TE-2 Deliverable Schedule.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Base-wide Custodial - Fort Novosel
- Solicitation number
- W9124G24Custodial
About this file
This document appears to be a Deliverable Schedule for a federal contract opportunity. It outlines the various deliverables, their frequency, format, and submission requirements for a Base-wide Custodial contract at Fort Novosel, AL.
The key details include:
- 40 specific deliverables ranging from work logs, training certificates, quality control plans, safety plans, and cleaning reports
- Deliverable due dates varying from within 30 days of contract start, monthly, or 10 days prior to commencing work
- Deliverable formats include email, hard copy, and electronic documents like Excel and Word
- Deliverables are to be submitted to the Contracting Officer (KO), Contracting Officer's Representative (COR), and/or Administrative Contracting Officer (ACOR)
- The contract is for custodial services at Fort Novosel, AL, solicited by the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Deliverable | Frequency | # of Copies | Medium/Format | Submit To | |
| 1 | 1. Schedule of Services Work Log, PWS paragraph 1.7.2 | By the 5th of the month. | Provide 1 copy by the end 5th of the month. | CD in MS Word, DVD, Briefing Slides on CD, Excel Spreadsheet | DPW Custodial COR/ACOR and Contract Management Services Branch Chief |
| 2 | 2. Restroom Custodial Log, PWS paragraph 1.7.2 | Update with each restroom custodial service. | Provide 1 copy per restroom. | Deliver a hard copy. | Post on inside door of restroom. |
| 3 | 3. Emergency Delay Notification, PWS paragraph 1.7.4.3 | Upon determination of unsafe weather conditions or work environment. | Provide 1 copy. | Deliver an e-mail. | Custodial contract KO and COR/ACOR |
| 4 | 4. Work Schedule, PWS paragraph 1.7.5 | No later than 10 workdays prior to commencing work. | Provide 1 copy. | Deliver via e-mail. | Custodial contract COR/ACOR |
| 5 | 5. Anti-Terrorism (AT) Level I Training Certificates, PWS paragraph 1.7.7.6 | Within 30 days of contract start date and within 30 days for new employees that are hired after stat date. | Provide 1 copy. | Deliver via e-mail or hardcopy. | Custodial contract KO COR/ACOR |
| 6 | 6. iWatch Training Certificates, PWS paragraph 1.7.7.7 | Within 30 days of contract start date and within 30 days for new employees that are hired after stat date. | Two copies | Deliver via e-mail and hard copy | Custodial contract KO and COR/ACOR |
| 7 | 7. Security Checklist DRAFT, PWS paragraph 1.7.7.10 | Provide no later than the post award meeting | One copy | Deliver via e-mail | Custodial contract COR/ACOR |
| 8 | 8. Security Checklist APPROVED, PWS paragraph 1.7.7.10 | Provided to the COR no later than 0800 the day after services have been provided in facilities where the contractor has been issued a key or security code. | One copy | Deliver via e-mail | Custodial contract COR/ACOR |
| 9 | 9. Identification of Contractor Employees, PWS paragraph 1.7.10.3 | At the post award meeting and within 5 workdays as changes occur. | One copy | Deliver via e-mail | Custodial contract COR/ACOR |
| 10 | 10. Key Personnel, PWS paragraph 1.7.10.5 | Within one week of contract award | Two copies | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 11 | 11. The name of this person and an alternate, who shall act for the contractor when the Project Manager is absent, shall be designated in writing to the contracting officer. Paragraph 1.7.10.5.1 | Within one week of contract award | Two copies | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 12 | 12. The Contractor shall provide local phone numbers for normal duty hours and after-hours to the KO and the COR for the Project Manager and alternate(s) at contract start date and within 5 work days as changes occur. Paragraph 1.7.10.5.1 | At contract award and NLT 5 work days as changes occure | Two copies | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 13 | 13. The Contractor shall provide the KO and COR a local telephone number at which the Quality Control Manger, or his representative, may be contacted during normal working hours occur. Paragraph 1.7.10.5.2 | At contract award and NLT 5 work days as changes occure | Two copies | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 14 | 14. Quality Control Manager’s monthly inspection schedule, PWS paragraph 1.7.10.5.2 | NLT three (3) workdays prior to the inspection month. | One copy | Deliver via e-mail | Custodial contract COR/ACOR |
| 15 | 15. Daily QC Inspection Report, PWS paragraph 1.7.10.5.2 | NLT 0800 on the day following performance. | One copy | Deliver via e-mail | Custodial contract COR/ACOR |
| 16 | 16. Phase In/Phase Out Plan, PWS paragraph 1.7.10.6 | Within 10 business days after contract award. | Two copies | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 17 | 17. Quality Control Plan DRAFT, PWS paragraph 1.7.10.7 | NLT the post award meeting. | Two copies | Deliver via e-mail. | Custodial contract KO and COR/ACOR |
| 18 | 18. Quality Control Plan FINAL, PWS paragraph 1.7.10.7 | NLT the performance start date. The contractor shall receive the KO’s acceptance in writing of any proposed changes to the QCP five (5) days before the plan is effective. | Two copies | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 19 | 19. After acceptance of the quality control plan (QCP) the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to the QC system five (5) days prior to the changes being effective | The contractor shall receive the KO’s acceptance in writing of any proposed changes to the QCP five (5) days before the plan is effective. | Two copies | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 20 | 20. Emergency Medical Treatment, PWS paragraph 1.7.10.8.1 | NLT 30 minutes after incident. | Two copies | Deliver verbally followed up by a notification via e-mail. | Custodial contract KO and COR/ACOR |
