This federal contract opportunity is for construction services to update three isolation rooms at the Cheyenne VA Medical Center located in Cheyenne, Wyoming. The project includes demolishing and updating two existing isolation rooms and constructing a new third isolation room to meet current standards. The total estimated value of the contract is between $500,000 to $1,000,000. The NAICS code for the work is 236220. The solicitation is set aside for total small business concerns owned and controlled by service-disabled veterans. The contractor must use Handicare brand lifts as specified. The contractor will be responsible for assessing the contract documents and existing site conditions, requesting any clarification needed through the contracting officer, adhering to all facility security requirements, and coordinating any necessary outages or shutdowns at least 20 days in advance with the contracting officer's representative. All work must comply with applicable codes and VA master construction specifications. The contractor must provide a final phasing plan for approval and will be responsible for any damages to VA property.

View the file

Other files

File Type Posted
36C25921R0070 0003.docx DOCX document
Additional Phasing Considerations.pdf PDF
Update Isolation Room Bid RFI 1.docx DOCX document
36C25921R0070 0002.docx DOCX document
Site Visit Attendance.pdf PDF
36C25921R0070 Corrected Pg 18.pdf PDF
36C25921R0070 0001.docx DOCX document
36C25921R0070 Full Solicitation.docx DOCX document
S02 Past Performance Questionnaire.docx DOCX document
J and A 36C259-21-AP-2342 Brand Name Lifts 442 Signed.pdf PDF
36C25921R0070_2.docx DOCX document
SELF-PERFORMED CALCULATIONS.docx DOCX document
Update Isolation Rooms 100CD Submittal Package.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Veterans Affairs

Project Number 442-20-004

(VEG 20.21)

Cheyenne VAMC Update Isolation Rooms

2360 E. PERSHING AVE, CHEYENNE, WY 82001

Building No. 1-CA

PROJECT SPECIFICATIONS

100% Construction Document - Package

March 18, 2021

750 W. HAMPDEN AVE. #300

ENGLEWOOD, CO 80110

Ph (720) 550-6307

12-20

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 12-18 01 32 16.15 Project Schedules (Small Projects – Des ign/Bid/Build 02-15 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-20 01 42 19 Reference Standards 09-19 01 45 00 Quality Control 03-19 01 45 35 Special Inspections 03-19 01 57 19 Temporary Environmental Controls 01-11 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 09-13

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 02-16

DIVISION 04 – MASONRY (NOT USED)

DIVISION 05 – METALS

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 10-17 07 53 23 Ethylene-Propylene-Diene-Monomer Roofing 0 2-16 07 56 00.01 Fluid-Applied Roofing – Silicone 05-15 07 60 00 Flashing and Sheet Metal 07-14 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021 100% Construction Documents

VA Project Number: 442-20-004

00 01 10-2

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 08-16 08 14 00 Interior Wood Doors 02-16 08 32 13 ICU Sliding Glass Doors 01-21 08 71 00 Door Hardware 01-20 08 71 13 Automatic Door Operators 02-16 08 80 00 Glazing 10-15

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 02-15 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 06-18 09 30 13 Ceramic/Porcelain Tiling 09-15 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 02-16 09 65 16 Resilient Sheet Flooring 05-18 09 65 19 Resilient Tile Flooring 05-18 09 91 00 Painting 01-16

DIVISION 10 – SPECIALTIES

10 14 00 Signage 10-15

10 21 23 Cubicle Curtain Tracks 05-15 10 25 13 Patient Bed Service Walls 01-20 10 26 00 Wall and Door Protection 10-15 10 28 00 Toilet, Bath, and Laundry Accessories 02-1 6

DIVISION 11 – EQUIPMENT

11 73 00 Ceiling Mounted Patient Lift System 01-17

DIVISION 12 – FURNISHINGS

12 22 16 Drapery Track and Accessories 05-15 12 24 00 Window Shades 08-17 12 34 00 Manufactured Plastic Casework 10-15 12 36 00 Countertops 12-18

