Specs 4 14 2023.pdf
PDF 11 MB Posted
- Attached to
- Renovate Interior Space JACC Federal contract opportunity
- Solicitation number
- 520-23-106
About this file
This file describes a federal contract solicitation to renovate interior space. The solicitation number is 520-23-106 from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16 to renovate interior space at the JACC facility. Offerors are required to provide all labor, materials, equipment, and supervision to complete interior renovations, including demolition of existing non-load bearing interior walls, installation of new walls, flooring, ceilings, lighting, and fixtures. The period of performance is 180 calendar days from date of award. Proposals are due by January 15, 2023 and award is expected by February 15, 2023. Pricing is to be provided as a firm fixed price for the base requirement and fixed unit prices for any optional items. The solicitation is unrestricted and not set aside for small businesses.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Gulf Coast Veterans Healthcare System
Project Number: 520-23-106
Pensacola VA Clinic
Renovate Various Interior Spaces To Improve Primary Care And Other Specialty Services, JACC
Issued for Construction
PROJECT SPECIFICATIONS
Prepared For:
Gulf Coast Veterans Healthcare System Pensacola VA Clinic 790 Veterans Way Pensacola, FL 32503
Prepared By:
Gulf Coast Veterans Healthcare
System Pensacola VA Clinic 790 Veterans Way
Pensacola, FL 32503
Project Team:
Gulf Coast Veterans Healthcare
System Pensacola VA Clinic 790 Veterans Way
Pensacola, FL 32503
This page intentionally left blank.
Renovate Various Interior Spaces, JACC Project #: 520-23-106
00 01 10 - 1
GULF COAST VETERANS HEALTHCARE SYSTEM
ADDITION & RENOVATION
TABLE OF CONTENTS
SECTION 00 01 10
SECTIONS DIVISION AND SECTION TITLES DATE
DIVISION 00 — SPECIAL SECTIONS
00 01 10 Table of Contents 06-2021 00 01 15 List of Drawing Sheets 06-2020
DIVISION 01 — GENERAL REQUIREMENTS
01 00 00 General Requirements 11-2021 01 33 23 Shop Drawings, Product Data, and Samples 06-2021 01 33 24 Electronic Submittal Procedures 01 35 26 Safety Requirements 07-2020 01 42 19 Reference Standards 11-2020 01 45 00 Quality Control 05-2021 01 45 29 Testing Laboratory Services 11-2011 01 45 35 Special Inspections 06-2021 01 45 35.01 Schedule of Special Inspections Template 04-2018 01 57 19 Temporary Environmental Controls 01-2021 01 58 16 Temporary Interior Signage 07-2015 01 74 19 Construction Waste Management 01-2021 01 81 13 Sustainable Construction Requirements 10-2017 01 91 00 General Commissioning Requirements 10-2015
DIVISION 02 — EXISTING CONDITIONS
02 21 13 Site Surveys 01-2021 02 41 00 Demolition 08-2017
DIVISION 03 — CONCRETE
03 30 00 Cast-In-Place Concrete 01-2021
DIVISION 04 — MASONRY
04 01 00 Maintenance of Masonry 01-2021 04 05 13 Masonry Mortaring 10-2017 04 05 16 Masonry Grouting 01-2021 04 20 00 Unit Masonry 08-2017 04 72 00 Cast Stone Masonry 01-2021
DIVISION 05 — METALS
05 12 00 Structural Steel Framing 11-2018 05 21 00 Steel Joist Framing 11-2018 05 31 00 Steel Decking 01-2021 05 36 00 Composite Metal Decking 01-2021 05 40 00 Cold-Formed Metal Framing 01-2021 05 50 00 Metal Fabrications 08-2018
DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry 10-2017 06 16 63 Cementitious Sheathing 01-2021 06 20 00 Finish Carpentry 01-2021
00 01 10 - 2
