This document is an amendment to a solicitation for the Landslide Repairs in Lares, Puerto Rico project, Solicitation Number 693C73-24-B-000011. The purpose of this amendment is to provide a summary of responses to questions and clarifications asked by potential bidders, and to reschedule the bid opening date to June 18, 2024 at 2:00 p.m. EDT.

The solicitation is for sealed bids from certified Small Business Concerns only to repair landslide and washout damages caused by Hurricanes Irma and Maria on various highways in the Lares, Puerto Rico area. The work includes embankment reconstruction, reinforced soil slope systems, gabion walls, gravity retaining walls, drainage, paving, guardrails, signage, and other related work. The project will be split into multiple work schedules/contract options, with the total project cost expected to be between $5,000,000 and $10,000,000. Bid documents should be issued on or about May 9, 2024. Prospective contractors must be registered in the System for Award Management (SAM) database prior to submitting an offer.

View the file

Other files

File Type Posted
Results of Bid Opening - PR ER DOT PRMNT RPR(21).pdf PDF
Amendment 0003 - PR ER DOT PRMNT RPR(21).pdf PDF
Amendment 0003 - PR ER DOT PRMNT RPR(21).pdf PDF
Amendment 0002 - PR ER DOT PRMNT RPR(21).pdf PDF
ADV_Bidders Qualifications Form.doc DOC document
Technical Report - AC-831579_HWY-136.pdf PDF
Hydrologic-Hidraulic Analysis Report - AC-831579.pdf PDF
Lead Report - AC-901579_Hwy-107.pdf PDF
Lead Report - AC-901579_Hwy-107_Certification.pdf PDF
Utility Status Report - AC-901579.pdf PDF
Technical Report - AC-831579_HWY-134.pdf PDF
DTOPs Manual de Senales de Transito (MST).pdf PDF
Technical Report - AC-831579_HWY-135.pdf PDF
Geotechnical Report - AC-831579_Hwy-137.pdf PDF
Categorical Exclusion Form (NEPA) - Sch A_AC-831579_Hwy-133-140.pdf PDF
Hydrologic-Hidraulic Analysis Report - AC-830579_Hwy-106_Appendix B.pdf PDF
Plans - PR ER DOT PRMNT RPR(21) - Set_Sch B_AC-830579_Hwy-106_108.pdf PDF
Utility Status Report - AC-831579.pdf PDF
Geotechnical Report - AC-830579_Hwy-106.pdf PDF
PRHTAs Standard Specifications for Road and Bridge Construction.pdf PDF
PRHTAs Standard Drawings.pdf PDF
Plans - PR ER DOT PRMNT RPR(21) - Set_Sch A_AC-831579_Hwy-133-140_part 1 of 3.pdf PDF
Geotechnical Report - AC-831579_Hwy-136.pdf PDF
Asbestos Report - AC-901579_Hwy-107.pdf PDF
Hydrologic-Hidraulic Analysis Report - AC-830579_Hwy-108_Appendix C.pdf PDF
Geotechnical Report - AC-831579_Hwy-134.pdf PDF
Lead and Asbestos Report - AC-831579.pdf PDF
Technical Report - AC-830579_HWY-108.pdf PDF
USFWS Conservation Measures.pdf PDF
VETS-4212 Form.pdf PDF
Technical Report - AC-831579_HWY-133.pdf PDF
Asbestos Report - AC-901579_Hwy-107_Certification.pdf PDF
Technical Report - AC-830579_HWY-106.pdf PDF
Hydrologic-Hidraulic Analysis Report - AC-830579.pdf PDF
Geotechnical Report - AC-831579_Hwy-140.pdf PDF
Technical Report - AC-831579_HWY-140.pdf PDF
AC-901579_ LUMA Letter and Conctruction.pdf PDF
Utility Status Report - AC-830579.pdf PDF
Plans - PR ER DOT PRMNT RPR(21) - Set_Sch A_AC-831579_Hwy-133-140_part 2 of 3.pdf PDF
Lead and Asbestos Report - AC-830579.pdf PDF
Technical Report - AC-901579_HWY-107.pdf PDF
Geotechnical Report - AC-831579_Hwy-135.pdf PDF
Categorical Exclusion Form (NEPA) - Sch B_AC-830579_Hwy-106_108.pdf PDF
Geotechnical Report - AC-831579_Hwy-133.pdf PDF
IFB Solicitation - PR ER DOT PRMNT RPR(21).pdf PDF
PRHTAs Material Testing Schedule.pdf PDF
PRHTAs Standard Drawings_Revised GABI Drawings_GABI 9-10.pdf PDF
Geotechnical Report - AC-830579_Hwy-108.pdf PDF
Plans - PR ER DOT PRMNT RPR(21) - Set_Sch A_AC-831579_Hwy-133-140_part 3 of 3.pdf PDF
Plans - PR ER DOT PRMNT RPR(21) - Set_Sch B_AC-901579_Hwy-107.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

693C7324B000011 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ASHBURN VA 20147

ATTN: Construction

693C73

SUITE E2-3-300

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

ASHBURN VA 20147

ATTN: Acquisitions

693C73

SUITE E2-3-300

QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY

EASTERN FEDERAL LANDS HIGHWAY DIVISION

FEDERAL HIGHWAY ADMINISTRATION

See Block 1406/06/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/09/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project PR ER DOT PRMNT RPR(21)

The purpose of this Amendment is to:

1) Provide a summary of responses to questions/clarifications asked by potential bidders.

2) The Bid Opening date will be rescheduled to June 18, 2024, at 2:00 p.m. EDT.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment No. 0001

Questions/Clarifications

Questions/Clarifications

Bidders can send written questions or inquiries for clarification to: eflhd.contracts@dot.gov.

Questions can be submitted at any time, but questions submitted within 10 days of the bid opening may not be answered in time for the bidder to properly incorporate the responses into their bid.

The following questions and issues were asked via email. The Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised, and some questions may not have been included. The Government’s direct response to the sender may also have been updated below for better clarity.

1. The plans specified for base footing concrete Class A 3,000 PSI (SPEC. 601) and concrete class B (SPEC. 601) for gravity wall, however, in schedule A these items are not found except for specification 934 Structural concrete class III. Please clarify which specification will be used for retaining walls.

Response: Use Specification 934, Structural Concrete, Class II (General Use) for gravity retaining walls STEM Concrete and Structural Concrete, Class III (General Use) for gravity retaining walls Base Footing Concrete. When the plans and other contract documents reference specification 601 shall be interpreted as referring to Specification 934. Refer to Subsection 934-1.01.c of the SCRs for additional information.

Contractors are required to coordinate with the CO any noted difference in the plans before proceeding with the proposed work in accordance with FAR 52.236-21. Payment will be made for the actual quantities of work performed and accepted or material furnished according to the contract. The scheduled quantities may be increased, decreased, or deleted.