SRC_Admin_Complex_Specs_Binder_rev1.pdf

PDF 1 MB Posted

Attached to
Santa Rosa County Administration Building Green Infrastructure
Solicitation number
26-010
Issued by
Santa Rosa County, Mount Carmel CDP, Florida

About this file

This document comprises construction specifications for the Santa Rosa County Administration Building Green Infrastructure project in Milton, Florida, developed by the county's procurement office. The project encompasses comprehensive site development and construction work including clearing and grubbing, structure removal, pollution control, construction surveys, mobilization and demobilization, traffic control, water management, excavation, earthfill placement, drainfill installation, topsoiling, concrete work, asphalt paving, steel reinforcement, plastic pipe installation, rock riprap placement, metal fabrication, geotextile installation, and vegetative measures. The bid specifications detail 32 distinct bid items ranging from site preparation through final landscaping, with specific technical requirements for materials, equipment, compaction standards, testing procedures, and quality control protocols. The pre-bid conference is scheduled for January 12, 2026 at 10:00 a.m. at 6051 Old Bagdad Highway, Suite 301, Milton in the Engineering/Environmental Conference Room. Questions must be submitted through the Santa Rosa County Procurement Portal by 12:00 p.m. on Friday, February 13, 2026, with sealed bids due by 10:00 a.m. on Friday, February 20, 2026, for public opening.

The specifications require compliance with Florida Department of Transportation standards, ASTM testing methods, and American Concrete Institute requirements. All work must meet Class C or Class A compaction standards as specified for earthfill and drainfill materials, with concrete specified as either Class 3000M or Class 4000M depending on application. The contractor must implement a comprehensive quality control program with separate quality control personnel reporting directly to management, maintain detailed inspection and testing records, and obtain engineer approval before commencing work. Materials must be obtained from approved sources with testing documentation submitted prior to installation. The county reserves the right to waive irregularities in bids, reject any or all bids for documented reasons, and award contracts based on best value to Santa Rosa County. The procurement encourages participation from small businesses, minority-owned businesses, women-owned businesses, and disadvantaged business enterprises, with no discrimination based on race, color, religion, national origin, disability, sex, or age.

View the file

Other files

File Type Posted
Portable_Toilet_and_Restroom_Trailer_Rental_(Addendum_#1_Revision).pdf PDF
Portable_Toilet_and_Restroom_Trailer_Rental_(Addendum_#1_Revision).pdf PDF
Term_Contract_Agreement_(General_or_Professional_Services)_.pdf PDF
Term_Contract_Agreement_(General_or_Professional_Services)_.pdf PDF
PAYMENT_BOND.pdf PDF
PERFORMANCE_BOND.pdf PDF
PERFORMANCE_BOND.pdf PDF
PAYMENT_BOND.pdf PDF
Santa_Rosa_County_Administration_Building_Green_Infrastructure_(Addendum_#5_Revision).pdf PDF
Santa_Rosa_County_Administration_Building_Green_Infrastructure_(Addendum_#5_Revision).pdf PDF
SRC_Admin_Complex_-_Submittal_2.pdf PDF
SRC_Admin_Complex_-_Submittal_2.pdf PDF
Alternate_Bid_Pricing_Table_Revision_2.6.26.xlsx XLSX spreadsheet
Alternate_Bid_Pricing_Table_Revision_2.6.26.xlsx XLSX spreadsheet
Base_Bid_Pricing_Table_Revision_2.6.26.xlsx XLSX spreadsheet
Base_Bid_Pricing_Table_Revision_2.6.26.xlsx XLSX spreadsheet
Santa_Rosa_County_Administration_Building_Green_Infrastructure.pdf PDF
Draft_Contract_Federal_Santa_Rosa_County_Administration_Building_Green_Infrastructure.pdf PDF
Draft_Contract_Federal_Santa_Rosa_County_Administration_Building_Green_Infrastructure.pdf PDF
Draft_Contract_Federal_Santa_Rosa_County_Administration_Building_Green_Infrastructure.pdf PDF
2022_EPA_MX-02D19622_SRC_Admin_Complex_Grant_Agreement.pdf PDF
2022_EPA_MX-02D19622_SRC_Admin_Complex_Grant_Agreement.pdf PDF
2022_EPA_MX-02D19622_SRC_Admin_Complex_Grant_Agreement.pdf PDF
Alternative_Bid_Pricing_Table_SRC_Administration_Building_GI_(3).xlsx XLSX spreadsheet
Alternative_Bid_Pricing_Table_SRC_Administration_Building_GI_(3).xlsx XLSX spreadsheet
Alternative_Bid_Pricing_Table_SRC_Administration_Building_GI_(3).xlsx XLSX spreadsheet
Base_Bid_Pricing_Table_SRC_Administration_Building_GI_(3)_Rev3.xlsx XLSX spreadsheet
Base_Bid_Pricing_Table_SRC_Administration_Building_GI_(3)_Rev3.xlsx XLSX spreadsheet
Base_Bid_Pricing_Table_SRC_Administration_Building_GI_(3)_Rev3.xlsx XLSX spreadsheet
SRC_Admin_Complex_Specs_Binder_rev1.pdf PDF
SRC_Admin_Complex_Specs_Binder_rev1.pdf PDF
SRC_Admin_Complex_-_Alternate_Bid.pdf PDF
SRC_Admin_Complex_-_Alternate_Bid.pdf PDF
SRC_Admin_Complex_-_Alternate_Bid.pdf PDF
SRC_Admin_Complex_-_Submittal_1_(002).pdf PDF
SRC_Admin_Complex_-_Submittal_1_(002).pdf PDF
SRC_Admin_Complex_-_Submittal_1_(002).pdf PDF
2024_USEPA_Grant_Agreement_Time_Extension.pdf PDF
2024_USEPA_Grant_Agreement_Time_Extension.pdf PDF
2024_USEPA_Grant_Agreement_Time_Extension.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(210-VI-NEH, May 2001) 2-1