DIVISION 07 — THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 01-2021 07 13 52 Modified Bituminous Sheet Waterproofing 01-2021 07 18 13 Pedestrian Traffic Coatings 01-2021 07 21 13 Thermal Insulation 01-2021 07 22 00 Roof and Deck Insulation 01-2021 07 24 00 Exterior Insulation and Finish Systems 01-2021 07 27 27 Fluid-Applied Membrane Air Barrier, Vapor Retarding 01-2021 07 40 00 Roofing and Siding Panels 01-2021 07 52 16.12 Hot-Mopped Styrene-Butadiene-Styrene Modified Bituminous Membrane Roofing 01-
07 60 00 Flashing and Sheet Metal 01-2021 07 71 00 Roof Specialties 01-2021 07 72 00 Roof Accessories 01-2021 07 81 00 Applied Fireproofing 10-2017 07 84 00 Firestopping 01-2021 07 92 00 Joint Sealants 10-2017 07 95 13 Expansion Joint Cover Assemblies 01-2021
DIVISION 08 — OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-2021 08 14 00 Interior Wood Doors 01-2021 08 41 13 Aluminum-Framed Entrances and Storefronts 01-2021 08 51 13 Aluminum Windows 01-2021 08 56 19 Pass Windows 01-2021 08 71 00 Door Hardware 01-2021 08 80 00 Glazing 01-2021 08 90 00 Louvers and Vents 01-2021
DIVISION 09 — FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-2021 09 06 00 Schedule for Finishes 01-2021 09 22 16 Non-Structural Metal Framing 06-2018 09 29 00 Gypsum Board 04-2020 09 30 13 Ceramic Porcelain Tiling 01-2021 09 51 00 Acoustical Ceilings 12-2018 09 54 23 Linear Metal Ceilings 01-2021 09 65 13 Resilient Base and Accessories 01-2021 09 65 16 Resilient Sheet Flooring 05-2018 09 65 19 Resilient Tile Flooring 05-2018 09 91 00 Painting 01-2021
DIVISION 10 — SPECIALTIES
10 14 00 Signage 01-2021 10 21 23 Cubicle Curtain Tracks 01-2021 10 26 00 Wall and Door Protection 01-2021 10 28 00 Toilet, Bath, and Laundry Accessories 01-2021 10 44 13 Fire Extinguisher Cabinets 08-2018
DIVISION 11 — EQUIPMENT
11 41 21 Walk-In Coolers and Freezers 01-2021 11 53 23 Laboratory Refrigerators 01-2021 11 53 71 Solution Warming Cabinets 01-2021 11 71 02 Laboratory Washing and Sterilizing Equipment 01-2021
DIVISION 12 — FURNISHINGS
12 24 00 Window Shades 08-2017
00 01 10 - 3
12 32 00 Manufactured Wood Casework 01-2021 12 34 00 Modular Laminate Casework 01-2021 12 36 00 Countertops 12-2018
DIVISION 13 — SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components 01-2021
DIVISION 14 — CONVEYING EQUIPMENT
NOT USED
DIVISION 20 — MECHANICAL SUPPORT
NOT USED
DIVISION 21 — FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-2016 21 13 13 Wet-Pipe Sprinkler Systems 06-2015
DIVISION 22 — PLUMBING
22 05 11 Common Work Results for Plumbing 09-2020 22 05 12 General Motor Requirements for Plumbing Equipment 09-2020 22 05 19 Meters and Gauges for Plumbing Piping 09-2020 22 05 23 General-Duty Valves for Plumbing Piping 09-2020 22 07 11 Plumbing Insulation 09-2019 22 08 00 Commissioning of Plumbing Systems 11-2016 22 11 00 Facility Water Distribution 22 13 00 Facility Sanitary and Vent Piping 09-2020 22 14 00 Facility Storm Drainage 09-2015 22 15 00 General Service Compressed-Air Systems 09-2020 22 40 00 Plumbing Fixtures 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-2015 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-2015 22 66 00 Chemical-Waste Systems for Laboratory and Healthcare Facilities 09-2020
DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING
23 05 11 Common Work Results for HVAC 02-2020 23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment 02-2020 23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 02-2020 23 05 93 Testing, Adjusting, and Balancing for HVAC 02-2020 23 07 11 HVAC, Plumbing, and Boiler Plant Insulation 02-2020 23 08 00 Commissioning of HVAC Systems 02-2020 23 08 11 Demonstrations and Tests for Boiler Plant 08-2017 23 09 23 Direct-Digital Control System for HVAC 08-2020 23 21 13 Hydronic Piping 02-2020 23 21 23 Hydronic Pumps 02-2020 23 22 13 Steam and Condensate Heating Piping 02-2020 23 22 23 Steam Condensate Pumps 04-2020 23 23 00 Refrigeration Piping 02-2020 23 25 00 HVAC Water Treatment 02-2020 23 31 00 HVAC Ducts and Casings 02-2020 23 34 00 HVAC Fans 02-2020 23 36 00 Air Terminal Units 02-2020 23 37 00 Air Outlets and Inlets 02-2020 23 40 00 HVAC Air Cleaning Devices 03-2020 23 65 00 Cooling Towers 03-2020 23 73 00 Indoor Central-Station Air-Handling Units 03-2020 23 81 00 Decentralized Unitary HVAC Equipment 03-2020 23 81 43 Air-Source Unitary Heat Pumps 03-2020 23 82 16 Air Coils 03-2020
00 01 10 - 4
DIVISION 25 — INTEGRATED AUTOMATION
NOT USED
DIVISION 26 — ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-2016 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-2017 26 05 26 Grounding and Bonding for Electrical Systems 01-2017 26 05 33 Raceway and Boxes for Electrical Systems 01-2018 26 05 73 Overcurrent Protective Device Coordination Study 01-2018 26 08 00 Commissioning of Electrical Systems 11-2016 26 09 23 Lighting Controls 01-2018 26 22 00 Low-Voltage Transformers 01-2018 26 24 16 Panelboards 01-2018 26 27 26 Wiring Devices 01-2018 26 29 11 Motor Controllers 01-2018 26 29 21 Enclosed Switches and Circuit Breakers 01-2017 26 41 00 Facility Lightning Protection 01-2017 26 43 13 Surge Protective Devices 01-2017 26 51 00 Interior Lighting 01-2018 26 56 00 Exterior Lighting 01-2018
DIVISION 27 — COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-2019 27 05 26 Grounding and Bonding for Communications Systems 06-2015 27 05 33 Raceways and Boxes for Communications Systems 10-2018 27 08 00 Commissioning of Communications Systems 11-2016 27 10 00 Control, Communication and Signal Wiring 06-2015 27 11 00 Communications Equipment Room Fittings 06-2015 27 15 00 Communications Structured Cabling 01-2016 27 51 16 Public Address and Mass Notification Systems 10-2018 27 52 23 Nurse Call and Code Blue Systems 12-2020
DIVISION 28 — ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-2018 28 05 13 Conductors and Cables for Electronic Safety and Security 10-2018 28 05 26 Grounding and Bonding for Electronic Safety and Security 09-2011 28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 09-2011 28 08 00 Commissioning of Electronic Safety and Security Systems 11-2016 28 13 00 Physical Access Control System 10-2011 28 13 53 Security Access Detection 09-2011 28 23 00 Video Surveillance 09-2011 28 31 00 Fire Detection and Alarm 10-2011
DIVISION 31 — EARTHWORK
31 20 11 Earthwork (Short Form) 10-2012 31 23 19 Dewatering 10-2012 31 23 23.33 Flowable Fill 10-2012
DIVISION 32 — EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-2016 32 12 16 Asphalt Paving 09-2015 32 17 23 Pavement Markings 08-2016 32 84 00 Planting Irrigation 08-2016 32 90 00 Planting 08-2016
DIVISION 33 — UTILITIES
33 08 00 Commissioning of Site Utility Systems 11-2016 33 40 00 Storm Sewer Utilities 12-2017
00 01 10 - 5
DIVISION 34 — TRANSPORTATION
NOT USED
DIVISION 35 — WATERWAYS AND MARINE CONSTRUCTION
NOT USED
DIVISION 40 — PROCESS INTERCONNECTIONS
NOT USED
DIVISION 41 — MATERIAL PROCESSING AND HANDLING EQUIPMENT
NOT USED
DIVISION 42 — PROCESS HEATING, COOLING, AND DRYING EQUIPMENT
NOT USED
DIVISION 43 — PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND
STORAGE EQUIPMENT
NOT USED
DIVISION 44 — POLLUTION CONTROL EQUIPMENT
NOT USED
DIVISION 45 — INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT
NOT USED
DIVISION 46 — WATER AND WASTEWATER EQUIPMENT
NOT USED
DIVISION 48 — ELECTRICAL POWER GENERATION
NOT USED
This page intentionally left blank.
List of Drawing Sheets
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
A. The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI000 COVER SHEET
ARCHITECTURAL
A01 FIRST FLOOR IMPROVEMENT LOCATIONS
A02 SECOND FLOOR IMPROVEMENT LOCATIONS
A03 FIRST FLOOR DEMOLITION
A04 SECOND FLOOR DEMOLITION
A05 FIRST FLOOR ARCHITECTURAL
A06 SECOND FLOOR ARCHITECTURAL
FIRE PROTECTION
FP01 FIRE PROTECTION NOTES
FP02 FIRST FLOOR FIRE PROTECTION
FP03 SECOND FLOOR FIRE PROTECTION
MECHANICAL
M01 FIRST FLOOR - HVAC - BRAVO
M02 FIRST FLOOR - HVAC - CHARLIE/RADIOLOGY
M03 SECOND FLOOR - HVAC - EMPU
M04 SECOND FLOOR - HVAC - EYE CLINIC/INDIA/JULIET
M05 HVAC SCHEDULES
ELECTRICAL
E01 FIRST FLOOR – ELECTRICAL
E02 SECOND FLOOR – ELECTRICAL
List of Drawing Sheets
00 01 15 - 2
- - - END - - -
General Requirements
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
PART 1 - GENERAL
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (FAR 52.236-9)
1.10 RESTORATION
1.11 PHYSICAL DATA – SOIL CONDITIONS
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 WARRANTY MANAGEMENT
1.16 USE OF ROADWAYS
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.18 TEMPORARY USE OF EXISTING ELEVATORS
1.19 TEMPORARY TOILETS
1.20 AVAILABILITY AND USE OF UTILITY SERVICES
1.21 TESTS AND THIRD-PARTY INSPECTIONS
1.22 INSTRUCTIONS
1.23 GOVERNMENT-FURNISHED PROPERTY
1.24 RELOCATED EQUIPMENT and ITEMS
1.25 CONSTRUCTION SIGN
1.26 SAFETY SIGN
1.27 PHOTOGRAPHIC DOCUMENTATION
1.28 FINAL ELEVATION DIGITAL IMAGES
01 00 00 - 2
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for “Construction” operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Addition & Renovation as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Contracting Officer’s Representative (COR).
C. Offices of Triple C, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three weeks unless otherwise designated by the COR.
E. Prime Contractor Personal Minimum Requirements:
1. As Required in other parts of the Project Manual and Contract Requirements the following are minimum requirements:
a. The Superintendent shall be an employee of the Prime Contractor with authority to act as the contractor, responsible for the day-to-day operations at the construction site, planning, quality control, verification of delivery of approved material and equipment, subcontractor coordination responsibilities and execution of the complete project as per the contract documents.
1) The superintendent shall provide proof to the COR regarding completion of
30 hour OSHA.
2) Superintendent assigned to this project shall not be assigned to any other project and shall only have duties on one project at a time.
3) The Superintendent shall sign-in at the beginning of each day of work and
Sign-out at the end of the work day at the Office of Engineering Service. No work shall be performed by any contractors or subcontractors without the presence of the superintendent at the actual work site.
