IEP Portal Capacity Governance Board (CGB) July 24, 2014
(Extracted Version)
TIRNO-16-R-00026 IEP 1.5
SECTION J-ATTACHMENT C.4
Capacity Management Governance
The Portal Governance board has requested the creation of a dynamic capacity Governance model for IEP private cloud to meet the demands of the application groups and mitigate the current over allocation:
Background:
• With a successful tax season behind us, a review has been done regarding planned capacity and upcoming demand
Problem Statement:
• The IEP while having the capability to dynamically allocate capacity is not optimized to do so
• Applications are operating in a static model, holding on to a fixed number of corporate assets for IEP
• Demand continues to grow while the base needs are not contracting
Solution Approach:
• In order to manage capacity and move to a dynamic model, a Capacity Governance Board needs to be stood up to make decisions and provide organizational alignment
• The Capacity Governance Board ensures that IEP capacity objectives and project objectives are met and the expenditure of resources allocated is fiscally sound.
Today’s Objective:
PPMO is looking to gain concurrence on the framework for a Portal Capacity Governance Board and review the updated capacity plan to set the groundwork for ongoing capacity planning discussions
IEP Capacity Governance Problem Statement
2 IEP Capacity Governance | PPMO
Capacity Governance Process & Structure
3 IEP Capacity Governance Framework | PPMO 3
1. Capacity Demand Collection
• Capacity Operational Monitoring
& Report
• New Capacity Demand through
TRB
2. Capacity Analysis and Planning, Propose Solution, Priorization
3. Capacity Plan Review and Approval
• Capacity management stackholder meeting at Working group level.
• Capacity Governance Board (CGB)
4. Plan Implementation
(through new project or ticket)
• Reallocation
• Upgrade and Expansion
• Demand Mangagment (Alternatives for the demand)
Cap. Gov. Board:
Chairs
Advisory Panel
Working Groups: PPMO, AD, EITPMO, EOPS, ES, OLS, Cyber, IEP vendor
DCIO
Governance Mode of Operation
4 IEP Capacity Governance Framework | PPMO
The DCIO Resolves escalated issues from CGB; Ad-hoc meetings.
The IEP Capacity Governance Board (CGB) Approves adjustment plan of IEP existing capacity; Recommends capacity increase and expansion to IEP Governance Board; Resolves escalated risks & issues.
Escalates key decisions to CTO or DCIO; Monthly and ad-hoc meetings.
The Working Groups Reviews IEP capacity management report;
Collect capacity demands; Identify potential capacity management issues; Recommend capacity adjustment and plan to CGB; Ensures decisions and issues are resolved in a timely manner; Risks are managed and escalated appropriately. Weekly meetings.
Project governance provides the oversight necessary to approve recommendations, mitigate risks, resolve issues, and address enterprise concerns.
DCIO
Working Groups: PPMO, AD, EITPMO, EOPS, ES, OLS, Cyber, IEP Vendor
Cap. Gov. Board:
Chairs
Advisory Panel
Capacity Operating Guidelines
5 IEP Capacity Governance Framework | PPMO
• Procedural Guidelines
• Every meeting will record discussion points, decisions made, and actions
• ACIOs that are part of the CGB Advisory Panel are required to have representation at the WG meetings
• It is the representative’s responsibility to brief their respective ACIOs
• The WG Chair will pre-brief CGB Co-Chairs at least 1 day prior to a CGB meeting
• The Capacity Working Group (WG) is responsible to approve the following types of capacity requests:
• New Non-Production Environment Capacity Requests where capacity is available
• Reservation extensions where capacity is available
• Temporary above baseline capacity requests in non-Production environments where capacity is available
• The Capacity Governance Board (CGB) is responsible to approve the following types of capacity requests:
• Production environment capacity requests
• Reducing application capacity from Production environments
• Capacity requests with conflicts and risks within an environment
• Capacity requests where capacity is not available
• Reservation extensions with conflicts
• IEP policy changes that impact capacity