Construction Specification 2—Clearing and Grubbing

1. Scope The work consists of clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from the designated areas.

2. Marking The limits of the area(s) to be cleared and grubbed will be marked by stakes, flags, tree markings, or other suitable methods. All trees and plants to be removed will be according to design plans.

3. Clearing and grubbing All trees and all snags, logs, brush, stumps, shrubs, rubbish, and similar materials shall be cleared from within the limits of the designated areas. Unless otherwise specified, all stumps, roots, and root clusters that have a diameter of 1 inch or larger shall be grubbed out to a depth of at least 2 feet below subgrade for concrete structures and 1 foot below the ground surface at embankment sites and other designated areas.

4. Disposal All materials cleared and grubbed from the designated areas shall be disposed of at locations shown on the drawings or in a manner specified in section 7. The contractor is responsible for complying with all local rules and regulations and the payment of any and all fees that may result from disposal at locations away from the project site.

5. Measurement and payment Method 1—For items of work for which specific units prices are established in the contract, the cleared and grubbed area is measured to the nearest 0.1 acre. Payment for clearing and grubbing is made for the total area within the designated limits at the contract unit price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

Method 2—For items of work for which specific unit prices are established in the contract, the length of the cleared and grubbed area is measured to the nearest full station (100 feet) along the line designated on the drawing or identified in the specifications. Payment for clearing and grubbing is made for the total length within the designated limits at the contract unit price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

Method 3—For items of work for which specific unit prices are established in the contract, each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet are measured before removal. The size of each tree and snag is determined by measuring its trunk at breast height above the natural ground surface. The size of each log is determined by measuring the butt and by measuring its length from butt to tip.

The size of each stump is measured at the top. Diameter is determined by dividing the measured circumference by 3.14.

Payment for clearing and grubbing of each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet or larger is made at the contract unit price for its size designation as determined by the following schedule:

Measured diameter Size designation

(210-VI-NEH, May 2001) 2-2

(in) (in)

4 to 8

8 to 12 10

12 to 24 18

24 to 36 30

36 to 60 48 Over 60 60

The sum of such payments shall constitute full compensation for clearing and grubbing (including the clearing and grubbing of smaller trees, stumps, snags, logs, brush, shrubs, and roots), applicable permits and associated fees, and rubbish removal. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

Method 4—For items of work for which specific lump sum prices are established in the contract, payment for clearing and grubbing is made at the contract lump sum price. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and

All Methods—The following provisions apply to all methods of measurement and payment.

Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 7.

6. Items of Work and Construction Details

Items of work to be performed in conformance with this specification and the construction details therefore are:

Bid Item No. 1, Clearing and Grubbing

(1) This item shall consist of the clearing and grubbing of the area required for the installation of the works of improvement as shown on the drawings.

(2) All cleared and grubbed materials shall become the property and responsibility of the Contractor and shall be disposed of off the job site.

(3) Clearing and grubbing shall be limited only to those areas designated in item (1) above.

All other areas shall be left undisturbed.

(4) All clearing and grubbing shall be accomplished in such a manner as to minimize air and water pollution.

(5) Measurement and payment shall be according to the Santa Rosa County contract.

(210-VI-NEH, May 2001) 3-1

Construction Specification 3—Structure Removal

The work shall consist of the removal, salvage, and disposal of structures (including fences) from the designated areas.