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Str uctural

Components 01-14

DIVISION 14– CONVEYING EQUIPEMENT (NOT USED)

DIVISION 21- FIRE SUPPRESSION

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

00 01 10-3

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 09-20 22 05 23 General-Duty Valves for Plumbing Piping 09 -20 22 07 11 Plumbing Insulation 09-19 22 11 00 Facility Water Distribution 11-19 22 13 00 Facility Sanitary and Vent Piping 09-20 22 40 00 Plumbing Fixtures 09-15 22 62 00 Vacuum Systems for Laboratory and Healthca re Facilities 09-15 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20 23 05 12 General Motor Requirements for HVAC and St eam

Generation Equipment 02-20

23 05 41 Noise and Vibration Control for HVAC Pipin g and Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 09 23 Direct-Digital Control System for HVAC 08- 20 23 21 13 Hydronic Piping 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 HVAC Fans 02-20 23 36 00 Air Terminal Units 02-20 23 37 00 Air Outlets and Inlets 02-20 23 40 00 HVAC Air Cleaning Devices 03-20 23 82 16 Air Coils 03-20

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors an d Cables 01-17 26 05 26 Grounding and Bonding for Electrical Syste ms 01-17 26 05 33 Raceway and Boxes for Electrical Systems 0 1-18 26 24 16 Panelboards 01-18 26 27 26 Wiring Devices 01-18 26 29 11 Motor Controllers 01-18 26 51 00 Interior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installati ons 06-15

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

00 01 10-4

SECTION NO. DIVISION AND SECTION TITLES DATE

27 05 26 Grounding and Bonding for Communications S ystems 06-15 27 05 33 Raceways and Boxes for Communications Syst ems 10-18 27 10 00 Control, Communication and Signal Wiring 0 6-15 27 11 00 Communications Equipment Room Fittings 06- 15 27 52 23 Nurse Call and Code Blue Systems 10-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY (NOT USED)

DIVISION 31 – EARTHWORK (NOT USED)

DIVISION 32 – EXTERIOR IMPROVEMENTS (NOT USED)

DIVISION 33 – UTILITIES (NOT USED)

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 48 – ELECTRICAL POWER GENERATION (NOT USED )

Cheyenne, WY

March 18, 2021

07-15

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specifi cation form a part of the contract.