4) The Superintendent shall be responsible for submitting daily work logs to the COR at the end of every work day.
b. Site Safety and Health Officer (SSHO) shall be a separate qualified individual from the Prime Contractor’s Superintendent or CQC System Manager with duties only as the SSHO. See 01 35 26 SAFETY REQUIREMENTS for more information on roles and responsibilities for General Contractor’s staff.
c. CQC System Manager shall be a separate qualified individual from the Prime Contractor’s Superintendent or Site Safety and Health Officer (SSHO) with duties only as the CQC System Manager. See Section 01 45 00 Quality Control for more information on roles and responsibilities for CQC Personnel.
01 00 00 - 3
d. The Prime contractor shall provide services of a Project Manager whose responsibilities would include but not be limited to providing support to the Superintendent at the job site and shall be responsible for finance related tasks and scheduling.
F. Dig Permit
1. The contractor shall complete the VA dig permit with the COR and submit the Dig Safe notification prior to start of any excavation work.
G. Electrical Work Permit
1. The contractor shall complete the VA Electrical Work Permit with the COR and submit to the COR a minimum of 72 hours prior to start of electrical work within the facility.
H. Welding and Cutting
1. A daily Hot Work Permit is required and shall be coordinated with the COR. See Section
01 35 26, SAFETY REQUIREMENTS for additional requirements.
I. Contract Work Hours
1. Normal working hours are 700 am to 4:30 pm. Contractors who wish to work other than
“normal working hours” for work to be done during those hours must submit a written request to the Contracting Officer for approval. The request must state that the Contractor is requesting to work other than normal working hours at no additional expense to the Government. Such requests shall be coordinated with the COR and must be submitted to the CO five (5) working days in advance.
2. For certain aspects of work the Contractor shall be required to work off duty hours to perform that part of the work, for continued operations of the Medical Center. After duty hours and work shall be coordinated with and approved by the COR prior to commencement of work and must be submitted to the CO five (5) working days in advance.
a. Noisy demolition work, work at building entrances, electrical or other utility work necessary to pass within, above, traverse hallway corridors, temporary shutdowns of utilities for tie-in, hanging heavy steel, crane lifts, or other hazardous work over the top of occupied areas.
J. Contractor shall perform work in accordance with requirements of “ASHE Construction in a Healthcare Facility”.
K. Contractor shall provide Submittal Exchange®, Autodesk Build® and/or ProCore Project Site dedicated for this project, or approved equal (substitutions must be submitted with Contractor Bid), for the duration of the contract. Contractor will provide VA access to the site. Contractor will keep this site current and will use it for all submittals, RFIs, change documents, Record Drawing, electronic file management, and communication logs for the duration of the contract.
L. Contractor shall provide Infection Control Plan as required by Memorandum 111-40, Subj: VHA Directive 7715 Safety and Health During Construction dated April 6, 2017. Submit to COR for approval prior to the start of work.
M. Prior to commencing work, general contractor shall provide proof that an OSHA designated “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present. CP will have authority letter.
N. Per VA Directive 1085, smoking, vaping and smokeless tobacco are prohibited on the grounds of VA facilities, including in vehicles. This Directive applies to all Prime Contractor and Subcontractor employees.
O. A commissioning plan and Commissioning Manager(CxM) resume shall be submitted with contractor bids. The CxM shall work with the Commissioning Agent (CxA), who shall be a third-party entity outside of this contract, independently employed by the VA.
1. The CxM shall have been the principal CxM on at least three (3) comparable projects that have been completed within the previous five (5) years.
2. The CxM shall be certified by at least one of the following agencies:
01 00 00 - 4
a. National Environmental Balancing Bureau (NEBB)
b. AABC Commissioning Group (AGC)
c. Building Commissioning Association (BCxA)
3. Commissioning Services will be provided in accordance with the Department of Veterans Affairs Commissioning Process Manual. Prospective proposers shall review the Whole Building Commissioning Process Manual available on the VA Technical Information Library at http://www.cfm.va.gov/til/.
