This is a procurement timeline document for the State of Florida outlining the Request for Sealed Quotation (RFSQ) process for Professional Design Services related to Taxiway A Rehabilitation and Related Work at Orlando Executive Airport (ORL). The project encompasses pavement rehabilitation for Taxiway A and its connectors between Taxiway A1 and Taxiway A5, including construction of an aircraft holding bay with associated work such as asphalt mill and overlay, pavement removal and installation, clearing and grubbing, excavation, drainage, sodding, marking, lighting, and signage. The procurement timeline establishes key milestones including a pre-submittal meeting and site visit scheduled for February 13, 2026, a solicitation release date of February 8, 2026 (with a minimum 30-calendar-day open period per Florida Statute), a solicitation due date of March 12, 2026, procurement committee evaluation and shortlisting on April 7, 2026, short-listed firm interviews on April 14, 2026, a five-business-day appeal period ending April 21, 2026, and board approval for ranking and award scheduled for May 20, 2026. The total estimated timeline comprises 156 business days from procurement intake through project kickoff.
The document specifies that all task orders of $250,000 or greater require board approval, and all task orders of $0 and above require construction committee approval. The procurement involves multiple internal stakeholders including procurement agents, department representatives, legal services, risk management, small business development, and finance review at various stages. The General Counsel and Chief Development Officer approvals are required, with concurrent federal FAA review noted. A newspaper advertisement deadline is set for February 4, 2026, and the deadline for questions is February 20, 2026. Contract negotiations are allocated 30 calendar days following the appeal period, with the notice of award to be sent following board approval and the conclusion of the appeal period.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFSQ Base Agreement
| #26-386-RFSQ- BP-00502 ORL TAXIWAY A REHABILITATION AND RELATED WORK | |||||
| Tasks | Allocated Business Days | Actual Dates | Kendrick Proposed | Notes | |
| Industry Day Date (Prepared by SPA): | N/A | None | |||
| Department's AAR Completes PIF: | 5 | ||||
| - Small Business Review (Attach Document) | |||||
| - Risk Management Review (Attach Document) | |||||
| - Board Notice Date Obtained by Department (Attach Board Memo to the PIF) | |||||
| Approved Procurement Intake Form (PIF) Received Date: | Friday, December 19, 2025 | ||||
| Senior Manager Procurement Assigns PIF to Senior Procurement Agent (SPA) | Friday, December 19, 2025 | ||||
| SPA Completes Procurement Project Plan and Creates RFSQ in OpenGov. Invite Collaborators: Scott,Torie, Tuan, Tara, OAR, PM (Or PEW: Brad, Kevin, Karla, Keegan, Chris) | 10 | Wednesday, January 07, 2026 | Tuesday, December 23, 2025 | ||
| - Department/AAR to Finalize Scope | 1 | Thursday, January 08, 2026 | Friday, December 26, 2025 | ||
| Department's AAR/AVP/VP Review and Approve in OpenGov Concurrent: Scott, Torie, Tuan, Tara, OAR, PM, Karen Ryan (Or PEW: Brad, Kevin, Karla, Keegan, Chris, Karen Ryan) | 5 | Friday, January 16, 2026 | Monday, December 29, 2025 | If the project is rushed they should be able to make this a priority | |
| Federal - FAA Review - Concurrent with Department | 3* | Wednesday, January 21, 2026 | N/A | ||
| EVP - Chief Development Officer - Jeffrey Brown | 2 | Friday, January 23, 2026 | Tuesday, December 30, 2025 | ||
| Senior Manager Procurement Review and Approve in OpenGov: Cheryl | 2 | Tuesday, January 27, 2026 | Wednesday, December 31, 2025 | ||
| AVP/SVP Procurement Review and Approve in OpenGov - Concurrent: Kelly and Olimpia | 2 | Thursday, January 29, 2026 | Friday, January 02, 2026 | ||
| Legal Services Review and Approve in OpenGov - Concurrent with Department: (Karen Ryan) | 0 | Thursday, January 29, 2026 | |||
| General Counsel Review: (by General Counsel) | 5 | Wednesday, February 04, 2026 | Friday, January 09, 2026 | ||
| Due Date for Newspaper Advertisement (Prepared by SPA): | 3 | Wednesday, February 04, 2026 | Monday, January 12, 2026 | Pending GC approval (possibly earlier) | |
| Solicitation Release Date (Must Stay Open for at Least 30 Calendar Days, per FL Statute): | 20 | Sunday, February 08, 2026 | Tuesday, January 13, 2026 | ||
| - Pre-Submittal Meeting Date (5 Days After Release): | Friday, February 13, 2026 | Tuesday, January 20, 2026 | |||
| - Site Visit Date (Same Date as Pre-Submittal Date): | Friday, February 13, 2026 | Tuesday, January 20, 2026 | |||
| - Deadline For Questions (5 Days After Pre-Submittal Date): | Friday, February 20, 2026 | Tuesday, January 27, 2026 | |||
| - Deadline for Department to Answer Questions (2 Days) | Tuesday, February 24, 2026 | Friday, January 30, 2026 | |||
| - Legal Services Review of Final Addendum (3 Days) | Friday, February 27, 2026 | Wednesday, February 04, 2026 | |||
| - Release Addendum | Monday, March 02, 2026 | Thursday, February 05, 2026 | |||
| - Solicitation Due Date: | Thursday, March 12, 2026 | Friday, February 13, 2026 | |||
| SPA to Complete Responsive/Responsible/Reference Checks and send Matrix to SMEs, Legal, SBD, Risk, & Finance with Due Dates | 5 | Friday, March 20, 2026 | Thursday, February 19, 2026 | ||
| SPA Send Responses to PC Committee & Schedules 1on1 Briefings: | 10 | Friday, April 03, 2026 | Thursday, March 05, 2026 | ||
| - PC Memo Deadline | N/A | N/A | |||
| Procurement Committee Evaluation of Written Submittals AND SHORTLISTING Date: | 5 | Tuesday, April 07, 2026 | Tuesday, March 10, 2026 | ||
| SPA Sends Interview Questions to Short-Listed Firms | Wednesday, April 08, 2026 | Wednesday, March 11, 2026 | Pushed out the time a couple days due to Thanksgiving week | ||
| SPA Schedules and Facilitates 1-on-1's if Needed | 5 | N/A | N/A | ||
| Procurement Committee Short-Listed Firms Interview Date & Ranking | 10 | Tuesday, April 14, 2026 | Tuesday, March 17, 2026 | ||
| SPA Posts Notice of Intent to Award on OpenGov | Tuesday, April 14, 2026 | Tuesday, March 17, 2026 | |||
| SPA Sends Notice of Intent to Award to Firm(s) with Instructions RE: Performance & Payment Bonds, Certificate of Insurance (Suppliers have 10 Days to comply after Board approval) | Wednesday, April 15, 2026 | Wednesday, March 18, 2026 | |||
| Appeal Period End Date (5 Business Days): | 5 | Tuesday, April 21, 2026 | Wednesday, March 25, 2026 | ||
| SPA Facilitates Contract Negotiations/Development (30 Calendar Days): | 20 | ||||
| Board Memo Submitted by Department by Due Date: | 15 | Thursday, April 30, 2026 | Thursday, March 26, 2026 | ??? | |
| Board Date For Approval of Ranking and Award: | 15 | Wednesday, May 20, 2026 | Wednesday, April 15, 2026 | ||
| SPA Sends Notice of Award to Firm(s) | 1 | ||||
| SPA Facilitates Contract Execution | 10 | ||||
| SPA Saves all Contract Documents in Box and Then Sends Notice to Project Controls so They Can Download all Contract Documents into their System / Final Handoff to Project Controls | |||||
| AAR Facilitates Project Kickoff Meeting | |||||
| Department Issues Tasks as Appropriate | |||||
| Total Business Days | 156 | ||||
| All Task Order $250,000 or Greater Will Require Board Approval | |||||
| All Task Orders $0+ Require Construction Committee Approval |