Amendment 0005_70Z04724RPCNI0006.pdf
PDF 1 MB Posted
- Attached to
- REBUILD FAMILY HOUSING FORT WADSWORTH PHASE I AT U. S. COAST GUARD SECTOR NEW YORK, STATEN ISLAND, NY
- Solicitation number
- 70Z04724RPCNI0006
About this file
This document is an Amendment to Solicitation 70Z04724RPCNI0006 for the design-build demolition and construction of Fort Wadsworth Family Housing Facilities located at U.S. Coast Guard Sector New York, Staten Island, NY. The project includes demolition of several apartment buildings, site preparation, installation of new utilities, road and sidewalk repairs, and new multiplex construction with supporting infrastructure. Key changes in this Amendment include:
- Extending the proposal due date from October 29, 2024 to November 26, 2024 to allow time for a Project Labor Agreement.
- Increasing the page limits for the Conceptual Design and Sequence of Design / Construction narrative factors from 7 to 10 pages each.
- Clarifying requirements for the use of natural gas for HVAC, plumbing, and appliances.
- Adding a requirement for a lightning protection system for the housing clusters.
- Removing references to outdated Executive Orders 13423 and 13514.
The solicitation is restricted to current DHS/USCG National Multiple Award Construction Contract III - Pool One (NMACC III-Pool 1) contractors, and a Project Labor Agreement is required.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
REBUILD FAMILY HOUSING FORT WADSWORTH PHASE I AT U. S. COAST GUARD SECTOR NEW YORK, STATEN
ISLAND, NY
Contracting Division USCG/Facilities Design & Construction Center 5505 Robin Hood Rd, Suite K Norfolk, VA 23513-2431
9A. AMENDMENT OF SOLICITATION NUMBER
0005 10/21/2024
70Z04724RPCNI0006
08/27/2024
Description of Amendment 0005: SEE CONTINUATION PAGE
Amendment 0005
70Z04724RPCNI0006
SOLICITATION 70Z04724RPCNI0006 IS AMENDED AS FOLLOWS:
TASK ORDER ANNOUNCMENT:
1. RFI #09, Closing Date Refer to Task Order Announcement page 4, CLOSING DATE.
Change “submit proposals on October 29, 2024” to “submit proposals on November 26, 2024”.
2. RFI #56, 52.204-8 Annual Representations and Certifications Refer to Task Order Announcement page 6, FAR 52.204-8 Delete: FAR 52.204-8 Annual Representations and Certification (May 2024).
Replace with: FAR 52.204-8 Annual Representations and Certification (May 2024) (Deviation JAN 2024)
3. RFI #59, Narrative page count Refer to Task Order Announcement page 23, Non-Price Factor 1-Page Limit.
Change page limit from 7 pages to 10 pages.
4. RFI #60, Narrative page count Refer to Task Order Announcement page 23, Non-Price Factor 2-Page Limit.
Change page limit from 3 pages to 10 pages.
5. RFI #150, Deadline for submissions of RFI(s) Refer to Task Order Announcement page 4, RFI Deadline.
Change deadline date from October 15, 2024, to October 29, 2024.
6. Amendment attachment: RFI Questions and Responses
RFP GUIDE SPECIFICATIONS 21-14089081 (Phase I):
RFI #50 RFP Specification Section 01800-1.13 Electrical
ADD Paragraph:
“Provide a lightning protection system for each cluster of housing units. System shall be master labeled by a testing laboratory or by a testing laboratory certified installer. Provide a perimeter ground ring around the housing clusters with minimum size #1/0 bare stranded copper cable,10 foot x ¾ inch copper clad steel ground rods at maximum 10-foot intervals and with a minimum of two test wells for ground rod access. All connections to the ground ring shall be exothermically welded. Building lightning protection shall comply with NFPA 780”
Amendment 0005
70Z04724RPCNI0006
RFI #70, RFP Specification Section 01800-1.3.2.4
DELETE: Second sentence; "See Appendices L and M, regarding credits, roles, and responsibilities related to achieving certification.”
RFI #68, RFP Specification Section 01800-1.3.2
DELETE: Regarding LEED, remove “v4” throughout RFP.
ADD: For clarification purposes, the project shall follow requirements of the LEED v4.1 Residential:
Multifamily.
RFI #66 Section 01800 1.3.2.2 LEED Rater
ADD Paragraph:
“LEED Green rater shall be retained as a third-party contractor. LEED Green Rater shall be involved with. LEED Green Raters must be involved with the project from the design phase (prior to a preliminary rating, as required by rating system) and throughout the construction process and are responsible for providing on-site verification services for registered LEED residential projects, verifying that the project is designed and built to the rigorous requirements of the LEED rating system through documentation review and onsite verification, and assembling the project submittal package for submission to GBCI for certification review.”
RFI #23, #24, #57 RFP Specification 01800-1.3.1
DELETE: “Executive Order (EO) 13423 and Executive Order (EO) 13514
END OF AMENDMENT LANGUAGE
Note
Failure to acknowledge amendments may be cause for rejection of your offer.
RFI# Date RFP Reference RFI Questions Government Response Amendment 0 30-Sep-24 Attachments Attachment D file has an error when trying to open. See amendment 0004 for file re-upload. 0004 1 2-Oct-24 01 80 00, 1.3.1, 1.3.2, and 1.4.10
1.4.10 specifies the use of natural gas for residential appliances (ranges/stoves and/or dryers), and mechanical and plumbing equipment. 1.3.1 Sustainable Design specifies project compliance with Executive Order 13514, dated October 5, 2009. The stated goal of EO 13514 is "to establish an integrated strategy towards sustainability in the Federal Government and to make reduction of greenhouse gas emissions (GHG) a priority for Federal agencies." Please confirm the use of natural gas as specified in 1.4.10 is compliant with EO 13514.
