Technical Specifications Summary: Peeltree Road Portals Project
This document comprises technical specifications for an Abandoned Mine Land (AML) reclamation project administered by the West Virginia Department of Environmental Protection (WVDEP) involving the remediation of five mine portals located along Peeltree Road in Barbour County, West Virginia. The project scope encompasses erosion and sediment control installation, drainage channel construction, unclassified excavation and regrading, mine seal installation, bat gate placement, road rehabilitation, subsidence feature remediation, and revegetation of disturbed areas. The contractor is responsible for all surveying activities, material procurement, delivery, and the development of as-built plans prior to project completion. Key work items include mobilization and demobilization (capped at 10% of total bid), construction layout and surveying (capped at 5% of total bid), quality control testing (capped at 3% of total bid), site preparation including clearing, grubbing, and structure demolition (capped at 10% of total bid), erosion and sediment control measures, and revegetation operations. The contractor must comply with all applicable NPDES stormwater permitting requirements and assume co-applicant status for the construction stormwater general permit.
The contractor must obtain and maintain all necessary permits and licenses, including Water Quality Certification from WVDEP, burning permits from the West Virginia Department of Natural Resources, and stream activity permits. Specific payment methodologies are detailed for each bid item, with mobilization and demobilization paid in two installments (50% upon project initiation and 50% upon final inspection), and construction layout paid in three stages (50% upon completion, 25% throughout construction, and 25% upon acceptance of as-built plans). All borrow and disposal areas require WVDEP approval and must comply with NEPA environmental compliance requirements, including restrictions on historic sites, wetlands, endangered species habitats, and floodplain areas. The contractor bears full responsibility for sediment control maintenance, spill cleanup, hazardous material identification and removal, and payment of any fines or violations resulting from non-compliance with permit conditions. Material certifications, compaction testing, and soil analysis reports must be submitted for engineer approval prior to incorporation into the work.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
SECTION PAGE
I. SPECIAL PROVISIONS
I. Location/Site Description
II. Scope of Work
III. Borrow (Disposal) Areas
IV. Disposal of Unsuitable Material
V. Permits, Licenses, and Fees
VI. NPDES Stormwater Requirements
VII. Construction Sign
II. TECHNICAL SPECIFICATIONS
1.0 Mobilization and Demobilization
2.0 Construction Layout
3.0 Quality Control
4.0 Site Preparation
5.0 Erosion and Sediment Control
6.0 Revegetation
7.0 Drainage Structures
8.0 Unclassified Excavation
9.0 Mine Seals
10.0 Utilities
11.0 Traffic Control
13.0 Administration
Peeltree Road Portals
I. SPECIAL PROVISIONS
I. LOCATION / SITE DESCRIPTION
Three open and two suspected collapsed portals are within 50 feet of and run in succession parallel to the road. A convenient wide spot along the road shoulder allows for parking and illegal dumping. The portals are in plain view and easily accessible. Signs of visitation such as trash and footprints were evident. Starting from the south, Portal 1 (39° 06’30.9 80° 09’
42.9”) has an approximately 5 feet wide x 1.5 feet tall opening. Mine timbers and a mine pool were visible inside. Air movement was noticeable and an odor of sulfur was detected.
Drainage measured pH 7.7. Portal 2 (39° 06’ 31.1 80° 09’ 43.0”) has an approximately 8 feet wide x 4 feet tall opening. A stack of 6” x 6” timber cribbing in the entry draws the attention of passing motorists. The area upslope of this entry has an area of Priority 3 subsidence craters and holes. Portals 3 (39° 06’ 32.5 80° 09’ 43.7”) and 4 (39° 06’ 33.1”
80° 09’ 43.4”) are completely collapsed. Portal 5 is wide open with dimensions approximately 8 feet wide x 3 feet tall and discharging a moderate to high volume of pH
7.9, Fe 0 mg/L water.
Directions to site:
Directions to Site: From Philippi, travel south on US 119 and pass the Volga-Century
Elementary School. Continue south to Peeltree Road, CR 34, on the right. Turn right and drive 1.0 miles to portals on the right.
The GPS location is as follows: 39° 06’ 30”N 80° 09’ 42”W
II. SCOPE OF WORK
The work covered by the Special Provisions and Technical Specifications consists of furnishing all labor, plant, power, equipment and supplies, and performing all operations necessary for the completion of the project. The Contractor shall perform all operations necessary for:
E&S Controls Drainage Channels Unclassified Excavation/Regrading Mine Seals Bat Gates Road Rehabilitation Subsidence Features Revegetation
The Contractor shall also be responsible for surveying, including establishing construction baseline, measuring and developing all completed quantities on the job, and the ordering, purchase and delivery of any and all materials required for construction or required for development of support areas. The Contractor shall perform all other operations as incidental to the program as specified herein.
III. BORROW (DISPOSAL) AREAS
All borrow (disposal) areas must be approved by WVDEP. Should the Contractor decide to obtain and utilize any borrow areas outside of construction limits, or move material from one property owner to another, unless designated on the plans, the Contractor shall be responsible to obtain from the property owner(s) of the borrow areas, all necessary rights of entry, including rights of entry for WVDEP and OSMRE for inspection purposes. The said rights of entry agreement must state that the property owner(s) indemnify and hold harmless the WVDEP for Contractor’s action for any injury or damages whatsoever resulting from the use of the property.
