This performance work statement outlines environmental construction and optimization services required at Air Force bases in the Southwest region under task order FA8903-20-R-0013. The contractor shall provide project management, planning, reporting, and meeting support to maintain remedies and implement optimization activities at former George Air Force Base in California, former March Air Force Base in California, former Norton Air Force Base in California, former Williams Air Force Base in Arizona, and former Air Force Research Laboratory Mesa in Arizona. Services include regulatory engagement, documentation, and technical discussions to support restoration efforts at these installations in accordance with applicable federal and state laws and regulations. The performance period covers contractual and technical kickoff meetings with deliverables such as a progress report and meeting materials due within specified timeframes.

View the file

Other files for this federal contract opportunity

Other files attached to Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS) Southwest Region, newest first.
File Type Posted
06042020_FA8903-20-R-0013_BECOS_RFP_Questions_and_Answers_Set 3.xlsx XLSX spreadsheet
06032020_FA8902-20-R-0013_BECOS_RFP_QA Set 2 of 2.xlsx XLSX spreadsheet
Solicitation Amendment FA890320R00130002 SF 30 2.pdf PDF
20200603_FA890320R0013_BECOS_Southwest_Section_L_Amendment_01.docx DOCX document
Solicitation Amendment FA890320R00130001 SF 30.pdf PDF
05222020_v2_FA890320R0012_BECOS_Southwest_Questions and Answers set 1 of 2.xlsx XLSX spreadsheet
FA890320R0013 Southwest Amendment Changes.docx DOCX document
Southwest Solicitation Clauses Added and Removed.docx DOCX document
20200521_FA890320R0013_Southwest_BECOS_Section_M_Amendment_01.docx DOCX document
20200520_FA890320R0013_BECOS_Southwest_Section_L_Amendment_01.docx DOCX document
20200519_Southwest TO2 Price Model_Amendment_01.xlsx XLSX spreadsheet
IDIQ DD1423 CDRLS EXHIBIT B002-B003 (MGMT) Southwest BECOS vf1.pdf PDF
IDIQ PWS Attch 2 Southwest Acr and Def BECOS vf3.docx DOCX document
TO 2 PWS Attch 2 Williams Base Spec Req Southwest BECOS vf2.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT C001 (MGMT) Southwest BECOS vf1.pdf PDF
20191217_Compensation Plan Model.xlsx XLSX spreadsheet
TO 2 PWS Attch 1 Southwest Site List BECOS vf5.xlsx XLSX spreadsheet
IDIQ DD1423 CDRLS EXHIBIT B005-B006-B007 (ADMN) Southwest BECOS vf1.pdf PDF
IDIQ PWS Southwest BECOS vf4.docx DOCX document
CA20200025 31Jan20 Riverside Building Heavy.pdf PDF
20200203_FA890320R0013_BECOS_Southwest_Section_L v6.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT A001-A002-A004 (MISC) Southwest BECOS vf1.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT A010 (QCIC) Southwest BECOS vf1.pdf PDF
20200203_FA890320R0013_Southwest_BECOS_Section_M v4.docx DOCX document
TO 2 PWS Attch 2 March Base Spec Req Southwest BECOS vf2.docx DOCX document
CA20200026 31Jan20 San Bernadino Building Heavy.pdf PDF
TO 2 PWS Attch 2 George Base Spec Req Southwest BECOS vf2.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT B001 (MISC) Southwest BECOS vf1.pdf PDF
20200131_FA890320R0013_BECOS_Relevancy_PPQ v2.docx DOCX document
20200122_Southwest FFP FBLR Tables v2.xlsx XLSX spreadsheet
Southwest IDIQ_Sched B_CLIN Structure and Price Model_v1_02112020.xlsx XLSX spreadsheet
IDIQ DD1423 CDRLS EXHIBIT A003-A012 (MGMT) Southwest BECOS vf1.pdf PDF
TO 2 CDRLs Exhibit A B Southwest BECOS vf1.docx DOCX document
IDIQ PWS Attch 1 Southwest Site List BECOS vf3.xlsx XLSX spreadsheet
Solicitation Southwest FA890320R0013 vf.pdf PDF
TO 1 CDRLs Exhibit A B Southwest BECOS vf1.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT A007-A008-A009 (ENVR) Southwest BECOS vf1.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT A013 (MISC CONT) Southwest BECOS vf1.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT A014 (DRPR) Southwest BECOS vf1.pdf PDF
AZ20200031 31Jan20 Maricopa Building.pdf PDF
20200131_FA890320R0013_BECOS_Relevancy_Matrix v2.docx DOCX document
20200131_FA8903-20-R-0013_BECOS RFP Questions and Answers Template v2.xlsx XLSX spreadsheet
IDIQ DD1423 CDRLS EXHIBIT A005-A006-A011 (CMAN) Southwest BECOS vf1.pdf PDF
TO 2 PWS Attch 2 Norton Base Spec Req Southwest BECOS vf2.docx DOCX document
AZ20200017 31Jan20 Maricopa Heavy.pdf PDF
IDIQ PWS Attch 4 Southwest Perf Obj Def and Req BECOS vf2.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT B004 (CMAN) Southwest BECOS vf1.pdf PDF
IDIQ PWS Attch 3 Southwest Del Rev Process BECOS vf2.docx DOCX document
TO 2 PWS Southwest BECOS vf3.docx DOCX document
20200109_Southwest TO2 Price Model v2.xlsx XLSX spreadsheet
Show all 50

Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS) Southwest Region has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4890-06-R-9999

Attachment 1

APRIL XX, 2009

- final –

FA8903-20-R-0013 TO 1

southWEST region 5 December 2019

BASE REALIGNMENT AND CLOSURE (brac) Environmental Construction and Optimization Services (BECOS)

INDEFINITE DELIVERY/INDEFINITE QUANTITY (ID/IQ)

PERFORMANCE WORK STATEMENT (PWS)

FOR

ENVIRONMENTAL RESTORATION

AT

AIR FoRCE BRAC INSTALLATIONS – Southwest Region

Contract NUmber: FA8903-20-R-0013

Task Order: 01

5 December 2019

Table of Contents

1.0Introduction5
1.1Scope5
1.2General BECOS Scope and Requirements6
1.3Applicable Documents7
1.4Work Ramp-Up and Transition7
1.4.1Work Ramp-Up – Not Applicable7
1.4.2Transition of Work – Not Applicable7
1.5Remedial System Components – Not Applicable7
1.6Government Furnished Information (GFI) – Not Applicable7
2.0Project Administration8
2.1Management, Planning, and Reporting Requirements8
2.2Project Management Plan (PMP) – Not Applicable8
2.3Project Website – Not Applicable8
2.4Contractor’s Progress, Status, and Management Report (CPSMR)8
2.5Cost/Schedule Status Report (CSSR) – Not Applicable8
2.6Meeting and Conference Services8
2.6.1Meeting/Teleconference Support8
2.6.2Public Meetings and Hearings – Not Applicable9
2.6.3Regulatory/Professional Interface9
2.6.4Notification Requirements9
2.6.5Site Access: Permits, Easements, and Work Site Access – Not Applicable10
2.7Work Site Coordination – Not Applicable10
2.8Photo Documentation – Not Applicable10
2.9Contractor Documentation10
2.10Record Keeping10
3.0GENERAL REQUIREMENTS10
3.1Technical Plans and Reports – Not Applicable11
3.1.1Technical Plans – Not Applicable11
3.1.2Technical Reports – Not Applicable11
3.2Quality Program Plan (QPP) – Not Applicable11
3.2.1Work Plans (WP) – Not Applicable11
3.2.2Health and Safety Plan (HSP) – Not Applicable11
3.2.3Sampling and Analysis Plan (SAP) – Not Applicable11
3.2.4Construction Quality Plan (CQP) – Not Applicable11
3.3Chemistry Requirements – Not Applicable11
3.3.1Quality Assurance – Not Applicable11
3.3.2Laboratory Selection – Not Applicable11
3.3.3Analytical Data Management – Not Applicable11
3.3.4Environmental Resources Program Information Management System (ERPIMS) – Not Applicable11
3.4Computer-Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates – Not Applicable11
4.0GENERAL Environmental requirements11
4.1Site Characterization – Not Applicable11
4.2Site Preparation – Not Applicable11
4.3Conservation – Not Applicable11
4.4Environmental Construction – Not Applicable11
4.4.1Inspections – Not Applicable11
4.4.2Delivery and Warranty of Installed Equipment and Systems – Not Applicable12
4.4.3Completion of Conceptual Design – Not Applicable12
4.4.4Innovative and Proven Technologies – Not Applicable12
4.5Operations and Maintenance (O&M) – Not Applicable12
4.6Demolition – Not Applicable12
4.7Demobilization and Site Restoration – Not Applicable12
5.0Environmental Media12
5.1Air Quality – Not Applicable12
5.2Storage Tank Management – Not Applicable12
5.3Wastewater and Storm Water – Not Applicable12
5.4Water Quality – Not Applicable12