4. See section 01 91 00 – General Commissioning Requirements for additional requirements and information.
5. Covid-19:
a. Contractor is responsible for following current Covid-19 protocols as identified by the VHA, station, and CDC requirements. Coordinate with COR prior to arrival on site.
1.3 STATEMENT OF BID ITEM(S)
A. Contractor shall completely prepare project site for operations, including demolition and removal of existing site elements, and furnish labor and materials and perform work for the Veterans Affairs Gulf Coast Health Care System, Project 520-331, Construct Addition and Renovations to Joint Ambulatory Care Center, Pensacola, FL, Addition & Renovation as required by drawings and specifications. Period of performance is projected to be no greater than 540 calendar days.
The work will require construction of 11,731 sf of Addition onto the existing roof of a ~207,191 SF building. This includes the addition of a new chiller tower (CT-3) in the mechanical yard, and replacement of the water chiller (CH-3) and associated pumps in existing mechanical room 1B179. The programs that will be supported in this addition will support Phlebotomy and Laboratory Services and the Infusion Clinic. There is also ~92,000 SF of surface parking to be constructed in the existing grass areas in the parking lot. The existing building shall remain operational during the entirety of the construction project.
B. The construction shall be Phased as follows below. Each Phase shall be completed in its entirety, for all disciplines, from demolition to final punch-walk and acceptance by the VA, prior to the commencement of the subsequent Phase. The Contractor shall prepare and submit their own Phasing Plan along with the Interim Life Safety Plans and Construction Schedule, to show accommodation of these phases. Period of performance not to exceed 18 months for all phases. Phases 2A and 2B shall be completed concurrently with Phase 1. Two weeks minimum required between Phase 2A and Phase 2B to allow for traffic patterns and parking to be shifted.
1. Phase 1:
a. Perform all scope of work associated with “Area F” – the Phlebotomy, Blood Draw, Core Lab, Infusion Clinic, and Associated Spaces. Include all associated scope of work with Ahu-2-N being installed on the third floor mechanical space. Also include all scope of work associated with the installation of new Chiller Tower 3, in the existing mechanical yard, and replacement of water Chiller 3 (CH-3). Contractor to provide proposed phasing and construction timeline plan for review and approval by the VA.
2. Phase 2A:
a. Perform all scope of work associated with new parking lot areas A and C.
Coordinate any required shutdowns to adjacent parking lot areas with the COR – plan work to minimize the number of required shutdowns during operating hours.
Period of Performance not to exceed 6 months. Work to be performed concurrently with Phase 1.
1)
3. Phase 2B:
a. Perform all scope of work associated with new parking lot area B. Coordinate any required shutdowns to adjacent parking lot areas with the COR – plan work to minimize the number of required shutdowns during operating hours. Period of http://www.cfm.va.gov/til/
01 00 00 - 5
Performance not to exceed 6 months. Work to be performed concurrently with Phase 1. Two weeks minimum required between Phase 2A and 2B to allow for traffic patterns and parking to be shifted.
C. Work includes general construction, alterations, and certain other items. Contractor shall provide services but not limited to furnish all supervision, labor, equipment, materials, and transportation necessary to accomplish work for the demolition, replacement, and construction as required by specifications and drawings, including basis of design established in 09 06 00
SCHEDULE OF FINISHES.
D. Electrical Work: Electrical work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project including materials and construction equipment to provide new electrical, communications and security systems to the new addition detailed by the construction drawings and specifications.
a. All new and existing systems within the Scope of Work shall be commissioned (or recommissioned) per Specification 01 91 00.
E. Provide access control for all the required doors, coordinate with the door hardware schedule for additional requirements.
F. Mechanical, Plumbing and Fire Protection Work: Work includes all labor, material, equipment and supervision to perform the required Mechanical, Plumbing and Fire Protection construction work on this project including provide materials and construction equipment as detailed by the construction drawings and specifications.
