This document is a Task Order Announcement (TOA) for a design-build construction project to rebuild family housing facilities at U.S. Coast Guard Sector New York in Staten Island, NY. The project scope includes demolition of existing apartment buildings, site preparation, utility work, and construction of new multiplex housing units. The contract will be awarded under the National Multiple Award Construction Contract III - Pool One (NMACC III-Pool 1) to one of the existing NMACC III-Pool 1 contractors. Proposals are due by October 29, 2024, and the contract performance period is 1,256 calendar days. The total contract price limitation is approximately $52 million. A project labor agreement is required for this large-scale construction project. The government will evaluate proposals based on price, a conceptual building/site design factor, and a sequence of design/construction factor. Award will be made to the contractor providing the best value to the government.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FACILITIES DESIGN AND CONSTRUCTION CENTER
5505 ROBIN HOOD RD., SUITE K
NORFOLK, VA 23513
Gabriel D. Perez Senior Field Contracting Officer
Gabriel.D.Perez@uscg.mil 206-851-9647
Sharan A. Lind
Senior Field Contracting Officer Sharan.A.Lind@uscg.mil
571-607-4595
Maria (Helen) Chapa-Johnson Contracting Officer
Maria.E.Chapa-Johnson@uscg.mil 206-815-3535
NATIONAL MULTIPLE AWARD
CONSTRUCTION CONTRACT III - POOL ONE (NMACC III-Pool 1)
TASK ORDER ANNOUNCEMENT #
70Z04724RPCNI0006
Design/Build Construction for
REBUILD FAMILY HOUSING FORT WADSWORTH PHASE I
AT U. S. COAST GUARD SECTOR NEW YORK,
STATEN ISLAND, NY
ISSUE DATE: August 27, 2024 mailto:Gabriel.D.Perez@uscg.mil mailto:Sharan.A.Lind@uscg.mil mailto:Maria.E.Chapa-Johnson@uscg.mil
United States Coast Guard Ombudsman Program
FAR 52.216-32 Task-Order and Delivery-Order Ombudsman (Sept 2019)
(a) In accordance with 41 U.S.C. 4106(g), the Agency has designated the following task-order and delivery-order Ombudsman for this contract. The Ombudsman must review complaints from the Contractor concerning all task-order and delivery-order actions for this contract and ensure the Contractor is afforded a fair opportunity for consideration in the award of orders, consistent with the procedures in the contract. Email OPAP@uscg.mil and copy the Contracting Officer.
(b) Consulting an ombudsman does not alter or postpone the timeline for any other process (e.g., protests).
(c) Before consulting with the Ombudsman, the Contractor is encouraged to first address complaints with the Contracting Officer for resolution. When requested by the Contractor, the Ombudsman may keep the identity of the concerned party or entity confidential, unless prohibited by law or agency procedure.
(End of clause) mailto:OPAP@uscg.mil
TASK ORDER ANNOUNCEMENT # 70Z04724RPCNI0006 IS ISSUED ONLY TO THOSE OFFERORS
UNDER THE NATIONAL MULTIPLE AWARD CONSTRUCTION CONTRACT III, POOL ONE
(NMACC III-Pool 1) INDEFINITE DELIVERY/INDEFINITE QUANTITY (IDIQ)
I. GENERAL REQUIREMENTS
Title: Design/Build-Rebuild Family Housing Fort Wadsworth, Phase I at U. S. Coast Guard Sector New York
Location of the work: Staten Island, New York 10305-5005
Project Number: 21-14089081
Specifications and Drawings: RFP Guide Specifications 21-14089081 (provided in electronic format via Sam.gov and/or DoD Safe)
Supplementary Documents: Project 21-14089081 Attachments and Appendices (provided in electronic format via Sam.gov and/or DoD Safe)
Wage Determination: General Decision No. NY20240003, Modification No. 07 dated 08/23/2024, New York, Richmond County (provided in electronic format via Sam.gov and/or DoD Safe)
Disclosure of Magnitude: The Government requests offerors notify the Contracting Officer as soon as practicable if they determine the project cannot be accomplished within the below price limitation. The design and construction costs will be subject to the funds available for this project.
