182351 Addendum No. 1 SIGNED.pdf PDF
PreBid Bldg 1203.pptx PPTX presentation
1203 Pre-Bid Roster.pdf PDF
W50S6N-22-B-0002 Solicitation.pdf PDF
FAKZ182351 Type B-3 Drawings SIGNED.pdf PDF
EAL.pdf PDF
FAKZ182351 Type B-3 Specifications REVISED SIGNED.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F-35 – REPAIR FUEL CELL, BUILDING 1203 FAKZ182351

ADDENDUM NO. 1 Page 1 of 2 Seay Seay & Litchfield, P.C. 24 May 2022

Date: 24 May 2022

To: Mr. Steve Shanks

Subject: ADDENDUM NO. 2

Project: F-35 – REPAIR FUEL CELL, BUILDING 1203

Job #: ANG# FAKZ182351 / SSL# 18073

From: David Donovan

The plans and Specifications for the F-35 – Repair Fuel Cell, Building 1203, dated 1 April 2022 are amended as follows. (Where there are conflicts between the plans and specifications and the addendum, this addendum shall govern).

Item No. 1: Refer to specifications. Delete specification section 00 0102 Project

Information and Summary and replace it with the attached specification section 00 0102 with a revised date of May 14, 2022.

Item No. 2: Refer to specifications. Add the attached specification section 23 0593

“Testing, Adjusting, and Balancing for HVAC” with a revised date of 18 May 2022.

Item No. 3: Refer to specifications. Delete specification section 26 0100 Electrical and replace it with the attached specification section 26 0100 with a revised date of May 14, 2022.

Item No. 4: Refer to specifications. Delete specification section 26 0271 Medium

Voltage Transformers and replace it with the attached specification section 26 0271 with a revised date of May 14, 2022.

Item No. 5: Refer to specifications. Delete specification section 28 1300 Security

System and replace it with the attached specification section 28 1300 with a revised date of May 14, 2022.

Item No. 6: Refer to specifications. Add the attached specification section 32 1723.13

“Painted Pavement Markings” with a revised date of May 14, 2022.

Item No. 7: Refer to drawings. Delete drawing sheets A2.1, A2.2, and M3.1 and replace them with the attached drawings sheets A2.1, A2.2, and M3.1, with a revised date of May 18, 2022.

F-35 – REPAIR FUEL CELL, BUILDING 1203 FAKZ182351

ADDENDUM NO. 1 Page 2 of 2 Seay Seay & Litchfield, P.C. 24 May 2022

Item No. 8: Refer to drawings. Delete drawing sheets E0.1, E1.1, E1.2, E2.1, E2.3, E3.1, E3.2, E3.3, and E3.4 and replace them with the attached drawings sheets E0.1, E1.1, E1.2, E2.1, E2.3, E3.1, E3.2, E3.3, and E3.4 with a revised date of May 17, 2022.

Item No. 9: Refer to drawings. Add the attached drawing sheet E2.1A “Partial First

Floor Plan – Lighting, Luminaire Schedule, & Notes” with a revised date of 5/17/2022.

End of Addendum #1

F-35: Repair Fuel Cell, Building 1203 1 April 2021 187th Fighter Wing, Dannelly Field ANG, Montgomery, AL Type B-3 Submittal SSL# 18073 / ANG# FAKZ182351 Revised May 14, 2022

PROJECT INFORMATION AND SUMMARY 00 0102 - 1

SECTION 00 0102 - PROJECT INFORMATION AND SUMMARY

PART 1 GENERAL

1.01 PROJECT IDENTIFICATION

A. Project Name: F-35: Repair Fuel Cell, Building 1203, located at 187th Fighter Wing, Air National Guard (ANG) Base at Dannelly Field, Montgomery, AL.

B. Government Project Number: FAKZ182351

C. Architect's Project Number: 18073.

D. The Owner, hereinafter referred to as the Government: Alabama Air National Guard.

E. Owner's Representatives:

1. Contracting Officer: Mr. Craig Kast

2. Contracting Specialist: Mr. Stephen Shanks

3. Contracting Officer Representative: Major Adam Sanders, Base Civil Engineer

4. Alternate Contracting Officer Representative: Captain Nathan Brock, Deputy Base Civil Engineer

1.02 CONTRACT DURATION

A. 180 calendar days from notice to proceed to Beneficial Occupancy, this is in addition to 30 days for the punch list to be completely accomplished. (Deleted by Addendum No.

2)

B. 365 calendar days from notice to proceed to Beneficial Occupancy. Punch list activities are to be completely accomplished prior to Beneficial Occupancy.

1. The initial 155 calendar day duration is intended for material submittal approval and materials acquisition to accomodate long lead time items including the new electrical switch gear.

2. Work on-site will be limited to 210 calendar days and will be phased as outlined in section 1.08 of this specification section.

3. Contractor shall provide the Government 14 days written notice prior to on-site activities beginning. Contracting Officer will provide a written notice to proceed with on-site work. On-site work must be compelted within 210 days of the notice to proceed. (Added by Addendum No. 2)

PROJECT INFORMATION AND SUMMARY 00 0102 - 2

1.03 PROJECT DESCRIPTION

A. Project scope includes moodification of the existing facility architectural, structural, mechanical, plumbing, and electrical systems as required to support the F-35A Airframe. The proposed project includes, but is not limited to, the following:

1. Installation of a new split system air conditioning unit to provide cooling to the existing Corrosion Control Maintenance Bay.

2. Extension of the existing equipment platform/mezzanine in Stripping Room as required to accomodate the new interior air handler for the Corrosion Control Maintenance Bay.