| 21 | 21. The contractor shall utilize U.S. Army Corps of Engineers (USACE) Mishap Notification and Investigation Form 3394 to document all serious injuries. Paragraph 1.7.10.9 | If injuries incurred while an employee is performing work under this contract, the contractor shall verbally notify the KO/COR no later than (NLT) thirty (30) minutes after an emergency medical event, followed by a documented summary of events. | Two copies | Deliver verbally followed up by a notification via e-mail. | Custodial contract KO and COR/ACOR |
| 22 | 22. Environmental or OSHA Conflict, PWS paragraph 1.7.10.10 | Upon discovery of apparent conflict. | Two copies | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 23 | 23. Serious Hazard Notification, PWS paragraph 1.7.10.11 | Immediately upon discovery verbally followed with an e-mail notification. | Two copies | Deliver verbally followed up by a notification via e-mail. | Custodial contract KO and COR/ACOR |
| 24 | 24. Safety plan, PWS paragraph 1.7.10.11.1 | The Contractor shall submit the safety plan for the KO/COR review within 30 business days after contract award. Revised plan with KO/COR required changes shall be submitted five (5) business days prior to performance start date. | Two copies | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 25 | 25. Revisions to safety plan 1.7.10.11.1 | Revisions shall be submitted to the KO/COR five (5) business days prior to the effective date of change | Two copies | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 26 | 26. Spill Plan, PWS paragraph 1.7.10.11.2 | The contractor shall submit the spill plan to the KO/COR within 10 days of contract award. | Two copies. | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 27 | 27. ENV-AS001 Asbestos Containing Material certifying document PWS paragraph 1.7.10.12 | The contractor shall provide a hard or electronic copy with the employees name, date, and signature certifying the ENV-AS001 review with their NLT ten (10) workdays after first day of work. | One copy | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 28 | 28. OSHA/ADEM Asbestos Awareness Training, PWS paragraph 1.7.10.12 | Provide a copy of training certificates within 10 days of contract award. Update annually and with new employees | One Copy | Deliver certificate via e-mail | Custodial contract KO and COR/ACOR |
| 29 | 29. ISSA CIMS-GB Certification, PWS paragraph 1.7.12 | Obtain certification within 120 days of contract start date and keep current. | One copy | Deliver certificate via e-mail | Custodial contract KO and COR/ACOR |
| 30 | 30. ISSA CIMS-GB Section One, Four, and Six PWS paragraph 1.7.13 | Provide hard copies or electronic version upon certification and within 5 days of changes to policies, plans, or programs. | Two copies | Deliver via hard copy or electronically | Custodial contract KO and COR/ACOR |
| 31 | 31. Safety Data Sheets, paragraph 1.7.14 | NLT five (5) business days after contract award. | Prior to contract startup | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 32 | 32. Prior to contract startup, the Contractor shall submit to the COR and DPW-ENRD for approval, a list of proposed cleaning products, along with log of the Safety Data Sheets (SDS), to be used in accordance with the contract specifications. Paragraph 4.2.2 | Prior to contract startup | Prior to contract startup | Deliver via e-mail | Custodial contract KO and COR/ACOR |
| 33 | 33. Monthly Consumables and Cleaning Supplies, PWS paragraph 4.2.2 | Monthly | One copy | Deliver via e-mail | Custodial contract COR/ACOR |
| 34 | 34. Schedule of Services, PWS paragraph 5.6.1 | NLT ten (10) workdays prior to commencing work. | One copy | Deliver via e-mail | Custodial contract COR/ACOR |
| 35 | 35. Alternate Workday Schedule, PWS paragraph 5.6.1.1 | NLT ten (10) workdays prior to a federal holiday. | One copy | Deliver via e-mail | Custodial contract COR/ACOR |
| 36 | 36. Service Delay Notification, PWS paragraph 5.6.1.2 | NLT 0800 the day after service disruption | One copy | Deliver via e-mail | Custodial contract COR/ACOR |
| 37 | 37. Scheduled Cleaning Work Report Spreadsheet, PWS paragraph 5.6.2 | NLT COB on the 3rd workday of each month following scheduled work. | One Copy | Deliver a Microsoft Excel Spreadsheet via e-mail | Custodial contract COR/ACOR |
| 38 | 38. Unscheduled Cleaning Work Reports, PWS paragraph 5.6.3. | NLT COB on the 3rd workday of each month following completion of work. | One copy | Deliver a Microsoft Excel Spreadsheet via e-mail | Custodial contract COR/ACOR |
| 39 | 39. Access and Condition Report, PWS paragraph 5.6.4 | NLT 0800 daily Monday through Friday | One copy | Deliver via e-mail | Custodial contract COR/ACOR |
| 40 | 40. 3Rs Safety Training PWS paragraph 1.7.7.8 | Training must be completed by on-site personnel prior to the commencement of on-site work. Certificates of completion are valid for 1 year and training must be updated annually during the on-site performance of work. | One copy as requested | Deliver via e-mail | Custodial contract COR/ACOR |