The Contractor also shall submit a borrow/disposal area reclamation plan for prior approval by WVDEP. The Contractor shall observe the following NEPA compliance schedule relative to selecting and utilizing any off site borrow areas and/or any waste disposal areas.
a. No borrow (disposal) site operations will affect a site listed in, eligible for or proposed to be listed in the National Register of Historic Places.
b. No borrow (disposal) operations will be located within one-quarter mile of any federally listed established or prospective component of the National Wild and
Scenic River System under 16 USC 1274 and 1276.
c. Borrow (disposal) site operations will not cause a significant encroachment within the base floodplain (CE.O. 11988: Floodplain Management).
d. Borrow (disposal) site operations will not be located in or affect a critical habitat of a federally listed endangered or threatened species under 16 USC 1531, et. seq.
e. No borrow (disposal) operations will occur in wetland areas which are designated by appropriate agencies.
f. Borrow (disposal) site operations will be consistent with any approved plans governing ambient air quality.
g. Adherence to these mitigation measures does not relieve the Contractor of the obligation or responsibility to obtain any other federal, state, or local approvals required to use borrow (disposal) areas and conduct such activities.
h. Documentation: Copies of borrow (disposal) site approvals and concurrences will be submitted to the WVDEP prior to the commencement of reclamation activities.
i. Site Monitoring: Borrow (disposal) activities will be monitored by the state to ensure compliance with contractual requirements, applicable federal, state, and local laws, and any permit conditions.
IV. DISPOSAL OF UNSUITABLE MATERIAL
All waste areas shall be obtained in accordance with Special Provisions Section III
(Borrow/Disposal Areas) of these specifications. All unsuitable materials (wood, trash, debris, and garbage) as determined by the Engineer shall be wasted by the Contractor, at his/her expense, outside the limits of work conforming to the requirements of Sections 4.3.8 of these Specifications. Wood may be burned in conformity with Sections 4.3.7 of these
Specifications.
The Contractor shall observe the NEPA compliance schedule relative to selecting and utilizing any off-site disposal areas in accordance with Special Provisions Section III of these Specifications.
V. PERMITS, LICENSES AND FEES
The Contractor shall procure all permits and licenses, pay all charges and fees, and give all notices necessary and incidental to the due and lawful prosecution of the work. Permits required for this project may include but not be limited to: Water Quality Certification from WVDEP and burning permits from WVDNR and WVDEP Office of Air Quality. A copy of the permit/permits as procured shall be furnished to the Owner prior to initiation of the work under this Contract. The WVDEP will obtain the Permits (MM 109 Form) from
WVDOH and NPDES from WVDEP. Contractor shall be responsible for any Stream
Activity Permits necessary to complete the project work.
VI. NPDES STORMWATER REQUIREMENTS
The WVDEP-AML has obtained a Construction Storm Water General Permit for this project from WVDEP Division of Water and Waste Management (WVDEP DWWM). The registration for this reclamation project will be modified to include the Contractor as Co-
Applicant #1, with the WVDEP-AML being Co-Applicant #2. As such, the Contractor shall assume responsibility for compliance with the terms and conditions of the permit including modifications and any future correspondence such as registration renewal invoices, inspection reports, and notices of violation shall be forwarded to the Contractor.
Upon award of the contract, the Contractor shall complete a Co-Applicant #1 signature page and submit the completed form to WVDEP-AML prior to scheduling a Pre-
Construction Conference.
Upon receipt of the completed form, WVDEP-AML will request the WVDEP DWWM to modify the existing NPDES registration for this project to make the Contractor the Co-
Applicant #1 to the permit.
The WVDEP DWWM will notify the Contractor and WVDEP-AML when the successful transfer of registration under WV/NPDES Storm Water Construction General Permit
(No.WV0115924) is completed. A Notice to Proceed will not be issued until the contractor signs the co-applicant form and submits to the Office of Abandoned Mine Lands. Once the transfer has been completed, the WVDEP will continue to be responsible for any modification fees and annual renewal fees incurred up until the date of the final inspection of the project that occurs after completion of construction activities at the site. The
Contractor shall be responsible for any and all costs associated with violations and fines assessed against the project that are a result of the Contractor’s negligence, carelessness, or failure to install permanent controls as part of the work as scheduled.
The Contractor shall apply for a Notice of Termination (NOT) from WVDEP DWWM via the Construction Storm Water website http://www.dep.wv.gov/Programs/stormwater/csw/Documents/Construction upon completion of construction activities at the site. The NOT shall be issued by WVDEP
DWWM upon completion of the project. The Contractor will continue to be bound by the terms and conditions of the permit until the NOT has been approved by WVDEP
DWWM. Once the project is complete, the Contractor will still bear responsibility for the
NPDES registration until a NOT is received from the WVDEP DWWM.
Co-Applicant #1 Signature Page
Co-Applicant #1: ________________________________________
New and/or Modification of NPDES Storm Water of Construction Project
Name: _________________________________________________
BY COMPLETING AND SUBMITTING THIS APPLICATION, I HAVE REVIEWED AND UNDERSTAND
AND AGREE TO THE TERMS AND CONDITIONS OF THE GENERAL PERMIT ISSUED ON DECEMBER
05, 2012. I UNDERSTAND THAT PROVISIONS OF THE PERMIT ARE ENFORCEABLE BY LAW,
VIOLATION OF ANY TERM AND CONDITION OF THE GENERAL PERMIT AND/OR OTHER
APPLICABLE LAW OR REGULATION CAN LEAD TO ENFORCEMENT ACTION.
I CERTIFY UNDER PENALTY OF LAW THAT I HAVE PERSONALLY EXAMINED AND AM FAMILIAR
WITH THE INFORMATION SUBMITTED ON THIS FORM AND ALL ATTACHMENTS AND THAT,
BASED ON MY INQUIRING OF THOSE INDIVIDUALS IMMEDIATELY RESPONSIBLE FOR
OBTAINING THE INFORMATION. THE INFORMATION SUBMITTED IS, TO THE BEST OF MY
KNOWLEDGE AND BELIEF, TRUE, ACCURATE, AND COMPLETE. I AM AWARE THAT THERE ARE
SIGNIFICANT PENALTIES FOR SUBMITTING FALSE INFORMATION, INCLUDING THE POSSIBILITY
OF FINE AND IMPRISONMENT.