1. All new mechanical systems shall be addressable and controllable via the existing
Engineering Control Center (ECC) and HVAC Shop. The ECC system shall monitor space conditions and unit status and shall alarm the HVAC shop as detailed by the mechanical control drawings and specifications.
2. All controls, fire systems, security systems, etc. shall be an extension of the existing, in-place systems. Coordinate extensions and parts with the existing system manufacturers to ensure compatibility and continuity between existing and new parts of the whole system.
G. New Fire Protection systems shall be an extension of the existing systems per the construction drawings and specifications.
H. Contractor shall reconfigure existing plumbing piping and provide new plumbing piping and fixtures as required by the construction drawings and specifications.
I. Site Work: Site work includes all labor, material, equipment and supervision to perform the required hardscape and landscape construction work on this project including materials and construction equipment to provide new concrete walkways, planting beds, artificial turf, fencing, trees and additional landscape materials to the building addition detailed by the construction drawings and specifications.
1. Protection for existing plantings, trees and hardscape to remain shall be installed, maintained and enforced by contractor.
J. Inspections: Comprehensive Third-Party inspections, testing and written reports for all Divisions are required and paid for by the General Contractor. Contractor shall employ third party inspection consultants to perform all inspections required by this contract. All new and existing systems, including mechanical, electrical, plumbing, and fire protection, within the scope of work are required to be inspected.
K. All new and existing systems within the Scope of Work shall be commissioned (or recommissioned) per Specification 01 91 00.
L. ITEM I, GENERAL CONSTRUCTION: BASE BID – Work includes all work as described previously in item A. Including general construction, alterations, required grading and drainage for new parking lot(s), and removal of existing structures and other items as outlined in the contract documents.
01 00 00 - 6
M. ALTERNATE NO.1: BASE BID except remove all scope of work associated with ~51,200 SF of new parking – see GI100.
N. ALTERNATE NO.2: ALTERNATE 1 except remove all scope of work associated with ~39,000 SF of new parking – see GI100.
O. ALTERNATE NO.3: ALTERNATE 2 except reduce window quantity by 8 – see A-201.
P. ALTERNATE NO.4: ALTERNATE 3 except remove all scope associated with 600 ton chiller (CH-3) replacement in mechanical room 1B179.
Q. The construction period duration of 540 calendar days includes all pre-construction activity, construction, and post-construction testing, third-party inspections, Owner inspections, and commissioning. Contractor shall submit a comprehensive schedule of work in compliance with
01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD).
1. Contractor shall submit and obtain approval for all project submittals including coordination drawings prior to beginning physical construction.
2. Contractor shall perform Commissioning of all new systems and existing systems impacted by the project according to requirements in sections:
a. 01 91 00 – GENERAL COMMISSIONING REQUIREMENTS.
b. 21 08 00 – COMMISSIONING OF FIRE SUPPRESSION SYSTEMS.
c. 22 08 00 – COMMISSIONING OF PLUMBING SYSTEMS.
d. 23 08 00 – COMMISSIONING OF HVAC SYSTEMS.
e. 26 08 00 – COMMISSIONING OF ELECTRICAL SYSTEMS.
f. 27 08 00 – COMMISSIONING OF COMMUNICATIONS SYSTEMS.
g. 28 08 00 – COMMISSIONING OF SECURITY SYSTEMS.
h. 33 08 00 – COMMISSIONING OF SITE UTILITIES.
3. A detailed commissioning plan is required to ensure that all systems are calibrated, programmed, and all graphic displays are accurate and approved by applicable VA staff.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
B. Refer to specifications for installation requirements for each Division. Refer to drawings for estimated quantities and schematic layouts/locations. Contractor shall provide a complete, commissioned, functioning systems. Contractor shall provide all testing reports prior to the start of commissioning. This project will require night and weekend work, Renovation includes requirements for Testing and Balancing the HVAC for the existing and new systems configuration.
