Timeline_April_Board_#26-386-RFSQ-_BP-00502_ORL_TAXIWAY_A_REHABILITATION_AND_RELATED_WORK_-_Procurement_Timeline_for_RFSQ_1-Step_-12.19.26.xlsx
XLSX spreadsheet 71 KB Posted
- Solicitation number
- 26-386-RFSQ
- Issued by
- Florida
About this file
This is a procurement timeline document for the Greater Orlando Aviation Authority (GOAA) detailing the Request for Statement of Qualifications (RFSQ) process for professional design services for Orlando Executive Airport Taxiway A Rehabilitation and Related Improvements (Project BP-00502). The solicitation encompasses comprehensive design services for rehabilitating Taxiway A and connectors between Taxiway A1 and Taxiway A5, including construction of an aircraft holding bay, with work involving asphalt pavement mill and overlay, pavement removal and reconstruction, clearing and grubbing, excavation, grading, drainage improvements, sodding, and installation of markings, lighting, and signage. The procurement timeline establishes key milestones beginning with procurement intake form approval on December 19, 2025, followed by a solicitation release date of February 8, 2026, with the solicitation remaining open for a minimum of 30 calendar days per Florida statute. The pre-submittal meeting and site visit are scheduled for February 13, 2026, the question deadline is February 20, 2026, and proposals are due March 12, 2026. The Procurement Committee evaluation and shortlisting is scheduled for April 7, 2026, with interviews on April 14, 2026, Notice of Intent to Award posted on April 14, 2026, and the appeal period ending April 21, 2026. Final Board approval for ranking and award is scheduled for May 20, 2026, with total business days allocated at 156 for the entire process.
The estimated design cost for this project is $700,000, with funding sourced from 95% FAA Airport Improvement Program (AIP) grants, 4% Florida Department of Transportation funding, and a 1% local match from GOAA. The project is subject to federal FAA review concurrent with departmental review and is governed by federal regulations including Title VI Civil Rights requirements and Transportation Security Administration directives. Respondents must meet minimum qualifications including prime consultant experience on at least two similar airfield projects valued at $5,000,000 or more within the past five years and possess Florida professional engineering licensure. The evaluation criteria allocate 30 points for proposed approach and methodology, 25 points for relevant project experience, 25 points for qualifications of key personnel, 10 points for quality control program, and 10 points for other CCNA factors. Insurance requirements include Commercial General Liability ($1,000,000), Automobile Liability ($1,000,000), Professional Liability ($1,000,000 per claim), and Pollution Liability coverage. Current U.S. Department of Transportation regulations prohibit counting Disadvantaged Business Enterprise (DBE) participation for this specific contract, though such participation goals are typically standard for GOAA procurements.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFSQ Base Agreement
| #26-386-RFSQ- BP-00502 ORL TAXIWAY A REHABILITATION AND RELATED WORK | |||||
| Tasks | Allocated Business Days | Actual Dates | Kendrick Proposed | Notes | |
| Industry Day Date (Prepared by SPA): | N/A | None | |||
| Department's AAR Completes PIF: | 5 | ||||
| - Small Business Review (Attach Document) | |||||
| - Risk Management Review (Attach Document) | |||||
| - Board Notice Date Obtained by Department (Attach Board Memo to the PIF) | |||||
| Approved Procurement Intake Form (PIF) Received Date: | Friday, December 19, 2025 | ||||
| Senior Manager Procurement Assigns PIF to Senior Procurement Agent (SPA) | Friday, December 19, 2025 | ||||
| SPA Completes Procurement Project Plan and Creates RFSQ in OpenGov. Invite Collaborators: Scott,Torie, Tuan, Tara, OAR, PM (Or PEW: Brad, Kevin, Karla, Keegan, Chris) | 10 | Wednesday, January 07, 2026 | Tuesday, December 23, 2025 | ||
| - Department/AAR to Finalize Scope | 1 | Thursday, January 08, 2026 | Friday, December 26, 2025 | ||