Comply with 01800-1.4.10 that specifies natural gas for residential appliances. 0005
2 2-Oct-24 01 80 00, 1.3.2, and 1.4.10
1.4.10 specifies the use of natural gas for residential appliances (ranges/stoves and/or dryers), and mechanical and plumbing equipment. 1.3.2 LEED for Homes Certification specifies the Mandatory requirement EQc2.2 Enhanced Combustion Venting Measures - Install no combustion equipment in the homes. Natural gas appliances and mechanical and plumbing equipment are combustion equipment requiring combustion venting. Please confirm whether all electric appliances and mechanical and plumbing equipment are to be provided to comply with 1.3.2.
Due to site constraints, use of natural gas is authorized. 0005
3 2-Oct-24 01 80 00, 1.3.1 Please confirm whether the project site is located within an EPA radon zone, and if the buildings are to be designed and constructed with radon-resistant construction techniques in compliance with LEED for Homes v4.
Shall be determined by the DOR. 0005
4 2-Oct-24 01 80 00, 1.4.6, FEMA map 3604970331F
1.4.6 specifies that the "Contractor shall determine the most efficient and economical main building finish floor elevation based upon the closest 100-year floodplain elevation to the site established by FEMA, the International Building Code and ASCE 24-14." "The site is in Zone X, per FEMA map 3604970331F dated September 5, 2007." No base flood elevations or depths are shown within this zone. FEMA map 3604970331F shows the closest 100-year floodplain elevation to the site as Zone AE (EL 11/ NGVD 29).
Please clarify the base flood elevation to be used for the project site.
To be answered in a future amendment.
5 2-Oct-24 Existing Utilities Please confirm if the Contractor should include consumption costs for existing utilities (water, electric, natural gas) used during the construction of the project?
To be answered in a future amendment.
6 2-Oct-24 Pre-Existing Hazardous Material
Please confirm that Owner will indemnify the Contractor for any loss, cost, expense, or fine related to any pre-existing hazardous material.
Indemnification is an inherent violation of the Anti-deficiency Act, and such clauses requiring such, are unenforceable against the government. To the extent that unknown or unforseen site conditions arise, the contractor is entitled to submit e request for equtiable adjustment, and pursue remedy through the claims process.
7 2-Oct-24 Liquidated Damages
Please confirm that Liquidated Damages will be the sole and exclusive remedy for delay. Reference FAR 52.212-12, and our approrpropriate termination clause in the NMACC III-Pool 1 IDIQ.
8 2-Oct-24 Consequential Damages
Please confirm a mutual waiver of consequential damages, as listed, will be inserted into the final contract documents: “In no event shall any Indemnified Party or the Contractor be liable to the other for any indirect, special or consequential damages (including, but not limited to, loss of profits, interest, earnings or loss of use) whether arising in contract, tort or otherwise.”
Reference FAR 52.212-12, and our approrpropriate termination clause in the NMACC III-Pool 1 IDIQ.
9 2-Oct-24 Upon speaking to the NY Building and Construction Trades Council (NYBCTC), it is a lengthy process to get an executed Project Labor Agreement in place to include in our proposal. As of 10/1/24, we are still working to get a draft PLA from the NYBCTC. Once received, it will need to be reviewed and comments submitted to the NYBCTC, then negotiated, then approved by all the local trade unions, and then sent to DC for final approval by the North American Building Trades Unions, NABTU, (NYBCTC's parent company). Once we have a final PLA, we need to have our bidding subcontractors agree to the PLA prior to submitting our price proposal. This process can easily take two months from receipt of the draft PLA.
Please consider adding an additional four weeks to the current due date adjusting the due date to 26 November 2024?
Change CLOSING DATE from " October 29, 2024" to "November 26, 2024". (See Amendment 0005).
10 2-Oct-24 Specification section 01800, 1.9.3 – States there are no salvage requirements. During the Site Visit on 9/17/24, it was indicated there maybe some appliance that USCG will want to retain prior to the start of demolition activities. If so, please confirm who (contractor or Government) will be responsible for the removal and salvage of any appliances (ranges, washers/dryers, refrigerators, dishwashers, furnaces, water heaters) USCG wants to retain. If no appliances are being retained by USCG, please confirm the contractor is responsible for removal and disposal of all appliances.
To be answered in a future amendment.
11 2-Oct-24 We cannot find the proposal text requirements. Please provide or confirm the offerors proposal shall match the same format requirements as the NMACC III (Phase II) non-price factors which was "Text pages 8-1/2 x 11 format with 10 point minimum, Times New Roman font on text pages" and "Drawing 11 x17 inches with 9 point minimum, Times New Roman font on Drawings."
Confirmed, yes. 0005
12 2-Oct-24 Specification section 01800, 1.11 – Permits the use of gas fired water heater. Since natural gas is on site, please confirm natural gas is allowed to be used for this project?
Confirmed, yes. 0005
13 2-Oct-24 Specification section 1800, 1.11.8 – Provides requirements for gas distribution for the project. Since natural gas is on site, please confirm natural gas is allowed to be used for this project?
Confirmed, yes. 0005
14 2-Oct-24 Specification section 1800, 1.12.1.3.1.2 – Please confirm gas furnaces are allowed for this project since natural gas is on site?
Confirmed, yes. 0005
15 2-Oct-24 Confirm it is to be assumed for bidding purposes the existing electrical service can accommodate the new building usage.
Confirmed, yes. 0005
16 2-Oct-24 Specification section 01800,1.11.3 - confirm freeze proof and not frost proof are to be provide at the exterior based on project location climate?
To be answered in a future amendment.
17 2-Oct-24 Confirm the existing housing units HVAC and water heater units are natural gas? To be answered in a future amendment.
18 2-Oct-24 Confirm it is to be assumed for bidding purposes the existing sanitary and water service can accommodate the new buildings usage?
To be answered in a future amendment.
19 2-Oct-24 Confirm it is to be assumed for bidding purposes the existing electrical service can accommodate the new building usage.
To be answered in a future amendment.
20 2-Oct-24 For bidding purposes, please confirm we should assume all existing utilities we are to tie into are in good working condition?
To be answered in a future amendment.
21 2-Oct-24 Specification section 01800, 1.1.1.4 states residential buildings except for mechanical and equipment rooms shall be accessible to the physically handicap per ADA. Please confirm this ADA compliant accessibility is only for the residential units identified as "Accessible" on Tables in section 1.1.1 and the RFP drawings?
To be answered in a future amendment.
22 2-Oct-24 Specification section 01800, 1.2 discussed prescriptive requirements but does not specifically identify such.
Please identify the prescriptive design elements provided in the RFP and RFP drawings?
RFP 01800-1.2 provides guidance on how the Contactor shall interpret the RFP drawings and specification contained herein.
23 2-Oct-24 Specification section 01800, 1.3 includes EO 13423 as Sustainable Documents we need to meet requirements and goals. This EO is very broad and generic. Please specifically identify the requirements / goals required in this EO for this project?
EO 13423 reference has been removed. See Amendment 005. 0005
24 2-Oct-24 Specification section 01800, 1.3 includes EO 13514 as Sustainable Documents we need to meet requirements and goals. This EO is very broad and generic. Please specifically identify the requirements / goals required in this EO for this project?
EO 13514 references has been removed. See Amendment 005. 0005
25 2-Oct-24 Specification section 01800, 1.4.5 Utility Meters states to re-use existing equipment where possible and return un- used to Facilities Engineer. Section 1.9.3 states no salvage. Does existing meters meet current RFP advanced metering requirements? For bidding purposes, please confirm we shall assume all new metering?
To be answered in a future amendment.
26 2-Oct-24 Specification section 01800, 1.4.7. Please confirm the only family housing units to be designed for any ADA compliance is the housing units identified as "Accessible"?
All units shall be designed to meet the applicable accessibility requirements for these spaces including UFAS, the Fair Housing Act Accessibility Guidelines, and ADA.
27 2-Oct-24 Specification section 01800, 1.4.10 Gas. Confirm we can use natural gas for HVAC and plumbing equipment?
To be answered in a future amendment.
28 2-Oct-24 Specification section 01800, 1.6.5 for bidding purposes please confirm that we should assume the percolation test will be acceptable and no corrective work resulting from the percolation test shall be included on our bid price?
To be answered in a future amendment.
29 2-Oct-24 Specification section 01800, 1.6.7.4 for bidding purposes please confirm that we should assume the soil test will be acceptable and no corrective work resulting from the soil test shall be included on our bid price?
To be answered in a future amendment.
30 2-Oct-24 Specification section 01800, 1.7.2 states minimum R value for all roofs and ceilings is R-49. Please clarify what all ceilings mean? Isn’t this just for the roof?
RFP states "The minimum acceptable R-Value for all roofs or ceilings that cover conditioned spaces is R-49." This language is present to allow contractors to determine their means & methods of how to insulate the structure. For reference, the IECC indicates a ceiling insulation minimum, however a mechanically-ventilated attic space with an insulated attic floor may also be appropriate for this RFP, as may a conditioned attic (with its insulation designed either above or below the roof structure.) This language is not meant to double the insulation requirement at the attic, but is used to allow flexibility in design consideration.
AMENDMENT 0005 PRE-PROPOSAL INQUIRY/REQUEST FOR INFORMATION - Family Housing Fort Wadsworth
31 2-Oct-24 Specification section 01800, 1.7.2.1 states a sample wall shall be constructed on site prior to ordering and installing any exterior materials. Please provide more detail / specifics of the exterior wall mockup required?
Sample walls are a standard of practice in building construction projects. Having a wall ready for exterior finish materials, once received, is necessary to display how the construction of this building comes together and allows a complete understanding of how materials are to be attached, punctured, or connected.
32 2-Oct-24 Specification section 01800, 7.2.3 Roof systems - are downspout splash blocks allowed? The Family Housing Design CSTO SILC-CSTO-36-11 55 13 11-01 that is a requirement for this RFP already requires splash blocks to be part of this RFP.
Where downspouts are not adjacent to sidewalks, provide precast concrete splash blocks and set splashblocks to redirect water away from the foundation along perimeter. At or adjacent to sidewalks and other hard surfaces, no splashblocks are allowed to be provided as part of this RFP: Instead, at or adjacent to concrete surfaces, provide rubber boots at downspouts to directly connect to below-grade stormwater system at bottom of downspout (assume minimum 12" from-grade boot) to prevent slippery conditions that may occur during inclement weather.
33 2-Oct-24 Specification section 01800, 1.7.4.9 states walls, partitions, and floor/ceilings separating dwelling units from public or service areas shall be no less than STC 50. Please confirm there are no public areas within these proposed buildings?
As this is an RFP for the design and construction of buildings, while public spaces may not exist in the drawings that are provided as part of this RFP, this cannot be confirmed as the decision to provide spaces leans on the contractor's expertise to determine.
