This is a U.S. Coast Guard pre-construction notification checklist for bridge projects in the Jacksonville sector, involving coordination between the Coast Guard's Southeast District Bridge Administration, Sector Jacksonville Waterways, and local bridge owners and contractors in Florida. The checklist establishes mandatory notification and operational requirements for any bridge construction or maintenance project affecting navigable waterways. Contractors must submit 60 days advance notice prior to project start and 30 days advance notice before any channel obstructions, closures, or opening restrictions occur. The form requires detailed project information including roadway and waterway identification, in-water equipment specifications, petroleum or hazardous material storage descriptions, proposed channel restrictions or vertical clearance limitations, and operational procedures for movable spans. For movable span operations, contractors must specify whether they require complete closure, single leaf opening, limited openings, or advance notice protocols, and provide advance notice timeframes for full opening and equipment repositioning to restore channel access.

All notifications must be submitted to Sector Jacksonville Waterways (D07-DG-SECJAX-WATERWAYS@uscg.mil) and Southeast District Bridge Administration (Jennifer.N.Zercher@uscg.mil). The checklist applies to the County of Volusia's Main Street Bridge No. 794004 Repairs project in Daytona Beach, which involves cleaning and painting structural steel on bascule and flacking spans, installing web repair plates, replacing bolts and rivets, removing abandoned air buffers and strike plates, and rehabilitating auxiliary drive machinery bearings. The contractor must maintain channel traffic, implement pollution controls, conduct environmental testing, perform functional span balancing checks, and provide operations and maintenance manuals and as-built surveys upon project completion. Hurricane plans are required for projects occurring between June and November.

View the file

Other files

File Type Posted
Main_Street_Bridge_No._794004_Repairs_-_Cleaning_and_Painting_(Addendum_#3_Revision).pdf PDF
Exhibit_G_-_Bid_Price_Sheet_-_REVISION_1.xls XLS spreadsheet
Main_Street_Bridge_No._794004_Repairs_-_Cleaning_and_Painting_(Addendum_#2_Revision).pdf PDF
Exhibit_C_-_Draft_Contract_26-B-121KW.pdf PDF
Main_Street_Bridge_No._794004_Repairs_-_Cleaning_and_Painting.pdf PDF
Bid_Price_Sheet.xls XLS spreadsheet
USCG_NOTIFICATION_BRIDGE_PRE-CONSTRUCTION_CHECKLIST_-_JAX.pdf PDF
Metals_Analysis_Report_Volusia_County_Main_Street_Bridge_23-04-01994.pdf PDF
Draft_Contract_26-B-121KW.pdf PDF
Sales_Tax_Exemption_Procedures.pdf PDF
Technical_Specifications.pdf PDF
Construction_Plans.pdf PDF
PRIME-SUB_FORM.xls XLS spreadsheet
Required_Types_and_Limits_of_Insurance.pdf PDF
4.Construction_Plans_Main_Street_Bridge_794004_Cleaning_and_Painting_6-30-2026.pdf PDF
6.Technical_Specification_T465_Moveable_Bridges_Main_Street_Bridge_6-30-2026.pdf PDF
7.Metals_Analysis_Report_Volusia_County_Main_Street_Bridge_23-04-01994.pdf PDF
9._PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing).xls XLS spreadsheet
5.Bid_Price_Sheet_Main_St_Bridge_794004_Cleaning_&_Painting.xls XLS spreadsheet
2.Scope_of_Work_and_General_Notes_Main_St_Bridge_No_794004.pdf PDF
3.General_Notes_Supplement_Main_St_Bridge_No_794004.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BRIDGE PRE-CONSTRUCTION NOTICE/REQUEST

Roadway/Bridge:

Waterway:

Bridge Owner:

Contractor Primary/24-Hour POC:

Project: Start Date/Time: Finish Date/Time:

Brief Project Description:

The Coast Guard requires all in-water equipment to be properly lighted. List any in-water equipment to be used:

Describe type/quantity of petroleum products or hazardous materials stored/transferred on site (if any):

Describe any proposed channel restrictions or closures and/or vertical clearance restrictions. Include dates/times of restriction(s):

On a movable span, are you requesting: Complete Closure, Single Leaf Opening, Limited Openings, Advance Notice.

Please Explain:

If Applicable:

Hurricane plan submitted for projects between June & November: Y/N How many hours advance notice needed for a full opening:

How many hours advance notice needed to move equipment to provide access to full channel:

Will in-water equipment remain in place or moved at end of workday:

POC for full opening/moving equipment:

60 days advance notice required prior to starting a project. 30 days advance notice required prior to any channel obstructions, closures, or opening restrictions. Make all notifications to Sector Jacksonville Waterways (D07-DG- SECJAX-WATERWAYS@uscg.mil) and to Southeast District Bridge Administration (Jennifer.N.Zercher@uscg.mil)