Drawing No. Title

GENERAL

GI001 COVER SHEET

GI002 GENERAL INFORMATION AND ABBR EVIATIONS

GI003 ACCESSIBILITY STANDARDS

GI004 STATEMENT OF CONDITIONS

GI005 PHASING PLAN

ARCHITECTURAL

AD112 SECOND FLOOR – OVERALL FLOOR PLAN & RCP - DEMOLITION

AD113 PENTHOUSE - FLOOR PLAN - DEM OLITION

AD130 ROOF PLAN - DEMOLITION

A112 SECOND FLOOR – OVERALL FLOOR PLAN & RCP

A113 PENTHOUSE - FLOOR PLAN

A130 ROOF PLAN

A410 ENLARGED PLANS & ELEVATIONS

A411 ENLARGED PLANS & ELEVATIONS

A412 ENLARGED PLANS & ELEVATIONS

A420 ENLARGED PLANS – FINISHES

A530 ROOF AND ENVELOPE DETAILS

A610 WALL TYPE SCHEDULE – WALL & CEILING DETAILS

A620 DOOR SCHEDULE & DOOR TYPES

PLUMBING

P-001 PLUMBING ABBREVIATIONS, SYMB OLS, AND LEGENDS

PP112 SECOND FLOOR PLUMBING PIPING PLANS

MECHANICAL

M-001 MECHANICAL ABBREVIATIONS AND GENERAL NOTES

M-002 MECHANICAL SYMBOLS AND LEGEN DS

MH112 SECOND FLOOR MECHANICAL DUCT WORK PLANS

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

07-15

00 01 15 - 2

MH113 PENTHOUSE MECHANICAL DUCTWOR K PLANS

MH114 PENTHOUSE ROOF MECHANICAL DU CTWORK PLAN

MP112 SECOND FLOOR MECHANICAL PIPI NG PLANS

M501 MECHANICAL DETAILS

M502 MECHANICAL DETAILS

M601 MECHANICAL EQUIPMENT SCHEDUL ES

M701 MECHANICAL CONTROLS

M702 SECOND FLOOR POSITIVE MODE A IRFLOWS DIAGRAM

ELECTRICAL

E001 ELECTRICAL ABBREVIATIONS AND GENERAL NOTES

E002 ELECTRICAL SYMBOLS

ED111 SECOND FLOOR ELECTRICAL DEMO PLAN

EL111 SECOND FLOOR ELECTRICAL LIGH TING PLAN

EP111 SECOND FLOOR AND ROOF ELECTR ICAL POWER PLANS

EP112 PENTHOUSE ELECTRICAL POWER P LAN

E501 ELECTRICAL DETAILS

E601 ELECTRICAL ONE-LINE AND PANE L SCHEDULES

E602 LIGHTING SCHEDULES AND TYPIC AL WIRING DIAGRAMS

- - - END - - -

Update Isolation Rooms Cheyenne, WY

March 18, 2021

12-18 i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

1.10 RESTORATION

1.11 PHYSICAL DATA

1.12 PROFESSIONAL SURVEYING SERVICES

1.13 LAYOUT OF WORK

1.14 AS-BUILT DRAWINGS

1.15 WARRANTY MANAGEMENT

1.16 USE OF ROADWAYS

1.17 RESIDENT ENGINEER'S FIELD OFFICE

1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.19 TEMPORARY USE OF EXISTING ELEVATORS

1.20 TEMPORARY USE OF NEW ELEVATORS

1.21 TEMPORARY TOILETS

1.22 AVAILABILITY AND USE OF UTILITY SERVICES

1.23 NEW TELEPHONE EQUIPMENT

1.24 TESTS

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021 ii

1.25 INSTRUCTIONS

1.26 GOVERNMENT-FURNISHED PROPERTY

1.27 RELOCATED EQUIPMENT AND ITEMS

1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT

1.29 CONSTRUCTION SIGN

1.30 SAFETY SIGN

1.31 PHOTOGRAPHIC DOCUMENTATION

1.32 FINAL ELEVATION Digital Images

1.33 HISTORIC PRESERVATION

Cheyenne, WY

March 18, 2021

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for bui lding operations, including demolition and removal of existing struct ures, and furnish labor and materials and perform work for Cheyenne V AMC as required by drawings and specifications.

B. Visits to the site by Bidders may be made only b y appointment with the

Medical Center Engineering Officer.

C. Offices of Valhalla Engineering, as Architect-En gineers, will render certain technical services during construction. Suc h services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Gov ernment without affirmations by Contracting Officer or his duly aut horized representative.

D. Tasks that are indicated to be completed by the COR throughout this document may be delegated to a Government Designate d Authority/

Representative at the COR’s direction.

E. Before placement and installation of work subjec t to tests by testing laboratory retained by Department of Veterans Affai rs, the Contractor shall notify the COR in sufficient time to enable t esting laboratory personnel to be present at the site in time for pro per taking and testing of specimens and field inspection. Such pri or notice shall be not less than three workdays unless otherwise desig nated by the COR.

F. All employees of general contractor and subcontr actors shall comply with VA security management program and obtain perm ission of the VA police, be identified by project and employer, and restricted from unauthorized access.

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -2

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: Work includes gene ral construction, alterations, roads, walks, grading, drainage, neces sary removal of existing structures and construction and certain ot her items.

ITEM II, Electrical Work: Work includes all labor, material, equipment, and supervision to perform the required electrical construction work on this project.

ITEM III, Mechanical Work: Work includes all labor, material, equipment, and supervision to perform the required Mechanical construction work on this project.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and admi nistrative security procedures that will remain effective for the entir e duration of the project.

2. The General Contractor is responsible for assuri ng that all sub-contractors working on the project and their employ ees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter t he project site without appropriate badge. They may also be subjec t to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shal l give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is sepa rate from any notices required for utility shutdown described lat er in this section.