5.5Natural and Cultural Resources12
5.5.1Cultural Resources – Not Applicable12
5.5.2Natural Resources – Not Applicable12
5.6Hazardous Material and Hazardous Waste Management – Not Applicable12
5.6.1Hazardous Waste Removal and Support – Not Applicable12
6.0Environmental REstoraTION12
6.1Preliminary Assessment (PA)/RCRA Facility Assessment – Not Applicable12
6.2Site Inspection (SI) – Not Applicable13
6.3Remedial Investigation (RI)/RCRA Facility Investigation – Not Applicable13
6.4Conceptual Site Model (CSM) – Not Applicable13
6.5Risk Assessment – Not Applicable13
6.6Treatability Studies, Pilot Tests, Bench Scale Tests – Not Applicable13
6.7Feasibility Study (FS)/Corrective Measures Study – – Not Applicable13
6.8Proposed Plans (PP)/Records of Decision (ROD)/Decision Documents (DD) – Not Applicable13
6.9Remedial Action (RA)/Corrective Measure Implementation – Not Applicable13
6.10Presumptive and Other Remedies – Not Applicable13
6.11Remedial Action-Operations (RA-O) – Not Applicable13
6.12Long-Term Management (LTM) – Not Applicable13
6.13Optimization – Not Applicable13
6.14Land Use Controls (LUC) – Not Applicable13
6.15Five-Year Reviews – Not Applicable13
6.16Response Complete (RC) – Not Applicable13
6.17Site Closeout (SC) – Not Applicable13
6.18Well and System Decommissioning – Not Applicable13
7.0services summary13
8.0Miscellaneous14
8.1Government Points of Contact (POC)14
8.2Supplies and Equipment Acquisition – Not Applicable14
9.0ROLES AND RESPONSIBILITIES14
10.0CONTRACTOR MANPOWER REPORTING REQUIREMENTS15
10.1Contractor Manpower Reporting15

Introduction

1.1 Scope

The Contractor shall provide all management, tools, supplies, equipment, and labor necessary to perform the BRAC Environmental Construction and Optimization Services (BECOS) requirements. This Performance Work Statement (PWS) defines the initial task order meeting support for implementation of the full range of environmental, construction, and optimization services necessary to conduct site restoration including maintenance of established remedies, implementation of optimization, and remediation activities to achieve performance objectives to include emerging requirements for environmental remediation as identified in this Task Order (TO). Regulatory engagement at the installations listed below can range from local to federal agencies at any given time during the TO performance. This PWS covers the following region and Air Force (AF) BRAC installations including any associate geographically separated unit (GSU) locations:

Southwest Region:

The former George Air Force Base (AFB) is located in the City of Victorville, San Bernardino County, California. The former George AFB is listed on the National Priorities List (NPL) and has a Federal Facilities Agreement (FFA) in place. Regulatory oversight is provided by United States Environmental Protection Agency (USEPA) Region 9 and the State of California, Regional Water Quality Control Board (RWQCB), Lahontan Region. Remedial activities at the former George AFB are being conducted under Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and state programs (non-CERCLA).