C. Refer to 09 06 00 SCHEDULE OF FINISHES for additional requirements and basis of design tables.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
a. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
01 00 00 - 7
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that escort arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of theCl Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the
Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as
01 00 00 - 8 authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings.
E. Workers are subject to rules of the Joint Ambulatory Care Center (JACC) applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of the Care Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Care Center areas required to remain in operation.
3. Where access by VA personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
4. Work on areas outside the building and/or construction site during any given phase shall require off hours work, nights and weekends, to maintain continued operations of the JACC Medical Center. Work affecting areas outside the designated building and/or construction site (including bringing materials onsite) shall be scheduled with COR per
1.6 and shall be performed after normal work shifts including nights and weekends.
a. The work will have to be carefully planned and phased for minimal disruption to the
JACC Facility activities. Under no circumstances will any area of the building be shut down and all services must remain operational. Under no circumstances shall there be utility outages, including brief cutovers, anywhere on the campus without the express written consent of the COR. The contractor shall plan and forecast upcoming work which may disrupt normal operations or interfere with staff or patients and report these in the weekly meetings.
1) Contractor shall provide temporary services, including temporary Air
Handlers, Generators, etc.
a) See Construction drawings for temporary equipment location related to ahu-10.
b. It may be necessary to postpone or reschedule work to accommodate the needs of the Medical Center. All such time shall be included in the base bid and shall not be billable to the government.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
01 00 00 - 9
I. Phasing:
1. The Medical Center must maintain its ongoing operation. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
a. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor.
2. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
3. Immediate areas of alterations not mentioned in preceding Subparagraph 1 will be temporarily vacated while alterations are performed.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR
K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for JACC Facility at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.
Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical
01 00 00 - 10
Center Director’s prior knowledge and written approval. Refer to specification Sections 26
05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11
REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 2 weeks in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the JACC Facility.
Interruption time approved by COR may occur at other than Contractor's normal working hours.
4. Interruptions such as utility interruptions/ closures of any system must be requested, in writing, at least 2 weeks prior to the desired time and shall be performed as directed by the COR .
5. In case of a contract construction emergency, service will be interrupted on approval of COR . Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
N. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
O. Coordinate the work for this contract with other construction operations as directed by COR.
This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
P. Construction staging area shall be level ground, and re-sod, and any damaged sprinkler heads in the staging area shall be repaired by the contractor. Staging area to be returned back to VA in existing condition prior to construction.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of the building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
01 00 00 - 11
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and
"CHANGES" (FAR 52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. The Contractor shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the facility.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
4. PCB Transformers and Capacitors : The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers and capacitors . The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental Protection Agency (EPA) and the Department of Transportation (DOT) as outlined in Code of Federal Regulation (CFR), Titled 40 and 49 respectively.
The EPA's Toxic Substance Control Act (TSCA) Compliance Program Policy Nos. 6- PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform Hazardous Waste Manifest (EPA Form 8700-22), along with the Uniform Hazardous Waste Manifest Continuation Sheet (EPA
01 00 00 - 12
Form 8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the Manifest to the COR.
a. Copies of the following listed CFR titles may be obtained from the Government
Printing Office:
40 CFR 261 ........................... Identification and Listing of Hazardous Waste
40 CFR 262 ........................... Standards Applicable to Generators of Hazardous Waste
40 CFR 263 ........................... Standards Applicable to Transporters of Hazardous Waste
40 CFR 761 ........................... PCB Manufacturing, Processing, Distribution in Commerce, and use Prohibitions
49 CFR 172 ........................... Hazardous Material tables and Hazardous Material Communications Regulations
49 CFR 173 ........................... Shippers - General Requirements for Shipments and Packaging
49 CRR 173........................... Subpart A General
49 CFR 173 ........................... Subpart B Preparation of Hazardous Material for Transportation
49 CFR 173 ........................... Subpart J Other Regulated Material; Definitions and Preparation
TSCA .....................................
This is the start of the file's text. The full file is on GovTribe.