3. Installation of new air compressors, extension of compressed air lines, and relocation of air drops in maintenance bays to meet F-35 aircraft/shop air requirements.

4. Installation of new breathing air system to support fuel tank maintenance activities.

5. Installation of new 270 VDC electrical converters, 480V AC receptacles, and other power devices required to support F-35 maintenance activities.

6. Replacement of existing facility transformer and main switchgear to support increases power requirements associated with the F-35 electrical requirements.

7. Minor site demolition and repair to accomodate electrical upgrades.

B. Intrusion Detection System (IDS), Access Controls, and CCTV:

1. The IDS system must be fully compatible with the existing USAF approved Advantor IDS Annunciator located in the 187th SFS BDOC.

2. As part of the base bid, the contractor is responsible for engaging Advantor Systems Cooperation (which is a sole source security system) for the procurement (purchase) and installation of the IDS, Access Controls, and CCTV systems. Refer to limited source justification included in the solicitation documents furnished by the Government.

3. The base bid shall include all plant, labor, and materials to provide all collateral support as required by Advantor (in addition to collateral support indicated in the contract documents) for installation of a fully operational IDS and CCTV systems as defined by Advantor System Corporation.

PROJECT INFORMATION AND SUMMARY 00 0102 - 3

4. The required scope of work is as outlined in the drawings. Advantor systems assisted in the design of the security systems and have furnished a "quote" as part of the design process. The "quote" is included in the project specifications for for reference and identification of the required devices/materials. The Contractor shall contact ADVANTOR and receive an updated "quote" as part of the bid process.

All costs to install a complete and operation IDS and CCTV systems shall be included in the Contractor's bid.

1.04 SUSTAINABILITY DESIGN AND ENERGY CONSERVATION:

A. The project design incorporates Sustainability Concepts to achieve optimum resource efficiency, constructibility, sustainability, and energy conservation.

B. The project has not been registered with the USGBC and is not inteded to be registered.

The project is not intended to achieve any level of LEED certification or any other sustainability certifications. however, in accordance with ANGETL 15-01-01, the project is intended to be "LEED Meritable" and incorporate sustainable design principles and criteria to the maximum extent possible.

C. In keeping with ANGETL 15-01-01 Contractor shall give preference to sustainable products and materials with higher levels of sustainability including but not limited to materials extracted and manufactured within 500 miles of the project site, materials manufactured using higher levels of recycled content, materials meeting VOC limitations, etc...

D. Where applicable, minimum thresholds for sustainability criteria are established within the technical specifications. Where not specifically indicated, the Contractor shall give preference to and provide materials that contribute the most to the project's sustainability goal.

E. Contractor shall provide "LEED Submittals" for all products, materials, and systems indicating a product or material's sustainable attributes for review and approval by the Government. However, input of LEED documentation into the USGBC's LEED Online system will not be required. Similarly, LEED credit templates documenting the project's LEED performance will not be required.

1.05 PERMITS, FEES AND NOTICES

A. Unless otherwise provided in the Contract Documents, the Contractor shall secure and pay for the building permit and other permits and governmental fees, licenses, and inspections necessary for proper execution and completion of the Work which are customarily secured after award of the Construction Contract and which are in effect on the date of receipt of bids.

PROJECT INFORMATION AND SUMMARY 00 0102 - 4

1. City of Montgomery Buidling Permit will not be required.

B. The Contractor shall comply with and give notices required by all laws, ordinances, rules, regulations, and lawful orders of public authorities applicable to performance of the Work.

1.06 USE OF SITE AND MISC. REQUIREMENTS

A. Construction Operations: Limited to areas noted on Drawings.

B. Arrange use of site and premises to allow:

1. Government occupancy & ongoing operations at adjacent facilities..

C. Access to site will be limited; obtain Contracting Officer Representative's approval of proposed routes of access.

D. Provide access to and from site as required by law and by the Government:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

3. Coordinate site lay down and storage areas with Government operations.

E. Keep existing sidewalks, roads, parking lots and drives on site clear and available at all times. Promptly remove mud, dirt, debris, etc. from sidewalks, streets, and public right-of-way during construction as it occurs.

F. Storage areas on site are very minimal and will be limited to materials that are to be immediately used in the progress of the work. If additional storage is required, then Contractor shall secure and be responsible to pay for such off site storage in a fully bonded and insured facility acceptable to the Government, with all items clearly identified as being assigned to this project.

G. Provide secure temporary barricades, fencing, etc. as required to separate the public from construction operations. Compliant safety and/or warning signage is to be provided as well in conjunction with fencing and barricades.

H. Construction operations are not to affect any of the ongoing operations thought the site and/or adjacent sites. Construction equipment is not to be attached to, or swing over existing buildings to remain, public areas, occupied buildings or parking lots, right-of-ways, etc.

PROJECT INFORMATION AND SUMMARY 00 0102 - 5

I. Comply with the Government's security requirements - refer to specification section 01 3553.

J. The contractor shall provide all testing, inspections, and similar services; these services also include those specified to be performed by an independent agency.

1.07 UTILITY OUTAGES AND SHUTDOWN

A. All electrical and communication shut downs shall be performed on a non-working day for the Government(Saturday, Sunday, Monday, or Holidays) unless specifically approved by the base Contracting Officer Representative.

B. Limit shutdown of utility services to 8 hours at a time, arranged at least 72 hours in advance with the Government.

C. Prevent accidental disruption of utility services to other facilities.

1.08 PHASING OF WORK

A. The work of this project shall be completed in one phase. However, the Contractor shall coordinate the work as required to ensure operations in areas of Building 1203 not impacted by the proposed scope of work can continue uninterrupted for the duration of the project.