The contract price limitation for contract award is approximately $52 Million. Contractors are notified that they are under no obligation to approach this ceiling; however, the Government may not be able to make an award if the dollar amount set for this project is exceeded.
Description of the work: This project is for design-build demolition and construction of Fort Wadsworth Family Housing Facilities located at U. S. Coast Guard Sector New York, Staten Island, NY. The scope includes demolition of several apartment buildings, carports and their foundations, preparation and clearing of existing site for new construction, removal, and installation of underground utilities, resurfacing and repair of roads and sidewalks, and new multiplex construction with new street lighting, landscaping, fencing, and new entrance gates. The project consists of one Base Item and 3 Option Items in accordance with the Price proposal Form.
OPTION ITEMS
NMACC III-Pool 1 Contractors are required to provide pricing for all option items (Option Items 1, 2 and 3). If awarded, options shall be completed within the contract performance period. Options will be considered in accordance with FAR 52.217-5 Evaluation of Options (JULY 1990).
Period of Performance: The contract performance period is 1256 calendar days after award of the Task Order for the Base and all Option Items. If awarded, the Option Items shall be completed within the contract completion date.
Liquidated Damages: Liquidated damages in the amount of $1,433.00 per day will be assessed, if necessary, in accordance FAR 52.211-12, Liquidated Damages-Construction (SEPT 2000). As described in F.1 of the contract.
Insurance/Bonds: Please review Section H.2 of the contract for insurance requirements and L.7 of the contract for bonding requirements. A bid guarantee is not required for this task order.
Utilities: Refer to appropriate Specification Sections.
Site visit: An organized site visit will be schedule on TBD. An amendment to the TOA will be issued to identify the site visit date and site visit information.
Authorized Representatives of the Contracting Officer: Kimberly Stone is the Contracting Officer's Representative (COR) for the purpose of day-to-day technical administration/inspection of all work under the contract. This includes, but is not limited to, administration of progress, approval of submittals, final inspection and providing technical assistance when required. The contractor is cautioned that in no instance is the above-named person authorized to approve any changes which will involve the quantity, quality, price, or performance of the contract.
A Construction Inspector (to be determined) will coordinate with the Contracting Officer’s Representative for the purpose of inspection of work under the contract. The Contractor is cautioned that in no instance is the Construction Inspector authorized to approve any changes, which involves the quantity, quality, price, or performance of the contract.
Instructions for Submitting Questions Regarding Task Order Announcement: Offerors are requested to review this Task Order Announcement as soon as possible upon receipt. If an offeror has any questions regarding the Task Order Announcement which require an answer from the issuing office, these questions shall be submitted, in writing via email to the Senior Field Contracting Officer, Gabriel Perez, Secondary Senior Field Contracting Officer, Sharan Lind and Contracting Officer, Maria (Helen) Chapa-Johnson, referencing section and paragraph of the solicitation, to the U.S. Coast Guard, Facilities Design and Construction Center (FD&CC), 5505 Robin Hood Rd, Suite K, Norfolk, VA 23513. Email addresses are: gabriel.d.perez@uscg.mil, sharan.a.lind@uscg.mil and maria.e.chapa-johnson@uscg.mil. Additionally, carbon copy (CC) emails to the bulk FD&CC email address FDCC-PROPOSALS@uscg.mil.
Deadline for submissions of Request for Information (RFI(s)) is 4:30 PM (EST) on October 15, 2024.
GENERAL SUBMISSION INSTRUCTIONS
PROJECT LABOR AGREEMENT: This project is considered a “Large-scale Construction Project” as defined in FAR 22.502. Accordingly, the requirements of FAR Subpart 22.5 will apply. The Offeror shall submit a signed Project Labor Agreement with their Price Proposal submission, in accordance with FAR Provision 52.222-33 and FAR Clause 52.222-34. Offerors that do not include a signed Project Labor Agreement complying with the terms of FAR 52.222-33 and 52.222-34 shall be considered nonresponsive and ineligible for award.