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -3

3. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the pr emises in the event of a national emergency. The General Contrac tor may return to the site only with the written approval of the Cont racting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate k eys and lock combinations to the Contracting officers representa tive (COR) for the purpose of security inspections of every area o f project including tool-boxes and parked machines and take a ny emergency action.

2. The General Contractor shall turn over all perma nent lock cylinders to the VA locksmith for permanent installation. See Section 08 71

00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor /Sub Contractors shall submit an electronic security memorandum desc ribing the approach to following goals and maintaining confide ntiality of

“sensitive information”.

2. The General Contractor is responsible for safeke eping of all drawings, project manual and other project informat ion. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photograp hs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Re turn the information to the Contracting Officer upon request .

4. These security documents shall not be removed or transmitted from the project site without the written approval of Co ntracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -4

6. Notify Contracting Officer and Site Security Off icer immediately when there is a loss or compromise of “sensitive in formation”.

7. All electronic information shall be stored in sp ecified location following VA standards and procedures using an Engi neering Document

Management Software (EDMS).

a. Security, access, and maintenance of all project drawings, both scanned and electronic shall be performed and track ed through the

EDMS system.

b. “Sensitive information” including drawings and o ther documents may be attached to e-mail provided all VA encryptio n procedures are followed.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (inc luding storage of materials) on Government premises to areas authoriz ed or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harml ess from liability of any nature occasioned by the Contractor's perfor mance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the appr oval of the

Contracting Officer and shall be built with labor a nd materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor a t its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandon ed and need not be removed.

C. The Contractor shall, under regulations prescrib ed by the Contracting

Officer, use only established roadways, or use temp orary roadways constructed by the Contractor when and as authorize d by the Contracting

Officer. When materials are transported in prosecut ing the work, vehicles shall not be loaded beyond the loading cap acity recommended by the manufacturer of the vehicle or prescribed by an y Federal, State, or local law or regulation. When it is necessary to cr oss curbs or

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -5 sidewalks, the Contractor shall protect them from d amage. The

Contractor shall repair or pay for the repair of an y damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing ma terials shall be as determined by the COR.

E. Workers are subject to rules and Policies of Che yenne V.A. Medical

Center applicable to their conduct, including but n ot limited to

Safety, Physical and Security procedures, and Infec tion Control procedures.

F. Execute work so as to interfere as little as pos sible with normal functioning of the Cheyenne V.A. Medical Center as a whole, including operations of utility services, fire protection sys tems and any existing equipment, and with work being done by oth ers. Use of equipment and tools that transmit vibrations and no ises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and

Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other th an assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not m ore than two workdays. Provide unobstructed access to Medical Ce nter areas required to remain in operation.

3. Where access by Medical Center personnel to vaca ted portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and saf ety requirements.

G. Utilities Services: Where necessary to cut ex isting pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (excep t telephone), they shall be cut and capped at suitable places where sh own; or, in absence

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -6 of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involve d:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the c onstruction project, for such items as water, sewer, electricit y, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

G. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses i n operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim lif e safety measure to be used during the work, and a schedule defining th e duration of the work with milestone subtasks. The work to be outli ned shall include, but not be limited to:

To ensure such executions, Contractor shall furnis h the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, b uilding or portion thereof. In addition, Contractor shall notify the C OR two weeks in advance of the proposed date of starting work in ea ch specific area of site, building or portion thereof. Arrange such dat es to ensure accomplishment of this work in successive phases mu tually agreeable to approved by the Contracting Officer and the COR. A sample Phasing Plan is indicated in the Drawings as a guideline. It is the CONTRACTOR’S

RESPONSIBILITY to develop a Phasing Plan to submit to the Contracting

Officer and COR for approval.