The former March AFB is located in the City of Riverside, Riverside County, California. March AFB was placed on the NPL in November 1989. An FFA was signed in September 1990 by the AF; the Department of Toxic Substances Control (DTSC); USEPA Region 9; and the RWQCB, Santa Ana Region. Site cleanup requirements are based on the CERCLA, Resource Conservation and Recovery Act (RCRA), and California State Water Resources Control Board. Regulatory oversight is provided by the DTSC, successor to the California Department of Health Services (CDHS) (the lead state agency per the FFA); USEPA; and the RWQCB.

The former Norton AFB is located in San Bernardino, San Bernardino County, California. The former Norton AFB is listed on the NPL and has an FFA in place. Sites are being addressed following the CERCLA and/or RCRA processes.

The former Williams AFB is located in Mesa, Maricopa County, Arizona, about 30 miles southeast of Phoenix. The former Williams AFB is listed on the NPL and has an FFA in place. The majority of sites are being addressed under the CERCLA process.

The former Air Force Research Laboratory (AFRL) Mesa is located in Mesa, Maricopa County, Arizona.

The former Ontario Air National Guard Station (ANGS) is located in Ontario, San Bernardino County, California.

The Contractor is solely responsible for reviewing all publicly available information and forming their independent, professional conclusions/interpretation of site conditions and requirements to achieve the performance objectives of this TO.

1.2 General BECOS Scope and Requirements

This PWS encompasses the full range of methods, technologies, and supporting activities necessary to support initial task order meetings required to conduct environmental restoration/remediation efforts to address environmental sites and conditions at Air Force installations and other locations in accordance with technical and regulatory requirements.

The AF is required to implement remedies as necessary to enable the mission, protect human health and the environment and comply with laws. The goal of the BECOS contract is to ensure the AF continues to fulfill all facets of its Environmental Restoration Program (ERP) mission, while effectively and efficiently managing the program in a performance-based, results-oriented and cost conscious framework. The AF desires all sites be cleaned up to standards that allow for the current or reasonably anticipated future land use of the property in accordance with approved decision documents. The AF is interested in reduction of long-term environmental liabilities and Life-Cycle Costs, through optimization of environmental restoration activities for sites while complying with applicable federal, state, and local laws and regulations. This could include a variety of environmental restoration services and construction necessary to maintain regulatory selected remedies, implement optimization to enhance remedial progress, and advance sites to completion in a cost effective manner. The efforts will be executed in accordance with technical and regulatory requirements to ensure protection of human health and the environment.

The Contractor shall function as an integral team member in support of the AF Civil Engineer Center (AFCEC) and BRAC mission, to include the sharing of information with other AFCEC Contractors and AF personnel, and cooperation with communities, regulators, and other government entities. Requirements such as the achievement of accurate, on-time, quality performance objectives and timely identification and solution of impediments to successful project execution are necessary to ensure efficient management of this TO. Early involvement in the process by all parties allows for the development of the most cost-effective and technically sound approach or solution. The AFCEC will rely on the Contractor’s expertise in recognizing and addressing problematic issues and successful execution of this TO. The Contractor shall perform all work in accordance with federal, state, and local statutes and regulations. Remedies shall conform to environmental permits, decision document requirements, or other legal requirements.

In carrying out each work assignment issued as a TO under the basic contract, the Contractor shall furnish the personnel, services, equipment, materials, facilities, and other requirements necessary for, and incidental to, the performance of work set forth herein.

Primary technical services shall be performed by individuals who are credentialed members of architectural, planning, science, and engineering professions. Disciplines such as architects, landscape architects, engineering disciplines typically associated with environmental engineers and scientists (e.g., professional engineer [PE], professional geologist [PG]), planners, cost estimators, Computer-Aided Design and Drafting (CADD) technicians, publication writers/editors, technical writers, graphic artists, and Geographic Information System (GIS) analysts are included. Generally, a credentialed professional (a) is licensed (e.g., registered professional engineer) to practice in the state where a facility is located and/or (b) commands the necessary expertise, in terms of knowledge and experience, to undertake the specified task.

List of Attachments:

None

1.3 Applicable Documents

The Contractor shall identify and comply with all applicable federal, state, and local statutes; Department of Defense (DoD) and AF instructions, manuals, handbooks, regulations, guidance, and policy letters (including DoD and AF policy and guidance for ERP and Emerging Contaminants); Executive Orders (EO); American Society for Testing and Materials (ASTM); American Petroleum Institute (API) Codes; National Association of Corrosions Engineers (NACE); National Fire Protection (NFPA); Steel Structures and Painting Counsel (SSPC); National Electrical Code (NEC); Uniform Fire Code (UFC); Occupational Safety and Health Administration (OSHA) regulations, and International Building Code (IBC) including all changes and amendments in effect on the date of issuance of this TO. It is the Contractor’s responsibility to identify and comply with all applicable requirements. In addition, the Contractor shall refer to the current versions of the DoD Policy and Guidelines for Acquisitions Involving Environmental Sampling or Testing and the United States AF Construction Management Implementation Guide.

It is the Contractor’s responsibility to identify and comply with all applicable or relevant and appropriate requirements (ARARs). The Contractor shall identify and comply with all applicable documents for the bases including RODs, ROD Amendments, Explanations of Significant Difference (ESD), RCRA Permits and subsequent modifications, Risk Evaluation Corrective Action Program (RECAP) documents, the Endangered Species Act, other Decision Documents, Deeds, and conveyance notices. Key base-specific documents are available on the AF Administrative Record at http://afcec.publicadmin-record.us.af.mil/Search.aspx.

1.4 Work Ramp-Up and Transition

1.4.1 Work Ramp-Up – Not Applicable

1.4.2 Transition of Work – Not Applicable

1.5 Remedial System Components – Not Applicable

1.6 Government Furnished Information (GFI) – Not Applicable

Project Administration

2.1 Management, Planning, and Reporting Requirements

The Contractor shall implement a full range of environmental construction and optimization services as required to meet the objectives of this TO and in accordance with all applicable documents. The Contractor shall supply all labor, equipment, and materials necessary to support the contractual and technical kick-off meetings. The Contractor shall perform management and planning functions, including performance measurement through the course of this effort.

2.2 Project Management Plan (PMP) – Not Applicable

2.3 Project Website – Not Applicable

2.4 Contractor’s Progress, Status, and Management Report (CPSMR)

The Contractor shall prepare and submit 1 CPSMR for each meeting, one documenting the activities supporting the post-award contractual kick-off meeting, and one documenting the activities supporting technical kick-off meeting (Option). The CPSMR shall be used to review and evaluate the overall progress of this TO, along with any existing or potential problem areas. The report shall be prepared in a format coordinated and approved by the COR including site level details and associated CLIN information. The CPSMR shall also be used to indicate information by installation on a regional basis, describing whether efforts for each site are on target for meeting site-specific performance objective. (CDRL B003)

The CPSMR shall include a summary of the events that occurred during the reporting period, discussion of performance, identification of problems, proposed solutions, corrective actions taken, outstanding issues, and projected tasks such as field work, reporting, etc., occurring in the next 90 days.

2.5 Cost/Schedule Status Report (CSSR) – Not Applicable

2.6 Meeting and Conference Services

2.6.1 Meeting/Teleconference Support

The Contractor shall attend and/or support one (1) post-award contractual kick-off meeting including teleconferencing capabilities to discuss contractual related elements required to support planning and implementation of task orders under the BECOS contract. This meeting will be held in San Antonio, TX at the AFCEC Office.