B. Within 10 days of the Notice to Proceed, the Contractor shall furnish a comprehensive phasing plan for review and approval by the Government. The phasing plan shall indicated the Contractor's schedule for completion of the work and overlay that schedule with timeframes for when the Corrosion Control Maintenance Bay, Fuel Cell Maintenance Bay, Stripping Room, and Clean Room will be inaccessbile and un-available for use by the Government. All other areas of the facility shall remain unobstructed and available for use by the Government for the duration of the project.

C. The Contractor shall phase the work in a manner that minimizes the amount of time in which these areas of the facility will not be available for use by the Government.

D. The work in the Corrosion Control Maintenance Bay and Fuel Cell Maintenance Bay shall be scheduled and coordinated in advance with the Government and meet the following minimum requirements:

1. Provide a minimum 21 day notice prior to beginning work in both the Fuel Cell Maintenance and Corossion Control Maintenance Bays. Do not proceed with work in these areas without written approval from the Contracting Officer.

PROJECT INFORMATION AND SUMMARY 00 0102 - 6

2. Work in the Corrosion Control Bay shall be completed in one phase with only one interruption in the Government's ability to occupy and operate out of the maintenance bay. Upon written approval by the Contracting Officer, the Contractor will be granted access to the Maintenace Bay to being work. Work shall be complete within 21 calendar days from the start of work.

3. Work in the Fuel Cell Maintenance Bay shall be completed in one phase with only one interruption in the Government's ability to occupy and operate out of the maintenance bay. Upon written approval by the Contracting Officer, the Contractor will be granted access to the Maintenace Bay to being work. Work shall be complete within 14 calendar days from the start of work.

4. Work shall be phased such that one of the two Maintenance Bays is accessible to the Government at all times.

E. A period of disruption is anticipated for the replacement of the primary service to the building. Work is to be coordinated and occur over a non-UTA weekend (reference phasing note 4 on sheet E1.1). A non-UTA weekend would allow approximately 84 hours for this work (Friday at +/- 17:00 through Tuesday at +/- 0500). If coordinated with a Government holiday weekend, the outage could be extended to approximately 108 hours (Thursday at +/- 17:00 through Tuesday at +/- 0500).

Preparatory work (concrete removal, installation of new conduits, etc…) for the service interruption will be allow during normal working hours preceding the service interruption. The requirement is to minimize the service interruption to allow ongoing F-16 maintenance activities during normal Government working hours.

The interruption of power for new electrical service can occur at the discretion of the Contractor provided 14 days written notice is provided to the Government, Government has provided written approval to proceed, and all materials required for the work have been acquired and are present on site. Service panel replacement does not have to coordinated with any of the phases of the Corrosion Control and Fuel Cell Maintenance bays discussed above. (Added by Addendum No. 2)

F. The Contractor shall be responsible for all means, methods, sequencing of work, demolition, and reparations to the property and facilities as reqiured to accomplish the work. This shall included but is not limited to the installation of all equipment, furnishings, and materials.

1.09 PROJECT CONSULTANTS

A. The Architect: Seay Seay & Litchfield, PC

1. Address: 1115 South Court Street.

PROJECT INFORMATION AND SUMMARY 00 0102 - 7

2. City, State, Zip: Montgomery AL 36104.

3. Phone/Fax: 334-263-5162 334-263-5170.

4. Project Manager: David Donovan, AIA

5. Prinicipals-in-Charge: Wes R. Osmer, AIA, LEED AP

B. Architect's Consultants:

1. Structural Engineering:

a. Blackburn Daniels O'Barr, Inc.

b. Address: 8805 County Rd. 40E

c. City, State, Zip: Lowndesboro, AL, 36752.

d. Phone/Fax: 334-265-0206 / 334-265-0207.

e. Contact: Mark O'Barr

2. Plumbing, Mechanical & Fire Suppression Engineering:

a. HHB Engineering, PC

b. Address: 104 Josie Run

c. City, State, Zip: Prattville, AL 36066

d. Phone: 334-358-2707

e. Contact: Tom Hattemer, PC

3. Electrical Engineering:

a. Gunn & Associates, PC

b. Address: 3102 Highway 14

c. City, State, Zip: Millbrook, AL 36054

d. Phone: 334-285-1273

e. Contact: Barry Gravlee, P.E.

PROJECT INFORMATION AND SUMMARY 00 0102 - 8

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

END OF SECTION

F-35: Repair Fuel Cell Building 1203 Addendum 1 18 May 2022 187th Fighter Wing, Dannelly Field ANG, Montgomery, ALType B-3 (100%) Submittal

SSL#18073 / ANG# FAKZ182351

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 1

SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including Requirements of the Government’s Solicitation and Division 01 Specification Sections, apply to this Section.

B. Refer to additional Div 23 specifications regarding Commissioning Activity requirements.

1.2 SUMMARY

A. Section Includes:

1. Balancing Air Systems:

a. New air handling unit.

b. Existing exhaust fans EF-1, EF-10, EF-12 & EF-13.

2. Testing, Adjusting, and Balancing Equipment:

a. Motors.

b. Condensing units.

c. Air handling units

d. Exhaust fans and exhaust arms

3. Control system verification.

1.3 DEFINITIONS

A. AABC: Associated Air Balance Council.

B. BAS: Building automation systems.

C. NEBB: National Environmental Balancing Bureau.

D. TAB: Testing, adjusting, and balancing.

E. TABB: Testing, Adjusting, and Balancing Bureau.

F. TAB Specialist: An independent entity meeting qualifications to perform TAB work.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 2

G. TDH: Total dynamic head.

1.4 PREINSTALLATION MEETINGS

A. TAB Conference: If requested by the Government, conduct a TAB conference at Project site after approval of the TAB strategies and procedures plan to develop a mutual understanding of the details. Provide a minimum of 14 days' advance notice of scheduled meeting time and location.