34 2-Oct-24 Specification section 01800, 1.7.4.9 states walls, partitions, and floor/ceilings separating dwelling units from public or service areas shall be no less than STC 50. Please define what rooms are defined as service areas? Also if these rooms are within the dwelling unit and not adjacent to another dwelling unit what STC rating shall these walls and ceilings have?
Follow RFP as written for the entirety of this RFI line item. For additional requirements regarding STC ratings necessary to provide as part of this RFP, see Appendix F. As this is a solicitation for the design and construction of buildings, while service spaces may not exist in the particular drawings that are provided as part of this RFP solicitation, the government cannot confirm that service spaces will not be provided as part of the design decisions that the A/E will make as part of their RFP response design. If any public or service spaces exist in the A/E proposal, the Sound Transmission Class must be provided to meet this RFP minimum.
35 2-Oct-24 Specification section 01800, 1.7.5.6 states windows need to pass South Florida protocols, TAS-201, TAS- 202, TAS- 203, have NOAs and Florida Product Approvals for large missel impact. Please confirm these South Florida hurricane requirements are required ?
To be answered in a future amendment.
36 2-Oct-24 Specification section 01800, 1.7.5.9 states louvers are to meet Miami-Dade structural tests. Please confirm this is required?
Confirmed. 0005
37 2-Oct-24 Specification section 01800, 1.8.3.2 please confirm exposed structural steel - Steel Structures in Corrosive Environments is required for this project?
Where structural steel is used in exposed areas, comply with 01800-1.8.3.2. 0005
38 2-Oct-24 Specification section 01800, 1.9.1.3 Being a Federal project, please confirm no NY state or local permits are required?
Shall be determined by the DOR 0005
39 2-Oct-24 Specification section 01800, 1.9.6. For bidding purposes, please confirm we shall assume PFAS is not known to be present?
PFAS is not known to be present. 0005
40 2-Oct-24 Please confirm that the provided flow test in Amendment 0002, Attachment E, file name “E USCG Ft Wadsworth Transmittal 54 Hydrant Flow Test” dated April 2023 is to be used for bidding purposes.
Confirmed, yes. 0005
41 2-Oct-24 Specification section 01800, 1.11 Plumbing and 1.12 HVAC references and details out the use of natural gas for plumbing and HVAC equipment. Since natural gas is on site, please confirm natural gas fired plumbing and HVAC equipment can be used for this project.
Confirmed, yes. 0005
42 2-Oct-24 Specification section 01800, 1.11 Plumbing and 1.12 HVAC references and details out the use of natural gas for plumbing and HVAC equipment. Since natural gas is on site, please confirm natural gas fired appliances can be used for this project.
Confirmed, yes. 0005
43 2-Oct-24 Specification section 01800, 1.11.3.1 states handicap water closets and lavatories shall confirm to ADA standards. Please confirm that only Accessible dwelling units are to receive and comply with ADA standards?
Confirmed, yes. 0005
44 2-Oct-24 Specification section 01800, 1.12.1.3.7 please confirm that radiant floor heating is required for all bathrooms? Even ones that are on above floors that have conditioned space below? Even bathrooms without showers?
To be answered in a future amendment.
45 2-Oct-24 Specification section 01800, 1.12.1.3.8 calls out for exhaust in powder rooms. What is defined as powder rooms, and is exhaust required in these rooms?
To be answered in a future amendment. 006
46 2-Oct-24 Specification section 01800, 1.12.1.6 Sea Salt Spray Resistance. Please confirm this section requirements are necessary for this project?
Confirmed, sea salt spray resistance is required. 0005
47 2-Oct-24 Specification section 01800, 1.13.1 Electrical Service. Please confirm the primary service is in good working condition and adequate for this project?
For bidding purposes, assume existing utilities will support the load demand of the new buildings. Primary service and work on it is outside the scope of this contract.
48 2-Oct-24 Specification section 01800, 1.13.1 Electrical Service. Please confirm the primary service and transformer is not part of this scope of work?
Confirmed, primary service and tranformer work is outside the scope of this contract. 0005
49 2-Oct-24 Specification section 01800, 1.13.10 Lighting. We do not find any requirements for lighting controls.
Please confirm automated lighting controls are not intended and not part of this project scope?
In paragraph 1.13 there is a reference to the design complying with the Family Housing Design CSTO SILC-CSTO-36-11 55 13 11-01. In this document there is guidance to lighting controls and references that the DOR should make note.
50 2-Oct-24 Specification section 01800, 1.13 Electrical. We do not see any requirements for lightning protection.
Please confirm lightning protection is not required for the buildings?
See Amenment 0005 0005
51 2-Oct-24 Specification section 01800, 1.14.1 requires camera at Entry Gate. We cannot find any other camera locations. Please confirm only camera is at Entry Gate?
Confirmed, yes. 0005
52 2-Oct-24 Specification section 01800, 1.18 states to comply with all applicable federal, state and local environmental requirements. Being a Federal project, does NY state and local AHJ / jurisdictions apply? Are we required to obtain NY state and local permits?
Shall be determined by the DOR 0005
53 2-Oct-24 Specification section 01800, 18.2 mentions FAA and FCC. Please confirm there are no requirements with respect to FAA and FCC?
Cannot confirm. The Contractor shall be responsible for identifying and obtaining all required permits.
54 2-Oct-24 Specification section 01800, 1.18.6 for bidding purposes, please confirm we shall assume there are no cultural, historic or archaeological resources known to be on the project site?
Cannot confirm. Refer to RFP Attachment B - Environmental. 0005
55 2-Oct-24 Please confirm the Option Items will be awarded at the same time as the Base award and the contract completion time for the Options are within the project Period of Performance?
