This is a Supplemental Price Breakdown by Division Sheet template designed for price analysis of the solicitation 36C26126R0037, Project 612A4-26-050, titled "Install Building 644 Dermatology Generator Site Prep" for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 21.
The document is a standard construction cost breakdown form requiring contractors to provide complete divisional cost allocations across the Uniformat Division of Work classification system. Bidders must itemize costs for applicable divisions including General Requirements, Existing Conditions, Concrete, Masonry, Metals, Wood and Plastic, Thermal and Moisture Protection, Doors and Windows, Finishes, Specialties, Equipment, Furnishings, Special Construction, Conveying Equipment, Fire Suppression, Plumbing, HVAC, Electrical, Communications, Electronic Safety and Security, Earthwork, Exterior Improvements, Utilities, and Transportation. The form requires contractors to provide a subtotal, followed by line items for Other costs, Bonds and Insurance, Overhead, and Profit, culminating in a total contract price. The document includes signature and date blocks for authorization by the contractor's representative and their title. This template is intended solely for government price analysis purposes and does not constitute specific pricing requirements or contractual terms.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C26126R0037 612A4-26-050
SOLICITATION: 36C26126R0037 PROJECT: 612A4-26-050
Install Generator Site Prep
PROVIDE COMPLETE DIVISIONAL COST BREAK-OUT FOR COMPLETE PROJECT.
*If necessary, add additional lines for each Division applicable to this project.
**This document is to be used only for price analysis
| REF |
| DESCRIPTION |
| TOTAL |
00000
| DIVISION 00-SPECIAL SECTIONS |
| $ |
| 01000 |
| DIVISION 1-GENERAL REQUIREMENTS |
| $ |
| 02000 |
| DIVISION 2-EXISTING CONDITIONS |
| $ |
03000
| DIVISION 3-CONCRETE |
| $ |
04000
| DIVISION 4-MASONRY |
| $ |
05000
| DIVISION 5-METALS |
| $ |
06000
| DIVISION 6-WOOD AND PLASTIC |
| $ |
07000
| DIVISION 7-THERMAL AND MOISTURE PROTECTION |
| $ |
08000
| DIVISION 8-DOORS AND WINDOWS |
| $ |
09000
| DIVISION 9-FINISHES |
| $ |
10000
| DIVISION 10-SPECIALTIES |
| $ |
11000
| DIVISION 11-EQUIPMENT |
| $ |
12000
| DIVISION 12-FURNISHINGS |
| $ |
13000
| DIVISION 13-SPECIAL CONSTRUCTION |
| $ |
14000
| DIVISION 14-CONVEYING EQUIPMENT |
| $ |
21000
| DIVISION 21-FIRE SUPPRESSION |
| $ |
22000
| DIVISION 22-PLUMBING |
| $ |
23000
| DIVISION 23-HEAT, VENTILATING, AND AIR CONDITIONING |
| $ |
26000
| DIVISION 26-ELECTRICAL |
| $ |
27000
| DIVISION 27-COMMUNICATIONS |
| $ |
28000
| DIVISION 28-ELECTRONIC SAFETY AND SECURITY |
| $ |
31000
| DIVISION 31-EARTHWORK |
| $ |
32000
| DIVISION 32-EXTERIOR IMPROVEMENTS |
| $ |
33000
| DIVISION 33-UTILITIES |
| $ |
34000
| DIVISION 34-TRANSPORTATION |
| $ |
SUB TOTAL:
OTHER
BONDS AND INSURANCE
OVERHEAD
PROFIT
TOTAL
| _______________________________________________ | ___________ |
| (Signature and Typed Name of Authorized Representative) | Date |
(Title of Authorized Representative)
File details come from the government source that posted it. Updated .