(CO-APPLICANT #1 SIGNATURE) DATE
Print Name: _________________________________________
Print Title: __________________________________________
Address: ____________________________________________
City: ______________________ State: _______ Zip: _________
Telephone Number: (_____) _______ - ____________________
Email: ______________________________________________
FEIN: _______________________________________________
VII. CONSTRUCTION SIGN
1. Work Required.
The work to be performed under this Section consists of providing all labor, material and equipment necessary to install a project sign as indicated on the detail included herein and as specified herein.
2. Materials.
(a) Sign face shall be 3/4" Marine Exterior plywood or aluminum or composite material. Posts and cross-brace shall be No. 2 Grade Pine or Fir, kiln dried and pressure treated.
(b) Hardware:
(1) All hardware shall be manufactured from good, commercial-quality material and meet all applicable ASTM standards.
(2) Spikes and nails shall be common wire-type and shall meet AISI steel specifications 1010 or 1020.
(3) All hardware shall be hot-dip galvanized in accordance with
ASTM A-153.
3 Execution.
(a) Project Sign. The sign board shall be cut to the dimensions shown on the detail herein. The sign shall painted with one (1) coat of primer and two (2) coats of white enamel. All exterior cut edges shall be smooth sanded prior to painting.
All edges shall be double primed. The letters, border and strips shall be painted as shown on the detail drawing. Posts and cross-brace shall be painted with two
(2) finished coats of brown enamel.
The Contractor shall bolt the sign to posts and provide required cross-bracing.
The posts and sign shall be erected and posts set in gravel base, as shown on the drawings. One (1) sign is required and is to be located at the discretion of the
Inspector.
(b) Payment. Payment for the work which shall include installation of the project sign shall be part of the lump-sum bid for "Mobilization".
II. TECHNICAL SPECIFICATIONS
1.0 MOBILIZATION AND DEMOBILIZATION
1.1 Description
This work shall consist of the performance of construction preparatory operations, including the movement of personnel and equipment to the project sites and for the establishment of the Contractor’s offices, buildings and other facilities including the construction of all temporary access roads as necessary to begin work on a substantial phase of the contract. The location of the Contractor’s office to be established shall be approved by WVDEP. It also shall include all demobilization activities involving the removal from the sites of all plant, equipment, supplies and personnel after completion of the work including cleanup of all rubbish and waste materials generated during the construction of this project and restoration of any damage to existing site improvements resulting from the Contractor’s activities at the site. This item shall also include the installation of the project sign at the beginning of the project and the removal of the sign prior to the Final Inspection. All equipment and material storage areas shall be approved by WVDEP.
Upon receipt of a notice to proceed, the Contractor shall initiate and complete measures necessary to commence the work. Mobilization shall also consist of delivering to the site and assembling in working order all necessary equipment, materials, and supplies to be furnished by the Contractor to complete the work.
Demobilization shall consist of the removal from the site of all the Contractor’s equipment and materials after completion of the work and cleanup of the site. Work shall be done to the satisfaction of the Regional Engineer.
1.2 Method of Measurement and Basis of Payment
The bid for “Mobilization and Demobilization” shall be lump sum and cannot be more than 10% of the TOTAL AMOUNT BID for the project. Partial payments will be as follows:
One-half of the amount bid will be released to the Contractor with the first estimate payable, not less than 15 days after the start of work at the project site.
The final one-half of the amount bid shall be released with the last estimate payable after the work is accepted by the WVDEP and after all Final Inspection submittals are received and approved by WVDEP.
Nothing herein shall be construed to limit or preclude partial payments otherwise provided for by the contract. No deduction will be made nor will any increase be made, in the lump sum mobilization and demobilization item amount regardless of decreases or increases in the final total contract amount or for any other cause.
1.3 Pay Item
Item 1.0, “Mobilization and Demobilization” per lump sum cannot be more than 10% of the TOTAL AMOUNT BID for the project.
2.0 CONSTRUCTION LAYOUT
2.1. Description
This item consists of furnishing, placing, and maintaining construction layout stakes, (based on the original baselines and/or control points in the plans), necessary for the proper performance of the work under this contract including borrow/waste areas. It shall further consist of determining the exact units of measure for payment. It also consists of checking and making any field adjustment to the plan alignment, grades and elevations as considered necessary by the Engineer.
Additionally, this item shall also include the preparation of “As-Built” Plans including the Reclamation Plan and any others specifically requested by the WVDEP. All of these “As-Built” Plans shall be provided prior to the Final Inspection Meeting. This item will be paid according to the following schedule: up to fifty percent of the total bid amount of this item will be released for payment when all required layout work is completed. The remaining 50% will be paid on the following schedule: 25% for layout throughout/end of construction, 25% on acceptance of as-builts. This layout shall include location stakes and cut-fill lines marked on the stakes for each pre-manufactured or formed on site structures (manholes, drop inlets, headwalls, etc.). The layout shall also include centerline stake with cut-fill lines for each channel and any areas of excavation and re-grade. The certified layout and cross-sections surveyed must be submitted to the WVDEP for approval prior to beginning construction for each item.
2.2. Materials
Conventional survey stakes, hubs, batter boards, flagging, templates, straightedges, and other devices necessary for laying out all parts of the work.