H. Contractor shall take all measures and provide a ll material necessary for protecting existing equipment and property in a ffected areas of construction against dust and debris, so that equip ment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Departm ent of Veterans

Affairs personnel and patients through other constr uction areas which

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -7 serve as routes of access to such affected areas an d equipment. These routes whether access or egress shall be isolated f rom the construction area by temporary partitions and have walking surfa ces, lighting etc., to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction pe riod.

1. Immediate areas of alterations not mentioned in preceding Paragraph

G will be temporarily vacated while alterations are performed.

H. When a building and/or construction site is turn ed over to Contractor, Contractor shall accept entire responsibility inclu ding upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specif ied.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for p re-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

I. Utilities Services: Maintain existing utility se rvices for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uni nterrupted services.

Where necessary to cut existing water, steam, gases , sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (incl uding telephone), they shall be cut and capped at suitable places whe re shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, se wers or electricity, or fire protection systems and communications syste ms may be interrupted without prior approval of the COR and C hief Engineer.

Electrical work shall be accomplished with all affe cted circuits or equipment de-energized. When an electrical outage c annot be accomplished, work on any energized circuits or equ ipment shall not

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -8 commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to spec ification

Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INST ALLATIONS, 27 05

11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt a ny such services to

COR, in writing, 7 days in advance of proposed inte rruption. Request shall state reason, date, exact time of, and approx imate duration of such interruption.

3. Contractor will be advised (in writing) of appro val of request, or of which other date and/or time such interruption w ill cause least inconvenience to operations of Medical Center. Inte rruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be reques ted, in writing, at least 15 calendar days prior to the desired time an d shall be performed as directed by the COR.

5. In case of a contract construction emergency, se rvice will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the c onstruction project, for such items as water, sewer, electricit y, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

J. Abandoned Lines: All service lines such as wires , cables, conduits, ducts, pipes and the like, and their hangers or sup ports, which are to be abandoned but are not required to be entirely re moved, shall be sealed, capped or plugged at the main, branch or pa nel they originate from. The lines shall not be capped in finished are as, but shall be removed and sealed, capped or plugged in ceilings, within furred

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -9 spaces, in unfinished areas, or within walls or par titions; so that they are completely behind the finished surfaces.

K. To minimize interference of construction activit ies with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to p arking and to occupied areas of buildings clear of construction m aterials, debris and standing construction equipment and vehicles.

L. Coordinate the work for this contract with other construction operations as directed by COR. This includes the sc heduling of traffic and the use of roadways, as specified in Article, U SE OF ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contract or shall make a thorough survey with the COR areas of buildings in which alterations occur and areas which are anticipated routes of acc ess, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient floori ng, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbi ng fixtures and accessories, electrical fixtures, equipment, veneti an blinds, shades, etc., required by drawings to be either reu sed or relocated, or both.

3. Shall note any discrepancies between drawings an d existing conditions at site.

4. Shall designate areas for working space, materia ls storage and routes of access to areas within buildings where al terations occur and which have been agreed upon by Contractor and C OR.

B. Any items required by drawings to be either reus ed or relocated or both, found during this survey to be nonexistent, o r in opinion of COR or the facility staff, to be in such condition that their use is impossible or impractical, shall be furnished and/o r replaced by

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -10

Contractor with new items in accordance with specif ications which will be furnished by Government. Provided the contract w ork is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "D IFFERING SITE

CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.24 3-4).

C. Re-Survey: Thirty days before expected partial o r final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furn ish a report on conditions then existing, of resilient flooring, do ors, windows, walls and other surfaces as compared with conditions of s ame as noted in first condition survey report:

1. Re-survey report shall also list any damage caus ed by Contractor to such flooring and other surfaces, despite protectio n measures; and will form basis for determining extent of repair wo rk required of

Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective mea sures:

1. Wherever existing roof surfaces are disturbed th ey shall be protected against water infiltration. In case of le aks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, ma terials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protecti on shall be maintained intact until all work in the area is com pleted.