1. Minimum Agenda Items:

a. The Contract Documents examination report.

b. The TAB plan.

c. Needs for coordination and cooperation of trades and subcontractors.

d. Proposed procedures for documentation and communication flow.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: Within 30 days of Contractor's Notice to Proceed, submit documentation that the TAB specialist and this Project's TAB team members meet the qualifications specified in "Quality Assurance" Article.

B. Certified TAB reports.

C. Sample report forms.

D. Instrument calibration reports, to include the following:

1. Instrument type and make.

2. Serial number.

3. Application.

4. Dates of use.

5. Dates of calibration.

1.6 QUALITY ASSURANCE

A. TAB Specialists Qualifications: Certified by AABC or NEBB.

B. Instrumentation Type, Quantity, Accuracy, and Calibration: Comply with requirements in ASHRAE 111, Section 4, "Instrumentation."

C. ASHRAE Compliance: Applicable requirements in ASHRAE 62.1, Section 7.2.2 - "Air Balancing."

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 3

D. ASHRAE/IESNA Compliance: Applicable requirements in ASHRAE/IESNA 90.1, Section 6.7.2.3 - "System Balancing."

1.7 FIELD CONDITIONS

A. Partial Government Occupancy: Project is to be completed in phases. Government may occupy areas of building before Substantial Completion. Cooperate with Government during TAB operations to minimize conflicts with Government's operations.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine the Contract Documents to become familiar with Project requirements and to discover conditions in systems designs that may preclude proper TAB of systems and equipment.

B. Examine installed systems for balancing devices, such as test ports, gage cocks, thermometer wells, flow-control devices, balancing valves and fittings, and manual volume dampers. Verify that locations of these balancing devices are applicable for intended purpose and are accessible.

C. Examine the approved submittals for HVAC systems and equipment.

D. Examine design data including HVAC system descriptions, statements of design assumptions for environmental conditions and systems output, and statements of philosophies and assumptions about HVAC system and equipment controls.

E. Examine ceiling plenums used for supply, return, or relief air to verify that they are properly separated from adjacent areas. Verify that penetrations in plenum walls are sealed and fire-stopped if required.

F. Examine equipment performance data including fan and pump curves.

1. Relate performance data to Project conditions and requirements, including system effects that can create undesired or unpredicted conditions that cause reduced capacities in all or part of a system.

2. Calculate system-effect factors to reduce performance ratings of HVAC equipment when installed under conditions different from the conditions used to rate equipment performance. To calculate system effects for air systems, use tables and charts found in AMCA 201, "Fans and Systems," or in SMACNA's

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 4

"HVAC Systems - Duct Design." Compare results with the design data and installed conditions.

G. Examine system and equipment installations and verify that field quality-control testing, cleaning, and adjusting specified in individual Sections have been performed.

H. Examine test reports specified in individual system and equipment Sections.

I. Examine HVAC equipment and verify that bearings are greased, belts are aligned and tight, filters are clean, and equipment with functioning controls is ready for operation.

J. Examine terminal units, such as variable-air-volume boxes, and verify that they are accessible and their controls are connected and functioning.

K. Examine strainers. Verify that startup screens have been replaced by permanent screens with indicated perforations.

L. Examine control valves for proper installation for their intended function of throttling, diverting, or mixing fluid flows.

M. Examine heat-transfer coils for correct piping connections and for clean and straight fins.

N. Examine system pumps to ensure absence of entrained air in the suction piping.

O. Examine operating safety interlocks and controls on HVAC equipment.

P. Report deficiencies discovered before and during performance of TAB procedures.

Observe and record system reactions to changes in conditions. Record default set points if different from indicated values.

3.2 PREPARATION

A. Prepare a TAB plan that includes the following:

1. Equipment and systems to be tested.

2. Strategies and step-by-step procedures for balancing the systems.

3. Instrumentation to be used.

4. Sample forms with specific identification for all equipment.

B. Perform system-readiness checks of HVAC systems and equipment to verify system readiness for TAB work. Include, at a minimum, the following:

1. Airside:

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 5

a. Verify that leakage and pressure tests on air distribution systems have been satisfactorily completed.

b. Duct systems are complete with terminals installed.

c. Volume, smoke, and fire dampers are open and functional.

d. Clean filters are installed.

e. Fans are operating, free of vibration, and rotating in correct direction.

f. Variable-frequency controllers' startup is complete and safeties are verified.

g. Automatic temperature-control systems are operational.

h. Ceilings are installed.

i. Windows and doors are installed.

j. Suitable access to balancing devices and equipment is provided.

3.3 GENERAL PROCEDURES FOR TESTING AND BALANCING

A. Perform testing and balancing procedures on each system according to the procedures contained in SMACNA's "HVAC Systems - Testing, Adjusting, and Balancing" and in this Section.

B. Cut insulation, ducts, pipes, and equipment cabinets for installation of test probes to the minimum extent necessary for TAB procedures.

1. After testing and balancing, patch probe holes in ducts with same material and thickness as used to construct ducts.

2. After testing and balancing, install test ports and duct access doors that comply with requirements in Section 233300 "Air Duct Accessories."