2.3. Construction Methods
2.3.1 The Contractor shall be responsible for the proper layout of the work. The Owner will provide the Contractor with survey information regarding the baselines and the existing surface features shown on the Construction Drawings. The Contractor shall make all calculations involved and shall furnish and place all layout stakes.
2.3.2 The Contractor shall provide field forces and shall set all additional stakes as needed, such as offset stakes, reference point stakes, slope stakes, grade stakes, stakes for drainage, or other structures, supplementary benchmarks, and any other horizontal or vertical controls necessary to secure a correct layout of the work including the re-establishment of the survey and construction baselines (as necessary), as shown on the Construction Drawings.
2.3.3 The Contractor shall be responsible for assuring the layout staking work is in conformance to the lines, grades, elevations, dimensions, and locations shown on the Construction Drawings or as required by the Engineer. The Contractor shall furnish a copy of his/her survey records for review by the Engineer and for the Owner's permanent file. These records shall be furnished as they are completed during the progress of the work.
2.3.4 Any inspection or review of the Contractor's layout by the Engineer and the acceptance of all or any part of it shall not relieve the Contractor of his/her responsibility to secure the proper dimensions, grades, and elevations of the several parts of the work.
2.3.5 The Contractor shall exercise care in the preservation of stakes and benchmarks, including existing property line markers, and shall have them reset at his/her expense when any are damaged, lost, displaced or removed. The Contractor shall use competent personnel and suitable equipment for the layout work required and shall provide that it be done under the supervision of, or directed by, a Licensed Land Surveyor registered in the State of West Virginia. As the survey progresses to completion, the Licensed Land Surveyor shall certify that the site layout is complete for all necessary grades (both cut and fill), location and grades of all ditches, all cross-sections related to cut-fill where grade lines are necessary for construction and or billing.
2.3.6 As-Built plans shall be provided to the WVDEP prior to the Final Invoicing. All work completed by the WV Licensed Land Surveyor on the As-Builts must be certified by the Licensed Land Surveyor as to completeness and accuracy of the plan submittal. The As- Builts shall be provided in two forms of electronic format in PDF and AutoCAD 2011- 2017 on either CD-ROM, DVD, or USB memory stick and one paper copy of the plans with the same size and scale as contained on the original plans.
The As-Builts Shall include the following:
1. Show all permanent work in place, and any deviations from original plans.
2. The preferred coordinate system and elevation datum need to be specified.
3. Show all horizontal and vertical dimensions (including invert elevations) of all installed components (i.e. pipes, drop inlets, mine seals, drainage channels, splash pads, manholes, etc.), as well as surveyed locations of the installed structures. Any other items deemed necessary (provided in the contract) by the WVDEP shall be included in the As-Builts.
4. Cut-fill sections shall have the area of the section marked by the section for easier calculation.
5. Have the lines on the plans shown in either color or line type to distinguish between our original plan lines, the contractor’s original survey lines and the final grade lines. This will apply for all cross-sections on the project.
6. All waste and borrow areas shall be shown and labeled.
7. Revegetation that is paid for by acreage, shall be per plan view acreage and shall be shown on a separate Autocad layer. The enclosed areas shall not include any graveled surfaces, paved surfaces, roads, ponds, treatment components, all non-vegetated channels, buildings, etc. (including any non-vegetated areas).
8. In Autocad, the zero (0) layer shall not be used to draw on other than to insert blocks for future insertion on appropriate layer.
9. As a standard, new baseline and final contours shall be provided with 2 feet minor contours and 10 feet major contours. Major contours shall have the elevation labeled.
Contour Labels shall not break the contour line (see setting in AutoCad).
10. Any control points shall be shown with coordinates and elevations labeled. If WV DEP provided control points, contractor shall reference elevations and coordinates to them. If no control points were set, then new points shall be set and utilized.
11. Any seep collectors, underdrains, or other structures inaccessible after covering, shall be surveyed for location, prior to covering.
12. Show total quantities for all items on the project. The format shall be in a tabular form (i.e. Bid Schedule or Summary of Quantities).
13. Changes (deviations) should be on separate “Change” layer, not on the original layers from the original plan.
ITEMS TO BE IDENTIFIED AND LABELED
ITEMS AUTOCAD LAYER REQUIRED
☒ Baseline Survey after Clearing & Grubbing, if required YES
☒ Intermediate Surveys, if required YES
☒ Final Survey YES
☒ Revegetation YES
☒ Pipes, Valves, Manholes YES
☒ Mine Seals, Bat Gates YES
☒ Seep Collectors, Clean Outs YES
☒ Drainage Channels & Ditches, Splash Pads, Culverts, Drop Inlets YES
☒ Ponds, Wetlands, Water Treatment Structures YES
☒ Sludge Pumps, Sludge Cells, Geo-Tube Pads, Sludge Valves YES
☒ Buildings, Residential/Commercial Structures, Concrete Pads YES
☒ Pump Vaults, Air Release Valves, Pump Line Connections YES
☒ Fencing around Structures and Property Lines YES
☒ Utilities (i.e. Overhead/Underground Electric, Gas, Water, Sewer) YES
☒ Buried Lines (i.e. Electric, communication, chemical, water, sewer) YES
☒ Gas Vents, Piezometers, Monitoring Wells, Core Drilling YES
☒ Roads, Driveways, Sidewalks YES
☒ Unforeseen Areas (i.e. Slips, Seeps, Subsidence Areas, Boreholes) YES
☐ Other, As Defined:____________________________________________
2.4. Method of Measurement and Basis of Payment
There shall be no measurement of the “Construction Layout” item as it is a lump sum. The lump sum payment also shall include the cost for providing the Engineer pre- and post- construction ground line cross-sections for all disturbed or re-graded areas including borrow areas and “As- Built” Plans as described herein. Said lump sum bid cannot be more than 5% of the TOTAL AMOUNT BID for the project. Neither deduction nor increase will be made in the lump sum “Construction Layout” item amount regardless of decreases or increases in the final total contract amount or for any other cause. This item will be paid according to the following schedule: up to fifty percent of the total bid amount of this item will be released for payment when all required layout work is completed as outlined in Specification 2.1. The remaining will be paid on the following schedule: 25% for layout throughout/end of construction, 25% on acceptance of as-builts
2.5. Pay item
Pay Item 2.0, “Construction Layout”, per lump sum cannot be more than 5% of the TOTAL AMOUNT BID for the project.
3.0 QUALITY CONTROL
3.1 Description
This work shall consist of testing for verification that the materials supplied and the work performed are in accordance with these specifications.
3.2 Materials
3.2.1 The Contractor shall submit a minimum of two (2) copies of shop drawings, catalog cuts and material certifications (as applicable) to the Engineer for all offsite materials to be incorporated into the work. Written approval from the Engineer will be required prior to incorporation of these items into the work.
3.2.2 The Contractor shall submit at least two (2) copies of the results of all tests conducted on in-situ material, and stone to be used in this project.
i. As a minimum, the compaction tests will include moisture content & density tests of the soil in accordance with the provisions of ASTM D698 (Standard Proctor) field density tests following compaction. A new Standard Proctor will be run when soil type changes occur on site and/or at the direction of the Engineer or his representative.
ii. Soil tests to determine the lime and nutrient requirements of the areas to be re-vegetated. (Or the 3 tons per acre preferred minimum for lime)
iii. Compressive strength test for grout in accordance with ASTM C109, and for concrete in accordance with ASTM C31 & C39.
3.2.3 Tests Required:
Pipe line Compaction Testing for backfill material density
Slope fill Compaction Testing for backfill material density
Soil Test As needed to determine Nutrient tests NPK
Material Certification Manufacture certification on all materials on project
Limestone Sodium sulfate test
Sandstone Riprap Certification that rock is non-acid producing and Sodium sulfate test
3.3 Construction Methods
3.3.1 The Contractor shall furnish the services of his own testing laboratory or select an independent testing laboratory, as long as the laboratory is under the direct supervision of a Registered Professional Civil Engineer. The laboratory must be approved by the Owner prior to testing.
3.3.2 The Contractor shall furnish a certified technician to perform the required testing at the project site. The technician shall submit a copy of his certification and a copy of that certification shall be submitted WVDEP at the Pre-Construction Conference. The technician shall be responsible for chain of custody of any samples that must leave the site.
3.3.3 Testing for compaction, soil nutrient and lime requirements for soil, compressive strength tests for concrete and grout, shall be performed as required by these specifications and/or ordered by the Engineer or his representative in writing. The Engineer will determine the locations and time of any testing herein specified and the need and extent of any testing in addition to that which is herein specified.
3.3.4 The contractor shall be responsible for performing laboratory tests of the coal, mine spoil, and any natural soil to identify the compaction requirements for their use as fill and cover material, respectively. In addition, field density tests shall be performed in accordance with the Construction Specifications. All test results shall be submitted to the Engineer for approval of compaction criteria prior to compacting the fill material and after fill material is placed to verify that the required compaction is obtained.
3.3.5 Only new and first class materials, which conform to the requirements of these Specifications, shall be used unless specified otherwise. When requested by the Owner, the Contractor shall furnish a written statement of the origin, composition, and manufacturer of any or all materials (manufactured or produced) that are to be used in the work. The sources of supply of each material used shall be approved by the Engineer before delivery is started. If, at any time, sources previously approved fail to produce materials acceptable to the Owner, the Contractor shall furnish materials from other approved sources.
3.4 Method of Measurement and Basis of Payment
There shall be no measurement of the “Quality Control” item as it is a lump sum. The quantity of quality control work done will be paid at the contract lump sum price bid for this item. Said lump sum bid cannot be more than 3% of the TOTAL AMOUNT BID for the project. Nothing herein shall be construed to limit or preclude partial payments on this item up to 100% of the bid amount. No deduction or increase shall be made in the lump sum “Quality Control” item amount regardless of decreases or increases in the final total contract amount or for any other cause.
3.5 Pay Item
Item 3.0, “Quality Control”, per lump sum cannot be more than 3% of the TOTAL AMOUNT BID for the project.
4.0 SITE PREPARATION
4.1 Description
4.1.1 Clearing & Grubbing
Work performed under this section shall include the removal and disposal of all trees, stumps, shrubs and any other vegetation, wood, debris, garbage of any nature from those areas specified below and/or shown on the plans and/or any other areas as approved by WVDEP. This work shall also include the preservation from injury to all vegetation, utilities or other objects to remain as well as all other ancillary work as described.
4.1.2 Demolition of Structures
This work shall consist of complete demolition and removal of such buildings, mining related structures, equipment and materials, existing ruins and foundation structures, as are specifically designated on the Plans for removal. Demolished concrete and cinder block structures and foundation ruins (all steel residue and wood (burned) must be removed from the site) can be disposed of on-site. Any demolished rubble must be thoroughly compacted in fill areas and not to be used as a replacement for structural materials.
4.1.3 Asbestos Material
This work shall consist of doing a thorough search of all existing structures on the project to ensure that there are no asbestos materials present. If there are any areas that are suspected then an inspection by a certified asbestos removal company will be required. If asbestos is found, the contractor will be responsible for removal and disposal at no cost to the WVDEP. No work shall be allowed at the location of the asbestos until the removal process is completed.
