36C26126R0037 0002.docx
DOCX document 818 KB Posted
- Solicitation number
- 36C26126R0037
About this file
This file is an Amendment/Modification (0002) to Solicitation 36C26126R0037 issued by the Department of Veterans Affairs, VA Sierra Pacific Network (VISN 21), VA Pacific Islands Health Care System in Honolulu, Hawaii. The amendment, dated June 10, 2026, clarifies solicitation requirements and provides responses to 20 Requests for Information (RFI) submitted by potential offerors. The project scope involves installing a dermatology generator site at Building 644, including site preparation work, artificial turf installation, handrail systems, curb ramps, concrete demolition and reconstruction, utility relocation, and associated electrical work. The proposal fee due date remains June 17, 2026 at 10:00 AM PDT, with no extension to the original deadline.
Key clarifications from the RFI responses include: artificial turf products must comply with Specification 013216 and Part 5 of the Statement of Work with manufacturer-approved installation methods; approximately 75 linear feet of permanent stainless-steel handrail must be installed at 34 inches above the walking surface in compliance with ADA standards; curb ramps must meet ADA requirements and Barrier Free Design Standards, with alternative details subject to Contracting Officer approval; up to 1,000 square feet of existing concrete must be demolished as needed to meet ADA slopes; the contractor is responsible for utility locating, all temporary power, temporary pedestrian routing, and traffic control plans; all personnel working on-site longer than 14 days require VA PIV badging; Site Superintendent and Quality Control roles must remain separate; and as-built electrical drawings for Building 644 have been added as SOW Attachment 11. Work outside normal hours (7:00 AM–5:00 PM) requires Contracting Officer approval.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 06-10-2026 612-26-3-6056-0047 612A4-26-050 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Pacific Islands Health Care System 711 Kapiolani Blvd Suite 200 Honolulu
HI
96813 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Pacific Islands Health Care System 711 Kapiolani Blvd Suite 200 Honolulu
HI
96813 To all Offerors/Bidders
36C26126R0037 05-13-2026
X X X X Project Title: Install Building 644 Dermatology Generator Site Prep This amendment clarifies the following to the Solicitation package:
1. Answers all RFIs and puts the site visit sign in sheet.
2. No change in proposal due date. Fee Proposal Due Date: June 17, 2026 by 10:00 AM PDT.
All other terms and conditions shall remain unchanged.
Charee Harris Contracting Officer RFI Questions and Responses For 36C26126R0037 Install Building 644 Dermatology Generator Site Prep Project specifications, SOW, and RFI responses are complementary and neither shall take precedent over the other. It is the sole responsibility of the contractor to seek clarification prior to submitting a bid amount if there should appear to be a discrepancy between solicitation documents. Otherwise, the most stringent (typically most expensive) requirement shall apply at the discretion of the COR.
| 1 |
| What product specifications are required for the new artificial turf shown in Attachment 7 (manufacturer, pile height, face weight, infill type, backing, and warranty)? |
Answer : The VA does not specify a required manufacturer. Product cut sheet submittal and physical sample submittals for artificial turf are required. Artificial turf submittals must comply with Specification 013216 (Shop Drawings, Product Data, and Samples). The product must meet all requirements in Part 5 – Artificial Grass Installations of the SOW, including manufacturer‑approved: installation, perimeter attachment, seams, and drainage requirements. Product specification requirements are provided in Part 5 – Artificial Grass Installations of the SOW.
| 2 |
| What are the detailed requirements for the handrail system shown in Attachment 9 (material, finish, post spacing, mounting details, and applicable standards)? |
Answer : The SOW states that the contractor shall furnish and install approximately 75 LF of permanent stainless‑steel handrail, including a continuous concrete handrail curb, matching nearby installations. Acknowledging nearby installation shows embedment, either surface mounting or embedment are acceptable mounting solutions to the VA. Installation must meet ADA standards with a height 34 inches above walking surface.
Image of nearby installation required to match shown below:
| 3 |
| Must the curb ramps be constructed as Type B with detectable warning surfaces per Attachment 4, or is an alternate detail acceptable? |
Answer : The SOW states, “Prior to beginning any construction work, the contractor shall perform a detailed topographic survey of all affected areas and submit layout drawings for review and approval by the COR. These drawings shall illustrate the proposed work, including but not limited to concrete limits and ramp configurations. Drawings shall indicate final grading and slope percentages.”
This requirement establishes that ramp configurations including any proposed alternatives are subject to COR review.
Alternative details are acceptable under specific criteria.
1) The alternative ramp detail meets or exceeds ADA requirements, and Barrier Free Design Standards: https://www.cfm.va.gov/til/etc/dsBarrFree-2025-05.pdf.
2) The alternative ramp detail matches all applicable VA specifications.
3) Maintains drainage requirements of the planned installation area.