The AF will be present for all technical meetings with the regulatory agencies; however, the Contractor shall coordinate the meeting, provide logistical support (e.g., facilities, audio/visual), presentation materials, agendas, meeting minutes, and lead technical discussions. The Contractor shall prepare, and submit for AF review not less than five (5) working days prior to the meeting (unless otherwise approved by the AF), presentation materials for meetings and an agenda. The Contractor shall prepare summaries/minutes for all meetings attended and submit for AF review not less than 10 working days after the meeting has occurred. (CDRLs B005, B006, B007)

The Contractor shall not contact, nor take direction from, any regulatory agency without prior notification and approval by the AF. In situations of imminent health or safety risks, regulators may direct the AF and their contractors to stop work.

2.6.2 Public Meetings and Hearings – Not Applicable

2.6.3 Regulatory/Professional Interface

The Contractor shall attend and/or support one (1) technical kick-off meeting including teleconferencing capabilities to conduct regulator introductions and discuss the environmental restoration program in general including goals, challenges, and concerns. This meeting will be held in a location central to the region and/or participants, whether at a contractor’s office or another location that can accommodate it.The Contractor shall provide all required support including preparation of presentation materials, agendas, minutes, and the maintenance of mailing list(s). (CDRLs A001, B005, B006, B007)

2.6.4 Notification Requirements

The Contractor is required to notify the CO and COR of critical issues that may affect the TO performance and/or human health and the environment. The types of issues that require notification include, but are not limited to, health risks, spills, Notices of Violation (NOV) (received or anticipated), and changes in key personnel, and finding unexploded ordnance (UXO). On critical issues, verbal notification shall be made immediately, followed by written notification within three working days. (CDRL A003)

If unanticipated UXO is discovered during field activities, the Contractor shall immediately stop work, report the discovery to the CO and COR, and implement the appropriate safety precautions. Field activities cannot continue until clearance is received from the CO.

The Contractor shall follow the 3Rs (Recognize, Retreat, and Report) Explosives Safety Education Program; see https://www.denix.osd.mil/uxo.

In the event of a dispute with or enforcement action from a regulatory agency arising from performance of work covered as required to meet the objectives of this TO, regardless of whether the AF is a named party, the Contractor shall notify the CO or COR within 24 hours. If the AF is a named party in the dispute or enforcement action, the Contractor shall provide support to the AF as required to resolve the dispute or enforcement action. If the AF is not a named party in the dispute or enforcement action, the Contractor shall provide its proposed response to the dispute or enforcement action to the AF for review and comment prior to submission. Contractor support typically includes preparing a briefing, point paper, and summary of technical data to support the AF position. (CDRL A001)

2.6.5 Site Access: Permits, Easements, and Work Site Access – Not Applicable

2.7 Work Site Coordination – Not Applicable

2.8 Photo Documentation – Not Applicable

2.9 Contractor Documentation

The Contractor shall create and maintain a Master Document List (MDL) for all documents including those maintained as part of the document repository, whether the document is a deliverable or not, which are prepared during the course of this TO. The MDL and its documents shall be maintained in libraries readily available for submittal to the government. The project website may be used to maintain all or portions of the document repository. The Contractor shall maintain the MDL and project documents for the duration of this TO and transfer custody to the AF within 90 calendar days prior to PoP expiration. For project documents produced in the final 90 calendar days of the PoP, the contractor shall submit an updated MDL and copies of subject writable and PDF documents (CDRL A001)

The Contractor shall maintain a document repository for all documents generated during this TO. The repository is intended to be a single access point repository for all documentation. It shall be accessible to the AF, with limited access to regulatory agencies, as appropriate. The Contractor shall provide notifications to the COR at the time data is included in the repository. The Contractor shall support coordination efforts with other contractors working onsite who may require access to these files. The Contractor shall prepare metadata sheets and consolidated report documentation including regulatory letters for applicable deliverables and submit electronic and/or hard copies as requested by the CO/COR to the AF administrative record (AR) management team for loading to the AR. At close-out, all repository documents will be transferred to DVD media and delivered to the COR. Original software versions, GIS files, spreadsheets and databases should also be included in the close-out DVD.