2. Marking Method 1—Each structure or structure part to be removed will be marked with stakes, flags, paint, or other suitable method.

Method 2—The area boundaries from which structures must be removed will be marked using stakes, flags, paint, or other suitable method. Structures to remain undisturbed or to be salvaged will be designated by special markings.

3. Removal Method 1—All structures designated for removal in the contract shall be removed to the specified extent and depth.

Method 2—Within the areas so marked, all visible and buried structures identified shall be removed to the specified extent and depth.

4. Salvage Structures or structure parts that are designated to be salvaged shall be carefully removed and neatly placed in the specified or approved storage location. Salvaged structures that are capable of being disassembled shall be dismantled into individual members or sections. Such structures shall be neatly and systematically match marked with paint before disassembly. All connectors and other parts shall be marked to indicate their proper location within the structure and shall be fastened to the appropriate structural member or packed in suitable containers.

Material from fences designated to be salvaged shall be placed outside the work area on the property on which the fence was originally located. Fence wire shall be rolled into uniform rolls of suitable size and neatly piled with other salvaged materials. Posts and rails shall be neatly stacked.

5. Disposal of refuse materials Refuse materials resulting from structure removal shall be disposed of in a manner and at locations specified in section 7 of this specification or in an acceptable manner and at locations approved by the contracting officer. Disposal by burning shall be in accordance with local rules and regulations.

6. Measurement and payment Method 1—For items of work for which specific unit prices are established by the contract, payment for the removal of each structure unit, except fences, is made at the contract unit price.

Fences removed or removed and salvaged are measured to the nearest linear foot. Payment for fence removal or removal and salvage is made at the contract unit prices for each type and size of fence.

(210-VI-NEH, May 2001) 3-2

Such payment will constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and

Method 2—For items of work for which specific lump sum prices are established by the contract, payment for structure removal is made at the contract lump sum price.

Such payment will constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and

Compensation for any item of work described in the contract, but not listed as a contract line item number in the bid schedule, is included in the payment for the item of work to which it is made subsidiary. Such items and items to which they are made subsidiary are identified in section 7 of this specification.

7. Items of Work and Construction Details Items of work to be performed in conformance with this specification and the construction details therefore are:

Bid Item No. 2, Structure Removal

(1) This item shall consist of the removal of the existing Asphalt, Curbing, Striping, Pipe

Sections, and other previous improvements and/or debris from within the work limits as shown on the drawings and as required for installation of proposed improvements.

(2) The items / debris removed shall become the property and responsibility of the contractor and shall be disposed of off the job site.

(3) Measurement and payment shall be according to the Santa Rosa County contract.

(210-VI-NEH, May 2001) 5-1

Construction Specification 5—Pollution Control

The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.

2. Material All material furnished shall meet the requirements of the material specifications listed in section 8 of this specification.

3. Erosion and sediment control measures and works The measures and works shall include, but are not limited to, the following:

Staging of earthwork activities—The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.

Seeding—Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.

Mulching—Mulching to provide temporary protection of the soil surface from erosion.

Diversions—Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.

Stream crossings—Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.

Sediment basins—Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s). These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Sediment filters—Straw bale filters or geotextile sediment fences trap sediment from areas of limited runoff. Sediment filters shall be properly anchored to prevent erosion under or around them. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Waterways—Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Other—Additional protection measures as specified in section 8 of this specification or required by Federal, State, or local government.

(210-VI-NEH, May 2001) 5-2

4. Chemical pollution

The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to dispose of chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer washwater, or asphalt, produced as a by-product of the construction activities. At the completion of the construction work, sumps shall be removed and the area restored to its original condition as specified in section 8 of this specification. Sump removal shall be conducted without causing pollution.

Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities shall be disposed of without causing pollution as specified in section 8 of this specification.

5. Air pollution

The burning of brush or slash and the disposal of other materials shall adhere to state and local regulations.

Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.

All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations. A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.

6. Maintenance, removal, and restoration All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed and the site restored to near original condition.

7. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in section 8 of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessive to need. Such payment will constitute full compensation for the completion of the work.

Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.

Method 3—For items of work for which lump sum prices are established in the contract, payment

(210-VI-NEH, May 2001) 5-3 will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating shall be the number estimated to complete the work as outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.

Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in section 8 of this specification.

8. Items of Work and Construction Details Items of work to be performed in conformance with this specification and the construction details therefore are:

Bid Item No. 3, Pollution Control

(1) This item shall consist of precautions taken by the Contractor to minimize degradation of water quality passing through the job site during construction operations. All necessary precautions shall be taken to ensure compliance with water quality standards of the State of Florida. All sections of the Florida Administrative code and all local, state, and federal regulations shall be adhered to at all times.