3. Install and join new insulation that matches removed materials. Restore insulation, coverings, vapor barrier, and finish according to Section 230713 "Duct Insulation," Section 230716 "HVAC Equipment Insulation," and Section 230719 "HVAC Piping Insulation."

C. Mark equipment and balancing devices, including damper-control positions, valve position indicators, fan-speed-control levers, and similar controls and devices, with paint or other suitable, permanent identification material to show final settings.

D. Take and report testing and balancing measurements in inch-pound (IP) units.

3.4 GENERAL PROCEDURES FOR BALANCING AIR SYSTEMS

A. Prepare test reports for both fans and outlets. Obtain manufacturer's outlet factors and recommended testing procedures. Cross-check the summation of required outlet volumes with required fan volumes.

B. Prepare schematic diagrams of systems' "as-built" duct layouts.

C. For variable-air-volume systems, develop a plan to simulate diversity.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 6

D. Determine the best locations in main and branch ducts for accurate duct-airflow measurements.

E. Check airflow patterns from the outdoor-air louvers and dampers and the return- and exhaust-air dampers through the supply-fan discharge and mixing dampers.

F. Locate start-stop and disconnect switches, electrical interlocks, and motor starters.

G. Verify that motor starters are equipped with properly sized thermal protection.

H. Check dampers for proper position to achieve desired airflow path.

I. Check for airflow blockages.

J. Check condensate drains for proper connections and functioning.

K. Check for proper sealing of air-handling-unit components.

L. Verify that air duct system is sealed as specified in Section 233113 "Metal Ducts."

3.5 PROCEDURES FOR CONSTANT-VOLUME AIR SYSTEMS

A. Adjust fans to deliver total indicated airflows within the maximum allowable fan speed listed by fan manufacturer.

1. Measure total airflow.

a. Set outside-air, return-air, and relief-air dampers for proper position that simulates minimum outdoor-air conditions.

b. Where duct conditions allow, measure airflow by Pitot-tube traverse. If necessary, perform multiple Pitot-tube traverses to obtain total airflow.

c. Where duct conditions are not suitable for Pitot-tube traverse measurements, a coil traverse may be acceptable.

d. If a reliable Pitot-tube traverse or coil traverse is not possible, measure airflow at terminals and calculate the total airflow.

2. Measure fan static pressures as follows:

a. Measure static pressure directly at the fan outlet or through the flexible connection.

b. Measure static pressure directly at the fan inlet or through the flexible connection.

c. Measure static pressure across each component that makes up the air-handling system.

d. Report artificial loading of filters at the time static pressures are measured.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 7

3. Review Record Documents to determine variations in design static pressures versus actual static pressures. Calculate actual system-effect factors. Recommend adjustments to accommodate actual conditions.

4. Obtain approval from Architect for adjustment of fan speed higher or lower than indicated speed. Comply with requirements in HVAC Sections for air-handling units for adjustment of fans, belts, and pulley sizes to achieve indicated air-handling-unit performance.

5. Do not make fan-speed adjustments that result in motor overload. Consult equipment manufacturers about fan-speed safety factors. Modulate dampers and measure fan-motor amperage to ensure that no overload occurs. Measure amperage in full-cooling, full-heating, economizer, and any other operating mode to determine the maximum required brake horsepower.

B. Adjust volume dampers for main duct, submain ducts, and major branch ducts to indicated airflows.

1. Measure airflow of submain and branch ducts.

2. Adjust submain and branch duct volume dampers for specified airflow.

3. Re-measure each submain and branch duct after all have been adjusted.

C. Adjust air inlets and outlets for each space to indicated airflows.

1. Set airflow patterns of adjustable outlets for proper distribution without drafts.

2. Measure inlets and outlets airflow.

3. Adjust each inlet and outlet for specified airflow.

4. Re-measure each inlet and outlet after they have been adjusted.

D. Verify final system conditions.

1. Re-measure and confirm that minimum outdoor, return, and relief airflows are within design. Readjust to design if necessary.

2. Re-measure and confirm that total airflow is within design.

3. Re-measure all final fan operating data, rpms, volts, amps, and static profile.

4. Mark all final settings.

5. Test system in economizer mode. Verify proper operation and adjust if necessary.

6. Measure and record all operating data.

7. Record final fan-performance data.

3.6 PROCEDURES FOR MOTORS

A. Motors 1/2 HP and Larger: Test at final balanced conditions and record the following data:

1. Manufacturer's name, model number, and serial number.

2. Motor horsepower rating.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 8

3. Motor rpm.

4. Phase and hertz.

5. Nameplate and measured voltage, each phase.

6. Nameplate and measured amperage, each phase.

7. Starter size and thermal-protection-element rating.

8. Service factor and frame size.

B. Motors Driven by Variable-Frequency Controllers: Test manual bypass of controller to prove proper operation.

3.7 PROCEDURES FOR CONDENSING UNITS

A. Verify proper rotation of fans.

B. Measure entering- and leaving-air temperatures.

C. Record fan and motor operating data.

3.8 PROCEDURES FOR HEAT-TRANSFER COILS

A. Measure, adjust, and record the following data for each water coil:

1. Entering- and leaving-water temperature.

2. Water flow rate.

3. Water pressure drop for major (more than 20 gpm) equipment coils, excluding unitary equipment such as reheat coils, unit heaters, and fan-coil units.