2.10 Record Keeping

The Contractor shall create and maintain in one location written (in bound, numbered logbook) and electronic records sufficient to recreate each sampling, analytical, testing and monitoring event, and shall make these records available to the Government upon request. The Contractor shall maintain records of, and derived from, all activities outlined in the appropriate portion of the Quality Program Plan (QPP) supporting the generation of these sampling and analysis records. The Contractor shall also retain written calculations using information obtained from sampling, analysis monitoring, and testing activities, to include all raw data. All information shall be provided to the Government upon request. (CDRL A001)

GENERAL REQUIREMENTS

The Contractor shall perform a full range of activities to meet all environmental construction and optimization services requirements, as required to meet the objectives of this TO.

3.1 Technical Plans and Reports – Not Applicable

3.1.1 Technical Plans – Not Applicable

3.1.2 Technical Reports – Not Applicable

3.2 Quality Program Plan (QPP) – Not Applicable

3.2.1 Work Plans (WP) – Not Applicable

3.2.2 Health and Safety Plan (HSP) – Not Applicable

3.2.3 Sampling and Analysis Plan (SAP) – Not Applicable

3.2.4 Construction Quality Plan (CQP) – Not Applicable

3.3 Chemistry Requirements – Not Applicable

3.3.1 Quality Assurance – Not Applicable

3.3.2 Laboratory Selection – Not Applicable

3.3.3 Analytical Data Management – Not Applicable

3.3.4 Environmental Resources Program Information Management System (ERPIMS) – Not Applicable

3.4 Computer-Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates – Not Applicable

GENERAL Environmental requirements

4.1 Site Characterization – Not Applicable

4.2 Site Preparation – Not Applicable

4.3 Conservation – Not Applicable

4.4 Environmental Construction – Not Applicable

4.4.1 Inspections – Not Applicable

4.4.1.1 Pre-Final Inspection – Not Applicable

4.4.1.2 Final Inspection – Not Applicable

4.4.2 Delivery and Warranty of Installed Equipment and Systems – Not Applicable

4.4.3 Completion of Conceptual Design – Not Applicable

4.4.4 Innovative and Proven Technologies – Not Applicable

4.5 Operations and Maintenance (O&M) – Not Applicable

4.6 Demolition – Not Applicable

4.7 Demobilization and Site Restoration – Not Applicable

Environmental Media

5.1 Air Quality – Not Applicable

5.2 Storage Tank Management – Not Applicable

5.3 Wastewater and Storm Water – Not Applicable

5.4 Water Quality – Not Applicable

5.5 Natural and Cultural Resources

5.5.1 Cultural Resources – Not Applicable

5.5.2 Natural Resources – Not Applicable

5.5.2.1 Integrated Natural Resource Management Plan (INRMP) – Not Applicable

5.5.2.2 Aquatic Resources (Waters of the U.S., Wetlands, Watersheds, and Floodplains) – Not Applicable

5.5.2.3 Coastal Zone Management – Not Applicable

5.5.2.4 Threatened and Endangered (T&E) Species/Species of Special Concern – Not Applicable

5.6 Hazardous Material and Hazardous Waste Management – Not Applicable

5.6.1 Hazardous Waste Removal and Support – Not Applicable

Environmental REstoraTION

6.1 Preliminary Assessment (PA)/RCRA Facility Assessment – Not Applicable

6.2 Site Inspection (SI) – Not Applicable

6.3 Remedial Investigation (RI)/RCRA Facility Investigation – Not Applicable

6.4 Conceptual Site Model (CSM) – Not Applicable

6.5 Risk Assessment – Not Applicable

6.6 Treatability Studies, Pilot Tests, Bench Scale Tests – Not Applicable

6.7 Feasibility Study (FS)/Corrective Measures Study – – Not Applicable

6.8 Proposed Plans (PP)/Records of Decision (ROD)/Decision Documents (DD) – Not Applicable

6.9 Remedial Action (RA)/Corrective Measure Implementation – Not Applicable

6.10 Presumptive and Other Remedies – Not Applicable

6.11 Remedial Action-Operations (RA-O) – Not Applicable

6.12 Long-Term Management (LTM) – Not Applicable

6.13 Optimization – Not Applicable

6.14 Land Use Controls (LUC) – Not Applicable

6.15 Five-Year Reviews – Not Applicable

6.16 Response Complete (RC) – Not Applicable

6.17 Site Closeout (SC) – Not Applicable