(2) The Contractor shall be responsible for containment of pollution sources including, but not limited to the required excavations, clearing and grubbing, earthfill, and other disturbed areas.

(3) Silt Containment barriers shall be installed prior to any excavation, structure removal, or placement of any improvements (permanent or temporary, except said barriers) and shall be maintained in effective condition at all locations until construction and vegetative measures are completed.

(4) Measurement and payment shall be according to the Santa Rosa County contract.

(210-VI-NEH, May 2001) 7-1

Construction Specification 7—Construction Surveys

The work consists of performing all surveys, measurements, and computations required by this specification. This item shall be performed by a Professional Land Surveyor licensed in Florida.

2. Equipment and material Equipment for construction surveys shall be of a quality and condition to provide the required accuracy. The equipment shall be maintained in good working order and in proper adjustment at all times. Records of repairs, calibration tests, accuracy checks, and adjustments shall be maintained and be available for inspection by the engineer. Equipment shall be checked, tested, and adjusted as necessary in conformance with manufacturer's recommendations.

Material is field notebooks, stakes, templates, platforms, equipment, spikes, steel pins, tools, and all other items necessary to perform the work specified.

3. Quality of work All work shall follow recognized professional practice and the standards of the industry unless otherwise specified in section 9 of this specification. The work shall be performed to the accuracy and detail appropriate for the type of job. Notes, sketches, and other data shall be complete, recorded neatly, legible, reproducible and organized to facilitate ease in review and allow reproduction of copies for job documentation. Survey equipment that requires little or no manual recording of field data shall have survey information documented as outlined in section 9 of this specification.

All computations shall be mathematically correct and shall include information to identify the bid item, date, and who performed, checked, and approved the computations. Computations shall be legible, complete, and clearly document the source of all information used including assumptions and measurements collected.

If a computer program is used to perform the computations, the contractor shall provide the engineer with the software identification, vendor's name, version number, and other pertinent data before beginning survey activities. Computer generated computations shall show all input data including values assigned and assumptions made.

The elevations of permanent and temporary bench marks shall be determined and recorded to the nearest 0.01 foot. Differential leveling and transit traverses shall be of such precision that the error of vertical closure in feet shall not exceed plus or minus 0.1 times the square root of the traverse distance in miles. Linear measurements shall be accurate to within 1 foot in 5,000 feet, unless otherwise specified in section 9 of this specification. The angular error of closure for transit traverses shall not exceed 1 minute times the square root of the number of angles turned.

The minimum requirements for placing slope stakes shall be at 100-foot stations for tangents, as little as 25 feet for sharp curves, breaks in the original ground surface and at any other intermediate stations necessary to ensure accurate location for construction layout and measurement. Slope stakes and cross sections shall be perpendicular to the centerline. Significant breaks in grade shall be determined for cross sections. Distances shall be measured horizontally

(210-VI-NEH, May 2001) 7-2 and recorded to the nearest 0.1 foot. Side shots for interim construction stakes may be taken with a hand level.

Unless otherwise specified in section 9 of this specification, measurements for stationing and establishing the location of structures shall be made to the nearest 0.1 foot.

Elevations for concrete work, pipes, and mechanical equipment shall be determined and recorded to the nearest 0.01 foot. Elevations for earth work shall be determined and recorded to the nearest

0.1 foot.

4. Primary control The baselines and bench marks for primary control, necessary to establish lines and grades needed for construction, are shown on the drawings and have been located on the job site.

These baselines and bench marks shall be used as the origin of all surveys, layouts, and measurements to establish construction lines and grades. The contractor shall take all necessary precautions to prevent the loss or damage of primary control points. Any stakes or control points lost or damaged by construction activity will be reestablished by the contractor or at contractor expense.

5. Construction surveys Before work starts that requires contractor performed surveys, the contractor shall submit in writing for the engineer's review: the name, qualifications, and experience of the individuals to be assigned to the survey tasks.

Method 1—Contractor performed surveys shall include:

• checking and any supplemental or interim staking

• performing quantity surveys, measurements, and computations for progress payment

• other surveys as described in section 9 of this specification

Method 2—Contractor performed surveys shall consist of all work necessary for:

• establishing line and grade for all work

• setting slope stakes for all work

• checking and any supplemental or interim staking

• establishing final grade stakes

• performing quantity surveys, measurements, and computations for progress payment

• other surveys as described in section 9 of this specification

Method 3—Contractor performed surveys shall consist of all work necessary for:

• establishing line and grade for all work

• setting slope stakes for all work

• checking and any supplemental or interim staking

• establishing final grade stakes

• performing quantity surveys, measurements, and computations for progress payments

• performing original (initial) and final surveys for determinations of final quantities

• other surveys as described in section 9 of this specification.

(210-VI-NEH, May 2001) 7-3

6. Staking The construction staking required for the item shall be completed before work on any item starts.

Construction staking shall be completed as follows or as otherwise specified in section 9 of this specification:

Clearing and grubbing—The boundary of the area(s) to be cleared and grubbed shall be staked or flagged at a maximum interval of 200 feet, closer if needed, to clearly mark the limits of work.

When contractor staking is the basis for determining the area for final payment, all boundary stakes will be reviewed by the engineer before start of this work item.

Excavation and fill—Slope stakes shall be placed at the intersection of the specified slopes and ground line. Slope stakes and the reference stakes for slopes shall be marked with the stationing, required cut or fill, slope ratio, and horizontal distance from the centerline or other control line.

The minimum requirements for placing slope stakes is outlined in section 3, Quality of work.

Structures—Centerline and offset reference line stakes for location, alignment, and elevation shall be placed for all structures.

7. Records All survey data shall be recorded in fully identified standard hard-bound engineering survey field notebooks with consecutively numbered pages. All field notes and printed data shall include the purpose or description of the work, the date the work was performed, weather data, sketches, and the personnel who performed and checked the work. Electronically generated survey data and computations shall be bound, page numbered, and cross referenced in a bound field notebook containing the index for all survey activities. All work shall follow recognized professional practice.

The construction survey records shall be available at all times during the progress of the work for examination and use by the engineer and when requested, copies shall be made available. The original field notebooks and other records shall be provided to and become the property of the owner before final payment and acceptance of all work.

Complete documentation of computations and supporting data for progress payments shall be submitted to the engineer with each invoice for payment as specified in section 9 of the specification. When the contractor is required to conduct initial and final surveys as outlined in section 5, Construction Surveys, notes shall be provided as soon as possible after completion to the engineer for the purpose of determining final payment quantities.

8. Payment Method 1—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds, after presentation of correct and accurate invoices by the contractor showing related costs and evidence of the charges of suppliers, subcontractors, and others for supplies furnished and work performed. Invoices for the total amount of the contract price will not be accepted until all surveys are complete and required documentation has been determined complete. If the total of such payments is less than the lump sum contract price for this item, the unpaid balance will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of all work under the bid item.

(210-VI-NEH, May 2001) 7-4

Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds with progress payment amounts determined as a percentage of the total work planned as projected from the contractor's approved construction schedule. Payment of the lump sum contract price will constitute full compensation for completion of all work under this bid item.

Payment will not be provided under this item for the purchase price of materials or equipment having a residual value.

and the item to which they are made subsidiary are identified in section 9 of this specification.

9. Items of work and construction details

Items of work to be performed in conformance with this specification and the construction details are:

a. Bid Item No. 4, Construction Surveys

(1) In Section 5, Construction Surveys, Method 3 will apply.

(2) The contractor shall notify the Contracting Officer’s Representative at least 7 days before beginning any surveys. The contractor shall schedule, with written confirmation, a conference with the Contracting Officer’s Representative, prior to beginning any surveys.

In this conference the contractor shall outline the details of the proposed surveys.

(3) This item shall consist of performing all work specified herein:

a. establishing permanent references along the proposed alignment as shown on the drawings and at each structure location, berm location, pipe ends, edges (top and toe) of all rip rap, and any other construction item as applicable.

b. Establishing clearing boundaries.

c. Obtaining cross sections of the ground surface prior to construction. Cross sections shall be placed as a minimum at full stations, significant breaks in the original and final ground surface and other intermediate stations as necessary to assure accurate quantities. Proposed locations of sections shall be submitted to the Contracting Officer’s Representative for approval at the pre-survey conference.

d. Setting cut stakes for all excavation.

e. Setting line and grade for roads, channels, pipes, conduits, structures, and other appurtances.

f. Setting grades for all concrete work.

(210-VI-NEH, May 2001) 7-5

g. Setting line, grade, and fill stakes for fills.

h. Checking and supplemental staking of all cuts and fills as the work progresses.

i. Setting “blue tops” for final grading of all fills.

j. Restaking any layout, or references that are removed or destroyed.

k. Making progress payment surveys.

l. Obtaining cross sections of all constructed surfaces that are required for determining the limit of pay quantity.

m. Plotting all sections necessary for quantity computations.

n. Computing and checking all quantities for progress payments and final quantities for final payments.

o. Contract modifications will be made for construction contract modifications that require additional surveys.

(4) Surveys shall be certified by a surveyor licensed in the State of Florida.

(5) Excavation and fill quantities shall be computed by the average end area method or by acceptable electronic means approved by the Contracting Officer’s Representative.

Proposed method shall be discussed in the pre-survey conference.

(6) Measurement and payment shall be according to the Santa Rosa County contract.

(210-VI-NEH, May 2001) 8-1

Construction Specification 8—Mobilization and Demobilization

The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.

2. Equipment and material Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable;

and other items specified in section 4 of this specification.

Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.

This work includes mobilization and demobilization required by the contract at the time of award.

If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.

3. Payment Payment will be made as the work proceeds, after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment. Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.

Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.

4. Items of Work and Construction Details

Bid Item No. 5, Mobilization and Demobilization

This item shall consist of all work as described in Section 1 above.

(210-VI-NEH, May 2001) 9-1

Construction Specification 9—Traffic Control

The work shall consist of establishing traffic control and maintaining safe, convenient use of public roads and rights-of-way.

2. Traffic and access The contractor's operations shall cause no unnecessary inconvenience to the public. The public rights-of-way shall be maintained at all times unless interruption is authorized by proper local authority. Contractor's authorized closing or detour plans shall be provided to the engineer for approval.

Safe and adequate access shall be provided and maintained to all public protection devices and to all critical utility control locations. Facility access shall be continuous and unobstructed unless otherwise approved.

3. Storage of equipment and material in public streets Construction materials and equipment shall not be stored or parked on public streets, roads, or highways. During any material or equipment loading or unloading activities that may temporarily interfere with traffic, an acceptable detour shall be provided for the duration of the activity. Any associated expense for this activity is the responsibility of the contractor.

Excavated material, including suitable material that is intended for adjacent trench backfill or other earth backfill as specified in section 5 of this specification, shall not be stored on public streets, roads, or highways that remain in service for the public. Any waiver of this requirement must be obtained from the proper local authority and approved by the engineer. All excess and unsuitable material shall be removed from the site as soon as possible. Any spillage shall be removed from roadways before they are used by the public.

4. Street closures, detours, and barricades The contractor shall comply with the requirements of all applicable responsible units of government for closure of any street, road, or highway. The contractor shall provide the required barriers, guards, lights, signs, temporary bridges, and flaggers together with informing the public of any detours and construction hazards by the most suitable means available, such as local newspapers or radio stations. The contractor is also responsible for compliance with additional public safety requirements that may arise during construction. The contractor shall furnish, install, and, upon completion of the work, promptly remove all signs, warning devices, and other materials used in the performance of this work.

Unless otherwise specified, the contractor shall notify, in writing, the fire chief, police chief, county sheriff, state patrol, schools that operate school buses, or any other government official as may be appropriate no less than 7 days before closing, partly closing, or reopening any street, road, or highway.

Unless otherwise specified, the contractor shall furnish to the engineer a written plan showing the proposed method of signing, barricading for traffic control, and safety for street detours and closures.

(210-VI-NEH, May 2001) 9-2

All temporary detours will be maintained to ensure use of public rights-of-way is provided in a safe manner. This may include dust control, grading, and graveling as required in section 7 of this specification.

5. General and specific references All signs, signals, barricades, use of flaggers, and other traffic control and public safety devices shall conform to the general requirements set forth in the Manual of Uniform Traffic Control Devices (MUTCD) and the latest edition of Standard Highway Signs and Standard Alphabets for Highway Signs and/or OSHA Construction Industry Standards (29 CFR Part 1926), Subpart G, Signs, Signals, and Barricades unless otherwise specified in section 7 of this specification.

6. Measurement and payment For items of work for which specific lump sum prices are established in the contract, payment for the work is made at the contract lump sum price. Progress payments will be made based upon the percentage of estimated total time that traffic control will be required unless otherwise specified in section 7 of this specification. Payment will constitute full compensation for all flaggers, labor, materials, equipment, and all other items necessary and incidental to completion of the work.

and items to which they are made subsidiary are identified in section 7 of this specification.

7. Items of Work and Construction Details

Bid Item No.6, Traffic Control

(1) This item shall consist of providing traffic warning signs and providing traffic control during construction. Current work areas shall be clearly marked and traffic shall be directed to other areas within the parking lot.

(2) Warning signs and signals shall be placed in accordance with FDOT Manual on Uniform Traffic Control Devices (MUTCD) and a plan shall be designed and implemented by certified personnel.

(3) Flagmen shall be required when vehicles transporting equipment, materials, and supplies are entering and leaving the construction site.

(210-VI-NEH, May 2001) 10-1

Construction Specification 10—Water for Construction

The work consists of furnishing, transporting, measuring, and applying water as specified.

