Submittal Register.pdf

PDF 132 KB Posted

Attached to
SXHT 09-1000 - Repair Water Lines, Various
Solicitation number
FA252125B0008
Issued by

About this file

The Submittal Register is a comprehensive document detailing the required submittals for the SXHT 09-1000 Repair Waterlines project at Patrick Space Force Base in Florida. The register spans multiple specification sections and requires contractors to provide various preconstruction submittals, test reports, certificates, design data, and closeout documentation across different project phases, including environmental protection, quality control, concrete work, excavation, piping, and directional drilling.

Key submittal categories include preconstruction plans (such as Lifting Operation Plan, Accident Prevention Plan), quality control documentation, environmental protection plans, technical submittals for materials like concrete and piping, test reports, certificates for personnel qualifications, and final closeout documents like record drawings and operation and maintenance manuals. The submittal register is organized by specification section, with each entry indicating the specific paragraph, classification (G for government review, S for sample), and the type of documentation required, providing a structured approach to project documentation and compliance.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 9 PAGES

SXHT 09-1000 Repair Waterlines Various PSFB, Florida

01 11 00 SD-01 Preconstruction Submittals

3.9.1 GLifting Operation Plan

1.10 GUtility Outage Requests

1.10 GConnection Requests

1.8.5 GAF 3952

1.12.1 GSolid Waste Disposal Diversion

Tracking

1.7 GPremises/Access Plan

1.8.1 GStorage Area Request

3.8.1 GContractor Survey Record

Drawings

3.10 GSuperintendent Contact and

Qualifications

3.6.1 GWork Clearance Request; AF

Form 103

1.11.2 GLay-Down Area

3.10.1Licenses And Certificates

SD-05 Design Data

3.3.2Safety Data Sheet (SDS)

