This document contains questions and answers related to a solicitation for Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS) in the Southwest Region. The solicitation is for an Indefinite Delivery Indefinite Quantity (IDIQ) contract to provide environmental remediation and monitoring services at multiple sites located at former military bases including George Air Force Base, Norton Air Force Base, and Williams Air Force Base. Services will include long-term monitoring, removal actions, corrective measures studies and implementation, and operation and maintenance of existing remediation systems. The contract holder will be responsible for tasks such as compliance sampling, soil vapor monitoring, well replacement and decommissioning, and operating remediation systems such as soil vapor extraction units. The document provides clarification on the scope of work, available documentation, and other details to support offerors in preparing proposals, which were due by June 15, 2020 following an extension. The Department of the Air Force is the contracting agency.
View the file
Other files
Show 40 more
Latest 50 of 52 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Q # | Document Reference | RFP QUESTIONS | DATE RCVD | Document Reference | GOV'T RESPONSE | RESPONSE DATE |
| 151 | IDIQ PWS Attch 1 Southwest Site List BECOS vf3 | Line 32 ST012 - The Admin Record included reports through 2016. Based on the comments from Agencies and responses to comments, it appears that there was a Work Plan for the EBR Pilot Study: Amec Foster Wheeler Environment & Infrastructure Inc., 2018. Pilot Study Implementation Work Plan for Operable Unit 2 Revised Groundwater Remedy, Site ST012, Former Williams Air Force Base, Mesa, Arizona. Please provide a complete copy of this Work Plan, and all associated addenda or variances/modification memos. | 15-May-20 | AR | The pilot study work plan is available in the online Administrative Record file as documents 597626 and 571843.1 through 571843.9. The first file was revised to expand Appendix F and correct Appendix H. Two field variances memos, numbers 6 and 7, have been issued and these are posted on the Williams Google documents site. | 1-Jun-20 |
| 152 | IDIQ PWS Attch 1 Southwest Site List BECOS vf3 | Please provide copies of O&M Manuals, SAPs, and QAPPs for all existing systems (SVE and EBR) | 15-May-20 | General | All documents provided on AR and Google site that will be provided pre-award. Additional documents available upon request post award. | 1-Jun-20 |
| 153 | IDIQ PWS Attch 1 Southwest Site List BECOS vf3 | For George AFB Site CG070, it states that the site is contaminated with PFAS. It does not appear from the Annual Monitoring Reports that groundwater samples are being analyzed for PFAS. Should the bidders assume that samples are not analyzed for PFAS and that IDW does not need to be analyzed for PFAS compounds? | 15-May-20 | Not Applicable | Bidders should assume that groundwater samples are not analyzed for PFAS. |
| Bidders should assume characterization, handling, and disposal of IDW according to the most current applicable federal, state, local, DoD/AF guidance, and the HQ USAF/A4, Air Force Guidance Memorandum Establishing Aqueous Film Forming Foam (AFFF)-Related Waste Management Implementation Guidance, AFGM 1908-32-71, Sep 2019. | 20-May-20 | ||||||
| 154 | IDIQ PWS Attch 1 Southwest Site List BECOS vf3 | George AFB shows Sites ST067a and ST067b. However, a search on the Administrative Record could not identify and documents related to the current status of Site ST067a. What are the specific requirement that need to be performed on TO 002 related to Site ST067a? Please clarify the SOW. | 15-May-20 | AR #s 759 and 916 | The removal and abandonment of the Liquid Fuels Distribution System (LFDS) portion of Site ST067a is found in the Final Report for Liquid Fuel Distribution System Removal, Underground Storage Tank Removal and Oil-Water Separator Inspection dated Janaury 1995 and prepared by Odgen Environmental Services, which is AR #s 759 and 916. | 20-May-20 | |
| 155 | IDIQ PWS Attch 1 Southwest Site List BECOS vf3 | For George AFB Site SS030, the table states that Petroleum Sites Corrective Action Plan (CAP), Part I is under RWQCB review since 24 June 2013. Is there any action that needs to be performed with the CAP on TO 002? Same question for Site OT071. Please clarify the SOW. | 15-May-20 | Not Applicable | The Petroleum Sites Corrective Action Plan (CAP) for flightline Sites SS030, ST054, ST057 and SS084, and the Pesticide CAP for Site OT071 are NOT part of TO 02. This is will be handled on a case by case basis. | 20-May-20 | |
| 156 | TO 2 PWS Attch Williams Base Spec Req Southwest BECOS vf2 | Please provide a copy of the following: AMEC, 2013a. Final Groundwater Monitoring Work Plan, Site LF004, Former Williams Air Force, Base, Mesa, Arizona. 5 August 2013. | 15-May-20 | AR | The Final Groundwater Monitoring Work Plan, Site LF004 is available in the online Administrative Record file as document 1631. | 1-Jun-20 | |
| 157 | TO 2 PWS Attch Williams Base Spec Req Southwest BECOS vf3 | How many PFAS analytes are required for reporting at Williams AFB, Landfill 004 Site : 18, 24 or 33 PFAS analytes? | 15-May-20 | NA | No PFAS analytes are required to be reported at Williams AFB Landfill 004 under this project. | 1-Jun-20 | |
| 114 | Southwest IDEQ_Schedule B_CLIN Structure and Price Model_v1_02112020.xlsx | Excel file “Southwest IDEQ_Schedule B_CLIN Structure and Price Model_v1_02112020.xlsx” shows that Sites FT082 and SS083 are under severable and RAO CLIN 008. However, Excel file “20200109_Southwest TO2 Price Model v2.xlsx” shows George Sites FT082 and SS083 are under non-severable CLINs 0016 and 0017, respectively. Which is correct? Also, Excel file “20200109_Southwest TO2 Price Model v2.xlsx” shows the same CLIN being used for non-severable Site SS083 at George and base year severable CLIN involving LTM sites at March. Is this correct? | 27-Apr-20 | Southwest IDEQ_Schedule B_CLIN Structure and Price Model_v1_02112020.xlsx | The IDIQ Schedule B CLIN Structure and Price Model supporting the basic contract includes both severable and non-severable CLINs for multiple sites including George Sites FT082 (severable RA-O CLIN 0008 and non-severable CLIN 0016) and SS083 (severable RA-O CLIN 0008 and non-severable CLIN 0017). The performance objective identified in the TO 2 Attch 1 Southwest Site List (vf5) for George Sites FT082 and SS083 is RC, a non-severable activity which encompasses all tasks identified at the site under TO 2. As such, the TO 2 price model accurately captures George Sites FT082 and SS083 under non-severable CLINs 0016 and 0017, respectively. |
The TO 2 Price Model has been corrected to reflect severable CLIN 0019 for LTM sites at March (revised from CLIN 0017) which aligns with the Southwest IDIQ Schedule B CLIN Structure and Price Model. Four other subsequent severable CLINs in the TO 2 Price Model (base and option year tabs) required revisions to properly align with the IDIQ Schedule B CLIN Structure and Price Model including: RA-O Sites for March (changed from CLIN 0018 to 0020), LTM Sites for Norton (changed from CLIN 0022 to 0025), LTM Sites for Williams (changed from CLIN 0025 to 0031), and RA-O Site at Williams (changed from CLIN 0026 to 0032). No changes are required to the IDIQ Schedule B CLIN Structure and Price Model.