4.1.4 Gravel Road Rehabilitation Stone
Any regrading or resurfacing necessary to restore existing roads or driveways used during construction to a condition that is equal to or better than the condition encountered before construction activities.
4.1.5 Access Road
Additional access roads constructed to gain access to, travel between or otherwise required for equipment/vehicular site access shall be kept to a minimum and only constructed where necessary upon approval from the WVDEP, where applicable. If the Contractor constructs such travel routes, they shall be reclaimed and revegetated according to Section 6 upon completion of the construction activities, as deemed necessary by the WVDEP, with associated costs being incidental to Item 4.0 Site Preparation. Any additional access shall require the Contractor to obtain written permission from the respective land owner.
4.1.6 Separation Fabric
Stabilization fabric shall be woven fabric that is used to stabilize any soft areas on an access road surface prior to stone application.
4.1.7 Spill Containment Area
Spill containment measures shall be used for fuel and lubricant storage areas. All containers, barrels, buckets, cans, etc., are to be legally disposed of offsite. Used lubricants are to be disposed of according to state law to minimize pollution to the local surface and ground water supplies. Spills are the responsibility of the Contractor and need immediate clean up and maintained at no expense to the State. Fuel tanks manufactured with secondary containment are desirable; the minimum secondary containment shall be 110 percent.
4.2 Materials
4.2.1 Any equipment and construction materials required for clearing, grubbing, structure demolition, grading, and stone placement.
4.2.2 Gravel Road Rehabilitation Stone shall consist of 1 ½” crusher run limestone.
Limestone shall meet the requirements of AASHTO #1 and be free from foreign materials.
4.2.3 Separation fabric shall be Mirafi 600X or equal.
4.2.4 Tree wound dressing: any damage to trees shall be painted with Treekote or an equivalent antiseptic and waterproof paint. This sealer shall be asphaltic base and shall not contain coal tar creosote, turpentine or other material harmful to plants or animals.
4.3 Construction Methods
4.3.1 Clearing and Grubbing: The specific areas to be cleared and grubbed are as shown on the Contract Drawings and are generally described as, but not limited to, those specific areas of excavation, backfill, soil borrow or drainage structure installation.
4.3.2 The Contractor shall clear the site within the limits of the areas to be regraded. The WVDEP shall exercise control over clearing and shall designate all trees, plants and other objects to be removed or to remain.
4.3.3 Clearing and grubbing shall be completed prior to initiation of earthwork operations only to the extent necessary to complete the work. The Contractor shall confine his operations strictly to required areas. If he clears and grubs beyond the required areas, whether knowingly or accidentally, he shall, at his expense, replant and otherwise restore all areas outside the limit lines to a condition equal to that existing prior to start of work.
4.3.4 All timber eight (8) inches in diameter and larger at stump height shall be saw cut prior to grubbing operations. Timber shall be topped with the branches removed and stacked and stockpiled in an appropriate manner in an accessible location approved by the WVDEP on the property from which it was cut. Timber to be stockpiled shall not be pushed down by equipment prior to being cut nor can it be indiscriminately shoved into a stockpile.
4.3.5 All stumps, roots, buried logs and brush shall be removed. Grass, however, may be incorporated into the re-soiling material. Taproots and other projections over 1½ inches in diameter shall be grubbed out to a depth of at least ten (10) inches below the planned subgrade or slope elevation. All holes remaining after the grubbing operation shall have the sides broken down to flatten out the slopes, and shall be filled with suitable materials, moistened and properly compacted.
4.3.6 Cleared and grubbed areas shall be worked such that positive drainage is provided to prevent ponding of water except for the purpose of sediment control sumps as approved by the WVDEP.
4.3.7 All organic material shall be burned completely to ash or otherwise removed from the site and disposed of in a manner approved by the WVDEP. Burning of the combustible material will not be permitted on or near refuse, mine portals or within close proximity to coal seams, residence, structures or utilities. The Contractor shall obtain all permits and licenses required prior to burning the material. A plan showing the location of material to be burned and all fire control measures to be implemented, including copies of permits and licenses, shall be submitted to the WVDEP’s representative at the site for approval.
If a permit cannot be obtained because of the conditions stated above the tree top and stumps can be chipped or disposed of offsite to an approved location.
4.3.8 All other materials generated from required clearing and grubbing operations shall be removed and disposed of by the Contractor. All garbage, construction debris, mining debris, etc., shall be disposed of in approved waste areas or landfills (disposal tickets must be furnished to WVDEP). It shall be the responsibility of the Contractor to obtain, at no expense to the WVDEP, all necessary waste and borrow areas or landfills for the disposal of waste materials in accordance with any applicable local, state, and/or federal regulations including compliance with NEPA requirements (See Section III for NEPA Compliance Schedule). All waste and borrow areas must be approved by the WVDEP and the Contractor must provide a reclamation plan for approval. In addition, for all waste and borrow areas outside the construction limits, the Contractor must obtain from the property owner a right-of-entry agreement in which the property owner indemnifies and holds the WVDEP harmless from any injury or damages whatsoever resulting from the use of the property.
4.3.9 It shall be the sole responsibility of the Contractor to correctly locate and avoid all underground, on-ground, and overhead utilities, facilities and other structures and constructions, and for that purpose, shall employ all necessary precautions and methods to ensure avoidance of and damage to such constructions. In the event damage does occur, the Contractor shall notify the affected Owner and the WVDEP immediately and make or have made all necessary repairs and bear the expense thereof and resulting damage caused thereby.