Refer to Task Order Announcement, page 3 OPTION ITEMS, page 28 OPTION ITEMS Price Sheet, and FAR Clause 52.217-5 in the NMACC II-Pool 1 IDIQ.
56 2-Oct-24 Please confirm if we need to provide just section 52.204.24(d) completed for the Reps and Certs in our proposal, or do we also need to provide in our proposal 52.204-8 provided in the TOA as well?
Yes, provide 52.204.24(d). And yes 52.204-8 as per HSAR guidelines. See amendment to add (DEVIATION JAN 2024) to FAR 52.204-8 Annual Representations and Certifications (May 2024) on page 6 of Task Order Announcment.
57 2-Oct-24 Please confirm that the only Executive Orders that are part of this RFP / Contract are the ones specifically listed in the RFP, specifically EO 13423 and EO 13514?
EO 13514 and EO 13423 references have been removed from the RFP Specification with Amendment 005. The Task Order Announcement did not specifically list all applicable Executive Orders by numbers. Refer to Task Order Announcment page 4, PROJECT LABOR AGREEMENT, FAR Subpart 22.5. Refer to FAR Provision 52.222-33(c)(6) and FAR Clause 52.222-34(c)(6). Furthermore, ALL Executive Orders in the the NMACC III-Pool 1 IDIQ apply as well.
58 2-Oct-24 Non-Price Factor 1 - Conceptual Design / Site Narrative. States to provide a written narrative to describe proposed "means and methods" of the conceptual building design… Means and methods typically is for the construction approach of the design. Please confirm "means and methods" for Factor 1 means the "design approach"?
To be answered in a future amendment.
59 2-Oct-24 Non-Price Factor 1 - Conceptual Design / Site Narrative. Factor 1 allows for 7 pages for the narrative. Due to the numerous design disciplines, and other requirements listed in (a) through (d), please increase the narrative page count to 10 pages?
Narative page count is increased from 7 to 10 pages (see amendment 0005). 0005
60 2-Oct-24 Non-Price Factor 2 - Sequence of Design / Construction. Factor 2 allows 3 pages for this narrative. Due to the numerous requirements listed in (a) and (b) including approach for design and construction, permitting, construction phasing, permitting, commissioning, project closeout, logistical approach, safety, etc., please consider increasing the page count to 10 pages for Factor 2?
Narative page count is increased from 3 to 10 pages (see amendment 0005). 0005
61 2-Oct-24 RFP Drawing (C-101) shows area for laydown. Can we use the project site for trailers and parking? To be answered in a future amendment.
62 2-Oct-24 RFP Drawing (C-101) shows haul routes are depicted on the drawings and C-103 only has portions of the haul routes being milled and overlay. For bidding purposes, shall we assume haul routes are in good condition and adequate and only mill and overlay will be required? Should we assume areas not shown to be milled and overlay will not require any re-surfacing?
To be answered in a future amendment.
63 2-Oct-24 Please confirm that the dwelling unit appliances listed in the Appendix K Outfitting Item Information Sheets are to be electric, and not gas fired appliances since there is conflicting information in the RFP?
To be answered in a future amendment.
64 4-Oct-24 Conceptual Site Plan C-103 identifies Drainage Improvements Known Problem Area 2 at the intersection of Ayers Road and USS North Carolina Road. However, C-103 does not show any road pavement work (2" mill & overlay) at this location. Please clarify the drainage problem at Area 2, such as the omission or under sizing of storm drainage structures in the area.
To be answered in a future amendment.
65 4-Oct-24 A-106 provides proof of concept 4-BR Townhouse Plans. Clusters No. 5, 8, 2 & 10 include a 4-BR Townhouse Accessible. Please confirm that only the single story Duplex units are to be accessible (ADA compliant).
To be answered in a future amendment.
66 4-Oct-24 01 80 00 1.3.2.2 states that the Contractor is to retain a LEED for Homes Rater on their design team. USGBC specifies that a LEED Green Rater cannot be a member of the design or contractor team for a LEED for Homes project, since the Rater is a member of the Verification Team. Please clarify that Contractors are to retain a 3rd party LEED Green Rater for this project.
Confirmed, retain a 3rd party LEED Green rater. See Amendment 005. 0005
67 4-Oct-24 01 80 00 1.3.2.5 Mandatory EAp1.2 Exceptional Energy Performance states, "For modeling purposes, the ductless mini-split heat pump should be allocated no more than 70% of the heating load." 1.12.1.3.6 states "ductless split units are prohibited for residential construction." Please clarify if use of ductless mini-split systems are prohibited for this project.
To be answered in a future amendment.
68 4-Oct-24 01 80 00 RFP Guide Specification, Section 01800, Paragraph 1.3.2 requires LEED for Homes v4. However, Section 01800, Paragraph 1.3.2.1 requires the use of "the latest LEED for Homes rating system in the design and construction of this project." The latest LEED for Homes rating system that is available is LEED v4.1 Residential: Single Family Homes. Please clarify if LEED for Homes v4 or LEED v4.1 Residential: Single Family Homes is required.
The project should follow LEED 4.1 Residential Multifamily since the project contains towhhomes. See Amendment 005
69 4-Oct-24 01 80 00 RFP Guide Specification, Section 01800, Paragraph 1.3.2.5 lists a series of MANDATORY and PREFERRED credits in support of the LEED certification. However, these credits are from an outdated version of LEED (we believe it is LEED for Homes v2008/v2010). The requirements will not be directly translatable to the current required LEED version. Please revise the list of MANDATORY and PREFERRED credits to align with the required LEED certification or remove the list from the RFP.