Cheyenne, WY

March 18, 2021

01 00 00 -11

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work remov ed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of t he Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that re main property of the Government shall be removed or dislodged from p resent locations in such a manner as to prevent damage which would b e detrimental to re-installation and reuse. Store such items where d irected by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings loca ted in rooms and spaces in which work is to be done under this contr act shall remain the property of the Government. When rooms and spac es are vacated by the Department of Veterans Affairs during the alter ation period, such items which are NOT required by drawings and s pecifications to be either relocated or reused will be removed by th e Government in advance of work to avoid interfering with Contracto r's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

A. The Contractor shall preserve and protect all st ructures, equipment, and vegetation (such as trees, shrubs, and grass) o n or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contrac t. The Contractor shall only remove trees when specifically authorize d to do so and shall avoid damaging vegetation that will remain in place . If any limbs or branches of trees are broken during contract perfor mance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and p aint the cut with a tree-pruning compound as directed by the Contractin g Officer.

B. The Contractor shall protect from damage all exi sting improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -12 the Contractor. The Contractor shall repair any dam age to those facilities, including those that are the property o f a third party, resulting from failure to comply with the requireme nts of this contract or failure to exercise reasonable care in performin g the work. If the

Contractor fails or refuses to repair the damage pr omptly, the

Contracting Officer may have the necessary work per formed and charge the cost to the Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENT AL CONTROLS, for additional requirements on protecting vegetation, s oils and the environment. Refer to Articles, "Alterations", "Res toration", and

"Operations and Storage Areas" for additional instr uctions concerning repair of damage to structures and site improvement s.

D. Refer to FAR clause 52.236-7, "Permits and Respo nsibilities," which is included in General Conditions. The Contractor is r esponsible for employing best management practices. The affected a ctivities often include, but are not limited to the following:

- Providing waste receptacles at convenient locatio ns and provide regular collection of wastes;

- Locating equipment wash down areas on site, and p rovide appropriate control of wash-waters;

- Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

- Providing adequately maintained sanitary faciliti es.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair ex isting work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, an d do not disturb any ducts, plumbing, steam, gas, or electric work witho ut approval of the

COR. Existing work to be altered or extended and th at is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restor ing work, shall

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -13 conform in type and quality to that of original exi sting construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work comple te and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work , shall be patched, repaired, reinstalled, or replaced with new work, a nd refinished and left in as good condition as existed before commenc ing work.

C. At Contractor's own expense, Contractor shall im mediately restore to service and repair any damage caused by Contractor' s workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications sy stems (including telephone) which are not scheduled for discontinuan ce or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered b y adjustment to contract time and price in accordance with clause e ntitled "CHANGES"

(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 PHYSICAL DATA (NOT USED)

1.12 PROFESSIONAL SURVEYING SERVICES (NOT USED)

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work as indicat ed on the drawings and shall be responsible for all measurements in connec tion with the layout. The Contractor shall furnish, at Contractor 's own expense, all stakes, templates, platforms, equipment, tools, mat erials, and labor required to lay out any part of the work. The Contr actor shall be responsible for the coordination of the layout with subcontractors, drawings, and existing conditions.

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of t he project, to include all contract changes, modifications, and cl arifications.

B. All variations shall be shown in the same genera l detail as used in the contract drawings. To ensure compliance, as-built d rawings shall be

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -14 made available for the Resident Engineer's COR revi ew, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR and Chief of Facilities Management within 15 calendar days af ter each completed phase and after the acceptance of the project by th e Contracting

Officer and the COR.

D. Paragraphs A, B, & C shall also apply to all sho p drawings.

1.15 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty man agement plan which contains information relevant to FAR 52.246-21 Warr anty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include wi thin the warranty management plan all required actions and documents to assure that the

Government receives all warranties to which it is e ntitled. The plan must be in narrative form and contain sufficient de tail to render it suitable for use by future maintenance and repair p ersonnel, whether tradesman, or of engineering background, not necess arily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was app roved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval p rior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the proje ct acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured fro m time of acceptance, by the Contactor and the Contracting Of ficer. Include in the warranty management plan, but not limited to, t he following:

1. Roles and responsibilities of all personnel associa ted with the warranty process, including points of contact and t elephone numbers within the company of the Contractor, subcontractor s, manufacturers or suppliers involved.