| 1-Jun-20 | ||||||
| 158 | George FT082, SS083 | Attachment 1 states that the"Ongoing SVE to be completed under current PBR contract" for George sites FT082 and SS083. Who is responsible for the the monthly compliance sampling and semi-annual full site soil vapor sampling events for FT082 and SS083? | 15-May-20 | AR #s 590472 through 590472.4 | The awarded BECOS contractor will be responsible for the monthly compliance sampling and semi-annual full site soil vapor sampling to comply with the substantive requirements imposed by the Mojave Desert, Air Quality Management District (MDAQMD) . | 1-Jun-20 |
| 159 | Norton CG097 | For Norton Site CG097, well decomissioning is part of this TO. In the August 2019 BCT Update for Norton on the admin record, it states that there are 26 single screened MWs and 6 multilevel MWs. Can the government furnish a list of these monitoring wells and their depths, diameters, etc for the prospective contractors to estimate the cost of decommissioning these wells? | 15-May-20 | google site | Document will be uploaded to Google documents site. | 1-Jun-20 |
| 160 | George General | In PWS Attachment 2 for George AFB, it states "Contractor is responsible for decommissioning wells that are already approved for decommissioning and are listed in Table 2-2 of the Basewide Groundwater Monitoring 2017 Annual Report, Former Norton Air Force Base, available on the reference website (refer to Table 1D, Alternative Endpoints)." Where can Table 1D be found? | 15-May-20 | General | The 2017 Annual Report Table 2-2 presents our proposed sampling of three landfill wells and has nothing to do with well decommissioning and the report has no Table 1D. | 1-Jun-20 |
| 161 | Norton FT082 | For Norton Site FT082, the Site Supplemental Report is missing from the admin record. Can the government furnish the latest version of this report? | 15-May-20 | General | Norton does not have a FT082 site. | 1-Jun-20 |
| 162 | Williams ST012 | Can the government furnish the Williams Draft ST012 SVE System and EBR Pilot Study 2018 First and Second Quarter Performance Report and any subsequent performance reports? | 15-May-20 | AR/google site | No perforrmance reports have yet been finalized since the initiation of the EBR pilot test in December 2018. Progress reporting is part of the monthly BRAC Cleanup Team presentations. The presentations for May 2019 through April 2020 will be uploaded to the Google documents site. December 2018 revised minutes are availabe on the online Administrative Record file as document 592367. | 1-Jun-20 |
| 163 | Williams ST012 | Attachment 1 states that "New monitoring wells, replacement monitoring wells and well abandonment due to rising groundwater levels is included in this TO" for Williams Site ST012. Can the government furnish or reference a document that states how many wells need to be installed, replaced, and abandoned for costing purposes? | 15-May-20 | TO 2 PWS | The requested details are not established. It is the contractors responsibility to determine the number of wells appropriate to meet the remediation and monitoring requirements. | 1-Jun-20 |
| 164 | Section L, 3.4 | Please confirm that Past Performance Questionnaires (PPQ’s) are to be submitted to the government no later than the proposal due date and time. | 15-May-20 | Section L | Confirmed. | 1-Jun-20 |
| 165 | Section L, 3.4 | We have received Past Performance Questionnaires (PPQs) from the government for our relevant projects in the past 90 days. Would it be acceptable to submit previously-completed PPQs with our proposal? | 15-May-20 | Section L | No, only the PPQ in Section J IAW Section L. | 1-Jun-20 |
| 44 | IDIQ PWS Attch 1 Southwest Site List BECOS vf3 | Line 32 ST012 - The Admin Record included reports through 2016. Based on the comments from Agencies and responses to comments, it appears that there was a Work Plan for the EBR Pilot Study: Amec Foster Wheeler Environment & Infrastructure Inc., 2018. Pilot Study Implementation Work Plan for Operable Unit 2 Revised Groundwater Remedy, Site ST012, Former Williams Air Force Base, Mesa, Arizona. Please provide a complete copy of this Work Plan, and all associated addenda or variances/modification memos. | 5/20/20 | AR | The pilot study work plan is available in the online Administrative Record file as documents 597626 and 571843.1 through 571843.9. The first file was revised to expand Appendix F and correct Appendix H. Two field variances memos, numbers 6 and 7, have been issued and these are posted on the Williams Google documents site. | 2-Jun-20 |