4. Dry-bulb temperature of entering and leaving air.

5. Wet-bulb temperature of entering and leaving air for cooling coils.

6. Airflow.

B. Measure, adjust, and record the following data for each electric heating coil:

1. Nameplate data.

2. Airflow.

3. Entering- and leaving-air temperature at full load.

4. Voltage and amperage input of each phase at full load.

5. Calculated kilowatt at full load.

6. Fuse or circuit-breaker rating for overload protection.

C. Measure, adjust, and record the following data for each refrigerant coil:

1. Dry-bulb temperature of entering and leaving air.

2. Wet-bulb temperature of entering and leaving air.

3. Airflow.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 9

3.9 CONTROLS VERIFICATION

A. In conjunction with system balancing, perform the following:

1. Verify temperature control system is operating within the design limitations.

2. Confirm that the sequences of operation are in compliance with Contract

Documents.

3. Verify that controllers are calibrated and function as intended.

4. Verify that controller set points are as indicated.

5. Verify the operation of lockout or interlock systems.

6. Verify the operation of valve and damper actuators.

7. Verify that controlled devices are properly installed and connected to correct controller.

8. Verify that controlled devices travel freely and are in position indicated by controller: open, closed, or modulating.

9. Verify location and installation of sensors to ensure that they sense only intended temperature, humidity, or pressure.

B. Reporting: Include a summary of verifications performed, remaining deficiencies, and variations from indicated conditions.

3.10 TOLERANCES

A. Set HVAC system's airflow rates and water flow rates within the following tolerances:

1. Supply, Return, and Exhaust Fans and Equipment with Fans: Plus or minus 10 percent, except as required to maintain building pressurization as designed.

2. Air Outlets and Inlets: Plus or minus 10 percent.

3. Heating-Water Flow Rate: Plus or minus 10 percent.

4. Cooling-Water Flow Rate: Plus or minus 10 percent.

B. Maintaining pressure relationships as designed shall have priority over the tolerances specified above.

3.11 PROGRESS REPORTING

A. Initial Construction-Phase Report: Based on examination of the Contract Documents as specified in "Examination" Article, prepare a report on the adequacy of design for systems balancing devices. Recommend changes and additions to systems balancing devices to facilitate proper performance measuring and balancing. Recommend changes and additions to HVAC systems and general construction to allow access for performance measuring and balancing devices.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 10

3.12 FINAL REPORT

A. General: Prepare a certified written report; tabulate and divide the report into separate sections for tested systems and balanced systems.

1. Include a certification sheet at the front of the report's binder, signed and sealed by the certified testing and balancing engineer.

2. Include a list of instruments used for procedures, along with proof of calibration.

3. Certify validity and accuracy of field data.

B. Final Report Contents: In addition to certified field-report data, include the following:

1. Pump curves.

2. Fan curves.

3. Manufacturers' test data.

4. Field test reports prepared by system and equipment installers.

5. Other information relative to equipment performance; do not include Shop

Drawings and Product Data.

C. General Report Data: In addition to form titles and entries, include the following data:

1. Title page.

2. Name and address of the TAB specialist.

3. Project name.

4. Project location.

5. Architect's name and address.

6. Engineer's name and address.

7. Contractor's name and address.

8. Report date.

9. Signature of TAB supervisor who certifies the report.

10. Table of Contents with the total number of pages defined for each section of the report. Number each page in the report.

11. Summary of contents including the following:

a. Indicated versus final performance.

b. Notable characteristics of systems.

c. Description of system operation sequence if it varies from the Contract

Documents.

12. Nomenclature sheets for each item of equipment.

13. Data for terminal units, including manufacturer's name, type, size, and fittings.

14. Notes to explain why certain final data in the body of reports vary from indicated values.

15. Test conditions for fans and pump performance forms including the following:

a. Settings for outdoor-, return-, and exhaust-air dampers.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 11

b. Conditions of filters.

c. Cooling coil, wet- and dry-bulb conditions.

d. Face and bypass damper settings at coils.

e. Fan drive settings including settings and percentage of maximum pitch diameter.

f. Inlet vane settings for variable-air-volume systems.

g. Settings for supply-air, static-pressure controller.

h. Other system operating conditions that affect performance.

D. System Diagrams: Include schematic layouts of air and hydronic distribution systems.

Present each system with single-line diagram and include the following:

1. Quantities of outdoor, supply, return, and exhaust airflows.

2. Water and steam flow rates.

3. Duct, outlet, and inlet sizes.

4. Pipe and valve sizes and locations.

5. Terminal units.

6. Balancing stations.

7. Position of balancing devices.

E. Air-Handling-Unit Test Reports: For air-handling units with coils, include the following:

1. Unit Data:

a. Unit identification.

b. Location.

c. Make and type.

d. Model number and unit size.

e. Manufacturer's serial number.

f. Unit arrangement and class.

g. Discharge arrangement.

h. Sheave make, size in inches, and bore.

i. Center-to-center dimensions of sheave and amount of adjustments in inches.

j. Number, make, and size of belts.

k. Number, type, and size of filters.

2. Motor Data:

a. Motor make, and frame type and size.

b. Horsepower and rpm.

c. Volts, phase, and hertz.

d. Full-load amperage and service factor.

e. Sheave make, size in inches, and bore.

f. Center-to-center dimensions of sheave and amount of adjustments in inches.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 12

3. Test Data (Indicated and Actual Values):

a. Total airflow rate in cfm.

b. Total system static pressure in inches wg.

c. Fan rpm.

d. Discharge static pressure in inches wg.

e. Filter static-pressure differential in inches wg.

f. Preheat-coil static-pressure differential in inches wg.

g. Cooling-coil static-pressure differential in inches wg.

h. Heating-coil static-pressure differential in inches wg.

i. Outdoor airflow in cfm.

j. Return airflow in cfm.

k. Outdoor-air damper position.

l. Return-air damper position.