4.3.10 Demolition of Structures: Buildings, mining related structures, existing ruins and foundation structures, shall be removed to the existing ground level or one foot below final grade, which operation shall include removal of concrete slabs or any other type of floors and/or walls resting upon the ground. Basement floors shall be shattered. Pits, trenches, holes or basements shall be backfilled. Coal and/or refuse spillage, concrete, cinder blocks, and foundation ruins shall be excavated and/or removed and incorporated into the fill material. Demolished concrete, cinder blocks and foundation ruins to be incorporated into the fill shall be of size less than 2 feet in any dimension. Boulders, structures, concrete pads and foundations shall be broken and buried in the deepest portion of the fill areas. Broken pieces shall not be consolidated in one area, but shall be dispersed throughout the fill areas to ensure that compaction requirements are achieved.
4.3.11 Trash, garbage, railroad ties, roofing shingles, tires, plastic, metal and other unsuitable material resulting from demolition shall be disposed of by the Contractor at his/her own responsibility and expense outside the work limits in an approved landfill, as approved by the Engineer, unless otherwise directed (disposal tickets must be furnished to WVDEP).
Bricks and stone blocks shall be disposed as per these specifications.
4.3.12 In the area where structures and buildings are demolished and removed, the removal operation shall extend to 1 foot below finished grade. The area shall then be regraded as necessary to blend into adjacent finished grades. Regrading shall be such that all areas are free draining and surface runoff will not pool or impound as directed by the Engineer.
4.3.13 Offsite Disposal or Borrow: Should offsite disposal or borrow be necessary, the Contractor shall observe the NEPA Compliance Schedule as per Section III of the Special Provisions.
4.3.14 Access Roads: Existing site access roads shall provide safe, all-weather access to the site.
These existing roads, including stoned and paved roads, shall be maintained during construction and left in a better than or equal to condition. The Contractor is responsible for locating and avoiding all underground and overhead utilities and constructions during access road grading and maintenance.
4.3.15 Gravel Road Rehabilitation Stone: Stone to be placed for “Gravel Road Rehabilitation Stone” shall conform to the detail as shown on the plans. The rehabilitation stone location is shown on the plans and as approved by the Engineer.
4.3.16 Separation Fabric: Separation Fabric shall be placed on a prepared subgrade prior to placement of surfacing and resurfacing stone. In areas that will not support the stone due to soft conditions, Separation fabric will be required as directed by the Engineer.
4.3.17 Fence: When existing fences are encountered within or near work limits, which by necessity of the construction activities require their dismantling, the Owner shall be consulted to secure their approval for the need of fencing, as well as determination as to whether temporary and/or permanent fencing will be utilized. The Contractor will be required to re-construct fence lines of any type located within the project area. Temporary fencing shall be installed along the alignment selected by the Owner, with sufficient material included to alter said alignment as may be required to accommodate the construction activity. Similarly, approval for the use and location of permanent fencing shall be obtained from the Owner well in advance of construction. Typically, permanent fencing shall be compatible with that which existed and installed in the location of the existing fence. Existing fences outside the construction limits and near or adjacent to the project area are to remain undisturbed in place. Any fencing damaged outside the work limits shall be repaired or replaced at the expense of the Contractor, to a condition equal to, or better than, its original condition. Wire for permanent or temporary fencing shall be 15 ½ gauge 4 pronged barbed wire unless otherwise required.
4.3.18 Property Markers: Any existing property markers disturbed or removed during construction activities shall be replaced accurately and to an “as good as” or “better than” condition and as approved by the WVDEP. This work will be paid under Section 2.0 Construction Layout of these Specifications.
4.4 Method of Measurement and Basis of Payment
4.4.1 There shall be no measurement of the “Site Preparation” item as it is a lump sum. The “Site Preparation” item shall be paid per lump sum price. The amount shall not exceed 10% of the TOTAL AMOUNT BID for each bid. Payment shall be for doing all the work herein prescribed in a workmanlike and acceptable manner; including the furnishing of all labor, materials, tools, equipment, supplies, and incidental necessary to complete the work. This includes all clearing grubbing and demolition required on the project site. No deduction will be made, nor will any increase be made, in the lump sum “Site Preparation” amount regardless of decreases or increases in the final total contract amount or for any other cause.
4.4.2 The “Gravel Road Rehabilitation Stone” item shall be paid per ton based upon weigh tickets from the commercial supplier of the stone that is delivered and placed at the locations identified on the plan drawings and shall include all materials, labor, equipment and incidentals necessary to complete the work.
4.4.3 Separation Fabric shall be incidental to Gravel Road Rehabilitation Stone.
4.5 Pay Items
Item 4.1, “Site Preparation”, per lump sum. Cannot be more than 10% of the “Total Amount Bid” for the project.
Item 4.2, “Gravel Road Rehabilitation Stone”, per ton.
5.0 EROSION & SEDIMENT CONTROL
5.1. Description
This item shall consist of furnishing all materials, equipment, labor and incidentals necessary for the installation of Straw Wattles, Sediment Control Barrier Structures (e.g.
silt fence or super silt fence), Check Dams and Stabilized Construction Entrances as designated in the Drawings. Additional quantities may be added at the discretion of the
WVDEP.
The CONTRACTOR shall be given a NPDES Permit with an approved erosion and sediment control plan at the pre-construction meeting. This plan shall include measures to be utilized for temporary and permanent sediment and erosion control. This plan shall also include the measures as outlined herein. The NPDES approved plan does not relieve the CONTRACTOR of his/her responsibility to be in compliance with any and all permits. All costs associated with meeting the federal and/or state regulations shall be the sole responsibility of the Contractor.
NOTE: Sediment Control Measures shall be required on the perimeter of the project site for sediment control in accordance with the NPDES requirements. The silt fence for sediment control shall be installed before any construction work begins. This fence shall remain and be maintained during the entire construction process. Erosion control shall be placed on regraded outslope areas concurrent with construction and prior to revegetation.
The following are the minimum requirements of the NPDES Permit and/or the NPDES BMP Manual.
VEGETATIVE PRACTICES
Except as noted below, stabilization measures shall be initiated as soon as practicable in portions of the site where construction activities have temporarily or permanently ceased, but in no case more than fourteen days after the construction activity in that portion of the site has permanently ceased.
Where the initiation of stabilization measures by the fourth day after construction activity temporarily or permanently ceases is precluded by snow cover, stabilization measures shall be initiated as soon as conditions allow.
Where construction activity will resume on a portion of the site within 14 days from when activities ceased, (e.g., the total time period that construction activity is temporarily halted is less than 14 days) then stabilization measures do not have to be initiated on that portion of the site by the seventh day after construction activities have temporarily ceased.
Areas where the seed has failed to germinate adequately (uniform perennial vegetative cover with a density of 70%) within 30 days after seeding and mulching must be reseeded immediately, or as soon as weather conditions allow.
Diversions must be stabilized prior to becoming functional.
EROSION & SEDIMENT CONTROL CONSTRUCTION SEQUENCE
Install stabilized construction entrance as shown on site plans.
Install perimeter sediment control devices as shown on site plans.
Clear and grub site.
Provide sediment control for any topsoil stockpiles.
Commence rough grading of site. Continue to maintain and inspect all erosion and sediment controls.
Fine grade site.
Install additional erosion and sediment controls as shown on site plans.
Permanently seed and mulch all disturbed areas within 7 days of reaching final grade and install erosion control wattles.
Upon completion of project including adequate stabilization, remove all remaining erosion and sediment controls.
5.2. Materials
5.2.1 Sediment Control Barriers: silt fencing materials and installation shall meet all applicable requirements of the manufacturer’s specifications and the typical details.
5.2.2 Erosion Control Wattles: ACF Environmental straw wattles or approved equals, shall be installed at locations shown on the plans. Straw wattles shall be 12 inches in diameter and follow installation of Specification 5.4.3. Straw wattles shall consist of an internal fill material of compressed straw fibers and an exterior encasement of a photodegradable polypropylene netting.
5.2.3 Stabilized Construction Entrances shall consist of coarse 3-6 inch stone over a geotextile fabric.
5.2.4 Rock Check Dams: Rock check dams shall be required at the locations as shown on the plans. The rock check dams shall be constructed with 3”-6” stone.
5.3. Maintenance
5.3.1 During the course of the project, sediment control barriers shall be maintained in sound condition and accumulations of silt which may threaten their effectiveness shall be removed. Silt removed from the sediment control structures shall be taken to an approved disposal area.
5.3.2 The Stabilized Construction Entrance shall be maintained in a condition that will prevent tracking or flowing of sediment onto access roads. This may require periodic top dressing with additional stone as conditions demand and repair and/or cleanout of any measures used to trap sediment. All sediment spilled, dropped, washed or tracked onto public rights-of-way must be removed immediately.
5.3.3 Wheels on all vehicles shall be cleaned to remove sediment prior to entrance onto public rights-of-way. If washing is required, it shall be done on an area stabilized with stone and which drains into approved sediment trapping device. If the street is washed, precautions must be taken to prevent muddy water from running into waterways or storm sewers.
5.3.4 At a minimum, all erosion and sediment controls on the site will be inspected at least once every seven calendar days and within 24 hours after any storm event of greater than 0.5 inches of rain per 24-hour period.
5.3.5 All controls should be cleaned out when sediment reaches one half the sediment capacity of that control.
5.3.6 Inspection and maintenance records must be kept onsite.
5.4. Installation
5.4.1 Silt Fence: Fence posts shall be a minimum of 48" long driven 16" minimum into the ground. Where ends of geotextile fabric come together, they shall be overlapped, folded and stapled to prevent sediment bypass. Silt Fence shall be inspected after each rainfall event and maintained when bulges occur or when sediment accumulation reached 50% of the fabric height.
5.4.2 Stabilized Construction Entrance: A stabilized construction entrance shall be required at the access point of the construction site. The stabilized construction entrance shall consist of filter fabric and a minimum of six (6) inches of 3” to 6” stone. The stone entrance shall be a minimum of seventy (70) foot long and twelve (12) foot in width.
This stone construction access must conform to the detail drawings shown in the plans.
5.4.3 Straw Wattles: A trench shall be excavated to a depth of 1/3 of the diameter of the wattle. Lay the first Straw Wattle snugly in the excavated trench. No daylight should be seen under the Wattle. Pack soil from trenching against the Wattle on the uphill side.
When installing running lengths of Straw Wattles, butt the second Wattle tightly against the first. DO NOT overlap the ends. Stake the Straw Wattles at each end and four foot on center. For example:
A twenty-five (25) foot wattle uses 6 stakes.
A twenty (20) foot wattle uses 5 stakes.
A twelve (12) foot wattle uses 4 stakes.
Stakes should be driven through the middle of the Wattle, leaving 2 - 3 inches of the stake protruding above the Wattle. A heavy sediment load will tend to pick the Wattle up and could pull it off the stakes if they are driven down too low. It may be necessary to make a hole in the Wattle with the pick end of your mattock in order to get the stake through the straw. When Straw Wattles are used for flat ground applications, drive the stakes straight down; when installing Wattles on slopes, drive the stakes perpendicular to the slope.
Drive the first end stake of the second Wattle at an angle toward the first Wattle in order to help abut them tightly together.