Addendum #01 ARFQ DEP2200000009 Peeltree.pdf
PDF 7 MB Posted
- Attached to
- Addendum #02 Peeltree Road Portals
- Solicitation number
- ARFQ 0313 DEP2200000009 3
- Issued by
- Barbour County, West Virginia
About this file
This is Addendum #1 to a request for quote (ARFQ) issued by the Department of Environmental Protection (DEP) for solicitation number DEP2200000009 regarding the Peeltree Road Portals Project. The addendum documents responses to vendor questions and comments raised during a pre-bid conference, clarifying project requirements and specifications. Key clarifications include confirmation that subsidence socks are paid per unit, traffic control signage is anticipated to be sufficient with temporary flagging potentially needed for short durations with no separate pay item, and that bat gate installation must occur between May 1 and August 31 due to temperature requirements. Small trees requiring removal for reclamation activities may be windrowed on-site. The contractor is required to complete all construction activities within 45 days from the notice to proceed.
The Engineer's Estimate for the project is $108,794.00, with liquidated damages of $1,000.00 per day assessed after the 45-day completion deadline. The addendum requires vendors to acknowledge receipt of all addenda issued for the solicitation by completing an Addendum Acknowledgement form and submitting it with their bid to avoid potential bid disqualification. All other provisions of the original solicitation and any previously issued addenda remain in full force and effect unless specifically modified by this addendum.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AGENCY SOLICITATION NUMBER – ARFQ ______________
Addendum Number: ____
The Purpose of this addendum is to modify the solicitation identified as (“Agency Solicitation”) to reflect the change(s) identified and described below.
Applicable Addendum Category:
[ ] Modify bid closing date and time
[ ] Modify specification of product or service being sought
[ ] Attachment of vendor questions and responses
[ ] Attachment of pre-bid sign-in sheet
[ ] Correction of error
[ ] Other
Description of Modification to Solicitation:
This Addendum issued to publish and distribute the attached documentation to the vendor community.
Additional Documentation: Documentation related to this Addendum (if any) has been included herewith as Attachment A and is specifically incorporated herein by reference.
Terms and Conditions:
1. All provision of the Agency Solicitation and other addenda not modified herein shall remain in full force and effect.
2. Vendor should acknowledge receipt of all addenda issued for this Agency Solicitation by completing an Addendum Acknowledgement, a copy of which is included herewith. Failure to acknowledge addenda may result in bid disqualification. The addendum acknowledgement should be submitted with the bid to expedite document processing.
DEP2200000009
1. To attach pre-bid meeting sign in sheets and notes
Addendum #1 - Questions During Pre-Bid Meeting
PEELTREE ROAD PORTALS PROJECT
DEP2200000009
The following comments and questions were identified from the Pre-Bid Conference and Vendor submittals. The answers provided herein take precedence over verbal answers at the PBC should there be any conflict between the two.
Questions:
1) How are the subsidence socks paid?
a. Subsidence Socks are paid per Each
2) What will be needed for Traffic Control?
a. It is anticipated that signage should be sufficient for most activities. A temporary flagger may be needed for short durations during certain activities. There is no separate pay item for Traffic Control and will be considered incidental to project activities as stated in the specifications.
Comments:
1. The dates for Bat Gate installation are May 1 to August 31. Installation outside of this window is dependent on warmer temperatures.
2. Small trees that are needing removed for reclamation activities are allowed to be windrowed on-site.
3. The Engineer’s Estimate for this project is $108,794.00
The Contractor shall have 45 days from the date of the Notice to Proceed to complete construction activities on the project. The $1,000.00 per day liquidated damages clause will be in effect after the 45 days.