F. Apparatus-Coil Test Reports:

1. Coil Data:

a. System identification.

b. Location.

c. Coil type.

d. Number of rows.

e. Fin spacing in fins per inch o.c.

f. Make and model number.

g. Face area in sq. ft..

h. Tube size in NPS.

i. Tube and fin materials.

j. Circuiting arrangement.

2. Test Data (Indicated and Actual Values):

a. Airflow rate in cfm.

b. Average face velocity in fpm.

c. Air pressure drop in inches wg.

d. Outdoor-air, wet- and dry-bulb temperatures in deg F.

e. Return-air, wet- and dry-bulb temperatures in deg F.

f. Entering-air, wet- and dry-bulb temperatures in deg F.

g. Leaving-air, wet- and dry-bulb temperatures in deg F.

h. Water flow rate in gpm.

i. Water pressure differential in feet of head or psig.

j. Entering-water temperature in deg F.

k. Leaving-water temperature in deg F.

l. Refrigerant expansion valve and refrigerant types.

m. Refrigerant suction pressure in psig.

n. Refrigerant suction temperature in deg F.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 13

o. Inlet steam pressure in psig.

G. Fan Test Reports: For supply, return, and exhaust fans, include the following:

1. Fan Data:

a. System identification.

b. Location.

c. Make and type.

d. Model number and size.

e. Manufacturer's serial number.

f. Arrangement and class.

g. Sheave make, size in inches, and bore.

h. Center-to-center dimensions of sheave and amount of adjustments in inches.

2. Motor Data:

a. Motor make, and frame type and size.

b. Horsepower and rpm.

c. Volts, phase, and hertz.

d. Full-load amperage and service factor.

e. Sheave make, size in inches, and bore.

f. Center-to-center dimensions of sheave, and amount of adjustments in inches.

g. Number, make, and size of belts.

3. Test Data (Indicated and Actual Values):

a. Total airflow rate in cfm.

b. Total system static pressure in inches wg.

c. Fan rpm.

d. Discharge static pressure in inches wg.

e. Suction static pressure in inches wg.

H. Air-Terminal-Device Reports:

1. Unit Data:

a. System and air-handling unit identification.

b. Location and zone.

c. Apparatus used for test.

d. Area served.

e. Make.

f. Number from system diagram.

g. Type and model number.

h. Size.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 14

i. Effective area in sq. ft..

2. Test Data (Indicated and Actual Values):

a. Airflow rate in cfm.

b. Air velocity in fpm.

c. Preliminary airflow rate as needed in cfm.

d. Preliminary velocity as needed in fpm.

e. Final airflow rate in cfm.

f. Final velocity in fpm.

g. Space temperature in deg F.

I. Instrument Calibration Reports:

1. Report Data:

a. Instrument type and make.

b. Serial number.

c. Application.

d. Dates of use.

e. Dates of calibration.

3.13 VERIFICATION OF TAB REPORT

A. The TAB specialist's test and balance engineer shall conduct the inspection in the presence of Government and commissioning authority.

B. Government or Commissioning authority shall randomly select measurements, documented in the final report, to be rechecked. Rechecking shall be limited to either 10 percent of the total measurements recorded or the extent of measurements that can be accomplished in a normal 8-hour business day.

C. If rechecks yield measurements that differ from the measurements documented in the final report by more than the tolerances allowed, the measurements shall be noted as

"FAILED."

D. If the number of "FAILED" measurements is greater than 10 percent of the total measurements checked during the final inspection, the testing and balancing shall be considered incomplete and shall be rejected.

E. If TAB work fails, proceed as follows:

1. TAB specialists shall recheck all measurements and make adjustments. Revise the final report and balancing device settings to include all changes; resubmit the final report and request a second final inspection.

TESTING, ADJUSTING, AND BALANCING FOR HVAC 230593 - 15

2. If the second final inspection also fails, Government may contract the services of another TAB specialist to complete TAB work according to the Contract Documents and deduct the cost of the services from the original TAB specialist's final payment.

3. If the second verification also fails, design professional may contact AABC Headquarters regarding the AABC National Performance Guaranty.

F. Prepare test and inspection reports.

3.14 ADDITIONAL TESTS

A. Within 90 days of completing TAB, perform additional TAB to verify that balanced conditions are being maintained throughout and to correct unusual conditions.

B. Seasonal Periods: If initial TAB procedures were not performed during near-peak summer and winter conditions, perform additional TAB during near-peak summer and winter conditions.

END OF SECTION 230593

This page intentionally left blank

187th Fighter Wing, Danelly Field ANG, Montgomery, AL

SSL# 18073 / ANG# FAKZ182351

ELECTRICAL Section 260100-1

SECTION 260100

ELECTRICAL

PART 1 - GENERAL

1.01. RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including requirement of the Government’s Solicitation and Division I specification sections apply to work specified in this section.

1.02. QUALIFICATIONS OF ELECTRICAL CONTRACTORS:

A. Electrical contractor must be properly established as an electrical contractor by the State of Alabama. Electrical contractor shall have had previous experience in the satisfactory installation of at least three systems of this type and size in the State of Alabama.

1.03. CODES, PERMITS AND INSPECTIONS:

A. Comply with applicable laws of the community, with latest edition of National Electrical Code (NEC), NFC 70, and the International Building Code(IBCC) or the edition adopted by the local authority having jurisdiction, where not in conflict with those laws, and with the service rules of the local utility company.

B. Obtain and pay for all permits and deposits, and arrange for inspections as required.

C. After completion of the work, submit certificate of final inspection and approval from the local electrical inspector, certifying that the installation complies with all regulations governing same.