2. Facilities and equipment The contractor shall install and maintain access and haul roads and furnish, operate, and maintain all pumps, meters, piping, tanks, storage, and other facilities required to load, transport, store, distribute, and use construction water as specified.

These facilities shall be equipped with accurate, work dedicated meters; tanks of known volume;

or other devices that provide a correct measurement of water supplied. Meters shall be installed at the point of delivery into water hauling equipment or application system, such as sprinkler systems or flooding systems, as specified.

3. Dust abatement and haul road maintenance Water for dust abatement and haul road maintenance shall be applied to haul roads and other dust producing areas as needed to prevent air pollution or excessive dust (which causes impaired vision on trafficked roads and in work areas) and to maintain the roads in good condition for safe and efficient operation during periods of use. Roads that may be jointly used with the public and by the contractor's equipment shall have dust abatement provisions acceptable to the public entity that has road maintenance responsibility. Compensation for water used for dust abatement and haul road maintenance shall be as specified in section 8 of this specification.

4. Earthfill, drainfill, and rockfill Water required for proper installation of earthfill, drainfill, and/or rockfill shall be used in the fill materials as specified in the applicable construction specification(s). Compensation for construction water used for earthfill, drainfill, and/or rockfill shall be as specified in section 8 of this specification.

5. Concrete, mortar, and grout Water required in the mixing or curing of concrete, shotcrete, roller compacted concrete, or other portland cement mortar or grout shall meet the requirements of the applicable construction specifications and shall be used in conformance with those specifications. Payment for construction water used in these items is covered by the applicable concrete, mortar, or grout specification, or a combination of these.

6. Other construction requiring water Water required and used for other construction activities under this contract, but not specifically covered by this specification shall be considered subsidiary to the item(s) of work that requires its use.

7. Measurement and payment Method 1—For water items for which specific unit prices are established in the contract, the volume of water furnished and used in accordance with the specifications will be measured to the nearest 1,000 gallons.

(210-VI-NEH, May 2001) 10-2

Payment for water is made at the contract unit price. Such payment will constitute full compensation for the direct costs of water. All other costs necessary for applying water are subsidiary to the items of work they are associated.

Method 2—For water items for which specific unit prices are established in the contract, the volume of water furnished and used in accordance with the specifications will be measured to the nearest 1,000 gallons.

Payment for water and the cost associated with transportation, distribution, and application is made at the contract unit price. Such payment will constitute full compensation for completion of the work.

Method 3—For water items for which specific unit prices are established in the contract, the volume of water used in accordance with the specifications will be measured to the nearest 1,000 gallons.

Payment for water is made at the contract unit price. Such payment, excluding water cost, will constitute full compensation for completion of the work.

All methods—The following provisions apply to all methods of measurement and payment:

• The measurement for payment will include all water used except as noted in sections 5, 6, and 8 of this specification. Measurement for payment will not include water that is used inappropriately or in excessive to need.

• Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary.

Such items and the items to which they are made subsidiary are identified in section 8 of this specification.

8. Items of work and construction details

a. Subsidiary Item, Water for Construction

(1) This item shall consist of all water necessary and incidental to curing of concrete, obtaining proper moisture content for compaction of earthfill, proper watering of new vegetation, and all other items that may require water to be successfully installed as required on the drawings and in the specifications.

(2) No separate payment shall be made for this item. Compensation shall be included in the payment for the respective bid item to which it is incidental.

(210-VI-NEH, May 2001) 11-1

Construction Specification 11—Removal of Water

The work consists of the removal of surface water and ground water as necessary to perform the construction required by the contract in accordance with the specifications. It shall include: (1) constructing, installing, building, and maintaining all necessary temporary water containment facilities, channels, and diversions; (2) furnishing, installing, and operating all necessary pumps, piping, and other facilities and equipment; and (3) removing all such temporary works and equipment after their intended function is no longer required.

2. Diverting surface water The contractor shall install, maintain, and operate all cofferdams, channels, flumes, sumps, and all other temporary diversion and protective works needed to divert streamflow and other surface water through or around the construction site. Control of surface water shall be continuous during the period that damage to construction work could occur. Unless otherwise specified and/or approved, the diversion outlet shall be into the same drainageway that the water would have reached before being diverted.

The contractor shall furnish the contracting officer, in writing, a proposed plan for diverting surface water before beginning any construction activities for which a diversion is required, unless waived in section 8 of this specification. Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities related to this activity during the process of completing the work as specified.

3. Dewatering the construction site Foundations, cutoff trenches, and all other parts of the construction site shall be dewatered and kept free of standing water and muddy conditions as necessary for the proper execution of the work. The contractor shall furnish, install, operate, and maintain all drains, sumps, pumps, casings, well points, and all other equipment required to properly dewater the site as specified.