To be answered in a future amendment. 006
70 4-Oct-24 01 80 00 RFP Guide Specification, Section 01800, Paragraph 1.3.2.4 makes reference to Appendices L and M.
These were not found in the RFP package. Please provide.
Appendix L and M do not exist. See Amendment 005. 0005
71 4-Oct-24 01 80 00 Is there electrical load information (kilowatts demand) over a 12-month continuous period for any of the existing units?
That information is not available. 0005
72 4-Oct-24 01 80 00 Is a copy of the site power distribution system single line available? Can the government provide electric service equipment information and sizes (amps, volts, phase) for the following multi-family units? Units to be demolished: 423, 427, 428, 430, 431, 432; Units to remain: 434, 440, 436, 438, 437, 435
This information is not available. 0005
73 4-Oct-24 01 80 00 Can the government confirm the output voltage/phase of the existing to remain 300 KVA transformers? For bidding purpose, the contractor may assume the output to the units is 208-3.
This assumption must be confirmed by the DOR.
74 4-Oct-24 01 80 00 The "A ICAM Utilities Survey" doesn't show full site distribution. Is an electrical site plan showing full site electrical distribution available?
The government does not have this information. 0005
75 4-Oct-24 01 80 00 Is each existing housing unit fed at 208-3 via a meter center with a MCB that subfeeds an individual 208-1 meter and services disconnect for each tenant? Can the government provide more information on the existing units' metering set up?
For bidding purpose, the contractor may assume that each unit is fed 208-3. This assumption must be confirmed by the DOR. The government does not have additional information to provide on the existing units' metering set up. The DOR should investigate and address in their design.
76 4-Oct-24 01 80 00 RFP 1.13.3.3 says "Work on the primary side of the transformers, to include replacement, repair, and relocation of the transformers is not authorized in this project". There appears to be a possible conflict with the location of new Unit No. 3. and the existing transformer serving existing Unit #440. Can the government provide a surveyed location of transformer feeding existing building 440 and MV line to the next downstream transformer?
The government cannot provide the requested information. 0005
77 4-Oct-24 01 80 00 The RFP Guide Specification references old Executive Order (EO) numbers: 14057 (Biden) revoked 13834 (Trump) which revoked 13693 (Obama) which revoked 13423 (Bush) and 13514 (Obama). 13423 and 13514 are the only EOs referenced in the RFP. Are the old referenced EOs 13423 and 13514 still applicable? How does that affect enforcement of EO 14057?
To be answered in a future amendment.
78 4-Oct-24 01 80 00 Per EO 14057, electrification of the housing via electric heating and electric water heating will drive the demand loads on two of the existing transformers above 300 KVA, resulting in the need to add utility transformers and associated medium voltage distribution. RFP 1.13.3.3 says "Work on the primary side of the transformers, to include replacement, repair, and relocation of the transformers is not authorized in this project". How will this scope change due to EO 14057 be addressed?
To be answered in a future amendment.
79 4-Oct-24 01 80 00 RFP section 1.13.6.4 says "... Provide a manual transfer switch with connections to the main service panel and utility service so that a portable generator could be connected to provide power to the main service equipment in the event of extended outage of utility power." Is the intention to provide a single point connection (such as a meter stack with 2 meters) to the duplexes, and would the government prefer a 3-phase or a 1-phase connection for the duplexes?
The DOR shall provide a beneficial solution to this requirement in their design. 0005
80 4-Oct-24 Drainage Improvements Known Problem Area 3 noted on C-103 is outside the project limits boundary shown on C-101. Please confirm scope of work associated with resolving drainage Problem Area 3 is to be included within the RFP response.
To be answered in a future amendment.
81 10/7/2024 Tax Status Please confirm if this project is taxable or if USCG will consider this a capital improvement project per NY and will provide us the form to allow permanent materials to be tax exempt.
Refer to FAR clause 52.229-3 Federal, State, and Local Taxes in the NMACC III-Pool
1 IDIQ.
82 10/7/2024 Attachment D - Page 2`
The Watershed Study mentions a negative slope in the pipe between MH-6 and MH-41. The area of the park interior to Iowa Circle drains to CB-14 which flows towards MH-6. If stormwater cannot flow downstream from MH-6 due to the negative slope, the drainage issues noted in the park area may not be able to be resolved. Should fixing the pipe slope between MH-6 and MH-41 be included in this project's scope?
To be answered in a future amendment.
83 10/7/2024 C-103 / F-4 Drainage Improvements Known Problem Area 2 is outside the limits of pavement mill and overlays.
Replacing the pipes connecting to CB-33 and CB-34 would require surface restoration. Attachment D notes that pipes may be undersized and or at incorrect slopes in this area.
To be answered in a future amendment.
84 10/7/2024 01800-1.11.3.9.9 Floor drains are only noted in utility rooms per 01800-1.11.3.9.9. Are floor drains needed at the garage floors?
Floor drains are not required in garages. 0005
85 10/7/2024 Please confirm the USCG is the Authority have jurisdiction for all approvals of design and installation and no other special permitting with the port authority other the Environmental and Stormwater permitting with EPA is required.
To be answered in a future amendment.
86 10/8/2024 01800-1.4.5 / 01800-1.4.8
Water system spec 01800-1.4.5 states to provide a water meter for each housing unit. Spec 01800-1.4.5 stats that the Coast Guard is responsible for providing all meters. Please confirm the USCG is providing the water meters.
To be answered in a future amendment.
