Utility Status Report - AC-830579.pdf

PDF 171 KB Posted

Attached to
Landslide Repairs in Lares, Puerto Rico
Solicitation number
693C73-24-B-000011
Issued by

About this file

This document is a Utility Status Report for the Landslide and Road Damage Evaluation and Repair Recommendations project, which is part of the larger federal contract opportunity for Landslide Repairs in Lares, Puerto Rico.

The Utility Status Report provides details on the existing utilities located along PR-124 roadway within the project limits of Group-B, Sites B, C, and D. It identifies the utilities present, including water, telephone, and electric lines, and indicates that no utility relocations are currently proposed. The report lists the utility company names, contact information, and other design details. This information is important for understanding the existing infrastructure and any potential impacts to the planned landslide and road repair work under the overall federal contract opportunity.

View the file

Other files

File Type Posted
Results of Bid Opening - PR ER DOT PRMNT RPR(21).pdf PDF
Amendment 0003 - PR ER DOT PRMNT RPR(21).pdf PDF
Amendment 0003 - PR ER DOT PRMNT RPR(21).pdf PDF
Amendment 0002 - PR ER DOT PRMNT RPR(21).pdf PDF
Amendment 0001 - PR ER DOT PRMNT RPR(21).pdf PDF
ADV_Bidders Qualifications Form.doc DOC document
Technical Report - AC-831579_HWY-136.pdf PDF
Hydrologic-Hidraulic Analysis Report - AC-831579.pdf PDF
Lead Report - AC-901579_Hwy-107.pdf PDF
Lead Report - AC-901579_Hwy-107_Certification.pdf PDF
Utility Status Report - AC-901579.pdf PDF
Technical Report - AC-831579_HWY-134.pdf PDF
DTOPs Manual de Senales de Transito (MST).pdf PDF
Technical Report - AC-831579_HWY-135.pdf PDF
Geotechnical Report - AC-831579_Hwy-137.pdf PDF
Categorical Exclusion Form (NEPA) - Sch A_AC-831579_Hwy-133-140.pdf PDF
Hydrologic-Hidraulic Analysis Report - AC-830579_Hwy-106_Appendix B.pdf PDF
Plans - PR ER DOT PRMNT RPR(21) - Set_Sch B_AC-830579_Hwy-106_108.pdf PDF
Utility Status Report - AC-831579.pdf PDF
Geotechnical Report - AC-830579_Hwy-106.pdf PDF
PRHTAs Standard Specifications for Road and Bridge Construction.pdf PDF
PRHTAs Standard Drawings.pdf PDF
Plans - PR ER DOT PRMNT RPR(21) - Set_Sch A_AC-831579_Hwy-133-140_part 1 of 3.pdf PDF
Geotechnical Report - AC-831579_Hwy-136.pdf PDF
Asbestos Report - AC-901579_Hwy-107.pdf PDF
Hydrologic-Hidraulic Analysis Report - AC-830579_Hwy-108_Appendix C.pdf PDF
Geotechnical Report - AC-831579_Hwy-134.pdf PDF
Lead and Asbestos Report - AC-831579.pdf PDF
Technical Report - AC-830579_HWY-108.pdf PDF
USFWS Conservation Measures.pdf PDF
VETS-4212 Form.pdf PDF
Technical Report - AC-831579_HWY-133.pdf PDF
Asbestos Report - AC-901579_Hwy-107_Certification.pdf PDF
Technical Report - AC-830579_HWY-106.pdf PDF
Hydrologic-Hidraulic Analysis Report - AC-830579.pdf PDF
Geotechnical Report - AC-831579_Hwy-140.pdf PDF
Technical Report - AC-831579_HWY-140.pdf PDF
AC-901579_ LUMA Letter and Conctruction.pdf PDF
Plans - PR ER DOT PRMNT RPR(21) - Set_Sch A_AC-831579_Hwy-133-140_part 2 of 3.pdf PDF
Lead and Asbestos Report - AC-830579.pdf PDF
Technical Report - AC-901579_HWY-107.pdf PDF
Geotechnical Report - AC-831579_Hwy-135.pdf PDF
Categorical Exclusion Form (NEPA) - Sch B_AC-830579_Hwy-106_108.pdf PDF
Geotechnical Report - AC-831579_Hwy-133.pdf PDF
IFB Solicitation - PR ER DOT PRMNT RPR(21).pdf PDF
PRHTAs Material Testing Schedule.pdf PDF
PRHTAs Standard Drawings_Revised GABI Drawings_GABI 9-10.pdf PDF
Geotechnical Report - AC-830579_Hwy-108.pdf PDF
Plans - PR ER DOT PRMNT RPR(21) - Set_Sch A_AC-831579_Hwy-133-140_part 3 of 3.pdf PDF
Plans - PR ER DOT PRMNT RPR(21) - Set_Sch B_AC-901579_Hwy-107.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Utility Status Report