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -15

2. Furnish with each warranty the name, address and te lephone number of each of the guarantor’s representatives nearest pro ject location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC bal ancing, pumps, motors, transformers and for all commissioned syste ms such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature o f construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and supplie rs.

e. Name and phone numbers of manufacturers or supplier s.

f. Names, addresses and phone numbers of sources of sp are parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting da te of warranty of construction. Items which have extended warranti es must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to conti nue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons t o call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -16

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment co vered by extended warranties.

7. Copies of instructions to be posted near selected p ieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance Bond: The Performance Bond must rema in effective throughout the construction period.

1. In the event the Contractor fails to commence and d iligently pursue any construction warranty work required, the Contra cting Officer will have the work performed by others, and after c ompletion of the work, will charge the remaining construction warran ty funds of expenses incurred by the Government while performin g the work, including, but not limited to administrative expens es.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Governm ent at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instr uctions. Failure to respond will be cause for the Contracting Office r to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract compl etion, and at a time designated by the Contracting Officer, the Contract or shall meet with the Contracting Officer to develop a mutual underst anding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty de fects, priorities with respect to the type of defect, reasonable time required for

Contractor response, and other details deemed neces sary by the

Contracting Officer for the execution of the constr uction warranty will be established/ reviewed at this meeting. In connec tion with these

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -17 requirements and at the time of the Contractor’s qu ality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorize d to initiate and pursue construction warranty work action on behalf of the Contractor.

This point of contract will be located within the l ocal service area of the warranted construction, be continuously availab le and be responsive to Government inquiry on warranty work action and s tatus. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty S ervice Requirements:

Following oral or written notification by the Contr acting Officer, the

Contractor shall respond to construction warranty s ervice requirements in accordance with the “Construction Warranty Servi ce Priority List” and the three categories of priorities listed below . Submit a report on any warranty item that has been repaired during the warranty period.

Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was co mpleted. If the

Contractor does not perform the construction warran ty within the timeframe specified, the Government will perform th e work and back charge the construction warranty payment item estab lished.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to comple tion or relief.

2. Second Priority Code 2. Perform onsite inspection t o evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to compl etion or relief.

3. Third Priority Code 3. All other work to be initiat ed within 3 workdays and work continuously to completion or rel ief.

4. The “Construction Warranty Service Priority List” i s as follows:

Code 1-Life Safety Systems

a. Fire suppression systems.

b. Fire alarm system(s).

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -18

Code 1-Air Conditioning Systems

a. Air conditioning leak in part of the building, if c ausing damage.

b. Air conditioning system not cooling properly.

Code 1 Doors

a. Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

Code 3-Doors

a. Interior/exterior personnel doors or hardware not f unctioning properly.

Code 1-Electrical

a. Power failure (entire area or any building operatio nal after 1600 hours).

b. Security lights.

c. Smoke detectors.

Code 2-Electrical

a. Power failure (no power to a room or part of buildi ng).

b. Receptacles and lights not operational (in a room o r part of building).

Code 3-Electrical

a. Exterior lights not operational.

Code 1-Gas

a. Leaks and pipeline breaks.

Code 1-Heat

a. Power failure affecting heat.

Code 1-Plumbing

a. Hot water heater failure.

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -19

b. Leaking water supply pipes.

Code 2-Plumbing

a. Flush valves not operating properly

b. Fixture drain, supply line or any water pipe leakin g.

c. Toilet leaking at base.

Code 3- Plumbing

a. Leaky faucets.

Code 3-Interior

a. Floors damaged.

b. Paint chipping or peeling.

c. Casework damaged.

Code 1-Roof Leaks

a. Damage to property is occurring.

Code 2-Water (Hot)

a. No hot water in portion of building listed.

Code 3

a. All work not listed above.

E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approve d by the Contracting

Officer. Attach each tag with a copper wire and spr ay with a silicone waterproof coating. Also submit two record copies o f the warranty tags showing the layout and design. The date of acceptan ce and the QC signature must remain blank until the project is ac cepted for beneficial occupancy. Show the following informatio n on the tag.