| 45 | IDIQ PWS Attch 1 Southwest Site List BECOS vf3 | Please provide copies of O&M Manuals, SAPs, and QAPPs for all existing systems (SVE and EBR) | 5/20/20 | AR | Items are uploaded on the AR. | 2-Jun-20 |
| 46 | IDIQ PWS Attch 1 Southwest Site List BECOS vf3 | For George AFB Site CG070, it states that the site is contaminated with PFAS. It does not appear from the Annual Monitoring Reports that groundwater samples are being analyzed for PFAS. Should the bidders assume that samples are not analyzed for PFAS and that IDW does not need to be analyzed for PFAS compounds? | 5/20/20 | IDIQ PWS | Bidders should assume that groundwater samples are not analyzed for PFAS. Bidders should assume characterization, handling, and disposal of IDW according to the most current applicable federal, state, local, DoD/AF guidance, and the HQ USAF/A4, Air Force Guidance Memorandum Establishing Aqueous Film Forming Foam (AFFF)-Related Waste Management Implementation Guidance, AFGM 1908-32-71, Sep 2019. | 2-Jun-20 |
| 47 | IDIQ PWS Attch 1 Southwest Site List BECOS vf3 | George AFB shows Sites ST067a and ST067b. However, a search on the Administrative Record could not identify and documents related to the current status of Site ST067a. What are the specific requirement that need to be performed on TO 002 related to Site ST067a? Please clarify the SOW. | 5/20/20 | AR | The removal and abandonment of the Liquid Fuels Distribution System (LFDS) portion of Site ST067a is found in the Final Report for Liquid Fuel Distribution System Removal, Underground Storage Tank Removal and Oil-Water Separator Inspection dated Janaury 1995 and prepared by Odgen Environmental Services, which is AR #s 759 and 916. | 2-Jun-20 |
| 48 | IDIQ PWS Attch 1 Southwest Site List BECOS vf3 | For George AFB Site SS030, the table states that Petroleum Sites Corrective Action Plan (CAP), Part I is under RWQCB review since 24 June 2013. Is there any action that needs to be performed with the CAP on TO 002? Same question for Site OT071. Please clarify the SOW. | 5/20/20 | IDIQ PWS | The Petroleum Sites Corrective Action Plan (CAP) for flightline Sites SS030, ST054, ST057 and SS084, and the Pesticide CAP for Site OT071 are NOT part of TO 02. | 2-Jun-20 |
| 49 | TO 2 PWS Attch Williams Base Spec Req Southwest BECOS vf2 | Please provide a copy of the following: AMEC, 2013a. Final Groundwater Monitoring Work Plan, Site LF004, Former Williams Air Force, Base, Mesa, Arizona. 5 August 2013. | 5/20/20 | AR | The Final Groundwater Monitoring Work Plan, Site LF004 is available in the online Administrative Record file as document 1631. | 2-Jun-20 |
| 50 | TO 2 PWS Attch Williams Base Spec Req Southwest BECOS vf3 | How many PFAS analytes are required for reporting at Williams AFB, Landfill 004 Site : 18, 24 or 33 PFAS analytes? | 5/20/20 | TO 2 | No PFAS analytes are required to be reported at Williams AFB Landfill 004 under this project. | 2-Jun-20 |
| 166 | Section L | Amendment 1 does not respond to all RFIs. Offerors need the RFI responses with SOW clarifications BEFORE requesting subcontractors bids. In order to allow adequate time for subcontractors to respond Offerors' bid requests and time for Offerors to process sub bids and then prepare a comprehensive cost proposal for this extensive program, we respectfully request that the proposal due date be extended to a date that is three (3) weeks after all RFI responses have been posted. | 5/21/20 | General | Proposal deadline extended to 15 June 2020. See amendment 02. | 2-Jun-20 |
| 167 | Cost Proposal | The "6 mo ext” tab is locked and automatically calculated based on the previous option, however there is no way to add escalation to it because of this. Will the Govt consider unlocking this tab, so we can properly escalate our pricing for this task? | 5/22/20 | Section L | The 6 month tab remains as is. | 2-Jun-20 |