87 10/8/2024 01800-1.4.1.1 Spec 01800-1.4.1.1states “The Contractor shall perform test pits, vacuum excavating and utility potholing as required to determine the exact locations of underground utilities” however existing utility surveys are provided in the RFP (specifically contained within Amendment 2). Please confirm the utilities surveys provided in the RFP are to be used for pricing & design purposes and deviations from the provided information encountered on site will be treated as a differing site condition?
To be answered in a future amendment.
88 10/8/2024 01800-1.10.3.1.3 and
018000-1.10.3.1.3 notes PEX - Cross Linked Polyethylene or CPVC pipe can be used for fire protection.
Plumbing "New Building Design and Construction, page 20 (7.3 Mechanical materials) notes that Cross- Linked Polyethylene water (PEX) supply systems shall not be used. Please verify that PEX is approved for Fire suppression but not approved for plumbing.
To be answered in a future amendment.
89 10/8/2024 C-101 C-101 Existing Conditions Plan does not include the existing site utilities at the locations of the six structures to be demolished or the new family housing. Please provide the existing site utilities within the Project LOD.
To be answered in a future amendment.
90 10/9/2024 01800-1.12.1.3.7 01800-1.12.1.3.7: Radiant floor heating (electric or hydronic) is required for all bathrooms. The Room requirements, page 3 of 4 for Master Bathroom in Appendix F, Full Bathroom and Half-bathroom notes auxiliary heating (lamp or fan-forced coil) is needed. Please verify both radiant floor and auxiliary heating are both required.
To be answered in a future amendment.
91 10/9/2024 Appendix F Outdoor areas (patios) do not require fire protection or sprinkler system per the Appendix F Individual Space Criteria Sheets. Please verify sprinkler systems are not required.
To be answered in a future amendment.
92 10/9/2024 01800-1.4.10 Section 01800 -1.4.10: It is noted the contractor shall coordinate with the natural gas utility company to install new gas laterals to service the family housing units. Natural gas will be used for residential appliances (ranges/stoves and dryers), mechanical and plumbing equipment. Will the owner carry these costs associated for the natural gas utility company work or should an allowance be added to the bid form?
To be answered in a future amendment.
93 10/9/2024 01800-1.12.5 Please verify Testing, Adjusting and Balancing does not need to be 1st tier or direct contract under the General Contractor and that the TAB Agency can be hired under the Subcontractor.
To be answered in a future amendment.
94 10/16/2024 01800-1.5.3/4 01800-1.5.3 states for bidding purposes, assume foundations are reinforced concrete strip footings with a depth sufficient to overcome soil movement, as required by code. 01800-1.5.4 states that the contractor shall bear all costs of the actual foundation type. Please confirm that if it is determined that strip footings alone will not be sufficient to support he buildings after the geotechnical analysis is complete, the contractor will be compensated for additional costs associated with the increased foundation scope.
To be answered in a future amendment.
95 10/16/2024 01800-1.7.5.1.4 & 01800- 1.12.1.3.5
The garage door is specified to have an R value of 7 in 1.7.5.1.4 & 18 in 1.12.13.5. Please confirm requirement.
To be answered in a future amendment.
96 10/16/2024 01800- 1.12.1.3.10
Ceiling fans are noted to be included in bedroom, living / family room, and dining room areas. The 4BR townhouse kitchen on A102 shows a ceiling fan, please confirm if this is required.
97 10/16/2024 01800-1.15.2 Please confirm that all fiber and copper OSP cabling will be provided by the service provider, and contractor is only responsible for pathways
To be answered in a future amendment.
98 10/16/2024 01800-1.15.2 Please expound on what utility fees contractor is responsible for in relation to communications service providers
To be answered in a future amendment.
99 10/16/2024 01800 - 1.1.2.1 The potable/domestic water utility system is owned by the National Park Service. The existing units are individually metered for potable/domestic water. The new units shall be individually metered for potable domestic. Similarly, fire hydrants are owned by the National Park Service. Please confirm that the National Park Service is responsible for the installation of the potable/domestic water service up to the meter. No added costs should be included by the contractor.
To be answered in a future amendment.
100 10/16/2024 01800 - 1.1.2.2 The sanitary sewer utility system is owned by the National Park Service. The new units shall be individually metered. Please confirm that the National Park Service is responsible for the installation of the sanitary sewer services to the new units including the meter. No added costs should be included by the contractor.
To be answered in a future amendment.
101 10/16/2024 01 80 00-1.10 UFC 1-200-01 and UFC 1-300-06 are not in the list In Section 01800_1.1.3, “References, Codes, and Standards”. Additionally, Section 01800_1.10 requires the fire protection design and construction work to meet the applicable NFPA codes, and the occupancy type(s) to be as determined by the latest International Building Code. Please verify life safety code analysis and fire protection systems design should also follow UFC codes.
To be answered in a future amendment.
102 10/16/2024 01 80 00-1.10 The RFP Section 1.10.1.1.3 says “Provide clear strobes marked with the word “ALERT” for use by the fire alarm system.” According to MFPA 72, “ALERT” marking is typically required only for a combined system of fire alarm and mass notification. However, UFC 3-600-01 Section 9-18.6.3 directs the use of “ALERT” instead of “FIRE” for strobes. Please confirm whether UFC requirements apply to fire systems.
To be answered in a future amendment.
103 10/16/2024 01 80 02 Please confirm the number of On-Site inspections required for the QFPE. RFP references the following in Section 01802_1.11; however, fire protection on-site inspection/testing requirements are not listed.
1. Post-Award Conference (with flow test)
2. Rough-in Inspection (fire alarm and fire suppression systems)
3. Fire Stopping Inspection
4. Pre-final testing (fire alarm and fire suppression systems)
5. Final Testing (fire alarm and fire suppression systems)
6. Please confirm if the QFPE will be required to perform an in-person visual inspection of the location of the fire hydrants and fire department access.