6.18 Well and System Decommissioning – Not Applicable

services summary

As a minimum, the COR will monitor, review, and report on the Contractor’s performance and compliance with all Service Delivery Summary (SDS) items shown below (reference QASP, see appropriate section). The service requirements summarized below are the critical performance objectives that relate directly to mission essential items. The performance thresholds referenced in the table briefly describe the minimum acceptable levels of service required for each service requirement. The performance thresholds established for each of the performance objectives are the number of defects permitted before the COR notifies the CO in accordance with FAR 52.246-4, Inspection of Services - Fixed Price.

SERVICE SUMMARY AND DELIVERABLE TABLE

PWS Paragraph Reference
Performance Standard
Performance Threshold
Surveillance Method
2.6.1, 2.6.3
Effective engagement with regulatory and other stakeholders.
No instances of contactor negligence resulting in Notice of Violation (NOV)

No more than one instance of contractor/regulator interaction without AF prior knowledge As required

Miscellaneous

8.1 Government Points of Contact (POC)

Government POCs to be specified in this TO.

8.2 Supplies and Equipment Acquisition – Not Applicable

ROLES AND RESPONSIBILITIES

The primary stakeholder roles and responsibilities are as follows.

Air Force:

The AF, as lead agency and Quality Assurance Evaluator, has established its requirements in this PWS. The AF will:

· Facilitate regulatory interactions to achieve regulatory acceptance/concurrence.

· Respond to inquiries from a variety of sources to include congressional inquiries, public inquiries, media inquiries, and other federal government inquiries, as appropriate.

· Ensure Contractor compliance with the contract through surveillance, routine meetings, evaluation of reports, and assurance that performance milestones are met prior to making payment.

· Plan, program, budget, and execute funding for this TO and out years.

Contractor:

The Contractor will:

· Adhere to the terms of the TO and achieve performance objectives and milestones.

· Ensure high quality technical performance and end products.

· Manage project risk and proactively communicate with stakeholders regarding issues and remedies.

· Track and report TO performance.

· Provide support to the AF in response to inquiries from a variety of sources to include congressional inquiries, media inquiries, and other federal government inquiries.

· Ensure protection of human health and the environment during contract performance.

· Meet all applicable regulatory requirements associated with environmental restoration during TO performance.

CONTRACTOR MANPOWER REPORTING REQUIREMENTS

10.1 Contractor Manpower Reporting

The Contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this TO for the AF via a secure data collection site. The Contractor is required to completely fill in all required data fields at http://www.ecmra.mil.

Reporting inputs will be for labor executed during the period of performance for each Government fiscal year (FY), which runs 1 October through 30 September. While inputs may be reported any time during the FY, all data shall be reported no later than 31 October of each calendar year. Contractors may direct questions to the Contractor Manpower Reporting Application help desk.

Uses and Safeguarding of Information: Information from the secure web site is considered to be proprietary in nature when the contract number and contractor identity are associated with the direct labor hours and direct labor dollars. At no time will any data be released to the public with the contractor name and contract number associated with the data.

User Manuals: Data for AF service requirements must be input at the AF CMRA link. However, user manuals for government personnel and contractors are available at the Army CMRA link at http://www.ecmra.mil.

Unit Identification Code (UIC): FFFS20

(Note: UIC will be provided at Solicitation (if available) or provided (must be) at Award)

This information is a Congressional Mandate and reportable (deliverable).