01 33 00 SD-01 Preconstruction Submittals

1.7 GSubmittal Register

01 35 26 SD-01 Preconstruction Submittals

1.8 GAccident Prevention Plan (APP)

SD-06 Test Reports

1.12.2LHE Inspection Reports

1.5 GMonthly Exposure Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 9 PAGES

01 35 26 SD-07 Certificates

1.7.5Crane Operators/Riggers

1.9 GActivity Hazard Analysis (AHA)

1.13Hot Work Permit

01 45 00 SD-01 Preconstruction Submittals

1.5.2 GContractor Quality Control (CQC)

Plan

SD-06 Test Reports

Verification Statement

01 57 19 SD-01 Preconstruction Submittals

1.5.1Preconstruction Survey

1.5.2 GRegulatory Notifications

1.5.4 GEnvironmental Manager

Qualifications

1.5.5 GEmployee Training Records

1.6 GEnvironmental Protection Plan

1.6.9.1 GDirt and Dust Control Plan

1.9 GSolid Waste Management Permit

3.2.1.1 GStormwater Pollution Prevention

Plan

GStormwater Notice of Intent

3.12.2 GSpill Prevention Control And

Countermeasure (SPCC) Plan

3.8 GAF Form 3952

SD-05 Design Data

3.1.1Wildlife Survey

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 9 PAGES

01 57 19 SD-06 Test Reports

1.9.1 GMonthly Solid Waste Disposal

Report

3.2.1Inspection Reports

3.7.1.1.2Laboratory Analysis

01 74 19 SD-01 Preconstruction Submittals

1.6 GConstruction Waste Management

Plan

SD-06 Test Reports

1.8.2Quarterly Reports

1.8.3Annual Report

SD-11 Closeout Submittals

1.9 SFinal Construction Waste

Diversion Report

01 78 00 SD-02 Shop Drawings

1.5.7Detail Drawings

SD-03 Product Data

1.5.1Warranty Management Plan

1.5.5Warranty Tags

SD-08 Manufacturer’s Instructions

1.5.2Instructions

SD-10 Operation and Maintenance

Data

3.8 GOperation and Maintenance

Manuals

1.4 GSpare Parts Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 9 PAGES

01 78 00 SD-11 Closeout Submittals

3.1 GAs-Built Drawings

1.1.2 GRecord Drawings

GCertification of EPA Designated

Items

3.3Final DD Form 1354

3.2Final as-built

01 78 23 SD-10 Operation and Maintenance

Data

1.4 GFacility Data Workbook

GTraining Plan

GTraining Outline

GTraining Content

3.2.1 GOperation And Maintenance

Manual, Progress Submittal

3.2.2 GOperation And Maintenance

Manual, Prefinal Submittal

3.2.3 GOperation And Maintenance

Manual, Final Submittal

SD-11 Closeout Submittals

1.6.6.7 GRecord Drawings And Utility

Systems

03 30 00 SD-01 Preconstruction Submittals

Concrete Curing Plan

1.6.4 GQuality Control Program

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 9 PAGES

03 30 00 GQuality Control Personnel

Certifications

Quality Control Organizational

Chart

1.6.7 GLaboratory Accreditation

GForm Removal Schedule

Maturity Method Data

SD-02 Shop Drawings

Formwork

1.6.2.1 GReinforcing Steel

SD-03 Product Data

2.4.4 SJoint Sealants

2.4.3 SJoint Filler

2.1Formwork Materials

2.3.3.3 SRecycled Aggregate Materials

2.3.1 SCementitious Materials

2.4.5Vapor Retarder and Vapor Barrier

2.4.1Concrete Curing Materials

2.6 SReinforcement

Liquid Chemical Floor Hardeners and Sealers

2.3.4Admixtures

2.6.4Reinforcing Fibers

Mechanical Reinforcing Bar

Connectors

Waterstops

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 9 PAGES

03 30 00 SLocal/Regional Materials

Biodegradable Form Release

Agent

Pumping Concrete

Finishing Plan

2.4.2Nonshrink Grout

SD-04 Samples

Slab Finish Sample

Surface Finish Samples

SD-05 Design Data

1.6.1.1 GConcrete Mix Design

Formwork Calculations

SD-06 Test Reports

1.6.1.1 GConcrete Mix Design

Fly Ash

Pozzolan

Slag Cement

1.6.3.1Aggregates

GFiber-Reinforced Concrete

3.11.3.3 GCompressive Strength Tests

3.11.3.4Air Content

3.11.3.1Slump Tests

2.3.2Water

SD-07 Certificates

2.6.1Reinforcing Bars

Welder Qualifications

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 9 PAGES

03 30 00 1.6.5Field Testing Technician and

Testing Agency

SD-08 Manufacturer’s Instructions

2.4.4 SJoint Sealants

31 00 00 SD-01 Preconstruction Submittals

3.1.3 GExcavation and Trenching Plan

3.1.2.2 GDewatering Work Plan

3.8 GDisposition of Surplus Materials

1.4.1 GPreconstruction Meeting

SD-03 Product Data

Geotextiles

32 12 16.16 SD-03 Product Data

GMix Design

3.1 GContractor Quality Control

SD-06 Test Reports

GAggregates

3.1.3.2QC Monitoring

GBase Course In-Place Density

GSub grade In-Place Density

SD-07 Certificates

GAsphalt Cement Binder

Laboratory Accreditation and

Validation

Warm-mix Additive

32 92 23 SD-07 Certificates

2.1sods

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 9 PAGES

33 05 07.13 SD-01 Preconstruction Submittals

1.3.1 GQualifications

1.3.3 GHorizontal Directional Drilling

Plan

SD-03 Product Data

2.2.1 GPipe

2.2.2 GDrilling Fluids

2.2.3 GAdditives

2.2.4 GTracer Wire

SD-05 Design Data

3.2.2 GSecondary Containment Plan

SD-06 Test Reports

3.1Soil Test Data

SD-07 Certificates

2.1.1Drill Rod

1.3.4Fusion Technician Qualifications

SD-11 Closeout Submittals

3.4Record Drawings

3.4Complete Work Logs of Guided

Directional Drill Operations

33 11 00 SD-01 Preconstruction Submittals

3.1.1 GConnections

SD-03 Product Data

2.1.1 GPipe, Fittings, Joints and

Couplings

2.1.2 GValves

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 9 PAGES

33 11 00 2.1.2.6 GValve Boxes

2.1.3.1 GFire Hydrants

2.2.1 GPipe Restraint

2.2.2 GTapping Sleeves

2.2.5.1 GCorporation Stops

1.4.2.1.1 GBackflow Preventer

3.2.5 GDisinfection Procedures

SD-06 Test Reports

3.3.1.4 GBackflow Preventer Tests

3.3.1.3 GBacteriological Samples

3.3.1.2Leakage Test

3.3.1.1Hydrostatic Test

SD-07 Certificates

2.1.1Pipe, Fittings, Joints and

Couplings

2.1.1.1.1Lining

2.1.1.1.1Lining

2.1.1.2.1.2Lining for Fittings

2.1.2Valves

2.1.3.1Fire Hydrants

1.4.2.1.1.1Backflow Tester

2.1.5Backflow Certificate

SD-08 Manufacturer’s Instructions

2.1.1.2.2PVC Piping For Service Lines

2.1.1.3Copper Pipe For Service Lines

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR