The document is an AF3052 Construction Cost Estimate Breakdown form for a federal construction contract at Patrick Space Force Base, Florida. The solicitation (FA252125B0007) is for a Firm-Fixed-Price Construction Contract to construct a Weapons Maintenance Addition, with a project magnitude between $1,000,000 and $5,000,000. The opportunity is specifically set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB), meaning only SDVOSB concerns are eligible for award.

Key dates include a site visit badge request deadline of 11 June 2025, an on-site visit on 17 June 2025, question submissions due by 23 June 2025, and bid submissions due on 8 July 2025. The contract is contingent on fund availability, and the project will be executed by the Department of the Air Force Space Command. Primary points of contact are Charles Cowart (Contracting Specialist) and Patricia A. Bates (Procuring Contracting Officer), with contact information provided in the solicitation. The NAICS code is 236220, with a size standard of $45.0 million.

View the file

Other files

File Type Posted
FA252125B0007 Abstract of Bids.pdf PDF
WD FL20250196.pdf PDF
Solicitation Amendment FA252125B00070006 SF 30.pdf PDF
Solicitation Amendment - FA252125B00070005.pdf PDF
Furniture RFI 01.pdf PDF
Solicitation Amendment FA252125B00070005 SF 30.pdf PDF
QA Form SXHT 24-9000 rev1.pdf PDF
Solicitation Amendment - FA252125B00070004.pdf PDF
Solicitation Amendment FA252125B00070004 SF 30.pdf PDF
Solicitation Amendment FA252125B00070003 SF 30.pdf PDF
QA Form SXHT 24-9000.pdf PDF
Solicitation Amendment - FA252125B00070003.pdf PDF
SXHT 24-9000 QA Amendment 2.pdf PDF
Solicitation Amendment - FA252125B00070002 Conformed.pdf PDF
Solicitation Amendment FA252125B00070002 SF 30.pdf PDF
A04_SXHT 24-9000 Synopsis.pdf PDF
A04_SXHT 24-9000 Synopsis.pdf PDF
25B0007 Site Visit Sign in Sheet.pdf PDF
Wage Determination PSFB_6.6.2025.pdf PDF
Solicitation Amendment FA252125B00070001 SF 30.pdf PDF
Solicitation Amendment - FA252125B00070001.pdf PDF
A02a_SXHT 24-9000 PAFB-B9678add_FFE_Final Design_Redacted.pdf PDF
A07_SXHT 24-9000 Haz Waste.pdf PDF
A01a_SLD45 Front End SPEC FINAL.pdf PDF
Badge Request 45 SFS Form V13.pdf PDF
SDVOSB-SelfPerformanceCertificationWrksht.pdf PDF
Solicitation - FA252125B0007.pdf PDF
A01b_SXHT 24-9000 Project Specs EDITED.pdf PDF
A04_SXHT 24-9000 GPP Certification Signed.pdf PDF
Patrick SFB Wage Determination.pdf PDF
A02_SXHT 24-9000 Drawings.pdf PDF
A06_SXHT 24-9000 ODS.pdf PDF
A10_ Energy Management and Control Systems Standards.pdf PDF
QUESTION AND ANSWER FORM.docx DOCX document
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AF3052

CONSTRUCTION COST ESTIMATE BREAKDOWNFA252125B0007
CONTRACTORADDRESS
CONTRACT FORPROPOSED TOTAL CONTRACT PRICE
Contract No.ERROR:#REF!
PURCHASE REQUEST FORMPROJECT NUMBERWORK LOCATION
MATERIAL COSTLABOR COST
UNITOTHER
LINEITEMOFQUANTITYMANHOURSAVERAGETOTALDIRECTLINE
NO.MEASUREUNITTOTALMANDAYSRATECOSTSTOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

0.000.000.000.00
0.000.000.00
0.000.000.00
0.000.000.00
0.000.000.00
0.000.000.00
0.00
0.00
00.00
0.000.000.00
0.000.000.00
0.000.000.00
0.000.000.00
0.000.000.00
0.000.000.00
0.00
0.000.000.00
0.000.000.00
CECC FORM 3052PAGE 1
INSTRUCTIONS FOR COMPLETING AF FORM 3052
Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient
detail to permit itemizing of all direct costs.
Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples--square yards--SY, cubic yards--
CY, square feet--SF, linear feet--LF, board feet--BF, each--EA, pound--LB).
Col 3 Quantity. Constractor's estimate of quantity required in terms of unit of measure (couldmn 2). Itms and units of measure will
be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price
contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total costs (Col 5) for items listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in
column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.
Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the
contract and of significant dollar value.

Col 10 Line Total. Self-explanatory.

NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on
the last page as follows.

TOTAL MATERIAL COSTS $

TOTAL LABOR COSTS $

TOTAL OTHER DIRECT COSTS $

TOAL DIRECT COSTS $

OVERHEAD $

SUBTOTAL $

PROFIT $

TOTAL PRICE $

DATE FIRM NAME

TITLEBY
(Signature)

INSTRUCTIONS TO OFFERORS

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of
incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award
of a contract resulting from this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a
certificate of current cost or pricing data (see ASPR 3-807.3(e) and 3.807.4).
2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit
with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an
appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that
there be a clear understanding of
a. The existing, verifiable data
b. The judgmental factors applied in projecting from known data to the estimate, and
c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticalbe, the data will be described (with schdules as
appropriate), and made available to the contracting officer or his authorized representative on request.
4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine,
for the purpose of verifying the cost or pricing data submitted, those books, records, documents, and other supporting data which
will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right
may be exercised in connection with any negotiations prior to contract award.