EFL-FM-UTL-01(07)Page 1 of 2

Project : Landslide and Road Damage Evaluation and Repair Recommendations/Group-B/site-B Date: Aug 5, 2022

Preparer : José A. Batlle y Asociados, CSP PM : Jessie Agosto, CSA Group HDM :

Review

Interval:

Preliminary (30%)

Plan In Hand (70%)

Internal (90%)

External (95%)

Final / Certification (100%)

Other :

Utilities EXIST within project limits NO utilities exist within project limits Presence of existing utilities UNKNOWN

Existing utilities [ are are not ] identified on the Plans

Utility locating requirements are included in the SCR Sections 107 and/or 645

NO utilities are proposed to be relocated✖

Utility relocation plans are described in detail below

# Location and Utility Information Design Information

Roadway Name:

PR-124

Station / Station Range:

2+00 to 3+10.71

Left of CL Right of CL Both●

Type and/or Size Facility (** See Legend)

Type: W Size/Pole No. 2"φ

Utility Company Name:

A.A.A.

Primary Contact - Name & Number:

Detailed listing of Utilities on Project Plans

Additional Contact Information

Utility to participate in PreCon Meeting

Design Responsibility:

Payment Responsibility:

Responsible Party:

Work Completed:

Cost Estimate:

Date of Contract or Agreement: N/A

Remarks / Description of Relocation:

N/A

Roadway Name:

PR-124

Station / Station Range:

2+00 to 3+10.71

Left of CL Right of CL Both●

Type and/or Size Facility (** See Legend)

Type: T Size/Pole No.

Utility Company Name:

P.R.T.C.

Primary Contact - Name & Number:

Detailed listing of Utilities on Project Plans

Additional Contact Information

Utility to participate in PreCon Meeting

Design Responsibility:

Payment Responsibility:

Responsible Party:

Work Completed:

Cost Estimate:

Date of Contract or Agreement: N/A

Remarks / Description of Relocation:

N/A

General Information :

Group-B / Site-B PR-124, km 2.4

EFL-FM-UTL-01(07)Page 2 of 2

**P=Pole, T=buried Tel. Cable, TC=Tel Conduit, PD=Pedestal, G=Gas, W=Water, S=Sewer, SS=Storm Sewer, SFM=Sewer Force Main, MH=Manhole, TV=Buried Cable TV, FO=Fiber Optic, UE=Underground Electric, Other=See Remarks

Project : Landslide and Road Damage Evaluation and Repair Recommendations/Group-B/site-C Date: Aug 5, 2022

Preparer : José A. Batlle y Asociados, CSP PM : Jessie Agosto, CSA Group HDM :

Review

Interval:

Preliminary (30%)

Plan In Hand (70%)

Internal (90%)

External (95%)

Final / Certification (100%)

Other :

Utilities EXIST within project limits NO utilities exist within project limits Presence of existing utilities UNKNOWN

Existing utilities [ are are not ] identified on the Plans

Utility locating requirements are included in the SCR Sections 107 and/or 645

NO utilities are proposed to be relocated✖

Utility relocation plans are described in detail below

# Location and Utility Information Design Information

Roadway Name:

PR-124

Station / Station Range:

22+00 to 23+00

Left of CL Right of CL Both●

Type and/or Size Facility (** See Legend)

Type: W Size/Pole No. 4"φ

Utility Company Name:

A.A.A.

Primary Contact - Name & Number:

Detailed listing of Utilities on Project Plans

Additional Contact Information

Utility to participate in PreCon Meeting

Design Responsibility:

Payment Responsibility:

Responsible Party:

Work Completed:

Cost Estimate:

Date of Contract or Agreement: N/A

Remarks / Description of Relocation:

N/A

Roadway Name:

PR-124

Station / Station Range:

22+00 to 23+00

Left of CL Right of CL● Both

Type and/or Size Facility (** See Legend)

Type: T Size/Pole No.

Utility Company Name:

P.R.T.C.

Primary Contact - Name & Number:

Detailed listing of Utilities on Project Plans

Additional Contact Information

Utility to participate in PreCon Meeting

Design Responsibility:

Payment Responsibility:

Responsible Party:

Work Completed:

Cost Estimate:

Date of Contract or Agreement: N/A

Remarks / Description of Relocation:

N/A

# Location and Utility Information Design Information

Roadway Name:

PR-124

Station / Station Range:

22+00 to 23+00

Left of CL Right of CL Both●

Type and/or Size Facility (** See Legend)

Type: P Size/Pole No.

Utility Company Name:

P.R.E.P.A.

Primary Contact - Name & Number:

Detailed listing of Utilities on Project Plans

Additional Contact Information

Utility to participate in PreCon Meeting

Design Responsibility:

Payment Responsibility:

Responsible Party:

Work Completed:

Cost Estimate:

Date of Contract or Agreement: N/A

Remarks / Description of Relocation:

N/A

General Information :

Group-B / Site-C PR-124, km 21.9

**P=Pole, T=buried Tel. Cable, TC=Tel Conduit, PD=Pedestal, G=Gas, W=Water, S=Sewer, SS=Storm Sewer, SFM=Sewer Force Main, MH=Manhole, TV=Buried Cable TV, FO=Fiber Optic, UE=Underground Electric, Other=See Remarks

Project : Landslide and Road Damage Evaluation and Repair Recommendations/Group-B/site-D Date: Aug 5, 2022

Preparer : José A. Batlle y Asociados, CSP PM : Jessie Agosto, CSA Group HDM :

Review

Interval:

Preliminary (30%)

Plan In Hand (70%)

Internal (90%)

External (95%)

Final / Certification (100%)

Other :

Utilities EXIST within project limits NO utilities exist within project limits Presence of existing utilities UNKNOWN

Existing utilities [ are are not ] identified on the Plans

Utility locating requirements are included in the SCR Sections 107 and/or 645

NO utilities are proposed to be relocated✖

Utility relocation plans are described in detail below

# Location and Utility Information Design Information

Roadway Name:

PR-124

Station / Station Range:

23+40 to 24+00

Left of CL Right of CL Both●

Type and/or Size Facility (** See Legend)

Type: W Size/Pole No. 2"φ

Utility Company Name:

A.A.A.

Primary Contact - Name & Number:

Detailed listing of Utilities on Project Plans

Additional Contact Information

Utility to participate in PreCon Meeting

Design Responsibility:

Payment Responsibility:

Responsible Party:

Work Completed:

Cost Estimate:

Date of Contract or Agreement: N/A

Remarks / Description of Relocation:

N/A

Roadway Name:

PR-124

Station / Station Range:

23+40 to 24+00

Left of CL Right of CL Both●

Type and/or Size Facility (** See Legend)

Type: T Size/Pole No.

Utility Company Name:

P.R.T.C.

Primary Contact - Name & Number:

Detailed listing of Utilities on Project Plans

Additional Contact Information

Utility to participate in PreCon Meeting

Design Responsibility:

Payment Responsibility:

Responsible Party:

Work Completed:

Cost Estimate:

Date of Contract or Agreement: N/A

Remarks / Description of Relocation:

N/A

# Location and Utility Information Design Information

Roadway Name:

PR-124

Station / Station Range:

23+40 to 24+00

Left of CL Right of CL Both●

Type and/or Size Facility (** See Legend)

Type: P Size/Pole No.

Utility Company Name:

P.R.E.P.A.

Primary Contact - Name & Number:

Detailed listing of Utilities on Project Plans

Additional Contact Information

Utility to participate in PreCon Meeting

Design Responsibility:

Payment Responsibility:

Responsible Party:

Work Completed:

Cost Estimate:

Date of Contract or Agreement: N/A

Remarks / Description of Relocation:

N/A

General Information :

Group-B / Site-D PR-124, km 23.4

**P=Pole, T=buried Tel. Cable, TC=Tel Conduit, PD=Pedestal, G=Gas, W=Water, S=Sewer, SS=Storm Sewer, SFM=Sewer Force Main, MH=Manhole, TV=Buried Cable TV, FO=Fiber Optic, UE=Underground Electric, Other=See Remarks

06 Bb-EFL-FM-UTL-01_Utility-Status-Report
06 Bc-EFL-FM-UTL-01_Utility-Status-Report
06 Bd-EFL-FM-UTL-01_Utility-Status-Report