4) The COR approves the alternative as part of the required submittal for this SOW.
| 4 |
| What are the exact limits of the demolition area highlighted in red on Attachment 6 at Building 651, and how should any existing utilities in that area be handled? |
Answer : The SOW requires demolition of up to 1,000 square feet of existing concrete as needed to meet ADA slopes. The exact limits are to be field‑determined in coordination with the COR. All existing utilities must be protected; contractor must demolish and reconstruct in compliance with VA specifications, maintain drainage, and restore affected areas.
| 5 |
| Who is responsible for providing current utility locates prior to mobilization? |
Answer : The contractor is responsible for locating and avoiding utilities during demolition and construction.
| 6 |
| Since all this work is exterior, what security badge requirements, after-hours work restrictions, and hospital coordination procedures apply during construction? |
Answer : All individuals working on site longer than a period of 14 days out of a calendar year will need to be badged through the VA’s PIV process. Work outside of normal working hours (7:00am-5:00pm) is subject to approval by the COR.
| 7 |
| Is the new tap box shown in Attachments 3 and 5 in addition to the existing tap box, or must the existing tap box be removed or relocated? |
Answer : The existing tap box to be relocated to the new generator enclosure. No additional tap box is required.
| 8 |
| Please confirm Is it acceptable for the Site Superintendent to also serve as the qualified Site Safety and Health Officer (SSHO) and that no QC is required? |
Answer : The SOW does not waive QC or SSHO requirements, nor does it state that roles may be combined. VA specification requirements apply, and separate roles are required.
| 9 |
| Can you provide the most recent as-built or record drawings for the generator enclosure area at Building 644, including all site features, sidewalks, and turf areas? |
Answer : No such drawings are available to provide with this solicitation. The contractor is therefore required to field verify all existing site conditions, including grades, pavement limits, sidewalk alignments, landscape features, and any other elements necessary to complete the work in accordance with the SOW.
| 10 |
| Can you provide the original or as-built electrical drawings showing the existing tap box, conduit routing, power distribution, and any related utilities in the vicinity of Building 644? |
Answer : Please see “SOW Attachment 11 – Building 644 Electrical As‑Built Drawings”, which has been added to the solicitation through this amendment. The contractor is required to field verify all existing electrical conditions, including conduit routing, conductor sizes, tap box configuration, and any utilities within the work area, prior to commencing any electrical work.
| 11 |
| Are any topographic survey, grading plan, or site plan drawings available for the work area around Building 644? |
Answer : Please see response to question #9.
| 12 |
| Can you provide existing utility drawings (electrical, communications, water, sewer, storm drain, etc.) for the project work area? |
Answer : Please see response to question #10.
| 13 |
| What is the Contractor’s responsibility for furnishing and installing the complete concrete foundation pad, anchor bolts, and generator enclosure slab? |
Answer : The enclosure is intended for a mobile generator staged on asphalt. Therefore, no concrete generator foundation slab is required unless added by later amendment.
| 14 |
| Who is responsible for furnishing and installing the conduit and conductors from the new tap box to the generator? |
Answer : The contractor shall extend the existing conduit, replace conductors as needed, and install all conduit penetrations and terminations required for relocation of the tap box. The contractor is not responsible for connecting the mobile generator to the tap box unless required by a later amendment.
| 15 |
| Can you provide a copy of the site visit sign-in sheet or attendance list from the May 21, 2026 site visit? |
Answer : A copy will be attached with this response.
| 16 |
| What base preparation, subgrade requirements, drainage, or other materials are required under the artificial turf areas shown in Attachments 7 and 8? |
Answer : The SOW requires the contractor to perform all site prep, drainage work, subgrade preparation, and installation per manufacturer requirements and approved shop drawings. The system must meet all requirements in Part 5 – Artificial Grass Installations, including proper infill, brushing seams, and perimeter termination. Specific base material gradations are not provided and must follow manufacturer guidelines.
| 17 |
| Please confirm that the Site Super, SSHO and QC can have other collateral roles/duties as Competent Persons mentioned in the specs |
Answer : Individuals assigned to Site Super, SSHO, or QC can also be Competent Persons in regard to OSHA requirements (29 CFR 1926.20(b)(2).
| 18 |
| Please confirm that the Site Super and QC role can be one and the same individual as long as the requirements for each are met. |
Answer : The SOW does not authorize combining these roles.
| 19 |
| Please confirm whether temporary power will be provided by the Owner/VA for contractor use during construction, or if the contractor is responsible for furnishing all temporary power requirements for the duration of the project. |
Answer : The contractor is responsible for furnishing all temporary power requirements during construction.
| 20 |
| Please clarify the VA’s requirements for temporary pedestrian routing, barricades, and access control around Buildings 644, 646, and 651 during construction. Please confirm whether any specific phasing requirements, working area restrictions, or patient-access limitations will apply. |
Answer : The contractor must provide safe, ADA‑compliant temporary pedestrian routing around all active work areas. Access to Buildings 644 and 651 must be maintained at all times. Temporary ramps and any roadway obstruction measures must be provided by the contractor as needed. Traffic control plans are required to be submitted to the COR for any roadway obstruction activities. Sidewalk work requires a temporary ADA‑compliant pedestrian path throughout the entire duration of construction ensuring uninterrupted access to Buildings 644, 646, and 651.
See attached document: SOW Attachment 7 - Artificial Grass Area Site Layout.
See attached document: SOW Attachment 11 - Building 644 Electrical As-Built Drawings.