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -20

1.16 USE OF ROADWAYS

A. For hauling and deliveries, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performa nce of contract work. Temporary roads shall be constructed, and res toration performed by the Contractor at Contractor's expense. When nec essary to cross curbing, sidewalks, or similar construction, they m ust be protected by well-constructed bridges.

1.17 RESIDENT ENGINEER'S FIELD OFFICE (NOT USED)

1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical e quipment to provide heat, ventilation, plumbing, light, and power will be permitted subject to written approval and compliance with the followi ng provisions:

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -21

1. Permission to use each unit or system must be gi ven by COR in writing. If the equipment is not installed and main tained in accordance with the written agreement and following provisions, the

COR will withdraw permission for use of the equipme nt.

2. Electrical installations used by the equipment s hall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e., tra nsformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, co ordinated and adjusted. Installation of temporary electrical equi pment or devices shall be in accordance with NFPA 70, National Elect rical Code, (2014

Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be corr ect and it shall be determined that motors are not overloaded. The e lectrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuu m cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, an d aligned.

Vibrations must be eliminated.

4. Automatic temperature control systems for prehea t coils shall function properly and all safety controls shall fun ction to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elemen ts shall be replaced at completion of construction and prior to testing and balancing of system.

B. Prior to final inspection, the equipment or part s used which show wear and tear beyond normal, shall be replaced with iden tical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear du e to prolonged use will be repaired replaced by the contractor at the contr actor’s expense.

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -22

1.19 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevator for handling building materials and

Contractor's personnel will be permitted subject to following provisions:

1. Contractor makes all arrangements with the COR f or use of elevators.

Contractors may use elevators Nos. 8, 9, and 10 in the Buffalo

Building for shared use with the facility. The Medi cal Center must maintain its operation 24 hours a day, 7 days a wee k. Therefore, any interruption in service must be scheduled and coord inated with the

COR to ensure that no lapses in day-to-day operatio ns occur.

Personnel for operating elevators will not be provi ded by the

Department of Veterans Affairs.

2. Contractor covers and provides maximum protectio n of following elevator components:

a. Entrance jambs, heads soffits and threshold plat es.

b. Entrance columns, canopy, return panels and insi de surfaces of car enclosure walls.

c. Finish flooring.

3. If brake lining of elevators are excessively wor n or damaged during temporary use, they shall be removed and replaced b y new brake lining at the contractor’s expense.

4. All parts of main controller, starter, relay pan el, selector, etc., worn or damaged during temporary use shall be remov ed and replaced with new parts at the contractor’s expense.

1.20 TEMPORARY USE OF NEW ELEVATORS (NOT USED)

1.21 TEMPORARY TOILETS

A. Contractor may have for use of Contractor's wo rkers, such toilet accommodations as may be assigned to Contractor by Medical Center.

Contractor shall keep such places clean and be resp onsible for any damage done thereto by Contractor's workers. Failur e to maintain satisfactory condition in toilets will deprive Cont ractor of the privilege to use such toilets.

Cheyenne VAMC Update Isolation Rooms Cheyenne, WY

March 18, 2021

01 00 00 -23

1.22 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably require d amounts of utilities available to the Contractor from existing outlets a nd supplies, as specified in the contract. The Contractor shall car efully conserve any utilities furnished without charge.

1.23 NEW TELEPHONE EQUIPMENT

The contractor shall coordinate with the work of i nstallation of telephone equipment by others. This work shall be c ompleted before the building is turned over to VA.

1.24 TESTS

A. As per specification section 23 05 93 the contra ctor shall provide a written testing and commissioning plan complete wit h component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such s ystems before requesting final tests. Final test will not be cond ucted unless pre-tested.

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Con tracting Officer.

Contractor shall furnish all labor, materials, equi pment, instruments, and forms, to conduct and record such tests.

D. Mechanical and electrical systems shall be balan ced,…