| Department's AAR/AVP/VP Review and Approve in OpenGov Concurrent: Scott, Torie, Tuan, Tara, OAR, PM, Karen Ryan (Or PEW: Brad, Kevin, Karla, Keegan, Chris, Karen Ryan) | 5 | Friday, January 16, 2026 | Monday, December 29, 2025 | If the project is rushed they should be able to make this a priority | |
| Federal - FAA Review - Concurrent with Department | 3* | Wednesday, January 21, 2026 | N/A | ||
| EVP - Chief Development Officer - Jeffrey Brown | 2 | Friday, January 23, 2026 | Tuesday, December 30, 2025 | ||
| Senior Manager Procurement Review and Approve in OpenGov: Cheryl | 2 | Tuesday, January 27, 2026 | Wednesday, December 31, 2025 | ||
| AVP/SVP Procurement Review and Approve in OpenGov - Concurrent: Kelly and Olimpia | 2 | Thursday, January 29, 2026 | Friday, January 02, 2026 | ||
| Legal Services Review and Approve in OpenGov - Concurrent with Department: (Karen Ryan) | 0 | Thursday, January 29, 2026 | |||
| General Counsel Review: (by General Counsel) | 5 | Wednesday, February 04, 2026 | Friday, January 09, 2026 | ||
| Due Date for Newspaper Advertisement (Prepared by SPA): | 3 | Wednesday, February 04, 2026 | Monday, January 12, 2026 | Pending GC approval (possibly earlier) | |
| Solicitation Release Date (Must Stay Open for at Least 30 Calendar Days, per FL Statute): | 20 | Sunday, February 08, 2026 | Tuesday, January 13, 2026 | ||
| - Pre-Submittal Meeting Date (5 Days After Release): | Friday, February 13, 2026 | Tuesday, January 20, 2026 | |||
| - Site Visit Date (Same Date as Pre-Submittal Date): | Friday, February 13, 2026 | Tuesday, January 20, 2026 | |||
| - Deadline For Questions (5 Days After Pre-Submittal Date): | Friday, February 20, 2026 | Tuesday, January 27, 2026 | |||
| - Deadline for Department to Answer Questions (2 Days) | Tuesday, February 24, 2026 | Friday, January 30, 2026 | |||
| - Legal Services Review of Final Addendum (3 Days) | Friday, February 27, 2026 | Wednesday, February 04, 2026 | |||
| - Release Addendum | Monday, March 02, 2026 | Thursday, February 05, 2026 | |||
| - Solicitation Due Date: | Thursday, March 12, 2026 | Friday, February 13, 2026 | |||
| SPA to Complete Responsive/Responsible/Reference Checks and send Matrix to SMEs, Legal, SBD, Risk, & Finance with Due Dates | 5 | Friday, March 20, 2026 | Thursday, February 19, 2026 | ||
| SPA Send Responses to PC Committee & Schedules 1on1 Briefings: | 10 | Friday, April 03, 2026 | Thursday, March 05, 2026 | ||
| - PC Memo Deadline | N/A | N/A | |||
| Procurement Committee Evaluation of Written Submittals AND SHORTLISTING Date: | 5 | Tuesday, April 07, 2026 | Tuesday, March 10, 2026 | ||
| SPA Sends Interview Questions to Short-Listed Firms | Wednesday, April 08, 2026 | Wednesday, March 11, 2026 | Pushed out the time a couple days due to Thanksgiving week | ||
| SPA Schedules and Facilitates 1-on-1's if Needed | 5 | N/A | N/A | ||
| Procurement Committee Short-Listed Firms Interview Date & Ranking | 10 | Tuesday, April 14, 2026 | Tuesday, March 17, 2026 | ||
| SPA Posts Notice of Intent to Award on OpenGov | Tuesday, April 14, 2026 | Tuesday, March 17, 2026 | |||
| SPA Sends Notice of Intent to Award to Firm(s) with Instructions RE: Performance & Payment Bonds, Certificate of Insurance (Suppliers have 10 Days to comply after Board approval) | Wednesday, April 15, 2026 | Wednesday, March 18, 2026 | |||
| Appeal Period End Date (5 Business Days): | 5 | Tuesday, April 21, 2026 | Wednesday, March 25, 2026 | ||
| SPA Facilitates Contract Negotiations/Development (30 Calendar Days): | 20 | ||||
| Board Memo Submitted by Department by Due Date: | 15 | Thursday, April 30, 2026 | Thursday, March 26, 2026 | ??? | |
| Board Date For Approval of Ranking and Award: | 15 | Wednesday, May 20, 2026 | Wednesday, April 15, 2026 | ||
| SPA Sends Notice of Award to Firm(s) | 1 | ||||
| SPA Facilitates Contract Execution | 10 | ||||
| SPA Saves all Contract Documents in Box and Then Sends Notice to Project Controls so They Can Download all Contract Documents into their System / Final Handoff to Project Controls | |||||
| AAR Facilitates Project Kickoff Meeting | |||||
| Department Issues Tasks as Appropriate | |||||
| Total Business Days | 156 | ||||
| All Task Order $250,000 or Greater Will Require Board Approval | |||||
| All Task Orders $0+ Require Construction Committee Approval |