7. Please confirm if the QFPE will be required to witness hydrostatic testing and inspection of the underground mains.
8. Please confirm if the QFPE will be required to witness flushing of the underground mains prior to connection to the riser.
To be answered in a future amendment.
112 10/16/2024 01 80 00-1.10 The RFP Section 01800_1.10.9 specifies that “Exit requirements shall be based on the occupant load as calculated according to IBC.” If UFC 3-600-01 to be followed, in section 10-1.1, it requires to comply with NFPA 101 for all components and features related to means of egress. Please clarify which code, IBC or NFPA 101 should be followed to determine occupant load.
To be answered in a future amendment.
113 10/16/2024 01 80 00 Please confirm the type/style of fire department connection (FDC) for the new housing units. To be answered in a future amendment.
114 10/16/2024 01 80 00 Please clarify if manual pull stations are required for the fire alarm system If UFC 3-600-01 to be followed, in section 9-18.7.4.1, manual pull stations are required to be provided at all exits, regardless of occupancy.
Please confirm if this requirement applies to this project.
To be answered in a future amendment.
115 10/16/2024 The RFP is unclear regarding the domestic and fire incoming water service. Please confirm whether the intent is to provide separate domestic and fire services, which is consistent with the existing condition.
To be answered in a future amendment.
116 10/16/2024 01 80 00 Please confirm if each dwelling unit will require a dedicated fire water lateral, backflow preventer, and riser assembly, or if the dwelling units in a building can share a single fire water lateral and backflow preventer, but have separate riser assemblies in each utility room.
To be answered in a future amendment.
117 10/16/2024 01 80 00 RFP Section 1.10.1.1 - Please confirm that 60 hours of standby and 5 minutes of alarm for battery backup is required for the fire alarm system. UFC 3-600-01 requires 48 hours of standby and 15 minutes of alarm.
To be answered in a future amendment.
118 10/16/2024 RFP Drawings We noted that the RFP drawings A-101 & A-102 label the wall between adjoining units as a firewall, but according to IRC Section R302.2, only a fire-resistance-rated wall assembly is necessary for this application. Please confirm if the intent is to meet the firewall requirements, or if a fire-resistance-rated wall assembly would be sufficient to meet code.
To be answered in a future amendment.
119 10/16/2024 1802 Section 3.6 references "Inventory list of existing FFE to be relocated for concurrence". Is there FFE being relocated/reused? If so, will the government provide an inventory list with dimensions for DOR use? Will the GC be responsible for removing, storing, relocating? Question applicable to base scope + options.
To be answered in a future amendment.
121 10/16/2024 1802 These sheets identify furniture to be shown and keyed on the plans. "Some of the sheets say procurement and installation of furnishings and equipment are NOT included in the scope of this project." Is the procurement and installation of the furniture items that do not list this (with the exclusion if items listed as user provided) in the DOR and GC's scope? Question applicable to base scope + options.
To be answered in a future amendment.
124 10/16/2024 1802 Horizontal mini blinds are specifically called out at Bathrooms and Dining Room Area only. Are they to be at all exterior windows? Question applicable to base scope + options.
To be answered in a future amendment.
126 10/16/2024 01800 1.7.2.1;
IECC
Guide specification 01800, 1.7.2.1 indicates an R-value of exterior walls to be R-20. For this climate zone and wood framed walls, Energy Star/ IECC allows insulation to be R-20 continuous OR R-13 cavity insulation + R-5 continuous insulation. Confirm if R-13 cavity + R-5 continuous is acceptable.
To be answered in a future amendment.
128 10/16/2024 SILC-CSTO-36-
71 91 11 13-10
SILC-CSTO-36-71 91 11 13-10 (Amendment 2 attachment G, New Building Design and Construction),
5.3.1 indicates colors are to comply with an exterior color standard or Base Exterior Architectural Plan (BEAP). Please provide the exterior color standards or BEAP applicable to this project for color requirements and any other exterior building material requirements.
To be answered in a future amendment.
130 10/16/2024 01800 - 1.7.5.6.2 1.7.5.6.2 indicates windows to be "operable double hung windows that tilt infor ease of maintenance" and the window basis of design to be API Quality Windows. This company does not appear to provide double hung window units. Please provide alternate basis of design manufacturer and product line information.
To be answered in a future amendment.
131 10/16/2024 C-104 There are three locations called out for motorized traffic gates with key pad and security requirements.
There is no existing power and comms near any of these locations. Since the RFP excludes MV distribution and the addition of transformer, is the utility extending MV power distribution and adding transformers and comms to the three gates?
To be answered in a future amendment.
132 10/16/2024 1.13.3.3 Electrification of the housing via electric heating and electric water heating will drive the electric services (per each dwelling unit) above 200A at 208V-1ph (RFP requirement) and the demand load on two of the existing transformers above 300 KVA, resulting in the need to add utility transformers and associated medium voltage distribution. RFP 1.13.3.3 says "Work on the primary side of the transformers, to include replacement, repair, and relocation of the transformers is not authorized in this project". If two transformers are increased in capacity from 300 KVA to 500 KVA the buildings can be served from the existing locations. Will the utility consider this upgrade?
To be answered in a future amendment.
135 10/16/2024 01450 - 1.3 1.3 PERSONAL QUALIFICATIONS - SECTION 01450 Page 2 of 11 notes the following required staffing. 1.3.1 Superintendent: The superintendent shall have experience managing at least 3 prior design-build projects of a similar size and…