Dewatering systems that cause a loss of soil fines from the foundation areas will not be permitted.

The contractor shall furnish the contracting officer, in writing, a proposed plan for dewatering before commencing with any construction activity for which dewatering may be required, unless waived in section 8 of this specification. Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities for completing the specified work.

4. Dewatering borrow areas The contractor shall maintain all borrow areas free of surface water or otherwise provide for timely and effective removal of surface and subsurface water that accumulates within the borrow area, unless waived in section 8 of this specification. Borrow material shall be processed as necessary to achieve proper and uniform moisture content at the time of placement.

If pumping to dewater borrow areas is included as a bid item of work in the bid schedule, each pump discharge pipe shall be equipped with a water meter. The meter shall be such that the measured quantity of water is accurate within 3 percent of the true quantity. The contractor shall provide necessary support to perform accuracy tests of the water meter when requested by the

(210-VI-NEH, May 2001) 11-2 contracting officer.

5. Erosion and pollution control Removal of water from the construction site, including the borrow areas, shall be accomplished so that erosion and the transporting of sediment and other pollutants are minimized. Dewatering activities shall be accomplished in a manner that the water table water quality is not altered.

Pollution control activities shall not conflict with the requirements of Construction Specification 5, Pollution Control, if it is a part of this contract.

6. Removal of temporary works When temporary works are no longer needed, the contractor shall remove and return the area to a condition similar to that which existed before construction. Areas where temporary works were located shall be graded for sightly appearance with no obstruction to natural surface waterflows or the proper functioning and access to the works of improvement installed. The contractor shall exercise extreme care during the removal stages to minimize the loss of soil sediment and debris that was trapped during construction.

Pipes, casings, and any other material used to dewater the site shall be removed from temporary wells. The wells shall be filled to ground level with clean gravel or other suitable material approved by the contracting officer. The contractor shall exercise extreme care to prevent pollution of the ground water by these actions.

7. Measurement and payment Method 1—Items of work listed in the bid schedule for removal of water, diverting surface water, and dewatering construction sites and borrow areas are paid for at the contract lump sum prices.

Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

Method 2—Items of work listed in the bid schedule for removal of water, diverting surface water, dewatering construction sites, and dewatering borrow areas are paid for at the contract lump sum prices. Such payment will constitute full compensation for furnishing, installing, operating, and maintaining the necessary trenches, drains, sumps, pumps, and piping and for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work. The exception is that additional payment for pumping to dewater borrow areas and the removal of water will be made as described in the following paragraph.

If pumping to dewater borrow areas is a contract bid item, payment is made at the contract unit price, which shall be the price per 1,000 gallons shown in the bid schedule. Such payment will constitute full compensation for pumping only. Compensation for equipment and preparation and for other costs associated with pumping is included in the lump sum payment for removal of water or the lump sum payment for dewatering the borrow areas. Payment is made only for pumping that is necessary to dewater borrow areas that cannot be effectively drained by gravity or that must have the water table lowered to be usable as a suitable borrow source. Pumping for other purposes will not be included for payment under this item.

included in the payment for the contract line item to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 8 of this specification.

(210-VI-NEH, May 2001) 11-3

8. ITEMS OF WORK AND CONSTRUCTION DETAILS

Bid Item No. 7, Removal of Water

(1) This item shall consist of all works necessary and incidental to the removal of water in the work area as needed to install the works of improvement. A Geotechnical Report is available and is considered a part of the plans and specifications.

(2) The dewatering operation shall not create erosive conditions nor cause a condition of polluted water downstream from the work site.

(3) A written plan for dewatering the work site shall be submitted to the engineer for approval prior to beginning work. Unless otherwise approved in writing by the engineer, at minimum, a well point system adequate to handle the existing water condition shall be installed, operated, and maintained by the contractor until improvements are complete.

(210-VI-NEH, May 2001) 21-1

Construction Specification 21—Excavation

The work shall consist of the excavation required by the drawings and specifications and disposal of the excavated materials.

2. Classification Excavation is classified as common excavation, rock excavation, or unclassified excavation in accordance with the following definitions.

Common excavation is defined as the excavation of all materials that can be excavated, transported, and unloaded using heavy ripping equipment and wheel tractor-scrapers with pusher tractors or that can be excavated and dumped into place or loaded onto hauling equipment by excavators having a rated capacity of one cubic yard or larger and equipped with attachments (shovel, bucket, backhoe, dragline, or clam shell) appropriate to the material type, character, and nature of the materials.

Rock excavation is defined as the excavation of all hard, compacted, or cemented materials that require blasting or…

This is the start of the file's text. The full file is on GovTribe.