CLOSING DATE: To ensure consideration, submit proposals on October 29, 2024, at 4:30 PM (EST) Local Time, Norfolk, Virginia. Proposals submitted after this date may or may not be evaluated at the discretion of the Contracting Officer. The Contracting Officer will consider such factors as whether acceptance will unduly delay award or is necessary to increase competition. Agency close of business is presumed to be 4:30 pm local time.
Proposal Acceptance Period: 90 calendar days from receipt of offer.
The completed proposal shall be submitted using DoDSafe. The technical and price proposal shall be a separate attachment. The Contracting Officer will send an invite to submit through DoDSafe within 48 mailto:gabriel.d.perez@uscg.mil mailto:sharan.a.lind@uscg.mil mailto:maria.e.chapa-johnson@uscg.mil mailto:FDCC-PROPOSALS@uscg.mil hours of proposal due date and time. Offerors are to provide a preferred point of contact and email address to be used for DoDSafe submission, to the Contracting Officer, Maria (Helen) Chapa-Johnson at Maria.E.Chapa-Johnson@uscg.mil. Each electronic submission must be less than 36MB.
Proposals must be prepared in accordance with these submission instructions, providing all required information in the format specified. Failure of a proposal to comply with these general submission instructions and the specific submission instructions contained in this task order announcement may be grounds for exclusion of the proposal from further consideration.
The contractor shall be required to respond to its representation in accordance with FAR Provision 52.204-24(d) Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021). Contractors ARE required to include their representation in FAR 52.204-24(d) with the submission of their proposal by indicating in a statement that “It □ will, □ will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation.”
Electronic Submission of Payment Requests is a requirement for this Contract in accordance with H.21 Centralized Invoice Submittal in the base contract.
Invoice Processing Platform (IPP)
(a) Definitions. As used in these instructions -
(1) “Payment request” means a bill, voucher, invoice, or request for contract financing payment with associated supporting documentation. The payment request must: comply with the requirements identified in FAR 32.905(b), “Content of Invoices” and the applicable Payment clause included in this contract. In addition, discount offerings and small business status if available shall be stated. If travel was allowable and approved, components in accordance with FAR 31.205-46 shall be provided.
(b) Except as provided in paragraph (c) of this clause, the contractor shall submit payment requests electronically using the Invoice Processing Platform (IPP). Information regarding IPP, including IPP Customer Support contact information, is available at www.ipp.gov or any successor site.
(c) The contractor may submit payment requests using a method other than IPP only when the contracting officer authorizes alternate procedures in writing in accordance with Coast Guard procedures.
(d) If alternate payment procedures are authorized, the contractor shall include a copy of the contracting officer's written authorization with each payment request.
(e) IPP enrollment information is at https://www.uscg.mil/fincen/IPP/ .
II. ADDITIONAL CLAUSES
The following FAR Clauses and Agency specific Task Order Provisions/Clauses are being incorporated into this task order contract in addition to clauses already in the Base Contract:
mailto:Maria.E.Chapa-Johnson@uscg.mil http://www.ipp.gov/ https://www.uscg.mil/fincen/IPP/
FAR 52.203-17, Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (April 2024) (DEVIATION 14-01, Revision 1)
(a) This contract and employees working on this contract will be subject to the whistleblower rights and remedies established at 10 U.S.C. 4701 and Homeland Security Acquisition Regulation (HSAR) 3.900 (DEVIATION) through 3.905 (DEVIATION)..
(b) The Contractor shall inform its employees in writing, in the predominant language of the workforce, of employee whistleblower rights and protections under 10 U.S.C. 4701, as described in HSAR 3.900 (DEVIATION) through 3.905 (DEVIATION).
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in all subcontracts.
FAR 52.204-8 Annual Representations and Certifications (May 2024)
(a) (1) The North American Industry Classification System (NAICS) code for this acquisition is_236220.
(2) The small business size standard is _$45M.
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519 if the acquisition—
(i) Is set aside for small business and has a value above the simplified acquisition threshold;
(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b) (1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
(i) □Paragraph (d) applies.
(ii) □Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
https://www.law.cornell.edu/uscode/text/10/4701 https://www.acquisition.gov/far/subpart-3.9#FAR_3_900 https://www.acquisition.gov/far/subpart-3.9#FAR_3_905 https://www.law.cornell.edu/uscode/text/10/4701 https://www.acquisition.gov/far/subpart-3.9#FAR_3_900 https://www.acquisition.gov/far/subpart-3.9#FAR_3_905 https://www.acquisition.gov/far/52.204-7#FAR_52_204_7 https://www.acquisition.gov/far/52.204-7#FAR_52_204_7
(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless–
(A) The acquisition is to be made under the simplified acquisition procedures in part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that-
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services-Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations- Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance-Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
https://www.acquisition.gov/far/52.203-2#FAR_52_203_2 https://www.acquisition.gov/far/part-13#FAR_Part_13 https://www.acquisition.gov/far/52.203-11#FAR_52_203_11 https://www.acquisition.gov/far/52.203-18#FAR_52_203_18 https://www.acquisition.gov/far/52.204-3#FAR_52_204_3 https://www.acquisition.gov/far/52.204-7#FAR_52_204_7 https://www.acquisition.gov/far/52.204-5#FAR_52_204_5 https://www.acquisition.gov/far/52.204-26#FAR_52_204_26 https://www.acquisition.gov/far/52.209-2#FAR_52_209_2 https://www.acquisition.gov/far/52.209-5#FAR_52_209_5 https://www.acquisition.gov/far/52.209-11#FAR_52_209_11 https://www.acquisition.gov/far/52.214-14#FAR_52_214_14 https://www.acquisition.gov/far/52.215-6#FAR_52_215_6
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans’ Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial products or commercial services.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of biobased products in USDA-designated product categories; or include the clause at 52.223-2, Reporting of Biobased Products Under Service and Construction Contracts.
(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA–designated items.
(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals- Representation. This provision applies to solicitations that include the clause at 52.204-7.
(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xxi) 52.225-4, Buy American-Free Trade Agreements-Israeli Trade Act Certificate.
(Basic, Alternates II and III.) This provision applies to solicitations containing the clause at 52.225- 3.
(A) If the acquisition value is less than $50,000, the basic provision applies.
https://www.acquisition.gov/far/52.219-1#FAR_52_219_1 https://www.acquisition.gov/far/part-19#FAR_Part_19 https://www.acquisition.gov/far/19.000#FAR_19_000 https://www.acquisition.gov/far/52.219-2#FAR_52_219_2 https://www.acquisition.gov/far/part-19#FAR_Part_19 https://www.acquisition.gov/far/19.000#FAR_19_000 https://www.acquisition.gov/far/52.222-22#FAR_52_222_22 https://www.acquisition.gov/far/52.222-26#FAR_52_222_26 https://www.acquisition.gov/far/52.222-25#FAR_52_222_25 https://www.acquisition.gov/far/52.222-26#FAR_52_222_26 https://www.acquisition.gov/far/52.222-38#FAR_52_222_38 https://www.acquisition.gov/far/52.223-1#FAR_52_223_1 https://www.acquisition.gov/far/52.223-2#FAR_52_223_2 https://www.acquisition.gov/far/52.223-4#FAR_52_223_4 https://www.acquisition.gov/far/52.223-22#FAR_52_223_22 https://www.acquisition.gov/far/52.204-7#FAR_52_204_7 https://www.acquisition.gov/far/52.225-2#FAR_52_225_2 https://www.acquisition.gov/far/52.225-1#FAR_52_225_1 https://www.acquisition.gov/far/52.225-4#FAR_52_225_4 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3
(B) If the acquisition value is $50,000 or more but is less than $100,000, the provision with its Alternate II applies.
(C) If the acquisition value is $100,000 or more but is less than $102,280, the provision with its Alternate III applies.
(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan- Certification. This provision applies to all solicitations.
(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications. This provision applies to all solicitations.
(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(2) The following representations or certifications are applicable as indicated by the Contracting Officer:
__ (i) 52.204-17, Ownership or Control of Offeror.
__ (ii) 52.204-20, Predecessor of Offeror.
__ (iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
__ (iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment- Certification.
__ (v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Certification.
__ (vi) 52.227-6, Royalty Information.
__ (A) Basic.
__ (B) Alternate I.
__ (vii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The offeror has completed the annual representations and certifications electronically in SAM website accessed through https://www.sam.gov. After reviewing the SAM information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and https://www.acquisition.gov/far/52.225-6#FAR_52_225_6 https://www.acquisition.gov/far/52.225-5#FAR_52_225_5 https://www.acquisition.gov/far/52.225-20#FAR_52_225_20 https://www.acquisition.gov/far/52.225-25#FAR_52_225_25 https://www.acquisition.gov/far/52.226-2#FAR_52_226_2 https://www.acquisition.gov/far/52.204-17#FAR_52_204_17 https://www.acquisition.gov/far/52.204-20#FAR_52_204_20 https://www.acquisition.gov/far/52.222-18#FAR_52_222_18 https://www.acquisition.gov/far/52.222-48#FAR_52_222_48 https://www.acquisition.gov/far/52.222-52#FAR_52_222_52 https://www.acquisition.gov/far/52.227-6#FAR_52_227_6 https://www.acquisition.gov/far/52.227-15#FAR_52_227_15 https://www.sam.gov/ applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR Clause # Title Date Change
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
(End of provision)
FAR 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021) The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services—Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications-Commercial Products or Commercial Services. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.
(a) Definitions. As used in this provision—Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Prohibition. (1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.
Nothing in the prohibition shall be construed to—
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
https://www.acquisition.gov/far/4.1201#FAR_4_1201 https://www.acquisition.gov/far/52.204-26#FAR_52_204_26 https://www.acquisition.gov/far/52.212-3#FAR_52_212_3 https://www.acquisition.gov/far/52.204-26#FAR_52_204_26 https://www.acquisition.gov/far/52.212-3#FAR_52_212_3 https://www.acquisition.gov/far/52.204-25#FAR_52_204_25
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract. Nothing in the prohibition shall be construed to—
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) ( https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services".
(d) Representation. The Offeror represents that—
(1) It □ will, □ will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation. The Offeror shall provide the additional disclosure information required at paragraph (e)(1) of this section if the Offeror responds "will" in paragraph (d)(1) of this section; and
(2) After conducting a reasonable inquiry, for purposes of this representation, the Offeror represents that—
It □ does, □ does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror shall provide the additional disclosure information required at paragraph (e)(2) of this section if the Offeror responds "does" in paragraph (d)(2) of this section.
(e) Disclosures. (1) Disclosure for the representation in paragraph (d)(1) of this provision. If the Offeror has responded "will" in the representation in paragraph (d)(1) of this provision, the Offeror shall provide the following information as part of the offer:
(i) For covered equipment—
(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the original equipment manufacturer (OEM) or a distributor, if known);
(B) A description of all covered telecommunications equipment offered (include brand;
model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and https://www.sam.gov/
(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
(ii) For covered services—
(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable);
or
(B) If not associated with maintenance, the Product Service Code (PSC) of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
(2) Disclosure for the representation in paragraph (d)(2) of this provision. If the Offeror has responded "does" in the representation in paragraph (d)(2) of this provision, the Offeror shall provide the following information as part of the offer:
(i) For covered equipment—
(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known);
(B) A description of all covered telecommunications equipment offered (include brand;
model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
(ii) For covered services—
(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable);
or
(B) If not associated with maintenance, the PSC of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
FAR 52.204.26 Covered Telecommunications Equipment or Services-Representation (OCT 2020)
(a) Definitions. As used in this provision, “covered telecommunications equipment or services” has the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.
