USCG_NOTIFICATION_BRIDGE_PRE-CONSTRUCTION_CHECKLIST_-_JAX.pdf

PDF 300 KB Posted

Attached to
Main Street Bridge No. 794004 Repairs - Cleaning and Painting
Solicitation number
26-B-121KW
Issued by
Volusia County, Florida

About this file

This is a US Coast Guard pre-construction notification checklist and requirement document for the Main Street Bridge No. 794004 repairs project in Daytona Beach, Florida, administered by the County of Volusia Department of Public Works, Road & Bridge Division. The project involves comprehensive bridge rehabilitation including cleaning and painting of all structural steel on the bascule and flacking spans, installation of web repair plates, replacement of bolts and rivets, removal of abandoned air buffers and strike plates, and disassembly and reconditioning of bearings with grease repacking and replacement of grease fittings for the auxiliary drive machinery. The contractor must provide all labor, materials, equipment, removal and disposal services, traffic control, channel maintenance, pollution controls, environmental testing, functional checks including span balancing, operations and maintenance manuals, and restoration with as-built surveys and drawings. The Coast Guard requires 60 days advance notice prior to project start and 30 days advance notice prior to any channel obstructions, closures, or opening restrictions, with all notifications directed to Sector Jacksonville Waterways and Southeast District Bridge Administration.

The checklist establishes mandatory pre-construction requirements specific to in-water work and movable span operations. The contractor must identify all in-water equipment requiring proper lighting per Coast Guard standards, document petroleum products or hazardous materials storage and transfer, describe proposed channel restrictions or closures with specific dates and times, and specify whether any movable span opening requests require complete closure, single leaf opening, limited openings, or advance notice. Additionally, projects occurring between June and November must include a hurricane plan, with the contractor providing advance notice timelines for full channel openings and equipment movement. All in-water equipment disposition at workday end must be identified, along with points of contact for operating full openings or moving equipment to restore channel access.

View the file

Other files

File Type Posted
Main_Street_Bridge_No._794004_Repairs_-_Cleaning_and_Painting_(Addendum_#3_Revision).pdf PDF
Exhibit_G_-_Bid_Price_Sheet_-_REVISION_1.xls XLS spreadsheet
Main_Street_Bridge_No._794004_Repairs_-_Cleaning_and_Painting_(Addendum_#2_Revision).pdf PDF
Exhibit_C_-_Draft_Contract_26-B-121KW.pdf PDF
Main_Street_Bridge_No._794004_Repairs_-_Cleaning_and_Painting.pdf PDF
Bid_Price_Sheet.xls XLS spreadsheet
Metals_Analysis_Report_Volusia_County_Main_Street_Bridge_23-04-01994.pdf PDF
Draft_Contract_26-B-121KW.pdf PDF
Sales_Tax_Exemption_Procedures.pdf PDF
Technical_Specifications.pdf PDF
Construction_Plans.pdf PDF
PRIME-SUB_FORM.xls XLS spreadsheet
Required_Types_and_Limits_of_Insurance.pdf PDF
4.Construction_Plans_Main_Street_Bridge_794004_Cleaning_and_Painting_6-30-2026.pdf PDF
8._USCG_NOTIFICATION_BRIDGE_PRE-CONSTRUCTION_CHECKLIST_-_JAX.pdf PDF
6.Technical_Specification_T465_Moveable_Bridges_Main_Street_Bridge_6-30-2026.pdf PDF
7.Metals_Analysis_Report_Volusia_County_Main_Street_Bridge_23-04-01994.pdf PDF
9._PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing).xls XLS spreadsheet
5.Bid_Price_Sheet_Main_St_Bridge_794004_Cleaning_&_Painting.xls XLS spreadsheet
2.Scope_of_Work_and_General_Notes_Main_St_Bridge_No_794004.pdf PDF
3.General_Notes_Supplement_Main_St_Bridge_No_794004.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BRIDGE PRE-CONSTRUCTION NOTICE/REQUEST

Roadway/Bridge:

Waterway:

Bridge Owner:

Contractor Primary/24-Hour POC:

Project: Start Date/Time: Finish Date/Time:

Brief Project Description:

The Coast Guard requires all in-water equipment to be properly lighted. List any in-water equipment to be used:

Describe type/quantity of petroleum products or hazardous materials stored/transferred on site (if any):

Describe any proposed channel restrictions or closures and/or vertical clearance restrictions. Include dates/times of restriction(s):

On a movable span, are you requesting: Complete Closure, Single Leaf Opening, Limited Openings, Advance Notice.

Please Explain:

If Applicable:

Hurricane plan submitted for projects between June & November: Y/N How many hours advance notice needed for a full opening:

How many hours advance notice needed to move equipment to provide access to full channel:

Will in-water equipment remain in place or moved at end of workday:

POC for full opening/moving equipment:

60 days advance notice required prior to starting a project. 30 days advance notice required prior to any channel obstructions, closures, or opening restrictions. Make all notifications to Sector Jacksonville Waterways (D07-DG- SECJAX-WATERWAYS@uscg.mil) and to Southeast District Bridge Administration (Jennifer.N.Zercher@uscg.mil)

US Coast Guard Southeast District ꞏ Bridge Administration Branch (dpb) ꞏ 909 SE 1st Ave. ꞏ Miami, FL 33131

File details come from the government source that posted it. Updated .