1.04. MATERIALS:

A. All materials shall be new, and UL approved where a standard has been established.

B. Material substitutions will be considered only when evidence of equality and suitability, satisfactory to the Government has been presented in writing, with samples if requested by the Government.

C. It shall be understood that the Government has the authority to reject any material or equipment used which is not specified or approved, or showing defects of manufacture or workmanship, before or after such material or equipment is installed.

D. All materials shall be made in the United States. (ADD d-5/17/22)

1.05. WORKMANSHIP:

A. Execute all work so as to present a neat and workmanlike appearance when completed.

1.06. DESCRIPTION OF WORK:

A. Furnish all labor and materials required to complete the electrical work indicated on the drawings or herein specified. Major work included in Section 16 shall be:

B. Remove or relocate all electrical or electronic services located on or crossing through the project property, either above or below grade, which would obstruct the

Revised 14 May, 2022

ELECTRICAL Section 260100-2 construction of the project or conflict in any manner with the complete project or any code pertaining thereto.

C. Furnish and install a complete electrical light and power system including but not limited to the connection of all meters, switchboards, panelboards, circuit breakers, power outlets, convenience outlets, lighting fixtures, switches, and/or other equipment forming part of the electrical system.

D. Furnish and install a complete system of CAT 6 cables, communications outlets, patch panels, outlet boxes, face plates, conduit raceways, etc. for the communications system.

The contractor shall use the existing infrastructure and add patch panels to existing racks and add patch panel and communications cable and outlet as required for a complete and operational system.

E. Connect all electrical equipment whether furnished by this contractor or by others.

F. Furnish and install all disconnect switches not included as an integral part of equipment.

G. The contractor shall inspect repair and re-certify existing lightning protection system.

H. Once the new service entrance and grounding system is completed the contractor shall furnish ground resistance testing for the new grounding system. Provide test results to engineer for evaluation and acceptance.

I. Furnish and install a complete Lighting Control System. (ADD d-5/17/22)

J. Furnish and install a complete Fire Alarm/Mass Notification System compliant with applicable provisions of UFC 4-021-01 and the National Fire Protection Association (NFPA) Standard No. 72.

K. Provide review and necessary modifications to the building lightning protection system.

(LPS). The contractor shall engage a registered professional engineer whose area of practice includes lighting protection systems. The engineer shall review the existing building lightning protection design as well as the new building plans and provide a new LPS design for the building. This plan shall include repair of existing system components as well as providing additional components required by the building modifications indicated in the Governmentural, structural, mechanical, electrical, and plumbing plans. The new design arrived at by the LPS engineer shall be implemented by the electrical contractor as part of this project. (ADD d-5/17/22)

L. Complete the alterations, additions, and renovations to the electrical system in the existing building as specified herein or as shown on the drawings.

M. Procure and pay for permits and certifications as required by local and state ordinances and Fire Underwriters certificate of inspection.

N. Visit the site and determine conditions that affect this contract. Failure to do so will in no way relieve the Contractor of his responsibility under his contract.

O. Submit to the Government a certificate of final inspection from local and/or state inspection authorities.

P. Establish and maintain temporary electrical services for construction purposes.

1.07. DRAWINGS AND SPECIFICATIONS:

ELECTRICAL Section 260100-3

A. This Contractor shall examine drawings and Specifications relating to the work of all trades and become fully informed as to the extent and character of work required and its relation to all other work in the project prior to submission of bid and prior to the start of any construction.

B. Drawings and Specifications shall be considered as complementary each to the other.

What is called for by one shall be as binding as if called for by both. Where conflicts occur, secure clarification from the Government in advance of bidding; otherwise incorporate the more stringent conditions into the bid price.

C. Omissions from the drawings and specifications or the mis-description of details of work which are evidently necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omissions and details of work; they shall be performed as if fully and correctly set forth and described in the drawings and specifications

D. The drawings indicate diagrammatically the extent, general character, and the approximate location of the work to be performed. In the interest of clearness, the work is not always shown to scale or exact location. Check all measurements, locations of conduit, fixtures, outlets, and equipment with the detailed Architectural, structural, and mechanical drawings, and lay out work so as to fit in with ceiling grids, ductwork, sprinkler piping and heads, and other parts. Take finished dimensions at the job site in preference to using scale dimensions.

E. Where the work is indicated but with minor details omitted, furnish and install the work complete so as to perform its intended functions.

F. Where doubt arises as to the meaning of the plans and specifications, obtain the Government's decision before proceeding with parts affected; otherwise assume liability for damage to other work and for making necessary corrections to work in question.

G. Except as noted above, make no changes in or deviations from the work as shown or specified except on written order of the Government.

1.08. EXISTING CONDITIONS:

A. Before submitting a bid, visit the site and ascertain all existing conditions.

B. Make such adjustments in work as are required by the actual conditions encountered.

C. No consideration will be given after bid opening for alleged misunderstandings regarding utility connections, integration of work with existing system, or other existing conditions.

1.09. SUBMITTALS:

A. Follow procedure outlined in Division 1.

B. Submittals shall be bound together and shall include a coversheet indicating the following:

1. Project name

2. Trade contractor’s name

3. Supplier’s name

4. Name and phone number of supplier’s contact person

ELECTRICAL Section 260100-4

5. A list of each item submitted with manufacturers’ names and model numbers.

C. Within 20 days of award of contract and prior to beginning any work on the project submit six (6) copies of manufacturer's drawings/data sheets for the following items to the Engineer for review:

1. Conductors

2. Cable Pulling tensions. Provide cable pull tension calculations (lateral and longitudinal) on all…

This is the start of the file's text. The full file is on GovTribe.