Paint Booth SOW - Appendix B - Summary of Available Utilities within Hangar 253_v2_Addendum_JUN_26_2020.pdf

PDF 102 KB Posted

Attached to
Paint Booth- W508S8A -20-Q-0005
Solicitation number
W508SA
Issued by

About this file

This document includes a statement of work and solicitation for a paint booth and installation services. The New Hampshire Army National Guard requires a paint booth under CLIN 0001 and installation services under CLIN 0002 to meet the stated requirement. Quotes are due by the date specified in the solicitation. The solicitation number is W508S8A-20-Q-0005 and is set aside 100% for small business. A site visit is recommended and will be held the week of June 8, 2020 at Pease Air National Guard Base in Newington, New Hampshire. The government intends to evaluate offers and award without discussions to the responsible offeror whose quote is most advantageous based on past performance, technical approach, and price. The selected contractor must comply with the provided provisions and clauses.

View the file

Other files

File Type Posted
RFI Tracker Ver_4_Final_RFI_21___JULY_1_2020.pdf PDF
Paint Booth SOW - Appendix F - Hazardous Materials Building Inspection KC-46A Fuel Cell Hangar B253_JUN_26_2020.pdf PDF
52.212-3 Offeror Representations and Certifications-Commercial Items. _JUN_26_2020.pdf PDF
Paint Booth SOW - Appendix G - Asbestos Test Report_Corr Metal Siding B253_JUn_26_2020.pdf PDF
Paint Booth SOW - Appendix A - Hangar 253 Building Plans (Abridged Set for Paint Booth Installation)_v4_Addendum_JUN_26_2020.pdf PDF
Paint Booth SOW - Appendix H - Compressed Air Piping Specifications B253_JUN_26_2020.pdf PDF
Paint Booth Statement of Work Final_RFI Addendum_JUN_26_2020.pdf PDF
Paint Booth SOW - Appendix A1 - Hangar 253 Building Plans (Supplemental Drawings for Addendum)_JUN_26_2020.pdf PDF
RFI Tracker Ver_3_Final_Comments_JUN_26_2020.pdf PDF
Sign in Sheet_JUNE_10_2020.pdf PDF
Site Visit Info_Paint Booth_Wed_June_10_2020.docx DOCX document
Paint Booth SOW - Appendix A - Hangar 253 Building Plans (Abridged Set for Paint Booth Installation)_v3.pdf PDF
Paint Booth SOW - Appendix B - Summary of Available Utilities within Hangar 253.pdf PDF
Paint Booth Statement of Work 12MAR20.pdf PDF
Paint Booth SOW - Appendix E - FP Hydraulic Calc Revisions 11.30.2018 [Submittal]_Abridged.pdf PDF
Paint Booth SOW - Appendix C - NHDES Air Permit Application.doc DOC document
Paint Booth SOW - Appendix E - FP Hydraulic Calc Revisions 11.30.2018 [Submittal].pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX B – SUMMARY OF AVAILABLE UTILITIES WITHIN HANGAR 253

Revised 6/25/2020, all changes in RED

Provided at Rm 129 1 ½ inch gas line @ north wall 1 inch Compressed Air/Tool Lines at east and west walls ¾ inch domestic cold water supply pipe at west wall of Rm 129 Floor Drain located at north/center of room for potential Eye Wash/Shower drain Electrical service (all located along west wall):

• Panel HP-2 (480/277V 3Ph/4Wire, 200A main circuit breaker) o 15A 3-pole previously for Blast Booth Claim System (3HP) (Unused) o 15A 3-pole previously for Blast Booth Dry Honer (2HP) (Unused) o 20A 1-pole spare o 20A 3-pole spare

• Panel HP-4 (480/277V 3Ph/4Wire, 150A main circuit breaker) o 60A 3-pole previously for Despatch Oven Rm 129 (Unused) o 25A 3-pole spare o 25A 3-pole spare

• Panel LP-2 (208/120V)

• Panel LP-2A (208/120V)

Fire sprinkler system w/ drain/test valve located in the southeast corner of Rm 129 (capacity calculation needed for Paint Booth requirement)

• Surrounding Room Fire Suppression/Alarms – HC-2 coverage provided, 0.2GPM/SQFT @ Design Area of 2,500SF

Provided Elsewhere in Bldg 253 Electrical capacity at Panel RDP-1 (480/277V 3Ph/4Wire) in Room 147 of Bldg 253, depicted as Room B on drawing AE-101:

• 70A 3-pole for Blast Booth Exhaust Fan (20HP) planned at Rm 120 (Circuit breaker installed/wiring not installed)

• 100A 3-pole spare

• 70A 3-pole for Paint Booth Exhaust Fan (20HP) planned at Rm 120 (Circuit breaker installed/wiring not installed)

Compressed Air-Breathing Air (closest breathing air supply is at CTK Rm 123 or at Mechanical Mezzanine above and west of Room 129)