(c) Representation. The Offeror represents that it □ does, □ does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.
FAR 52.222-33 Notice of Requirement for Project Labor Agreement (Alternate III) (JAN 2024)
(a) Definitions. As used in this provision, the following terms are defined in clause 52.222-34, Project Labor Agreement, of this solicitation “construction,” “labor organization,” “large-scale construction project,” and “project labor agreement.”
(b)(1) If awarded the contract, the Offeror may be required by the agency to negotiate or become a party to a project labor agreement with one or more labor organizations for the term of the order. The Contracting Officer will require that an executed copy of the project labor agreement be submitted to the agency—
(i) With the order offer;
(ii) Prior to award of the order; or
(iii) After award of the order.
(2) The Offeror shall require its subcontractors to become a party to the resulting project labor agreement for the term of the order.
(End of Provision)
FAR 52.222-34 Project Labor Agreement (Alternate II) (JAN 2024)
(a) Definitions. As used in this clause-
Construction means construction, reconstruction, rehabilitation, modernization, alteration, conversion, extension, repair, or improvement of buildings, structures, highways, or other real property.
Labor organization means a labor organization as defined in 29 U.S.C. 152(5) of which building and construction employees are members.
Large-scale construction project means a Federal construction project within the United States for which the total estimated cost of the construction contract(s) to the Federal Government is $35 million or more.
https://www.sam.gov/ https://www.acquisition.gov/far/subpart-52.2#FAR_52_222_34 https://www.govinfo.gov/link/uscode/29/152
Project labor agreement means a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U. S.C.158(f).
(b) When notified by the agency ( e.g., by the notice of intent to place an order under 16.505(b)(1)) that this order will use a project labor agreement, the Contractor shall negotiate or become a party to a project labor agreement with one or more labor organizations for the term of the order. The Contracting Officer shall require that an executed copy of the project labor agreement be submitted to the agency—
(1) With the order offer;
(2) Prior to award of the order; or
(3) After award of the order.
(c) The project labor agreement reached pursuant to this clause shall—
(1) Bind the Contractor and subcontractors engaged in construction on the construction project to comply with the project labor agreement;
(2) Allow all contractors and subcontractors to compete for contracts and subcontracts without regard to whether they are otherwise parties to collective bargaining agreements;
(3) Contain guarantees against strikes, lockouts, and similar job disruptions;
(4) Set forth effective, prompt, and mutually binding procedures for resolving labor disputes arising during the term of the project labor agreement;
(5) Provide other mechanisms for labor-management cooperation on matters of mutual interest and concern, including productivity, quality of work, safety, and health; and
(6) Fully conform to all statutes, regulations, Executive orders, and agency requirements.
(d) Any project labor agreement reached pursuant to this clause does not change the terms of this contract or provide for any price adjustment by the Government.
(e) The Contractor shall maintain in a current status throughout the life of the order any project labor agreement entered into pursuant to this clause.
(f) Subcontracts. For each order that uses a project labor agreement, the Contractor shall—
(1) Require subcontractors engaged in construction on the construction project to agree to any project labor agreement negotiated by the prime contractor pursuant to this clause; and
(2) Include the substance of paragraphs (d) through (f) of this clause in subcontracts with subcontractors engaged in construction on the construction project.
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/16.505#FAR_16_505
The following BUY AMERICAN Provision and Clause applies in accordance with the thresholds established in the FAR and the NMACC III – Pool One.
52.225-11 Buy American-Construction Materials under Trade Agreements (NOV 2023)
(a) Definitions. As used in this clause—Caribbean Basin country construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal
Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C.40102(4), such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Designated country means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, North Macedonia, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);
(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
Designated country construction material means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if—
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029.
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together.
Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Free Trade Agreement country construction material means a construction material that-
(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.
Least developed country construction material means a construction material that-
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed. Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
United States means the 50 States, the District of Columbia, and outlying areas.
WTO GPA country construction material means a construction material that-
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C.1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction material, excluding COTS fasteners. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.
(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
["none"]
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(4)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(4)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost…